Infrastructure Project Status

This document provides a monthly review of various highway projects including project name, coordinator, physical progress, project cost, payment details, number of non-conformance reports, and status of extensions of time. Key details include 26 total projects listed, physical progress ranging from 0% to 95.82%, total project costs over 1.5 billion rupees for some projects, payments received between 0 rupees to over 1 billion rupees, and some projects noting extensions of time or pending approvals/issues.

Uploaded by

GDRPL NHAI
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
53 views2 pages

Infrastructure Project Status

This document provides a monthly review of various highway projects including project name, coordinator, physical progress, project cost, payment details, number of non-conformance reports, and status of extensions of time. Key details include 26 total projects listed, physical progress ranging from 0% to 95.82%, total project costs over 1.5 billion rupees for some projects, payments received between 0 rupees to over 1 billion rupees, and some projects noting extensions of time or pending approvals/issues.

Uploaded by

GDRPL NHAI
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 2

January-2024

MONTHLY REVIEW SHEET


Payment
Sr. Length of Physical Project cost of EPC Till date payment Total nos. of Nos. of closed
Project Name Coordinator Sub - Coordinator recommend till date Consultancy Fees Status of EOT (if any) Critical pending Issues
No. Project (km) Progress (%) Contractor (In Cr.) received of AE NCR NCR
of EPC Contractor

1 Rampachodavaram- Koyyuru Viki Patel Hinal Patel 70.12 50.68% 304.60 1497427771.00 48232718 13385153

2 Madanapalle Ashish Phanse Hemal Prajapati 40.460 4.53% 332.11 1,66,65,79,919.00 5,16,57,502.00 1,47,57,977.30 1 1 - -

3 Tadipatri Viki Patel Krupali Rathod 51.119 36.68% 4,24,99,00,000.00 1,34,98,80,395.00 5,61,29,734.00 79,12,041.00 11 1 _

4 Mudigubba Ashish Phanse Hemal Prajapati 33.00 7.05% 270.00 1,40,95,39,724.00 4,87,07,600.00 1,30,59,271.00 Nill Nill - -

5 Papgini Viki Patel Hani Patel 1.81 65.93% 54.51 333804628.67 1,22,30,360 9065465.58 1 0 - -

6 Raychoti Viki Patel Hinal Patel 53.59 24.01% 241.68 2416899240.00 49263100 18536389 6 4
7 Madhugiri Viki Patel Hani Patel 51.5 22.25% 235.00 417489225.51 6,87,69,180 0 2 0 - -

8 Kadiri bypass Ashish Phanse Bindiya Jagtap

9 Andhra Pradesh ROB (LC - 119) Viki Patel Hani Patel 1.2 Yet not started - - 99,34,000 - - - - -

10 Arunachal pradesh Viki Patel Hani Patel 35.26 40.55% 297.00 1096740500.16 7,32,39,520 3,50,69,676.35 2 EoT up to 04.02.2024 -
0
11 Assam Sunetra dutta Jeel Soni 30 Completed. 192.31 21505200 + (EOT) 2,39,68,205.00 - - - -

12 Purnia (Bihar) Sunetra dutta Jeel Soni 49 89.98% 1905.00 5,46,16,750.00 1,95,26,060.00 - - - -

13 Mindhola River Bridge Vijayant singh Darshna Gosai 0.74 0% 197.88 (Bridge) 0.00 5,13,58,896.00 0 Nill Nill -
14 NHAI Surat (Abhava-Khajod) Vijayant singh Darshna Gosai 3.4 10.51% 42.67 4,08,76,228.00 91,77,043 (without Nill Nill Pending (EPC Contractor) Pending utility shifting work
1,02,81,343 (with EOT)
15 NHAI Surat (Budhiya-Gabheni) Vijayant singh Darshna Gosai 3.18 21.84% 39.07 8,01,03,745.00 EOT) Pending (EPC Contractor)
2 2
16 Una-kodinar - Package -4 Aliakbar Lokhandwala Rutvi Vora 40.98 95.82% 555.00 0 0
17 Una-kodinar - Package -5 Aliakbar Lokhandwala Rutvi Vora 40.95 86.44% 623.00 32 15
6,63,22,728.00 1,99,79,217.00
18 Una-kodinar - Package -6A Aliakbar Lokhandwala Rutvi Vora 7.6 76.86% 158.20

