Surely Final
Surely Final
KATHMANDU UNIVERSITY
SCHOOL OF ENGINEERING
DEPARTMENT OF CIVIL AND GEOMATICS ENGINEERING
REPORT
ON
INTERNSHIP ACTIVITY
At
Sanjen Hydroelectric Project
Chilime VDC, Rasuwa
Submitted By:
Rushit Shrestha (019035-15)
Abhay Suwal (019041-15)
Ashish Tamang (019043-15)
Submitted To:
Department of Civil Engineering
And
Chilime Engineering and Services Company Ltd. (ChesCo)
Kapan Marg, Kathmandu
June 2019
INTERNSHIP REPORT AT SANJEN HEP 2019
ACKNOWLEDGEMENTS
We would like to express our heartfelt gratitude to Associate Prof. Dr. Prachand Man
Pradhan, Head of Department of Civil Engineeringand to our supervisor and lecturer, Prof.
Dr. Ing. Ramesh Kumar Maskey, for providing us this opportunity to express our skill and
knowledge about hydropower engineering by allowing us to enroll as interns in hydropower
projects. We would like to thank him for his constant availability, guidance, encouragement
and continuous support along the entirety of this period.
We would also like to thank Mr. Prajesh Bikram Thapa, CEO of Chilime Engineering and
Services Company Ltd. (ChesCo) for providing us necessary accommodation, fooding, and
transportation facilities during our internship period and also for providing the required
support and assistance through which our internship could be completed successfully.
We are very grateful to Er. Triratna Maharjan, Resident Engineer (SanjenHEP), Er.
Bikash Bajracharya, Interim Resident Engineer (SanejnUpper HEP) and to our supervisors
Er. Baburam Poudel,Senior Engineer Power House, Subash Manandhar, Overseer Power
House, Er. Pratik Bhatta, Senior Engineer Tunnel, Mr. Nabin Osti, Senior Geologist, Er.
Prithvi Dhwoj Khadka for providing us assistance and guidance during the entirety of our
internship period.
Finally we would like to thank all the engineers, overseers, and staffof ChesCo for providing
us guidance and support during our internship period both during our time in the site as well
as in the office, also we would like to thank the engineers, geologist and staff of Tundi
Construction (Pvt.) Ltd., contractor for Civil works of SHEP and electromechanical works
of both SHEP and SUHEP, and Bajra Guru Construction Co. Pvt. Ltd., contractor for civil
works of SUHEP, for providing assistance along the internship period. We are very grateful
to everyone who has provided us their valuable time and suggestion during the entirety of the
internship period which has helped immensely for the completion of our internship.
1|Page
INTERNSHIP REPORT AT SANJEN HEP 2019
ABSTRACT
This document finalizes the completion of internship at Sanjen HEP, under the supervision
ofChilime Engineering and Services Company Ltd. (ChesCo) and Department of Civil
Engineering of Kathmandu University for the completion of course of Civil Engineering
Program. The 1st part of our internship comprised of site work in SHEP and SUHEP whereas
the latter part comprised of office work.
Sanjen Hydroelectric Project is located in Chilime VDC of Rasuwa District. This project in
whole comprises of two hydroelectric projects; namely, Sanjen (Upper) Hydroelectric Project
(14.8 MW) and Sanjen Hydroelectric Project (42.5 MW) in cascade.
During our internship period we had the opportunity to visit and study both SHEP and
SUHEP, but this document is focused mainly upon Sanjen Hydroelectric Project(42.5 MW).
Our internship comprised of 4 weeks of site work and 2 week of office work. During the
duration of site visit construction of power house in SHEP and SUHEP was going on,
construction of headrace tunnel and penstock tunnel was going on for SHEP, using drill and
blast method, and construction of headworks at Chhupchung Khola at Simbu, to draft 0.5m 3/s
discharge for SHEP, was going on. Works including lab tests, field test were also carried out
and visit to nearby hydropower project was done. Office works included study of report,
preparation of bar bending schedule, bill of quantities, quantity work out and rate analysis for
tail race of SHEP, design of drainage system for access road, quantity work out for access
road gabion, topographic map preparation for catchment area calculation and for hydrological
study of Chhupchhung Khola.
