PILED RAFT FOUNDATIONS –
CHARACTERISTICS, DESIGN AND
APPLICATIONS
Harry G. Poulos
Tetra Tech Coffey, Australia
Lecture to GEG
20 September 2023
OUTLINE
• The mechanics of rafts with piles
• Design concepts & issues
• Overall load-settlement behaviour
• Design for localized behavior under columns
• Parameter assessment
• Examples of applications to tall buildings
FOUNDATION OPTIONS
DESIGN PHILOSOPHY
• Different from normal piles
• Share load between raft
and piles
• Raft provides extra load
capacity for piles
• Focus more on stiffness
than capacity
ANOTHER PERSPECTIVE
• The piled raft foundation can be considered as a pile-enhanced raft.
• The piles act to reduce the net load on the raft.
• If the pile capacity has not been fully mobilized, then the pile acts as a
spring that carries some of the column load and so reduces the load that
the raft has to carry.
• Even if a pile has reached its full capacity, it provides a negative (upward)
load that counteracts the downward column load.
• Thus, a piled raft (or a pile-enhanced raft) is able to be very effective in
reducing the raft thickness requirements while increasing the foundation
stiffness at the same time.
CIRCUMSTANCES FAVOURABLE FOR PILED RAFTS
• Where the raft can provide a
reasonable amount of stiffness and
load capacity, e.g.
Relatively stiff clay profiles
Relatively dense sands, weak
rocks
• Where soil movements due to
external causes do not occur
6
CIRCUMSTANCES UNFAVOURABLE FOR
PILED RAFTS
• Soft clays near the surface
• Loose sands near the surface
• Compressible layers at depth
• Where consolidation settlements may occur
Soil may move away from raft
• Where swelling movements may occur
Soil may impose additional uplift loading on piles
EARLY MODEL TEST DATA (Whitaker, 1957)
Optimum number
Optimum number
THE MECHANICS OF RAFTS + PILES
Ultimate geotechnical capacity:
Depends on mechanism of failure; σraft
• n x single pile capacity + net raft capacity for widely spaced piles
• Block capacity + external raft area capacity for closely-spaced piles
With more widely-spaced piles, there are two advantages: z
• Greater likelihood of “single pile” failure mechanism;
• Increased single pile capacity due to greater vertical stress
from raft contact pressure
fs = Ks (σv’ + σraft). tan(δ)
THE MECHANICS OF RAFTS + PILES
THE MECHANICS OF RAFTS + PILES
Settlement:
Depends on:
• Applied load
• Pile dimensions
• Ground stiffness and profile
• Group dimensions and number of piles
• Raft dimensions and raft stiffness
• Pile-soil-raft interactions (4 components)
Pile-soil-pile
Raft-soil-raft
Raft-soil-pile
Pile-soil-raft
DESIGN ISSUES
• Ultimate load capacity - vertical, lateral, moment
loading
• Maximum settlement
• Differential settlement
• Raft moments & shears
• Pile loads and moments
SETTLEMENT IS THE CRITICAL FACTOR FOR
LARGE FOUNDATIONS
STAGES OF DESIGN
Preliminary design –
• number of piles for capacity & settlement requirements
• assess pile locations for local requirements
Detailed design - –
• refine pile locations
• optimize raft thickness
• obtain detailed settlement, moment and pile load information
PRELIMINARY DESIGN - ULTIMATE LOAD CAPACITY
• Lesser of:
–raft plus individual piles
–block of piles + soil, plus raft outside block perimeter
• Need to consider effects of soil layering on raft & pile
capacity
NOTE: Raft pressures may enhance pile capacity
PRELIMINARY DESIGN - OVERALL LOAD -
SETTLEMENT ESTIMATION
• Estimate average settlement versus number of piles -
can use simple hand or computer methods. Allow for
cases where piles are fully utilized.
• Randolph's expressions give useful first estimate of
load sharing between raft & piles.
• Can thus obtain estimate of required number of piles
for specified ultimate capacity & settlement criteria.
