WPR # 5

The weekly progress report summarizes the work completed on a construction project over the past week. Key achievements included partition framing, gypsum board installation, false flooring completion, and electrical raceway installation. The plan for next week is to focus on finishes like tiles, laminate, and ceiling work. Some risks include delays in material delivery and slow vendor work. Project budgets and schedules are on track.

Uploaded by

Athar Iqubal
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
102 views34 pages

WPR # 5

The weekly progress report summarizes the work completed on a construction project over the past week. Key achievements included partition framing, gypsum board installation, false flooring completion, and electrical raceway installation. The plan for next week is to focus on finishes like tiles, laminate, and ceiling work. Some risks include delays in material delivery and slow vendor work. Project budgets and schedules are on track.

Uploaded by

Athar Iqubal
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 34

Weekly Progress Report # 5

Date 28-10-2023

Accelerating Success
• Project Details
• Project Layout
• Project Schedule
Contents • Project Dashboard
• Achievements in previous week
• Site Photographs
• Plan for next week
• Supports required
• Risk Log
• Design / Drawing Update
• Change Request
• Quotation
• Procurement Status
• Long Lead materials tracker
• EHS tracker
Project Details

Description Details
Project Name Genpact India Pvt Ltd

Location 3rd Floor, Uppal

Total Area 17500 Sft

Stakeholder Details
Client Genpact India Pvt Ltd

PMC Colliers International

Design Design Plus Associates

C&I Innovations Workspace

Overall Progress of Project


Timeline 31-10-2023

Total PO amount • *₹ 3,50,89,316

Status Construction Phase


* NOTE: Few PO yet to release
Approved Project Layout (3rd Floor)
Achievement in previous week
C &I
Partition & Modular workstation marking completed
Framing work completed
Single side Gypsum Board completed
Double side gypsum board completed
MDF paneling completed
Framing work completed
Punning work completed
Pelmet completed
Window sill completed
Above partition Work completed
Colum Paneling completed
 Gypsum ceiling is in Progress
Achievement in previous week
C &I
Step seating work is in progress
Round seating work is in progress
Rubber wood seating is in Progress
PCC work completed
Hub room false flooring is completed
Laminate fixing for AHU room Doors is in progress
Putty work is in progress
Primer work in Progress
Tiles work in Progress
Laminate panneling is in Progress
Board room partition is in Progress
Achievement in previous week
Fire Fighting
 Header installation is completed
Sub header and branches installation completed
Flexible fixing is completed
Pressure test is completed
Ahu Room, Hub Room Sprinkler dismantling is completed
Pressure Test is completed
Painting for sprinkler completed
Board Room Sprinkler work is in completed
AHU room and Hub Room New line laying completed
Achievement in previous week
FAPA
 FAPA line Marking completed
Existing cabling and conducting dismantling completed
FA conducting completed
Hotter and MCP for FA is condut dropping completed
PA conducting is compelted
FA cabling completed
PA cabling completed and
shaft cable for both (FAPA)is in progress
 Above detector Back box fixing completed
Above Detectors Fixing is in progres
Achievement in previous week
False Flooring
 Leg marking is completed
False flooring installation is completed
Edges cut pieces laying is in progress
False flooring cutting is in Progress for Workstation
Achievement in previous week
Access System

