0% found this document useful (0 votes)
95 views15 pages

LGP REPORT #3 - Simpasa

The document provides details about secondary smelting operations at the Kansanshi Copper Smelter. It discusses key equipment used in the process including Pierce Smith Converters, Evaporative Cooling Chambers, Anode Furnaces, and the Casting Wheel. It then describes 5 maintenance tasks performed on various pieces of equipment: 1) Changing gland packings on a bustle pipe swivel joint of PSC3, 2) Changing corroded hood panels on PSC3, 3) Changing a diesel pump on the PSC3 valve rack, 4) Changing tuyeres on PSC2, and 5) Preparing a tuyere drill. Key learning points are provided for each task.

Uploaded by

Beckham Chaile
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
95 views15 pages

LGP REPORT #3 - Simpasa

The document provides details about secondary smelting operations at the Kansanshi Copper Smelter. It discusses key equipment used in the process including Pierce Smith Converters, Evaporative Cooling Chambers, Anode Furnaces, and the Casting Wheel. It then describes 5 maintenance tasks performed on various pieces of equipment: 1) Changing gland packings on a bustle pipe swivel joint of PSC3, 2) Changing corroded hood panels on PSC3, 3) Changing a diesel pump on the PSC3 valve rack, 4) Changing tuyeres on PSC2, and 5) Preparing a tuyere drill. Key learning points are provided for each task.

Uploaded by

Beckham Chaile
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 15

MECHANICAL LGP REPORT NO.

3
SECONDARY SMELTING
KANSANSHI COPPER SMELTER

AUTHOR: Michael Simpasa

GLOBAL ID: 042479

MENTOR: Sydney Kapota

DATE: 27/05/2021
Table of Contents

Chapter 1 SECTION UNDERSTANDING ............................................................ 1-2

Introduction ............................................................................................................................................1-2

Pierce Smith Converters .........................................................................................................................1-2

Evaporative Cooling Chambers ..............................................................................................................1-2

Anode Furnace ........................................................................................................................................1-2

Cast Wheel ..............................................................................................................................................1-2

Main Aisle Cranes ..................................................................................................................................1-3

Chapter 2 PRACTICAL EXPERIENCE: .............................................................. 2-3

1. Changing gland packing on PSC3 bustle pipe swivel joint ............................................................2-3

2. Changing hood panels 1R and 1L ...................................................................................................2-4

3. Changing out a diesel pump on PSC3 valve rack ...........................................................................2-6

4. Task Changing tuyeres on PSC2 .....................................................................................................2-7

5. Preparing tuyere drill .......................................................................................................................2-9

7. Main Aisle Crane Main bale Inspection and PM ..........................................................................2-13

Other Involvements ...........................................................................................................................2-13

Further Key learning points...............................................................................................................2-14

Further Recommendations ................................................................................................................2-14

Maintenance strategies ......................................................................................................................2-14


Chapter 1 SECTION UNDERSTANDING

INTRODUCTION
The Secondary Smelting section is responsible for converting the matte (60-65% Cu) received from
primary smelting first into blister copper (85%Cu) in the Pierce Smith Converters and finally into anode
copper ((8.5% Cu) in the Anode furnace.
The pieces of equipment key to these processes include:

Pierce Smith Converters


There are four Pierce Smith Converters, PSCs, that convert matte to blister copper. Two are always
running, with one on standby and another on rehabilitation. The PSCs are aided in their function by
auxiliary equipment which include: tuyeres, the tuyere punch car, back flaps, holding and heat up
burners, main drive system, emergency hydraulic roll-out system.

Evaporative Cooling Chambers


The Evaporative Cooling chamber is responsible for cooling the off-gas from the converters before it is
transported to the scrubber for cleaning and further processing in the acid plant. The off-gas leaving the
converters through the primary hood door escapes into the ECC. Spray coolers at the entrance to the ECC
cool the off-gas and collect dust which falls to the bottom into tote boxes via pneumatic double flap
valves. The ECC cools the off-gas from the converters from 700°C to around 350°C aided by: water
spray lances, a spray water tank, two water pumps, double flap valves and a valve rack.

Anode Furnaces
There are two Anode Furnaces that convert blister copper from the converters into anode copper. They
have 2 tuyeres through which they receive air essential to the process. Auxiliary pieces of equipment
supporting the anode furnaces include: cooling water valve racks, charging doors, fuel valve racks,
combustion air fans, incinerators and an I.D fan

Casting Wheel
Two Anode casting wheels, each driven by two servo motor driven gears, are the final stage of copper
anode preparation. They receive molten anode copper from the furnaces. The anode copper is then cast
into solid anodes, ready for transportation. Pieces of equipment around the casting wheels include:
Casting molds, launders, bosh tanks, hydraulic pre-loosening system, sumps pumps, a cooling tower, a
hydraulic reject anode take off machine, a barium sulphate screw conveyor, mold dressing system,
exhaust fans, spray coolers, etc.
Main Aisle Cranes
There are three Main Isle Cranes that are used to move molten metal between the MSEF and the
converters, and between the converter and the anode furnaces. At any one point, two cranes are in
operation while the third is on maintenance. Each crane has a 100T main bale with two hooks and a 40T
auxiliary bale with a single hook. The main bale drum is driven by two electric motors while the auxiliary
is driven by one. Both systems have electrically actuated brakes and emergency hydraulic brakes in case
of power failure.