19 Una-kodinar - Package -6B Aliakbar Lokhandwala Rutvi Vora 33.18 74.22% 670.00

20 Aslali Aditya Pancholi Hani Patel 5.5 0.00% 41.46 0.00 75,05,036 36,31,281 - - approval pending -
(i)Issues with irrigation
21 Gadu porbandar Aditya Pancholi Bindiya Jagtap 1,50,94,877 1 1 Approved
division for approval of design
22 Pathankot Vijayant singh Mansi Shah 16.275 Yet not started - - 6,96,28,850.00 44,86,506.00 - - -

23 Dholera Krunal Patel Dhruv Patel 37.959 55.21% 942.67 Cr. 0.52 7,75,11,802.00 34 34 EOT Approved

24 Rajouri (J &K) Vijayant singh Mansi Shah 55.52 48.04 284.21 1302986338.00 7,71,01,840.00 4,29,89,149.00 4 4 -

25 Vijayapura - Sankeshwar Sunetra dutta Jeel Soni 79.77 50.03% 504.00 1066060528.00 3,91,35,850.00 1,43,99,084.00 29 21 - -
Approval of EOT-IV
26 Manipur-1A Krunal Patel Krupali Rathod 22.34 39.01% 1,51,14,70,000.00 529652113.70 3 3
pending from Authority
Approval of EOT-III
27 Manipur-1B Krunal Patel Krupali Rathod 17.66 73.34% 1,28,54,55,000.00 90,54,11,661.65 10,79,97,974.86 7,87,46,474.11 5 4
pending from Authority
Approval of EOT-III
29 Manipur-2B Krunal Patel Krupali Rathod 18.16 97.02% 1,45,86,85,000.00 1388313186.19 0 0
pending from Authority
Approval of EOT-IV
30 Nagaland -PKG-1 Krunal Patel Ashutosh Tripathi 21.72 94.95% 193.79 1,82,21,16,689.10 18 18 Tests on Completion (Sch-K)
awaited from Authority
31 Nagaland -PKG-2 Krunal Patel Ashutosh Tripathi 21.90 Terminated 202.00 75,17,96,490.95 10,77,46,208.00 10,45,31,755.00 - - N.A
A.E Extension of Time approval
Contractor submission due from authority
32 Nagaland -PKG-3 Krunal Patel Ashutosh Tripathi 22.70 73.27% 206.26 1,44,97,75,107.00 12 6
pending
33 Jalore - Rajasthan Vijayant singh Mansi Shah 41.115 31.20% 277.48 846261382.00 6,66,53,082.34 1,90,36,621.00 24 5

34 Barmer- Rajasthan ( Road ) Vijayant singh Mansi Shah 68.938 78.71% 173.05 1362523715.00 4 -

35 Barmer- Rajasthan ( ROB -LC-328-Barmer) Vijayant singh Mansi Shah 1.86 78.71% 39.91 284707410.00 7,17,07,941.00 1,34,11,318.00 1 -

36 Barmer- Rajasthan ( ROB -Jalore ) Vijayant singh Mansi Shah 2.044 76.03% 55.11 413001185.00 - -

37 Nathdhwara Dhaval Mistry Hemal Prajapati 88.8 0.39 411.04 Nill 6,97,62,205.00 Nill Nill Nill Nill
January-2024
MONTHLY REVIEW SHEET
Payment
Sr. Length of Physical Project cost of EPC Till date payment Total nos. of Nos. of closed
Project Name Coordinator Sub - Coordinator recommend till date Consultancy Fees Status of EOT (if any) Critical pending Issues
No. Project (km) Progress (%) Contractor (In Cr.) received of AE NCR NCR
of EPC Contractor