2|Page
INTERNSHIP REPORT AT SANJEN HEP 2019
EXECUTIVE SUMMARY
First four weeks of our internship was completed in the project site of SHEP in Chilime
VDC of Rasuwa District. During the time which construction of powerhouse, headworks,
head race and penstock tunnel were being carried out. And the final two weeks were spent
performing office work, including report study, preparation of bar bending schedule, bill of
quantities, quantity work out and rate analysis for tail race of SHEP, design of drainage
system for access road, quantity work out for access road gabion, topographic map
preparation for catchment area.
This report has been divided into six chapters. The first chapter deals with the introduction
part of this report which presents the objectives and scopes of the internship program as well
as brief about the Hydroelectric Project where the internship has been carried out i.e. Sanjen
Hydroelectric Project. The second chapter deals with the component of the HEP. This chapter
also includes brief of the construction processes that were being carried out such as tunnel
construction and concreting in the Power house with some of the problems faced in them.
Third chapter of this report presents about the construction equipments that were being used
for the construction of the HEP. Chapter four deals with quality control and assurance test
that were carried out which included tests for concrete and field density test. The sixth
chapter includes information about visit to a nearby HEP, Rasuwagadhi HEP. The last
chapter deals with the office work that has been carried out during the last two weeks of our
internship program.
3|Page
INTERNSHIP REPORT AT SANJEN HEP 2019
ABBREVIATIONS
% percentage
⁰ degrees
AC Alternating Current
amsl Above mean sea level
avg Average
b Breadth
BOOT Build Own Operate Transfer
BBS Bar Bending Schedule
cc Cubic centimeter
CEO Chief Executive Officer
ChesCo Chilime Engineering and Services Company Ltd.
cm Centimeter
cm2 Square centimeter
cumecs Cubic meter per second
d/s downstream
DHM Department of Hydrology and Meteorology
Dr. Doctor
E Easting
EDV Energy Dissipating Valve
e.g. example
Er. Engineer
etc et cetera
fck Characteristic Strength
FDC Flow duration curve
Gm Gram
GoN Government of Nepal
GWh Gigawatts hour
H Height
HEP Hydroelectric Plant
H.G Hydraulic gradient
HDPE High density polyethlene
HP Horse power
kg kilogram
km kilometer
km2 square kilometer
kN Kilo Newton
KU Kathmandu University
kV kilovolt
kWh kilowatts hour
kWhr kilowatt hour
l Length
ln logarithm
Ltd limited
m meter
M Magnitude
m/s meter per second
4|Page
INTERNSHIP REPORT AT SANJEN HEP 2019
m3 cubic metres
m3/s cubic metres per second
MCT Main Central Thrust
MDD Maximum Dry Density
mm millimeter
MPa Mega Pascal
MSL Mean Sea Level
MVA Mega Volt Ampere
MW Megawatt
MWI Monsoon wetness index
N Northing
NEA Nepal Electricity Authority
No. Number
Nos. Numbers
NRs Nepali Rupees
O &M Operation and Maintenance
OMC Optimal Moisture Content
PCC Plain Concrete Cement
Pg Page number
PH Powerhouse
PVC Polyvinyl chloride
Pvt Private
Q Discharge
RoR Run-off-River
rpm revolution per minute
SHEP Sanjen Hydro Electric Project
SUHEP Sanjen Upper Hydro Electric Project
sq. km square kilometer
T Time
u/s upstream
VDC Village Development Committee
WECS Water and Energy Commission Secretariat
Wt. Weight
Yrs years
5|Page
INTERNSHIP REPORT AT SANJEN HEP 2019
CONTENTS
Abstract......................................................................................................................................2
Executive summary....................................................................................................................3
Abbreviations.............................................................................................................................4
Chapter 1..................................................................................................................................14
Introduction..............................................................................................................................14
1.1. Overview of Internship..............................................................................................14
1.2. Objectives and Scopes...............................................................................................14
1.3. Project Background...................................................................................................15
1.4. Project Features.........................................................................................................18
1.5. Salient Features.........................................................................................................20
1.5.1. Salient Features of Sanjen Hydroelectric Project...............................................20
1.5.1 Comparison between SUHEP and SHEP...........................................................22
Chapter 2..................................................................................................................................23
Components of the project.......................................................................................................23
2.1. Project Layout...........................................................................................................23
2.2 Headworks.................................................................................................................24
2.2.1 Tailrace Canal and Forebay with side channel spillway....................................24
2.2.2 Feeder Canal from Chhupchung Khola..............................................................25
2.2.3 Feeder Canal from Chhupchung Khola..............................................................25
2.2.4 Weir of Chhupchung Khola...............................................................................25
2.3 Head Race..................................................................................................................28
2.3.1 Inlet Portal of Headrace Tunnel.........................................................................28
2.3.2 Head Race Tunnel..............................................................................................28
