Samana Miami-1 Block Work 26-Jan-24
Activity ID Activity Name Planned Start Planned Finish Original Duration Actual Start Actual Finish
(New EPS) 18-Jan-24 30-Mar-24 63d
Masonry & Plaster 18-Jan-24 30-Mar-24 63d
Masonry & Plaster 18-Jan-24 30-Mar-24 63d
Block Work 18-Jan-24 27-Mar-24 60d
Ground to Podium Floor 18-Jan-24 07-Feb-24 18d
A1000 Car Park 18-Jan-24 20-Jan-24 3d
A1010 Substation 25-Jan-24 27-Jan-24 3d
A1020 LV Room 29-Jan-24 31-Jan-24 3d
A1030 Retail Shop 01-Feb-24 03-Feb-24 3d
A1040 Enterance Lobby 05-Feb-24 07-Feb-24 3d
Podium to 1st Floor 08-Feb-24 14-Feb-24 6d
A1050 Part-1 08-Feb-24 10-Feb-24 3d
A1060 Part-2 12-Feb-24 14-Feb-24 3d
1st Floor to 2nd Floor 15-Feb-24 21-Feb-24 6d
A1070 Part-1 15-Feb-24 17-Feb-24 3d
A1080 Part-2 19-Feb-24 21-Feb-24 3d
2nd Floor to 3rd Floor 22-Feb-24 28-Feb-24 6d
A1090 Part-1 22-Feb-24 24-Feb-24 3d
A1100 Part-2 26-Feb-24 28-Feb-24 3d
3rd Floor to 4th Floor 29-Feb-24 06-Mar-24 6d
A1110 Part-1 29-Feb-24 02-Mar-24 3d
A1120 Part-2 04-Mar-24 06-Mar-24 3d
4th Floor to 5th Floor 07-Mar-24 13-Mar-24 6d
A1130 Part-1 07-Mar-24 09-Mar-24 3d
A1140 Part-2 11-Mar-24 13-Mar-24 3d
5th Floor to 6th Floor 14-Mar-24 20-Mar-24 6d
A1150 Part-1 14-Mar-24 16-Mar-24 3d
A1160 Part-2 18-Mar-24 20-Mar-24 3d
6th Floor to Roof 21-Mar-24 27-Mar-24 6d
A1170 Part-1 21-Mar-24 23-Mar-24 3d
A1180 Part-2 25-Mar-24 27-Mar-24 3d
Plaster 25-Jan-24 30-Mar-24 57d
Client: Samana SIA Holding Consultant: AREC Main Contractor: Reliant Contracting LLC
Sub: Aroos Alsaeed Plaster & Cladding Works L.L.C.