Contract Monitoring Checklist
It is the responsibility of each agency to ensure all contractual obligations are met and that
contract monitoring is documented. This appendix serves as a tool to assist the agency during that
process. Each contract is unique and the agency may add to this tool as required to meet its
particular circumstance.
Item # Contract Monitoring Agency Documentation Yes/No
1. Contract:
Contract number/ effective Contract #: _______________________________
date/contractor name/purchase order Contract Effective Date: _____________________
number.
Contractor Name:__________________________
Contract Renewal Options? Yes / No
Purchase Order #: _________________________
2. Agency Contract Administrator: Name: __________________________________
Name/ title/contact information of the
Title:____________________________________
person responsible for ensuring all
contractual obligations are met. Phone #: ________________________________
E-mail: _________________________________
3. Monitoring Procedures/Methodology: Agency has a written contract monitoring Yes/No
Written documented contract procedures?
monitoring procedures/methodology.
4. Delivery: Contract specified delivery date:
Delivery date specified in the Date agency received item(s): Full/
contract/date of delivery. Full or Partial Delivery? Partial
Delivery in Accordance with Contract? Yes/No
5. Acceptance: Items delivered were accepted (met contract
Item(s) delivered were in accordance specifications)? Yes/No
with contract specifications. Latent material defects? Yes/No
6. Warranty: Warranty work was required? Yes/No
Item(s) warranted in accordance with If so, warranty was performed in accordance with
contract. the contract? Yes/No
7. Invoice: Invoice matched purchase order price? Yes/No
Invoice price mirrored purchase order
price. If no, invoiced more or less than PO? More/Less
8. Default of Contract: Was the contractor held in default? Yes/No
Was contractor held in default of Was the contractor debarred? Yes/No
contract and/or debarred. Was a vendor complaint form provided to P&C? Yes/No
Additional Agency Monitoring Requirements (example)
9. Reports: Contractor reports were provided by the required
All reports required by the contract due date? Yes/No
were provided Contractor reports were accurate (when initially
timely/accurately/prescribed manner. submitted)? Yes/No
Contractor reports were in the prescribed Yes/No
manner?
Contract Monitoring performed by (print and sign): __________________________________
________________________________________
Version 2 3/1/2013