The Gantt chart outlines an 8-week project to install an automatic fire suppression system. It details 7 tasks including contract signing, materials mobilization, fabrication and installation of hangers and supports, fabrication and installation of pipes and fittings from the ground to 4th floor, installation of risers and crossmains, termination and welding works, fabrication and installation of a fire tank and pumps. The final task is testing and commissioning with a projected end date of December 17, 2023.

Uploaded by

hpopo75
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as XLSX, PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
485 views2 pages

Gantt Chart Sample

The Gantt chart outlines an 8-week project to install an automatic fire suppression system. It details 7 tasks including contract signing, materials mobilization, fabrication and installation of hangers and supports, fabrication and installation of pipes and fittings from the ground to 4th floor, installation of risers and crossmains, termination and welding works, fabrication and installation of a fire tank and pumps. The final task is testing and commissioning with a projected end date of December 17, 2023.

Uploaded by

hpopo75
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as XLSX, PDF, TXT or read online on Scribd
You are on page 1/ 2

GANTT CHART

Automatic Fire Suppretion System Installation 07/Aug/23


Lammart, Guimba START DATE END DATE

10/28/2023

11/30/2023

12/17/2023
8/23/2023

8/24/2023

9/10/2023

9/11/2023

9/16/2023

9/17/2023

10/8/2023

10/9/2023

11/5/2023

12/7/2023
8/7/2023

9/4/2023
Duration (In
Task Name Start Date End Date Days)

Contract Signing 8/7/2023 8/7/2023 1 1


Mobilization of materials 8/23/2023 8/24/2023 2 1 1
Fabrication and Installation of Hanger & Support From (Grd to 4th Floor) 9/4/2023 9/10/2023 6 1 1
Fabricationf Pipes and its fittings (Grd to 4th Floor) 9/11/2023 9/16/2023 5 1 1
Installing of Pipe Rizer From (Grd to 4th Floor) 9/17/2023 10/8/2023 22 1 1
Installing of Crossmain From (Grd to 3rd Floor) 10/9/2023 10/28/2023 20 1 1
Termination and welding works (from Branchline, FHC) at Grd to 3rd Floor 11/5/2023 12/17/2023 43 1 1 1 1
Fabrication of Fire Tank 11/30/2023 12/7/2023 8 1 1
Installation of Fire/ Jockey Pumps including its controller
& associated pipes, 11/30/2023 12/7/2023 8 1 1

Testing and Commitioning