2.3.3 Rock Trap...........................................................................................................29
2.3.4 Surge Shaft.........................................................................................................29
2.3.5 Valve Chamber...................................................................................................30
2.3.6 Penstock Tunnel.................................................................................................31
2.3.7 Adit Tunnel........................................................................................................32
2.3.7.1 Adit 1..........................................................................................................32
2.3.7.2 Adit 2..........................................................................................................32
2.4 Tunnel and it’s construction......................................................................................32
6|Page
INTERNSHIP REPORT AT SANJEN HEP 2019
2.4.1 Drilling...............................................................................................................33
2.4.2 Charging.............................................................................................................33
2.4.3 Stemming...........................................................................................................34
2.4.4 Detonation..........................................................................................................34
2.4.5 Ventilation..........................................................................................................34
2.4.6 Mucking.............................................................................................................34
2.4.7 Scaling................................................................................................................34
2.4.8 Geological Mapping...........................................................................................35
2.4.9 Installation of Support........................................................................................35
2.4.10 Excavation for incline in penstock.....................................................................37
2.4.11 Rock Support......................................................................................................37
2.4.11.1 Rib Support.................................................................................................37
2.4.11.2 Backfilling..................................................................................................38
2.4.11.3 Shotcreting..................................................................................................38
2.4.11.4 Invert Concrete and Concrete Lining..........................................................39
2.4.11.5 Rock Bolts...................................................................................................39
2.4.11.6 Grouting......................................................................................................39
2.4.12 Problems encountered during Tunneling...........................................................40
2.4.12.1 Seepage.......................................................................................................40
2.4.12.2 Over break...................................................................................................41
2.4.12.3 Lack of concrete padding for rock bolt pull out test...................................41
2.5 Surface Penstock.......................................................................................................42
2.6 Powerhouse................................................................................................................42
2.6.1 Mass Concreting.................................................................................................43
2.7 Generator Hall...........................................................................................................46
2.8 Control room.............................................................................................................46
Chapter 3..................................................................................................................................47
Construction Equipments.........................................................................................................47
3.1. Grouting Pump..........................................................................................................47
3.2. Hydraulic Excavator..................................................................................................47
3.3. Concrete Batching Plant............................................................................................48
3.4. Transit Mixer.............................................................................................................49
3.5. Sand Washing Plant...................................................................................................49
7|Page
INTERNSHIP REPORT AT SANJEN HEP 2019
8|Page
INTERNSHIP REPORT AT SANJEN HEP 2019
9|Page
INTERNSHIP REPORT AT SANJEN HEP 2019
10 | P a g e
INTERNSHIP REPORT AT SANJEN HEP 2019
LIST OF FIGURES
11 | P a g e
INTERNSHIP REPORT AT SANJEN HEP 2019
12 | P a g e
INTERNSHIP REPORT AT SANJEN HEP 2019
Table 31: Composition of concrete for Fiber Shotcrete in HRT Inlet Tunnel d/s (0+274 to
0+294)m...................................................................................................................................58
Table 32: Compressive Strength of 7 days concrete for Fiber Shotcrete in HRT Inlet Tunnel
d/s (0+274 to 0+294)m.............................................................................................................58
Table 33: Compressive Strength of 28 days concrete for Fiber Shotcrete in HRT Inlet Tunnel
d/s (0+274 to 0+294)m.............................................................................................................58
Table 34: Source of Materials for Power House Shear Wall(E.L. 1748.00-1749.00m)..........59
Table 35: Composition of concrete for Power House Shear Wall(E.L. 1748.00-1749.00m). .59
Table 36: Compressive Strength of 7 days concrete for Power House Shear Wall(E.L.