SIMPLIFIED METHODS OF ANALYSIS
Poulos-Davis-Randolph (PDR) method - tri-linear
load-settlement curve
Requires estimates of:
• pile group stiffness
• raft stiffness
• ultimate pile group & raft capacities
• raft-pile interaction factor
PILED RAFT UNIT (Randolph, 1994)
rc
Young' s Modulus E s
E so E sav E sl E sb
Soil L
Bearing
d= 2ro Depth
stratum
Fig.2 Simplified representation of pile-raft unit
Stiffness of piled raft depends on:
- Raft stiffness
- Pile group stiffness
- Interaction between piles and raft
POULOS-DAVIS-RANDOLPH (PDR) METHOD
Construct a Tri-Linear Load-Settlement Curve
Pu
B
Load
P1 A
Pile + raft
elastic
Pile capacity fully utilised, Pile + raft ultimate
raft elastic capacity reached
Settlement
Fig.3 Simplified load- settlement curve for preliminary analysis
POULOS-DAVIS-RANDOLPH (PDR) METHOD
• Piled raft stiffness:
Kpr = [Kp + Kr.(1-2αcp)]/(1-αcp2.Kr/Kp) Kp = pile group stiffness
Kr = raft stiffness
• Pile-raft interaction factor: αcp = pile-raft interaction factor
rc = raft area divided by number of piles
αcp = 1-ln(rc/r0)/ζ r0 = pile radius
ζ = ln(rm/r0)
rm = “magic radius” – see Randolph (1994)
• Proportion of load on Raft: Pup= ultimate capacity of piles
Pu = Pup + Pur
X = Kr(1- αcp)/[Kp+Kr.(1-2αcp )] Pur = ultimate capacity of raft
• Load at which pile capacity mobilized:
P1 = Pup/(1-X)
TYPICAL RESULTS FROM PRELIMINARY
ANALYSIS
40 80
Ultimate Load Capacity (MN)
Total Load = 12 MN
Central Settlement (mm)
30 60
20 40
10 20
0 0
0 5 10 15 20 25 0 5 10 15 20 25
Number of Piles Number of Piles
(a) Ultimate Load Capacity (b) Settlement
Fig. 10 Effect of number of piles on ultimate load capacity and settlement
Increasing the number of piles beyond a certain point has no benefits
ESTIMATING DIFFERENTIAL SETTLEMENTS
Can make use of approximations of Randolph (1994).
∆S/Sav = function of R = { n s / L }1/2
= f.R/4 for R <4
=f for R>4
f= 0.3 for corner to mid-side, and 0.5 for centre to
corner
DESIGN FOR LOCALIZED BEHAVIOR
When is a pile required under a column?
When:
• Maximum moment exceeds allowable
• Maximum shear exceeds allowable (punching shear)
• Maximum contact pressure exceeds allowable
bearing capacity of soil
• Local settlement exceeds allowable value
COLUMN LOAD ON RAFT
2c
x
t Raft E r , νr
Layer 1 E s1 , ν s
Layer 2 E s2 , ν s
Layer 3 E s3 , ν s
Figure 5 Individual Column Load-Raft on Layered Soil Profile
SOIL PROFILE FOR LOCALIZED DESIGN
• May be different to that for overall load-settlement estimate
• Consider average parameters within effective depth = 3a
a = characteristic length of raft
= function of raft thickness & modulus, & soil modulus
a = t.{Er.(1-νs2)/6.Es.(1-νr2)]1/3
where t = raft thickness, ν = Poisson’s ratio of soil, ν = Poisson’s ratio of raft, E = raft modulus,
E = soil modulus. s r r
s
MAXIMUM MOMENT CRITERION
Use solutions of Selvadurai (1979) to develop criterion.