Chapter 2 PRACTICAL EXPERIENCE:

1. Changing gland packing on PSC3 bustle pipe swivel joint

Problem

 Gland packings had worn out

Cause

 Pressure of gland follower on gland seal/swivel movements/high temperatures

Implication

 Air would leak, thereby reducing air pressure to the tuyeres, which would result in tuyeres being
chocked during operation
Solution
 Replace gland packings

Procedure

 Isolate LP Air valve


 Ensure bypass valve is closed
 Loosen bolts on flange follower
 Remove worn out gland packing
 Clean gland seat
 Cut new gland packing to required length
 Lubricate gland seat for easy installation
 Apply copper compound to gland packing
 Fit gland packing, ensuring the separation is at different points for all 4 GPs (90degrees apart)
 Push in gland follower
 Replace bolts
 Adjust bolts till gap between flange and gland follower is 35mm

Key Learning points


 Working principle of swivel joints

 The swivel joint uses a special type of gland packings with thick rubber strands in the center. The
rubber was incorporated to increase the life span of the packings which wear due to friction and
heat during operation. The gap between flange and gland follower is adjusted whenever air leaks
occur.

2. Changing hood panels 1R and 1L

Problem

 Hood panels were corroding on the inside

Cause

 Weak acid formed by the water from sprayers cooling the SO2 from the converter

Implication
 Overtime, the corroding plates would wear completely. The cooling water in the plates would
then be exposed to SO2, resulting in more weak-acid formation and corrosion of the other plates.
SO2 would the begin to escape through holes into the atmosphere.

Solution

 Replace mild steel plates with Stainless steel 304 plates

Procedure
- Uninstalling
 Drain cooling water
 Disconnect cooling water pipes
 Disconnect water spray lances
 Loosen and remove all panel 7R bolts
 Remove panel 7R with the aid of a chain-block to create room for moving panels 1R and 1L
 Weld lugs onto panel 1R (3 inside and 1 outside)
 Lower panel 1R using chain-blocks to the floor next to the PSC
 Lower panel 1L using chain-blocks to the floor next to the PSC
 Main Aisle Crane is used to lower it into the aisle to be picked by a fork lift

- Installing
 Lift stainless steel plates 1R and 1L using Main Aisle Crane onto PSC platform
 Weld lugs onto new plates
 Lift panels starting with 1L using chain-blocks and hold them in position
 Fix bolts and tighten
 Install cooling water pipes
 New plates have a different flange hole orientation; therefore, the old pipe flanges are cut, rotated
then re-welded
 Install panel 7R
 Install spray lances connect all other pipes

Key Learning points

 Stainless steel has better corrosion resistance properties than Mild Steel and is a better fit in
corrosive environments
 Type 304 stainless steel is a T 300 Series Stainless Steel austenitic. It has a minimum of 18%
chromium and 8% nickel, combined with a maximum of 0.08% carbon. It is defined as
a Chromium-Nickel austenitic alloy. It was selected for its rust and corrosion resistance and its
ability to work around temperatures of up to 870 degrees Celsius.
 316 Stainless Steel (Cr 16%, Ni 10%, Mo 2%) is another steel type that would have worked
especially due to its superior corrosion resistance (it is able to resist chloride attack). However, for
this application 304 achieves the same protection at a lower cost. Hence the selection.

Recommendations

 New stainless-steel plates must have flanges with similar hole orientation as existing pipes to
reduce the overall time taken to carry out this task.

3. Changing out a diesel pump on PSC3 valve rack

Problem
 There was nothing wrong with the pump. However, as a Precautionary measure, the diesel pump
is always changed during converter rehab. The pump is checked and refurbished if need be.

Implication
 The diesel pump not running would affect the holding and heat-up process of the converter. This
would impair the converter in a case of maintenance or shut down.
Procedure
 Isolate the pump manually (close valves on rack)
 Drain the pump by opening a valve
 Disconnect inlet and outlet pipes
 Undo pump holding down bolts
 Decouple pump and motor
 Remove pump
 Place new pump
 Couple pump and motor
 Connect pipes
 Tighten holding down bolts
 Energize pump

Key Learning points


 Holding burner and Heat-up burner functions and fuel/air feed system
 The holding burner helps keep the converters at temperatures above 800 degrees. This is done to
maintain the integrity of the refractory lining as well as save on time that would be used on burner
heat-up if the PSC was allowed to cool down frequently.

4. Task Changing tuyeres on PSC2


Problem
 Tuyere failed at pipe collar

Cause
 Shock from punching during operation on a weak weld

Implication
 Air would leak through crack, causing a drop in air pressure during tuyere blow. This would
cause molten metal to flow back into tuyere, damaging the tuyere assembly and resulting in an
inefficient converting process.