Conduct dropping in partition is completed


Conduct laying is completed
Raceway laying is completed
Cable laying is completed
Pannel fixing completed
Achievement in previous week
CCTV
 Existing tray and cables adjustment completed
Cable tray laying completed
Cables laying is in progress
Rack fixing and cabling is in Progress
Installation of
Achievement in previous week
HVAC
 Existing damper and plenum dismantling is Completed
 Existing Duct dismantling completed
Marking and duct support fixing is completed
Duct installation is in progress
Plemun installation in Ahu room is completed
Flange fixing is completed
Smoke testing is completed
Insulation for flange is in progress
Flexible installation is in Progress
Achievement in previous week
IT
 Existing Hub room dismantling is completed
 Cabling laying in work station area is completed
Rack fixing is in progress
Achievement in previous week
Electrical
 Conduct marking completed
Floor and ceiling raceway completed
Hub room Race way and electrical work completed
ceiling Raw power , conducting and box fixing completed
Ceiling and floor raw power cabling completed
WIFI conducting and box completed
Signage conducting wring and box fixing completed
Point wiring completed
Electrical Room Dismantling completed
Hub Room dismantling completed
Circuit laying in completed
Electrical Room DB fixing and DB framing is compelted
Lighting and Ups circuiting is completed
Achievement in previous week
Electrical
 Hub Room Race way completed
Signage raw power is completed
Cables laying for work station completed
DB Dressing is in progress

Project Dashboard – 3rd Floor
PROJECT BUDGET

Amount (INR)
Planned Vs Actual
Parameter
without tax
60%
*Total Committed Cost *

Estimate to Complete TBD


50%

Project Variance from Budget 40%

*NOTE: Few PO yet to release 30%

20%
PROJECT SCHEDULE
10%
3rd Scheduled Actual
0%
Project Start Date 20-09-2023 20-09-2023
Project End Date 31-10-2023 31-10-2023

Planned Actual
Site Photographes | 3rd floor

False Flooring :

Completed : Marking, Installation completed


In Progress: Edges cut pieces laying is in
progress
Site Photographes | 3rd floor

C&I :
Completed : Marking, Frame work, Board
fiixing,Lacqured glass,
In Progress: Primer, Tiles,laminte,inbuilt
furniture
Pending : Acosutic,Glass partition, glass door.
finishes
Site Photographes | 3rd floor

Electrical Works :
Completed : Marking, Ceiling, Partition conducting , Raw power,
point wiring, Race way and Hub Room, Circuting for signages
completed, Work station cabling compelted
In Progress: DB dressing in Hub room and electrical room is in
progress
Site Photographes | 3rd floor

Fire Fighting :
Completed : Marking, Main Header and sub header and Branches
completed, Pressure test completed.
In Progress: Repair works for existing pipe is in progress
Plan for next week
Laminate pannling
Ceiling framework and Gypsum Bord fixing
Acouistic fixing
Tiles laying
FA & PA cabling and fire Detectors Installation
Hub Room Readiness
Access cabling work in Hub room
Reader isntallation
IT Cabling
Inbuilt Furniture
Work station Marking
Work station installtion
Plan for next week

Painting
Duct flexible fixing
Grid ceiling frame work
Acoustic fixing
Board room partition work
Mcp and Hotter Devoce Fixing
FAPA cabling for board room is in Progress
FAPA cables connectivity to existing Cables for Washrooms and Pantry
Termination of boards at Hub room and reader installation
EM lock installation
DB incoming laying and end termination
Switch scokets installation
Support Required From client
PO for loose furniture yet to be relase
Graphis / Wallpaper Design need to be finalized
Risk and Mitigation
Sl.no Risk Priority Impact Mitigation
1 Glazed partition and delivery High Handing over of project will Material need to be delivered on
get effected site
2 Slow progress of work of High Handing over of project Vendors need to increase manpower
C&I and HVAC and Expedite work
3 Material Delivery of C & I High Handing over of project will Materials need to be get delivered
get effected on time
Design/Drawings Update | 3rd floor
Sr No Description Revision Approved On Status Remarks
01 All Layout R1 20 Sep 2023 Approved
02 3D Presentation R1 20 Sep 2023 Approved
03 Modular Drawing R1 27 Sep 2023 Approved
04 Raised Floor Shop R0 28 Sep 2023 Approved
Drawing
05 Detail Drawing R1 26 Sep 2023 Approved