Max. column load without pile is:
Pc1 = Md / Ax or Md / Bx
0.2
where Md = design moment
Ax , Bx = moment factors 0.1
B
Moment factors A, B
0
x
P
-0.1 O
A
Load
location
-0.2
0 0.05 0.10 0.15
x/a
Fig.6 Moment factors A & B for circular column
OTHER COLUMN LOAD CRITERIA
The other critical column loads:
• Pc2 for shear
• Pc3 for local bearing pressure;
• Pc4 for local settlement
Can be obtained similarly from Selvadurai’s elastic
solutions. Refer to Poulos (2001).
Date A
27
presentation
to <insert in
PILE REQUIREMENTS FOR A COLUMN LOCATION
A pile is required if the column load exceeds any of the
critical column loads, Pc1 to Pc4.
• For moment, shear or contact pressure requirement, the pile is
designed to provide deficiency in load capacity.
• For settlement, pile is designed to provide the required
additional stiffness.
CRITICAL COLUMN LOADS
Max. column load without a pile :
• increases as raft thickness increases
• increases as ultimate bearing pressure increases
• increases as soil modulus increases
Raft thickness is very important for
“local” design.
DETAILED DESIGN - REQUIREMENTS
• Analysis which can account for interaction between
piles & raft
• Ability to consider practical soil profiles
• Nonlinear soil - raft & soil - pile responses
• Non - uniform loadings
• Different pile types & sizes at various locations
below raft.
GASP & GARP are able to take the above factors into
account.
APPROXIMATE COMPUTER METHODS
Strip on Springs - GASP
• Strip sections of a raft analyzed
• Piles are modelled as non-linear interacting
springs
Plate on Springs - GARP
• Piles as for GASP
• Raft as elastic plate
ELPLA – Commercially available via GEOTEC SOFTWARE
GARP vs PDR METHOD
30 30
(a) 0.5 m Raft + 3 Piles (b) 0.5 m Raft + 9 Piles
Group Load (MN)
Group Load (MN)
20 20
10 10
0 0
0 20 40 60 80 100 120 0 20 40 60 80 100 120
Central Settlement (mm) Central Settlement (mm)
40
(c) 0.5 m Raft + 15 Piles
Group Load (MN)
30
GARP5
20 Approximate PDR method
10
0
0 20 40 60 80 100 120
Central Settlement (mm)
Fig. 9 Comparison between GARP and approximate analysis
MORE RIGOROUS COMPUTER METHODS
Two - Dimensional analyses:
• FLAC
• PLAXIS2D
• RS2
Full Three-Dimensional Analyses:
• FLAC 3D
• PLAXIS3D
• RS3
EXAMPLE PROBLEM APPLICATION
y
A A 1m
P1 P2 P1
2
A A
P1 P2 P1 x Bearing capacity of raft = 0.3 MPa
2
A A Load capacity of each pile = 0.873 MN (Compression)
P1 P2 P1 1 = 0.786 MN (Tension)
1m 2 2 2 2 1
E p = E r = 30000 MPa
ν p = νr = 0.2 P P2
1 P1
t r = 0.5 m
E = 20 MPa
l = 10 m
ν = 0.3
H = 20 m
d = 0.5 m
s=2 2 2 2m
Fig. 11 Hypothetical example used to compare results of various methods of piled raft analysis
COMPARISON BETWEEN PILED RAFT ANALYSES
20
2 3 4
1
5
15
Total load (MN)
10
1 P D R m e th o d
2 GARP5
5 3 GASP
4 F L A C 3-D
5 F L A C 2-D
0
0 20 40 60 80 10 0 12 0 14 0
C en tra l S e ttle m e n t (m m )
35
EFFECT OF IGNORING INTERACTIONS -
FOUNDATION STIFFNESS (MN/m)
2000
1800
1600
1400
1200
WITH INTERN.
1000
GROUP ONLY
800
NO INTERN.
600
400
200
0
9 PILES 15 PILES
Inclusion of interaction effects is
essential!
2D analysis is unreliable
SOME OTHER ISSUES
Lateral Loading:
Raft tends to take a larger proportion of the lateral load than for
vertical load. Full 3D analysis needs to be used at final design
stage.
