The document provides steps to perform resource scheduling by assigning a work center, adding maintenance orders to a new schedule, setting start dates and times, and checking the scheduled operations on the maintenance scheduling board.

Uploaded by

cardenaslila41
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
18 views20 pages

Resource Scheduling

The document provides steps to perform resource scheduling by assigning a work center, adding maintenance orders to a new schedule, setting start dates and times, and checking the scheduled operations on the maintenance scheduling board.

Uploaded by

cardenaslila41
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 20

Resource Scheduling

Resource Scheduling

Explanation Screenshot

To learn more about


how to perform
resource scheduling,
follow this interactive
tutorial.

In the following steps,


you will start resource
scheduling and
assign work center.

1. Choose Resource
Scheduling.

1
Resource Scheduling

Explanation Screenshot

2. To open the app,


select the Resource
Scheduling for
Maintenance
Plannersy tile.

3. Choose Go.

4. Choose Plus.

2
Resource Scheduling

Explanation Screenshot

5. In the Work
Center field, enter T-
ME01.

6. Choose Assign.

Note that you can


change your work
center assignment at
any time. To do this
use option My Work
Centers within card
Work Center
Utilization.

3
Resource Scheduling

Explanation Screenshot

You can now check


the different cards.

7. Choose Work
Center Utilization.

In the following steps,


you will add the
previously created
orders to a new
schedule and select
the next two days as
the time frame.

4
Resource Scheduling

Explanation Screenshot

The Maintenance
Order Operations has
already been
selected.

8. Select 4000182.

9. Choose Add to
Schedule.

5
Resource Scheduling

Explanation Screenshot

The Create New


Schedule has already
been selected.

10. In the Schedule


Name field, enter
Schedule 01.

11. Open the


Calendar list.

6
Resource Scheduling

Explanation Screenshot

12. Select 5.

13. Select 6.

14. Choose Create.

7
Resource Scheduling

Explanation Screenshot

Schedule 01 is now
opened.

15. Choose Schedule


Automatically.

16. Choose OK.

8
Resource Scheduling

Explanation Screenshot

In the following steps,


you will check option
Refine Schedule.

17. Choose Refine


Schedule.

18. Select 400182.

9
Resource Scheduling

Explanation Screenshot

19. Open the Set


Start Date list.

20. Select Set Start


Date and Time.

21. Choose Wed 5.

10
Resource Scheduling

Explanation Screenshot

22. Choose Start


Time.

23. Select 10.

24. Select 0.

11
Resource Scheduling

Explanation Screenshot

25. Select 0.

26. Choose OK.

27. Choose Set.

12
Resource Scheduling

Explanation Screenshot

28. Open the Freeze


Schedule list.

29. Choose Save and


Dispatch Operations.

Note that do not


Freeze the Schedule.

13
Resource Scheduling

Explanation Screenshot

30. Choose Back.

31. Choose Back.

You can now check


screen Work Center
Utilization.

14
Resource Scheduling

Explanation Screenshot

32. To return to the


launchpad, choose
SAP.

In the following steps,


you will check the
operations in the
Maintenance
Scheduling Board.

33. To open the app,


select the
Maintenance
Scheduling
Board tile.

15
Resource Scheduling

Explanation Screenshot

You can now check


the selection and
filter options for the
displayed
maintenance orders.

34. Choose Go.

35. Choose Zoom In.

16
Resource Scheduling

Explanation Screenshot

36. To expand the


400182 pane, choose
the arrow.

37. Select 1010.

38. Choose Change.

17
Resource Scheduling

Explanation Screenshot

You can now check


functions Change.

39. Choose Cancel.

40. Choose Cancel


Dispatch.

18
Resource Scheduling

Explanation Screenshot

41. Select 1010.

42. Choose Dispatch.

Note that for the


editing options to
become active, only
select the order
operations, not the
order header.

19
Resource Scheduling

Explanation Screenshot

You have
successfully
performed resource
scheduling.

This concludes the


interactive tutorial.

20