06 FA & PA shop Drawing R0 27 Sep 2023 Approved


07 HVAC Shop drawing 06-10-2023 Approved
08 Fire Rated Door R0 13-10-2023 Approved
09 Glazed fire rated Door R0 13-10-2023 Approved
10 Baffle and cell ceiling R0 11-10-2023
Shop drawing Approved
11 Glazed partition and R2 Approved
Door
12 Board room and 6 pax R1 20-10-2023 Approved 4 pax meeting room is convereted
layout into 6 pax meeting room
Changed Request
Sr No Changed Request Requested Requested By Approved By Impact
On
01 Dismantling Existing Plenum 27 Sep 2023 Mr Alok Cost + scope +time
and Fire Damper
02 Exiting Smoke Dictator and RI 27 Sep 2023 Mr Alok Cost
need to be used at site
03 Dismantling of Existing Board 06 oct 2023 Mr Alok Cost + scope +time
Room and laminate Panelling
Quotation Shared

Sr No Description Requested On Requested By Approved on Remarks


01 Glass Fire rated Door 12-10-2023 IWS 14-10-2023 Approved by Mr Alok

02 Dismantling of board Room and 13-10-2023 IWS Approval is pending


laminate panelling
03 WLD and Rodent Infiniti Negotiation is going on
Procurement status
Sr. No Packages Vendor PO Date PO Number PO Amount
01 PMC Colliers International 29-09-2023 1401222962 9,00,000
02 Architect and MEP design Services DesignplusAccossiates 30-08-2023 1401222166 5,66,000
03 Modular Furniture Space Wood 06-10-2023 1401223071 58,51,004
04 Raised Flooring supply AET Flexible space 14-09-2023 1401222598 43,37,892
05 Raised Floor Installation AET Flexible space 14-09-2023 1401222607 1,66,842
06 IT Velocis 6,70,466
07 C &I, (Graphics) IWS o3-10-2023 1401223000 7,99,075
08 Electrical Skyline Electricals 22-09-2023 1401222809 53,05,064
09 HVAC Ventec Airconditioning 22-09-2023 1401222825 39,94,320
10 FA Infiniti 29-09-2023 1401222944 11,88,848
11 Blinds Deck Décor 14-09-2023 1401222600 3,50,000
12 Chairs Aster Comfort 18-09-2023 1401222658 35,81,760
13 Carpet Spaceworkz solutions 25-09-2023 1401222837 16,80,712
14 Fire Fighting Techno Fire 20-09-2023 1401222746 25,43,453
15 Fire Extinguisher Kanadia Fyr Fighter 22-09-2023 1401222824 3,23,232
Procurement status
Sr. No Packages Vendor PO Date PO Number PO Amount
01 PA Infiniti 29-09-2023 1401222946 6,70,466
Testing & Commissioning

Sr. No Description Location Start Date End date Pass/Fail Remarks


Long Lead Material Tracker

Sr. Material Lead time Order Status of Material Material Remarks


No Status Delivery Date
1 Wooden 15 Ordered 20-10-2023 Material is not
Acoustic delivered
2 Glass Partition 15 Ordered 25-10-2023
3 Glass Door 15 Ordered
4 Fire rated Door 30 Ordered
5 Acoustic 10 Ordered 20-10-2023 Material is not
Delivered
6 Lacquered 7 Ordered 26-10-2023
Glass
7 Glass fire rated 45 Material will be
Door ordered on 16-10-2023
8 Baffle Ceiling 20 Ordered 25-10-2023
9 Grid ceiling 10 Ordered 20-10-2023
10 Cell Ceiling 20 Ordered 25-10-2023
Long Lead Material Tracker

Sr. Material Lead time Order Status of Material Material Remarks


No Status Delivery Date
1 DB 7 Order Delivered 14-10-2023
2 Switch Socket 10 Ordered Delivered 13-10-2023
EHS Tracker

Sr. No Description Remarks

1 Cumulative Manhours worked 205


2 Number of Near Miss Incident NIL
3 Number of First Aid Treatment injuries NIL
4 Number of Medical treatment injuries NIL
5 Number of Lost time injuries NIL
6 Number of Fatalities Reported NIL
7
8
THANK YOU