Hamada et al (2015):
αp = proportion of load carried by piles
Kgp=n*Kp1
n = no. of piles
Kp1 = lateral stiffness of single pile
Kr = raft stiffness = 2πGr/(2-ν)
r = equivalent radius of raft
β = (Es/4.EI)0.25
SOME OTHER ISSUES
Effect of Basement Walls:
They take some of the lateral load and reduce the bending
moments in the pile. Can be taken into account during the final
design stage.
Disconnected Piles:
• Piles act as ground reinforcement. OK for vertical load;
• Not ideal for lateral load
GEOTECHNICAL PARAMETER ASSESSMENT
Require:
• raft bearing capacity
• pile capacity
• soil stiffness for raft
• soil stiffness for piles – vertical & lateral.
For preliminary design, can use correlations with
SPT or CPT for soils, or with UCS for rocks.
For final design, large scale pile load tests are highly
desirable
CORRELATIONS WITH SPT
Decourt (1989, 1995):
Raft capacity: pu = K1 Nr kPa
Pile shaft : fs = a( 2.8Ns + 10) kPa
Pile base: fb = K2 Nb kPa
Soil modulus (raft): Es = 2Nr MPa
Soil modulus (pile): Es = 3N MPa
CORRELATIONS WITH UCS
(Conservative)
Raft capacity: pu = 1.5(UCS)
Pile shaft : fs = 0.3(UCS)0.5 MPa
Pile base: fb = 4.8 (UCS)0.5 MPa
Rock modulus (raft): Es = 100(UCS)
Rock modulus (pile): Es = 150(UCS)
MEASURES TO REDUCE RISKS
• Independent peer review of ground investigation report
• Independent peer review of foundation design
• Make use of relevant precedent information
• Independent supervision of foundation construction
• Foundation element (pile/barrette) testing
• Monitor settlements during construction
Compare measured versus predicted performance
Treat these measures as INSURANCE INVESTMENTS
EXAMPLES OF PILED RAFT DESIGN
• Artique – Gold Coast Australia
• Burj Khalifa – Dubai, UAE
• Convention Centre – Doha, Qatar
• Diamond Tower, Jeddah, KSA
• Incheon Tower – Incheon, South Korea
• Examples of excessive piles & foundation economy – Italy, Germany
EACH OF THESE CASES HAS PROVIDED LESSONS.
GOLD COAST PROJECT - ARTIQUE
•A 28 storey building on the
Gold Coast, Australia
•Structural Engineer designed a
fully piled to rock foundation
system
•Piling contractor engaged
Coffey to assess feasibility of
piled raft
•Based on results of feasibility,
piling contractor engaged
Coffey to optimize piled raft
design
ORIGINAL DESIGN
136 piles
founded
on rock
Slab
0.7m
thick
Contiguous bored pile wall Shear joint between core and podium
GEOTECHNICAL MODEL Es pu Es
Av. Su fs fb
DESCRIPTION (RAFT) (RAFT) (PILES)
SPT kPa kPa MPa
MPa MPa MPa
0
ASSUMED
BASE OF RAFT
-5
SAND
60 - 90 5.4 120 100 9.9
D-VD
-10
PEATY CLAY
(SOME SAND) 10 80 8 0.5 20 22 0.7
-15
F-St
SAND
60 - 90 5.4 120 100 9.9
D
RL (m)
-20
SANDY CLAY (H)
/CLAYEY SAND 14 250 25 1.5 40 60 2.0
-25 MD
-30 SAND WITH
SOME GRAVEL 25 - 37.5 2.25 50 48 4.1
MD
-35 SANDY GRAVEL 100 - 150 9.0 200 100 10.0
METASILTSTONE
- - 2000 - 2000 - 10.0
SW
-40
FEASIBILITY RESULTS
• Indicated that a raft foundation alone would have a
factor of safety of approximately 10 for ultimate
loading
• Settlements would govern. Estimated to be of the
order of 35mm to 60mm
• The number of piles would be of the order of 140 –
as per the foundation design supplied by contractor.
