0% found this document useful (0 votes)
203 views1 page

PMP Formula Pocket Guide

This document provides a concise summary of key formulas and concepts for the Project Management Professional (PMP) exam in 3 pages or less. It includes formulas and definitions for topics like earned value management, PERT scheduling, probability, depreciation, communications, and more. Acronyms and terms are defined. Users can print the guide, fold it for easy reference, and study formulas for the PMP exam wherever they go in a compact format.

Uploaded by

nanaba06
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
203 views1 page

PMP Formula Pocket Guide

This document provides a concise summary of key formulas and concepts for the Project Management Professional (PMP) exam in 3 pages or less. It includes formulas and definitions for topics like earned value management, PERT scheduling, probability, depreciation, communications, and more. Acronyms and terms are defined. Users can print the guide, fold it for easy reference, and study formulas for the PMP exam wherever they go in a compact format.

Uploaded by

nanaba06
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 1

PMP® Formula Pocket Guide

Print it - Fold it - Study wherever you go.

Earned Value Mathematical Basics


CV = EV - AC Average (Mean) = Sum of all members divided by the number of items.
CPI = EV / AC Median = Arrange values from lowest value to highest. Pick the middle
SV = EV - PV one. If there is an even number of values, calculate the mean of the
SPI = EV / PV two middle values.
EAC ‘no variances’ = BAC / CPI Mode = Find the value in a data set that occurs most often.
EAC ‘fundamentally flawed’ = AC + ETC
EAC ‘atypical’ = AC + BAC - EV Values
EAC ‘typical’ = AC + ((BAC - EV) / CPI) 1 sigma = 68.26%
ETC = EAC - AC 2 sigma = 95.46%
ETC ‘atypical’ = BAC - EV
ETC ‘typical’ = (BAC - EV) / CPI 3 sigma = 99.73%
ETC ‘flawed’ = new estimate 6 sigma = 99.99%
Percent Complete = EV / BAC * 100 Control Limits = 3 sigma from mean
VAC = BAC - EAC Control Specifications = Defined by customer; looser than
EV = % complete * BAC the control limits
PERT Order of Magnitude estimate = -25% to +75%
PERT 3-point = (Pessimistic+(4*Most Likely)+Optimistic)/6 Preliminary estimate = -15% to + 50%
PERT = (Pessimistic - Optimistic) / 6 Budget estimate = -10% to +25%
PERT Activity Variance = ((Pessimistic - Optimistic) / 6)^2 Definitive estimate = -5% to +10%
PERT Variance all activities = sum((Pessimistic - Optimistic) / 6)^2 Final estimate = 0%
Float on the critical path = 0 days
Network Diagram
Activity Duration = EF - ES + 1 or Activity Duration = LF - LS + 1 Pareto Diagram = 80/20
Total Float = LS - ES or Total Float = LF – EF Time a PM spends communicating = 90%
Free Float = ES of Following - ES of Present - DUR of Present Crashing a project = Crash least expensive tasks on critical
EF = ES + duration - 1 path.
ES = EF of predecessor + 1 JIT inventory = 0% (or very close to 0%.)
LF = LS of successor - 1
LS = LF - duration + 1
Minus 100 = (100) or -100

Acronyms
Project Selection AC Actual Cost
PV = FV / (1+r)^n BAC Budget at Completion
FV = PV * (1+r)^n BCR Benefit Cost Ratio
NPV = Formula not required. Select biggest number. CBR Cost Benefit Ratio
ROI = Formula not required. Select biggest number.
IRR = Formula not required. Select biggest number. CPI Cost Performance Index
Payback Period = Add up the projected cash inflow minus expenses CV Cost Variance
until you reach the initial investment. DUR Duration
BCR = Benefit / Cost EAC Estimate at Completion
CBR = Cost / Benefit EF Early Finish
Opportunity Cost = The value of the project not chosen.
EMV Expected Monetary Value
Communications ES Early Start
Communication Channels = n * (n-1) / 2 ETC Estimate to Complete
EV Earned Value
Probability FV Future Value
EMV = Probability * Impact in currency IRR Internal Rate of Return
Procurement LF Late Finish
PTA = ((Ceiling Price - Target Price) / Buyer's Share Ratio) + Target LS Late Start
Cost NPV Net Present Value
PERT Program Evaluation and Review Technique
Depreciation PTA Point of Total Assumption
Straight-line Depreciation:
Depr. Expense = Asset Cost / Useful Life
PV Planned Value
Depr. Rate = 100% / Useful Life PV Present Value
Double Declining Balance Method: ROI Return on Investment
Depr. Rate = 2 * (100% / Useful Life) SPI Schedule Performance Index
Depr. Expense = Depreciation Rate * Book Value at Beginning of Year SV Schedule Variance
Book Value = Book Value at beginning of year - Depreciation Expense
VAC Variance at Completion
Sum-of-Years' Digits Method:
Sum of digits = Useful Life + (Useful Life - 1) + (Useful Life - 2) + etc. Sigma / Standard Deviation
Depr. rate = fraction of years left and sum of the digits (i.e. 4/15th) ^ “To the power of” (2^3 = 2*2*2 = 8)

Visit www.pmprepcast.com for more PMP resources. Please see disclaimer on the PMP Formula Study Guide.
© 2008 ScopeCreep Project Management Consultants. All rights reserved. Version 1.1

You might also like