Procedure
 Obtain permit
 Isolate convertor
 Weld lug on the cover plates
 Remove tuyere cover plate
 Remove angle iron holding tuyere block
 Detach tuyere flexible hose
 Remove Y clamp
 Remove tuyere block
 Remove damaged tuyere pipe
 Install new tuyere pipe
 Install tuyere block
 Install Y clamp
 Install Angle iron holding tuyere block
 Attach tuyere flexible hose
 Install cover plates

Key Learning points

 Tuyere block assembly and operation


 Safety during tuyere installations is key due to hot environment and the gap between the PSC and
the platform

Recommendations
 Engage supplier to request reinforcement of weld, otherwise change supplier of tuyere pipes

5. Preparing tuyere drill


 After changing the refractory lining in the converter, the tuyere drill is used to drill holes in which
the tuyere pipe will be inserted. The hydraulic tuyere drill had to prepared for this.

5.1 Changing drill machine’s rotary motion hydraulic motor

 Motor was faulty- rotated at lower speed than other rotary motor.
 The Initial plan was to change motor
 However, it was observed that the rotary and axial feed motors were of different sizes
 Motors were then swapped.
 After swapping, the motor performed as expected.
 Minor oil leaks were observed on two of the four motors during the test

Recommendation

 The pumps must be refurbished to prevent any further loss of hydraulic oil.
5.2 Testing of tuyere drill

Task

Hydraulic system to be tested in preparation for tuyere hole drilling

Procedure
 Check hydraulic system for any visible faults
 Check hydraulic control panel
 Connect pipes to hydraulic motors
 Connect pipes to control panel
 Connect electric motor to power source
 Release Emergency stop on control panel
 Power hydraulic system
 Test rotational movement
 Test feed movement

Results
 The motors were able to rotate simultaneously and at similar speeds
 2 out of 4 motors were leaking through cracks

Recommendations

 Attend to all 4 motors; check them thoroughly and refurbish/replace them before the next drilling
job.

6. Ladle Inspection and thickness testing

 Inspections are carried out on ladles regularly to track wear on the ladles. The data collected helps
in planning for maintenance and ensure availability of the said equipment.
 If ladles are not inspected regularly, it would be hard to detect failure that occurs as a result of
operation such as wear and cracking. Failure during operation (molten metal leaks) would be
catastrophic to all surrounding personnel and equipment.

Procedure
 Obtain safe working permit
 Risk Assessment
 Prepare ultrasonic thickness tester
 Clean testing points
 Apply grease to tester probe
 Switch on the machine
 Adjust to suitable settings
 Place probe on cleaned points on ladle
 Record the thickness reading
 Take other measurements around the ladle as specified on the checklist

Key Learning points


 Ladles wear criteria and rehabilitation

Recommendations
 Ladle chains to be inspected more regularly using NDT
 Construct a concrete flat floor in main aisle for ladle dimensions’ measurement as current method
is inaccurate due to uneven floor.
7. Main Aisle Crane Main bale Inspection and PM

Problem
 Rivet was partially broken
 Main bale hook plates began separating
 Width deviated from 100mm initial to 140mm

Cause
 Constant heating and cooling from normal operation

Implication
 Cracks would propagate and finally cause the hook to separate into individual hooks

Procedure
 Obtain permit
 Clean hook – remove metal buildup with scraper
 Clean with grinder
 Weld using electrodes till both gaps are filled
 Grind further to clean weld
 Tuck rivet using electrode welding – to prevent it from falling out

Other Involvements

 Removing pneumatic cylinder from tuyere punch car


 Tuyere alignment
 Tuyere pressure testing
 Preventative maintenance (PM) of Cast wheel steam exhaust fan
 PM of Main Isle Cranes
 PM of Anode Furnace 1 draw bridge winches
 Crane trans-positioning
 PM and inspection of cooling water feed pump 4108
 PM and inspection of Hood winches for PSCs 1 and 2
 PM and inspection of PSC4 main drive
 PM and inspection of Fan FA4501
 Hydraulic system familiarization
 Aisle crane Main Bale rope inspection
 Changing oil rings on retractable vibrating feeder pneumatic cylinder
 Exhaust Fan4302 Pm and inspection
 Inspections on Sump pit pumps

Further learning points


 Developed an understanding of hydraulic systems, their symbolism, how to interpret hydraulic
circuits and the role they play in the secondary section.

Further Recommendations
 Train personnel in hydraulic systems
 Procure infrared thermometers for fitters- they have not been recording bearing and gearbox
temperatures during PMs

Maintenance strategies
The Secondary smelting section employ 3 types of maintenance: Preventative, Corrective and
Predictive. The type of maintenance deployed on any piece of equipment is dependent on the type of
equipment, its operation and the required availability of the equipment.

Preventative maintenance and visual inspections are practiced daily on different pieces of equipment
that are usually available e.g. pumps, fans, conveyors. Corrective maintenance is employed on units that
are usually running e.g. converters.

You might also like