However, piles only 18m long not 35m
Initial Assessment
• Goal was to assess serviceability criteria and opportunity
for design optimization
• Criteria set by structural engineer:
Maximum total displacement of building column to be
less than 50mm
Maximum differential displacement between adjacent
columns of 1/400
Method of Analysis
• Undertaken using GARP 8 program
• Assesses deflections, shear forces and moments in raft and pile
loads
• Final foundation system was a 0.8m thick raft with 136 piles.
CFA piles were 18m long, 0.7m diameter with a maximum
capacity of 4.2MN
Results of Initial Assessment
136 piles
Maximum raft
settlement of
36mm
Maximum
differential
settlement of
10mm (1/400)
OUTCOMES
• Number of piles reduced by 10% (13 piles)
• Pile length reduced from 35m to 18m
• Total pile length reduced by 2767m
(52% savings)
• Settlement criteria (both total and differential)
satisfied
BURJ DUBAI (KHALIFA)TOWER
Main challenges:
• World’s tallest building
• Foundation capacity for piles in
carbonate soils/rocks
• Concerns re cyclic loading of
piles
• High-rise to low-rise differential
settlements
SITE CHARACTERIZATION
• 30 boreholes
• SPT
• 60 PMT tests in 5 boreholes
• 6 standpipe piezometers
• Geophysics – cross-hole tomography
SIMPLIFIED PROFILE
4 Silty Sand
6 Calcarenite
17 Calcareous Sandstone Base of Tower Raft
4.5 Gypsiferous Sandstone
40 Conglomeritic Calcisiltite
Base of Tower Piles
22.5 Calcareous/Conglomeritic
>47 Claystone/Siltstone
INITIAL PILE DESIGN
• Tower:
196 piles, 1.5m diameter, 47.5m long
• Podium:
750 0.9m diameter piles, 30m long
• Raft: Tower pile layout
3.7m thick (tower)
Learnings from Emirates Towers design were used in the design.
Initial Tower Settlement Predictions
Analysis Settlement mm
(Flexible cap)
HYDER - REPUTE 66
HYDER - ABAQUS 72
COFFEY – FLAC 73
(axisymmetric)
COFFEY - PIGS 74
Subsequent Equivalent pier check (Coffey): 73 mm
LOAD TEST PROGRAM
• 3 static compression tests (1.5m dia.)
Various toe levels (35-55m long)
• 1 static compression test (0.9m dia.)
Shaft grouted
• 1 cyclic compression test (0.9m dia.)
• 1 static tension test (0.9m dia.)
• 1 lateral load test
• For all tests, results exceeded expectations
MEASURED SETTLEMENT CONTOURS –
FEBRUARY 2008
MEASURED TIME-SETTLEMENT – WING C
Predicted approx 75- Settlement in Wing C
27-Jun-06
80mm Distance along wing cross-section (m) 16-Jul-06
16-Aug-06
0 20 40 60 80
18-Sep-06
0
To February 2008 43mm -10
16-Oct-06
14-Nov-06
measured for 80% of dead -20
19-Dec-06
load
16-Jan-07
Settlement (mm)
-30 19-Feb-07
18-Mar-07
-40
12-Jul-07
Estimated 50 to 55mm -50 14-Aug-07
17-Sep-07
final settlement -60
17-Oct-07
-70 14-Nov-07
17-Dec-07
-80
Within design tolerances -90
18-Feb-08
design
CONSTRUCTION PROGRESS
Early 2006 Early 2007 Grand opening, 4 January 2010
EXAMPLE – TOWER IN DOHA
525 piles
d=1.0, 1.2, 1.5m
4 different lengths
Raft 4.0m thick, with local
thickening in core areas
EXAMPLE – TOWER IN DOHA:
Effect of Interaction Assumptions (GARP