1748.00-1749.00m)..................................................................................................................59
Table 37: Compressive Strength of28 days concrete for Power House Shear Wall(E.L.
1748.00-1749.00m)..................................................................................................................59
Table 38: Source of Materials for Power House Shear Wall(E.L. 1748.00-1749.00m)..........60
Table 39: Composition of concrete for Power House Shear Wall(E.L. 1748.00-1749.00m). .60
Table 40: Compressive Strength of 7 days concrete for Power House Shear Wall(E.L.
1748.00-1749.00m)..................................................................................................................60
Table 41: Compressive Strength of 28 days concrete for Power House Shear Wall(E.L.
1748.00-1749.00m)..................................................................................................................60
Table 42: Source of Materials of concrete for Fiber Shotcrete in HRT Inlet Tunnel d/s(0+409
to 0+417)m...............................................................................................................................61
Table 43: Composition of Fiber Shotcrete in HRT Inlet Tunnel d/s(0+409 to 0+417)m........61
Table 44: Compressive Strength of 7 days Fiber Shotcrete in HRT Inlet Tunnel d/s(0+409 to
0+417)m...................................................................................................................................61
Table 45: Source of Materials of concrete for Adit 1 Backfill –C12/15 (0+595.0m)..............62
Table 46: Composition of concrete for Adit 1 Backfill –C12/15 (0+595.0m).........................62
Table 47: Compressive Strength of 7 concrete for Adit 1 Backfill –C12/15 (0+595.0m).......62
Table 48: Result of Slump Tests..............................................................................................64
Table 49: Result of Field Density Test of compacted soil of powerhouse from EL 1746 to
1747m.......................................................................................................................................66
Table 50: Summary of Result of Field Density Test of compacted soil of powerhouse from
EL 1746 to 1747m....................................................................................................................66
Table 51: Result of Field Density Test of compacted soil of powerhouse from 1747 to
1749.80m..................................................................................................................................67
Table 52: Summary of Result of Field Density Test of compacted soil of powerhouse from
EL 1747 to 1749.80m...............................................................................................................67
Table 53: Summary of the menu are provided.........................................................................73
Table 54: Value of Standard Normal Variant for Corresponding Return Period....................77
13 | P a g e
INTERNSHIP REPORT AT SANJEN HEP 2019
CHAPTER 1
INTRODUCTION
After the completion of their in-campus course works, the final year students must work at
Host Organization related to hydropower development as interns. The internship will be for a
maximum of 6 working weeks with 8 hours per day of work load. This allows the students
the opportunity to acquire corporate knowledge, hands on technical skills, soft-skills and
potential placement. At the same time, the Host Organization benefits in terms of lead-time
and human resource identification.
Thus under such provision we have pursued our internship at Sanjen Hydroelectric Project in
Chilime VDC, Rasuwa under the supervision of Host Organization;Chilime Engineering and
Services Company Ltd. (ChesCo).
