INSPECTION AND TEST PLAN
Contractor ACC
Package No.
Description of Work Plaster Works
Location
Date :
Project Test Method Inspection Parties / Type of Inspection
Work phase (description of Codes and
NO Specificat / Type of Acceptance Criteria Frequency (Internal Checking ,Witness or Hold Point) Remarks
Inspection / Testing) Standards
ion Ref. Inspection CONTRACTOR
CONSL RA
SC C
1 Submittal
Approval of Materials & Plaster
1.1 Submittal Conforms to specification/Contract Conditions N.A H H
Accessories and shop drawings
1.2 MATERIAL DELIVERIES specs specs M.I.R Conforms to specification/Contract Conditions ALL DELIVERIES H H
2 Inspection
After application of spatter dash coat surface must
2.1 SPATTER-DASH COAT specs specs N.A be rough to generate bonding agent for plaster Prior to work progress H W
coats
2.2 Curing specs specs N.A Spater dash coat will be sprayed with water 5 days Prior to work progress H W
First fix ofMEP works have been executed
2.3 MEP Works specs specs N.A inspection and approved according to the approval Prior to work progress H H
shop drawing
Metal lath is fixed very well between concrete and
Surface Preparation, Metal Lath block,also over MEP works,Surface must be
fixation ,Dots & Guide lines washed by water to remove any dust,all exis offset
2.4 specs specs I.R Prior to work progress H H
(Including all accessories) must be cleared and protected,all dots shall be
for walls and ceiling straight and level , all internal dimension are
according to approval shop drawings
All surface shall be true and flat ,straight ,level and
plumb ,permissible deviation of surface shall be
2.5 Final Plaster after filling specs specs I.R Prior to work progress H H
2mm when measured from underside of a 3m
straight edge
All plaster coats made of mortar containing cement
shall be kept in aconstant moistened condition by
2.6 Curing specs specs N.A Prior to work progress H H
being sprayed as often as required for five (5)
days.
Testing
All plaster coats made of mortar containing cement
compressive strength for Morar shall be kept in aconstant moistened condition by
specs specs N.A Prior to work progress W W
cubics being sprayed as often as required for five (5)
days.
DISTRIBUTION:
ABBREVIATIONS : VERIFICATION CODES
SC - Subcontractor I - Inspection W - Witness Point
CONSTRUCTION MANAGER CONSULTANT OTHERS C - Contractor C - Internal Checking Point H - Hold Point
4.33 Inspection and Test Plan : Inspection and Test Plan
RA - Regulatory AuthorityR - Review T - Test