Analyses)
Run No. Details
Q1 Normal analysis – all interactions
included
Q2 Zero pile-pile interactions, but raft-raft,
pile-raft and raft-pile interactions
included
Q3 Zero pile-pile, pile-raft and raft-pile
interactions; only raft-raft interaction
accounted for
EXAMPLE – TOWER IN DOHA:
Effect of Interaction Assumptions
90
Maximum settlement mm
80 0.002
Maximum Rotation in x-
70
60 0.0015
direction rad
50
40 0.001
30
20 0.0005
10
0 0
Q1 Q2 Q3 Q1 Q2 Q3
Case Case
Maximum Settlement Maximum Rotation
50
70
Maximum Pile Load MN
Maximum Moment Mx
60 40
50
40 30
MNm
30 20
20
10 10
0
0
Q1 Q2 Q3
Q1 Q2 Q3
Case
Case
Maximum Raft Moment Maximum Pile Load
IGNORING THE PRESENCE OF THE RAFT
Doha Tower Case:
Value Allowing for raft Ignoring the raft
Max settlement mm 81.8 174.6
Min settlement mm 7.6 7.2
Max x-rotation rad 0.00176 0.01260
Max x-moment MNm 66.3 70.3
Min x-moment MNm -46.2 -45.0
Max pile load MN 34.4 67.2
% load on raft 24.6 0
DIAMOND TOWER, JEDDAH, KSA
KEY CHALLENGES
• Karstic limestone & random cavities
• Potential for building tilt
GEOTECHNICAL PROFILE
FOUNDATION DETAILS FOR TOWER
• 5.5m thick raft
• 145 bored piles 1.5 m in diameter
• Pile length = 40m
• Total vertical load for serviceability = 2859 MN
PILE LAYOUT
RANDOMLY GENERATED CAVITIES
Young’s Modulus Values from Various Sources
EFFECTS OF RANDOMLY LOCATED CAVITIES
• Effect of a single cavity was small extra 2-3mm
settlement (55-58mm settlement)
• Effect of multiple cavities: computed settlements
varied from 65 to 74mm, depending on location
• Non-symmetrical settlement pattern
EXAMPLE OF EFFECTS OF RANDOMLY LOCATED CAVITIES
EFFECTS ON RAFT MOMENTS
No Cavities With cavities
Largest increase is about 13%
OBSERVATIONS FROM ANALYSES
• Cavities cause some increases in settlement
• A single cavity causes relatively small settlement
increase
• Settlement pattern can be non-symmetrical
• Effects are generally not as great as might be feared –
redundant foundation system
EXAMPLE – INCHEON TOWER, S. KOREA
172 bored piles
d=2.5m
Typical pile length = 50m
Raft 5.5m thick
KEY CHALLENGES
• Reclaimed land
• Complex geology
• 600m tall building
• Limited tolerance to differential settlements
SITE CONDITIONS
GEOTECHNICAL CONDITIONS
8 separate soil
profiles modeled
within building
footprint
Contours of depth to bedrock
TYPICAL GEOTECHNICAL MODEL
Strata Ev Eh (MPa) fs fb
(MPa) (kPa) (MPa)
UMD 5 -11 29 - 48 -
7 - 15
LMD 30 21 50 -
Weathered Soil 60 42 75 -
Weathered Rock 200 140 500 -
Soft Rock (above EL-50m) 300 210 750 12
Soft Rock (below EL-
50m) 1700 1190 750 12
Ev = Vertical Modulus
Eh = Horizontal Modulus
fs = Ultimate shaft friction
fb = Ultimate end bearing
FOUNDATION SYSTEM
• Piles: 172
• Pile size : 2.5m dia.
• Founded minimum 2 pile diameters into soft rock or
below EL-50m
• Mat Thickness : 5.5m
COMPARISON OF COMPUTED
SETTLEMENTS
• Preliminary (equivalent pier): 75mm (av.)
• Detailed Design (GARP): 67mm (max.)
• Final Design Check (PLAXIS 3D): 56mm (max.)