14 | P a g e
INTERNSHIP REPORT AT SANJEN HEP 2019
Topographic surveys and field investigation drilling works have been carried out. The
Environmental Impact Assessment (EIA) report concluded that the Project is an
environmentally friendly project with few adverse impacts compared to most other
comparable run-of-river hydropower projects, and has been approved by the Government of
Nepal.
SUHEP is a run-of-river hydropower development with a live storage volume in the peaking
reservoir sufficient for 2 hours daily peaking operation. Compared with other run-of-river
projects investigated in Nepal, SUHEP is one of the attractive projects due to its low specific
investment costs and its limited environmental impacts. The intake for SUHEP is located at
Tiloche, some 165 km north of Kathmandu and 6 km south of the border with People’s
Republic of China, at a distance of 44 km north from the district headquarters, Dhunche. The
project will exploit a gross head of 161.3 m on the Sanjen River over a reach of about 2 km
along the river to the tailrace outlet about 150 m upstream from the confluence of the
ChhupchhungKhola with the Sanjen River. The surface powerhouse is located near Simbu
village, and three horizontal-axis Francis turbine/generating units are to be installed, each of
rated capacity 5.1 MW.
Sanjen Hydroelectric Project (SHEP) is located on the Sanjen River in Rasuwa District,
Bagmati Zone of the Central Development Region. SHEP is a cascade run-of-river
hydropower development that utilizes the water from the tailrace of SUHEP powerhouse.
15 | P a g e
INTERNSHIP REPORT AT SANJEN HEP 2019
Additionally, SHEP utilizes 0.5 m3/s water from ChhupchhungKhola. SHEP is one of the
attractive projects due to its low specific investment costs and its limited environmental
impacts. SHEP has major structures viz. forebay, headrace tunnel, underground surge tank,
inclined and horizontal pressure shaft, powerhouse and tail race structures.Generation
License for these projects was obtained from Ministry of Energy on August 2012 and
November 2011 respectively valid for 35 years including the period of construction on Build
Own Operate Transfer (BOOT) basis.
Geographically, the project area lies between longitudes from 85 0 16' 30' E to 850 18’ 15" E
and latitudes from 280 11' 00" N to 280 13' 00" N. Site is considered as remote area. The
project is accessible via Kathmandu-Trisuli road (72 km), Trisuli-Somdang Highway
(PasangLhamu Highway 72 km) and 6 km long access road up to existing headworks of
Chilime Hydroelectric Project. The access road to the power house and headwork is
constructed by the company.
The Site is situated in high altitude and sometimes snowfall occurs in winter. Concreting
during this period might be required to do in frosty condition. Construction works at forebay
will have to be carried out in high altitudes above 2100 m above mean sea level and
sometimes snowfall occurs in winter. In this elevation works may have to be executed in cold
condition and Concreting during this period might be required to do in frosty condition in the
winter season. Construction at powerhouse area is expected to be slightly more comfortable
since this area lies about 400 m lower from the level of forebay area.
16 | P a g e
INTERNSHIP REPORT AT SANJEN HEP 2019
17 | P a g e
INTERNSHIP REPORT AT SANJEN HEP 2019
Sanjen Hydroelectric Project receives tailwaters from SUHEP power house and additional 0.5
m3/s discharge from Chhupchung Khola at Simbu and its powerhouse is located at Chilime
Village adjacent to Headworks of existing Chilime Power Plant.
Project utilizes design flow of 11.57 m3/s at 40 percentile flow exceedance of long term
available river discharge and 442 m gross head to produce 42.5 MW power and 251.94 GWh
gross energy per annum. SHEP comprises a 3629m long headrace tunnel, a 1018m long
pressure shaft. Three vertical axes Pelton turbines of 15MW capacity each will be installed in
a surface powerhouse at Chilime Village in ChilimeVDC.Generation voltage of 11kV is
stepped up at the switchyard by 11/132 kV transformer and 1.1 km 132 kV transmission line
connected at Chilime hub will be constructed for power evacuation.
