2313721096130                                                        RIDDHI JAIN
9. REGRESSION
The following table shows the age (X) and blood pressure (Y) of 8 persons:
 X       52       63        45     36       72      65       47       25
 Y       62       53        51     25       79      43       60       33
Obtain the regression equations and find the expected blood pressure of a
person who is 49 years old.
CODING:
x=c(52,63,45,36,72,65,47,25)
y=c(62,53,51,25,79,43,60,33)
R1=lm(x~y)
R1
R2=lm(y~x)
R2
OUTPUT:
Reg=(0.7684*49)=11.8515
Reg x=0.6488y+17.6999 y=0.7684x+11.8515
2313721096130                                                                                  RIDDHI JAIN
10. CRITICAL PATH METHOD:
Construct the network for the project whose activities are given below and compute the ES, EF, LS,
LF, Total float and Free float of each activity and hence determine the critical path and the project
duration.
 Activity 1-2             2-3         3-4         3-7        4-5         4-7         5-6         6-7
 Duration 3               4           4           4          2           2           3           2
AIM:
To Calculate the ES, EF, LS, LF, Critical Path, Project Duration, Total Float (TF) & Free Float (FF) for the
given problem.
ALGORITHM:
• Click on Start – All programs – TORA
• Click on “Click Here” on the first page
• In the main menu click – “Project Planning” – Critical Path Method and then click “Go to Input
Screen”
• Enter the problem title as CPM and press Enter
• Enter all the values in the input grid
• Click on “Solve Menu” and press “No” in the save dialogue box
• Click on “Go to Output Screen”
• In the output screen, select “CPM Bar Chart”
• The output is displayed.
PROJECT NETWORK:
2313721096130            RIDDHI JAIN
OUTPUT: CPM BAR CHARTS
2313721096130                                                            RIDDHI JAIN
OUTPUT:
 ACTIVITY    DURATION    EARLIEST   LATEST   EARLIEST   LATEST   TOTAL   FREE
             (WEEKS)     START      FINISH   FINISH     START    FLOAT   FLOAT
 1-2         3           0          0        3          0        0       0
 2-3         4           3          3        7          3        0       0
 3-4         4           7          7        11         7        0       0
 3-7         4           7          7        11         14       7       7
 4-5         2           11         11       13         11       0       0
 4-7         2           11         11       13         16       5       5
 5-6         3           13         13       16         13       0       0
 6-7         2           16         16       18         16       0       0
RESULTS:
CRITICAL PATH: 1-2-3-4-5-6-7
PROJECT DURATION: 18 WEEKS
2313721096130                                                                            RIDDHI JAIN
11 PROGRAMME EVALUATION REVIEW TECHNIQUE [PERT]:
Construct the network for the project whose activities and the three estimates (in weeks) are given
below.
Compute
    i.      Expected duration
    ii.     Expected variance of project length
             Activity    1-2        1-3        1-4        2-4        2-5        3-5        4-5
             To          2          3          4          8          6          2          2
             Tm          4          4          5          9          8          3          5
             Tp          5          6          6          11         12         4          7
AIM:
To calculate the Expected Project Duration and Variance of the project length for the given data.
ALGORITHM:
• Click on Start – All Programs – TORA
• Click on “Click Here” on the first page
• In the main menu click – “Project Planning” – Critical Path Method and then click “Go to Input
Screen”
• Enter the problem title as PERT and press Enter
• Enter all the values in the input grid
• Click on “Solve Menu” and press “No” in the save dialogue box
• Click on “Go to Output Screen”
• In the output screen, select “PERT Calculations”
• The output is displayed.
PROJECT NETWORK:
2313721096130               RIDDHI JAIN
INPUT:
OUTPUT: PERT CALCULATIONS
2313721096130                                        RIDDHI JAIN
RESULTS:
CRITICAL PATH: 1-2-4-5
EXPECTED PROJECT DURATION: 17.83
EXPECTED VARIANCE OF PROJECT LENGTH: 1.1881(1.09)2