EXAMPLE – INCHEON TOWER, S. KOREA
Quantity Location Rigid Raft Flexible Raft
Pile Load (MN) Centre Pile 24 49
Centre Edge Pile 65 33
Corner Pile 85 43
Pile Stiffness (MN/m) Centre Pile 511 726
Centre Edge Pile 1418 932
Corner Pile 1604 1292
Raft Settlement (mm) Maximum 52 67
Minimum 26 28
FINAL DESIGN CHECK – 3D FE
ANALYSIS
FINAL DESIGN CHECK – 3D FE ANALYSIS
Visualization
No basement contact With basement contact
O-CELL TESTING
Date A presentation to <insert in footer> 86
PILE LOAD TEST RESULTS
• Design parameters are
conservative
• Scope exists for foundation
economy (if project resumes)
EXAMPLE OF EXCESSIVE PILES
(Mandolini et al, 2005). Twin towers in Naples
Total 637 piles
(L=20m, d=0.6m)
Designed with no
allowance for the
raft
EXAMPLE OF EXCESSIVE PILES
(Mandolini et al, 2005)
Computed versus measured settlements-excellent agreement
EXAMPLE OF EXCESSIVE PILES
(Mandolini et al, 2005)
Foundation system now analyzed with only 318 piles
Allowance made for raft
EXAMPLE OF EXCESSIVE PILES
(Mandolini et al, 2005)
• Computed settlement with 318 piles = 33mm
• Compared with 30mm for 637 piles!!
• Also, maximum differential settlement reduced by 10%
• Total piling length actually used = 12700m
• Total length that should have been used = 6300m
• So, would have very similar foundation behaviour with
50% savings on piling.
• Therefore, greatly enhanced sustainability.
EXAMPLE OF COST SAVINGS ON PILES
(Katzenbach, 2011)
Fully piled foundation:
•316 piles, 30m long: US$7.4M
Piled raft foundation:
•64 piles, av. 30m long: US$1.5M
•Savings: US$5.9M
EXAMPLE OF COST SAVINGS ON PILES
(Katzenbach et al (2016)
Mirax Tower A, Kiev, Ukraine
Fully piled foundation:
•120 barrettes, 40m long: US$5.8M
Piled raft foundation:
•64 piles, av. 33m long: US$2.5M
•Savings: US$3.3M
SOME GENERAL OBSERVATIONS ON PILED RAFTS
• Settlement decreases as number of piles increases
• Major reduction in settlement can occur for relatively small
number of piles
• Increasing number of piles beyond a certain point is ineffective
• Piles may reduce bending moments in raft if carefully located
• Raft thickness affects differential settlements much more than
total settlements
• Foundation performance may be improved by using piles of
varying length - shorter piles below lighter loads, longer for
heavy loads
CONCLUSIONS
• Piled rafts can provide considerable foundation
economy
• Also increased sustainability
• Considerable experience of successful application
• Combined raft-pile interaction can increase the pile
capacity – “get something for nothing”
BIBLIOGRAPHY
Katzenbach, R.; Leppla, S.; Choudhury, D. (2016). Foundation systems for high-rise structures. CRC
Press Taylor & Francis Group, New York, USA .
Mandolini, A., Russo, G. and Viggiani, C.(2005). “Pile foundations: experimental investigations,
analysis and design”. Proc. 16th Int. Conf. Soil Mechs. Geot. Eng., Osaka, IOS Press, 177-213.
Poulos, H.G. (2001). “Piled Raft Foundations – Design and Applications”. Geotechnique, 51(2): 95-
113.
Poulos, H.G. (2017). “Tall Building Foundation Design”. CRC Press, Boca Raton, Florida.
Poulos, H.G. (2021). “Practical approach for piled raft stiffness estimation”. Australian
Geomechanics, 56 (3): 57-69.
Randolph, M.F. (1994). “Design methods for pile groups and piled rafts”. State of the Art Rep.,
Proc., 13th ICSMFE, New Delhi, Vol. 5, 61–82.
Selvadurai, P. (1979). “Elastic analysis of soil-foundation interaction”. In Developments in
Geotechnical Engineering, Vol. 17, Elsevier, Amsterdam.