Hydrology
Sanjen (Upper) Hydroelectric Project is basically a run-off-river scheme with the provision
of daily peaking pondage for 1.2 hours. The headworks site of Sanjen (Upper) Hydroelectric
Project is located at Tiloche about 2 km upstream from the confluence of the SanjenKhola
and ChhupchungKhola. This project utilizes water from SanjenKhola. The main attractive
feature of this project is the peaking pondage. The design discharge is 11.07 m 3/s which is
equivalent to 40% exceedence flow.
Sanjen Hydroelectric Project (SHEP) is a cascade run-of-river scheme which diverts the
tail water coming from the powerhouse of Sanjen (Upper) Hydroelectric Project and the
additional water (0.50m3/sec) from the ChhupchhungKhola. The major headworks structure
of the SHEP will be a forebay cum intake structure. Water discharged from tailrace of
18 | P a g e
INTERNSHIP REPORT AT SANJEN HEP 2019
SUHEP powerhouse and the water from the ChhupchhungKhola through feeder canal system
will be collected in this forebay. There will be a simple intake structure, desander and a
feeder canal to feed water from ChhupchhungKhola which is designed to convey 0.5m 3/s of
water from the intake and discharge to the forebay of the interconnection system. Adding this
flow, the design discharge adopted for SHEP is 11.57 m 3/s. The forebay is provided with side
channel spillway.
Geology:
The project area is situated in the Higher Himalaya and the Lesser Himalaya, Central Nepal
separated by the Main Central Thrust (MCT). Chhupchhung weir lies in recent alluvial
deposits consisting of predominately coarse gravel toboulder derived from gneiss, schist,
quartzite and slate in sand matrix with large boulders ofaugen gneiss. Forebay/Intake of
SHEP is in a gently sloping terrain consisting of about 25-30m thick deposits with angular
gravel to boulder sized rock fragments of powerhouse lies on a flat alluvium terrace
consisting of a thick accumulation of alluvial deposits having sharp-textured, angular to sub-
rounded, coarse-grained soil with gravels.
Contracting Parties:
The Contract for the Construction of the main Civil Work is the major Contract under the
Sanjen Hydroelectric Project to generate 42.5 MW power (electricity). Since the taking over
of the site, the Contractor SEW Infrastructure Limited, India and Tundi Construction Co. Pvt.
Ltd., Nepal J/V (SEW-TUNDI JV), has been doing its best; in mobilizing resources and
executing the works.
Client
SanjenJalavidyut Company Limited (SJCL)
Ground and First Floor, Kapan Marg
Maharajgunj, Chakrapath, Kathmandu, Nepal
Consultant
Chilime Engineering Services Company Ltd.
Second and Third Floor, Kapan Marg
Maharajgunj, Chakrapath, Kathmandu, Nepal
Head Office: Maharajgunj, Chakrapath, Kathmandu, Nepal
Lot 2: Contractor
SEW (India) – Tundi (Nepal) Joint Venture
SEW Infrastructure Limited
6-3-871, Snehalata, Greenlands Road, Begumet,
HYDERABAD- 500 016, Andhra Pradesh, India.
TundiConstrucion Pvt. Ltd.
Shanti Basti, Sanepa , Ring Road,
Municipality: Lalitpur, Ward No.:03, Lalitpur, Nepal
19 | P a g e
INTERNSHIP REPORT AT SANJEN HEP 2019
Lot 3: Contractor
Dongfang Electric International Corporation (DEC)
18 Xixin Avenue, High-tech Zone west Park,
Chengdu, 611731, Sichuan, P.R. China
Lot 4: Contractor
Nepal Hydro & Electric Limited (NHE)
P.O. Box: -1, Butwal, Nepal
20 | P a g e
INTERNSHIP REPORT AT SANJEN HEP 2019
Energy Generation
Annual Energy Generation
Total 253.447 GWh
Dry Months Energy 35.116 GWh
Wet Months Energy 218.331 GWh
Annual Contract Energy
Total 243.31 GWh
Dry Months Energy 33.71 GWh
Wet Months Energy 209.60 GWh
Transmission Line Length 1km, 132KV
Access Road 7Km
Project Cost
Total cost before financing NRs. 5,024,289,001.
