SYSTEM DEVELOPMENT LIFE CYCLE (SDLC)
PT BANK SYARIAH INDONESIA
IT Strategic Planning Group
12 Desember 2023
Ketentuan Pelaksanaan
Strictly private and confidential
Ketentuan Pelaksanaan - Flow SDLC Project Inisiatif
IT Planning IT Planning IT BA IT Release IT Release IT PMO
Unit kerja bisnis Komite ITSC IT Dev Unit Testing (IT QA, IT IT PMO PM User
IT BP PM User PM IT SIT) PM User PM IT
Project Owner/ PM User IT PMO Vendor (Eksternal) CSO (Pentest) PM IT CTO
IT PMO PM IT Unit Implementasi
Unit Risk Dir Bidang TI
SOR Dir Bidang PM User
Dir Bidang/SEVP Bidang Procurement
Ketentuan Pelaksanaan - Flow SDLC Project Enhancement
IT Planning IT BA IT BA IT Release IT Release -
Unit kerja bisnis IT Dev IT Dev Unit Testing (IT QA, IT SIT) IT PMO
IT BP PM IT PM IT CSO (Pentest) PM User
Project Owner/ PM User IT PMO Vendor (Eksternal) PM IT
PM IT PM User Unit Implementasi
IT ASP
IT Arsitektur
Unit Testing
DDM
CSO
Ketentuan Pelaksanaan - Flow SDLC Agile Project Inisiatif
IT Planning Scrum Master Scrum Master Sekretariat RCB Squad Lead
Project Sponsor Squad Member Squad Member Scrum Master Squad Member
Project Lead Squad Suppport Squad Suppport Squad Member Squad Support
Reviewer Squad Support Product Owner
-
PMO Lead Product Owner PMO
PIC
Ketentuan Pelaksanaan - Flow SDLC Agile Project Enhancement
IT Planning Scrum Master Scrum Master Sekretariat RCB Squad Lead
Project Sponsor Squad Member Squad Member Scrum Master Squad Member
Project Lead Squad Suppport Squad Suppport Squad Member Squad Support
Reviewer Squad Support Product Owner
PMO Lead Product Owner PMO
PIC
-
Finalisasi Demand Analysis Document (DAD)
Finalisasi Dokumen Customer Request (CR)
Ketentuan Pelaksanaan - Flow SDLC
Join Planning Session
1 -List project inisiatif
Finalisasi DAD
-Demand Analysis Document 2
-Dok. FS
Finalisasi Customer Request
3 -Dok. CR
Forum Working Group
-Risalah Rapat
4
IT Planning
Unit Kerja Working Group (CTO, OPR, IPR, dan Unit Risk)
Unit kerja bisnis
IT BP
Project Owner/ PM User
PM IT
Tahap Perencanaan Tahap Pendefinisian Tahap Pengembangan Tahap Testing Plan Tahap Implementasi Tahap PIR
Ketentuan Pelaksanaan - Flow SDLC
Forum IT Steering Committee (ITSC)
5 -Risalah rapat/Nota Persetujuan
ITSC
Menyusun Project Charter
-Dok. Project Charter 6
Pengembangan External (Procurement
7 Management Plan)
-BA Aanwijzing -BA Negosiasi -BA Auction
-Proposal Teknis dari Vendor -PKS/SPK
Join Discusion Meeting
-FSD 8
-SUG (jika pengembangan eskternal)
Forum Arsitektur
9 -AAD
IT Planning Unit Kerja Reviewer (IT Risk, SOR) IT Infrastruktur
Project Owner/ PM User DH IT IT Arsitektur
PM IT IT Development/Vendor IT Application Services
Komite dan Peserta ITSC sesuai IT PMO Procurement
SK ITSC IT BA
Tahap Perencanaan Tahap Pendefinisian Tahap Pengembangan Tahap Testing Plan Tahap Implementasi Tahap PIR
Ketentuan Pelaksanaan - Flow SDLC
Development
10 - SDD (internal)
- TSD (ekternal)
Test Management Plan
- TMP Report 11
Testing (SIT, UAT, Stress Test, Pentest)
12 - SIT Report - Installation Guide
- BA UAT - Stress Test Report
- BA Pentest
RCB
- MoM RCB 13
Deploy
14 - BA Instalasi
● PM IT
● IT Testing ● Vendor Pentest
● IT Developer
● IT PMO ● IT Risk
● IT Release Management
● Project Owner/PM User ● IT Application Services ● Komite RCB
● IT QA ● IOG
● CSO
● IT Performance Testing ● IT Project Implementation
Tahap Perencanaan Tahap Pendefinisian Tahap Pengembangan Tahap Testing Plan Tahap Implementasi Tahap PIR
Ketentuan Pelaksanaan - Flow SDLC
Production Trial Run
15 - BA PTR
Go Live
- BA Go Live 16
Post Implementation Review
17 - PIR Report
- BA Project Closure
● Project Owner/PM User
● IT Development
● PM IT
● IOG
● IT QA
● IT PMO ● CTO
● IT Application Services
Tahap Perencanaan Tahap Pendefinisian Tahap Pengembangan Tahap Testing Plan Tahap Implementasi Tahap PIR
Roles Stakeholder Project
Project Manager IT (PM IT) Project Management Office
(PMO)
Berkoordinasi dengan project owner(PM User) Menerima kelengkapan dokumen pengembangan
dalam menyusun project charter terkait pembuatan oleh IT Development atau Vendor.
atau pengembangan sistem / aplikasi yang
merupakan project corplan / project Inisiatif Berkoordinasi dengan PM IT jika terjadi kendala atau
Strategis IT ketidaksesuaian sistem/ aplikasi dengan CR saat
Menyusun timeline pengembangan project yang proses SIT & UAT.
dikembangkan
Bersama dengan PM IT mengawal sistem / aplikasi
hingga berhasil diimplementasi & memastikan
Mengawal project hingga berhasil diimplementasi
kelengkapan dokumen project terpenuhi sesuai
sesuai dengan timeline yang ditentukan.
dengan prosedur yang berlaku.
Memastikan sistem/aplikasi yang dikembangkan
Melakukan hands over project ke IT Operation dan
sesuai dengan CR dan lolos seluruh tahapan uji
membuat berita acara Go Live.
coba.
Berkoordinasi dengan pihak terkait atas kebutuhan Mengumpulkan seluruh dokumen-dokumen yang
yang perlu dipenuhi selama proses pengembangan berkaitan dengan proses pengembangan sistem /
hingga implementasi berhasil. aplikasi ke portal JIRA.
Project Manager IT Activity
Memantau dan mengendalikan setiap milestone
project
Melakukan update problem solving atas issue teknis
Membuat form pengajuan untuk mendukung proses
development.
Arrange meeting weekly update project
Follow up atas action dalam weekly project
Melakukan pengaturan document project
Pencarian PTO SDLC
Akses ke aplikasi NPS dengan alamat : nps.bankbsi.co.id