Total financial cost NRs. 5,914,661,650.
Financial Indicators
As independent
IRR 15.36 %
ROE 18.47%
B/C 1.27
NPV (MNPR) 1090.848
As cascade system
IRR 14.087 %
RoE 16.589 %
B/C Ratio 1.14
NPV (MNPR) 841.373
Sanjen Upper
Sanjen Hydroelectric
Descriptions Hydroelectric project
project(SHEP)
(SUHEP)
Cascade Peaking Run-of-
Type of project Peaking Run-of-River
River
Design Flow 11.07m3 11.57m3
Gross Head: 161.3 m 442m
Off-take from tail-water of
Overflow weir type with
Headworks: SHUEP and chhupchung
undersluice and side intake
feeder
Surface Pondage
Desander Type and Size:
60m(l)x8.5m(b)x7.10m(h) 80m(l)x30m(b)x8m(h)
1377m(l) 3630m(l)
Headrace Tunnel length
and size:
3.5m(b)x3.75m(h) 3.5m(b)x3.75m(h)
480m 1020m
Penstok Length and size
1.1m to 2.5m in diameter 1.1m to 2.5m in diameter
Surface Semi surface
Power House Type and
Size:
45.8m(l)x14m(b)x23m(h) 57.5m(l)x30m(b)x15m(h)
Turbine type, Francis Pelton
21 | P a g e
INTERNSHIP REPORT AT SANJEN HEP 2019
CHAPTER 2
2.2 Headworks
23 | P a g e
INTERNSHIP REPORT AT SANJEN HEP 2019
24 | P a g e
INTERNSHIP REPORT AT SANJEN HEP 2019
the width of the weir is 12m. The cutoff wall is provided after the boulder riprap and at the start
of the upstream apron. The bottom level of the upstream cutoff wall is 2184.20mamsl. The u/s
cutoff wall is of the trapezoidal section with 0.5m width at the bottom and 1m width at the top.
For concreting of the weir, fore apron and back apron 0.1m thick structural concrete of grade C
8/10: X0 and 0.4m thick abrasion concrete C25/30 is used. The upstream apron is of length
6.51m. In rear apron weep holes are provided to relieve the upthrust given by the underground
water. The level of the downstream apron is 2184.00 amsl and the length is 14m. At the end of
the spillway of the weir, the cutoff wall is provided of thickness 0.50m at the bottom and 1.1m
thick at the top of the cut off wall. At the end of the rear apron, the small cutoff wall is also
provided 0.5m thick at the bottom and 1m thick at the top. For the downstream apron, first layer
filter fabric geotextile is provided and then lean concrete of 0.1m thick of grade C8/10 provided
then 0.4m concrete of grade C25/30 is provided on top of which abrasion resistant concrete of
0.1m thickness
2.2.5 Intake
The type of intake in Chupchung Khola is Orifice type intake. The sill level of the intake is
2187.50amsl so that 0.3m height is as the dead zone for sediment deposition in weir. The
0
intake trash rack is provided at an angle of 80 with the size of 1.5m width x 1.1m height.
The orifice opening is 0.7m. At the start of the orifice opening, intake gate of size 1.5 m
width and 0.7m height is provided. The intake gate is regulated by hoisting equipment. The
cutoff wall provided at the start of the intake with 0.5m width at the bottom and 1m width at
the top. The intake structure is of length 5.86m. The top level of the intake structure is at
2191.00m amsl elevation. The concrete grade of the intake structure is C25/30.
The gravel trap starts after the intake structure with the inlet transit of length 1.8m and total
section length of 13.06m with the slope of 1: 41.67. The normal water level at the gravel trap
25 | P a g e
INTERNSHIP REPORT AT SANJEN HEP 2019
is 2187.98mamsl. The concrete thickness provided is 0.6m. The flushing of the gravel trap is
done by a square culvert of dimension 0.7m. At the inlet of the culvert, gravel flushing gate
is provided which is regulated by hoisting equipment. The structural concrete thickness of
culvert is 0.3m all-around of concrete grade C25/30.
2.2.7 Spillway
After the gravel flushing along the feeder, canal spillway is provided of length 4m and
height of 1m. The spillway provided is broad chested spillway. Weep holes of 100mm
diameter are provided at the walls of the spillway. The total length of the spillway is
13.06m.
2.2.8 Desander
After the feeder canal, desander starts. Desander is of one chamber with hoper type. The
inlet transit length of the desander is 6m while the outlet transit length is 4.9m. The normal
water level at desander is 2187.88mamsl. At inlet transit, the expansion of 1m width of the
feeder canal to 4m width of desander takes place. The slope of desander is 1:50. The wall of
the desander varies from 0.3m at the top and increases upto 0.4m at the bottom section. The
height of the desander including free board is 2.55m. The hooper end at bottom is of width
0.8m and height varies from 0.2 at the start of the slope of the desander and increases to
0.95m. Two sub surface drains are provided along the length of the desander with opening
200mm diameter.
The flushing of desander is provided along with the side drain which flushes out the
sediment collected to the riprap area downstream of the weir. The slope of the desander
flushing canal is 1:31.59. The flushing of the desander is controlled by the regulating gate
kept at the start of the desander flushing canal regulated by the hoisting equipment. The size
of the desander flushing box culvert is 1.5m in height and 0.8m in width.
26 | P a g e
INTERNSHIP REPORT AT SANJEN HEP 2019
27 | P a g e
INTERNSHIP REPORT AT SANJEN HEP 2019
The details of the bends and varying slope in the HRT are presented in the tables below.
Table 3: Detail of bends and slope in HRT
28 | P a g e
INTERNSHIP REPORT AT SANJEN HEP 2019
About 60% of the length of the headrace tunnel is estimated to be shotcrete lined of 10 to 15
cm thickness and 40% of length is estimated to be concrete lined at this stage
For the purpose of construction of HRT two aditsare present, namely Adit 1 in Brapchhe and
Adit 3 which diverges into the penstock tunnel.
• To relief the wave developed due to the water hammer at the time of sudden load rejection
of turbine through open atmospheric zone near the plant.
• To protect the penstock from detrimental effect of water hammer pressure developed in the
pipe due to fast closure of spear valves of the turbine.
The surge shaft is of restricted orifice type at the bottom to supply the water requirements or
to store the excess water caused due to the variations in the power discharge resulting from
the variations in the power generations.
The surge shaft is present in here after the rock trap present at a chainage of 3+635.16 where
the start has been taken from the start of head race tunnel. Here the excavation diameter is
6.60m and nominal diameter for the surge tank is 5.50m whereas the opening for the surge
tank is 1.24m in diameter which increases to 2.64, reaches the nominal diameter 5.50m and
finally reaching 5.80m in diameter as thickness of concrete decreases. The surge shaft
consists of a dome of radius 3.30m which is connected to an aeration tunnel of diameter 2.70
lined by 50mm shotcrete at the crown and 20cm concrete of C20/25 grade as invert lining.
The aeration tunnel is present at downward slope of 1:27 with a bend of 20 m radius at
0+013.19 chainage from aeration tunnel portal ending at 0+028.76m. The aeration tunnel
portal consists of 35cm concrete of C20/25 at the top and 40 cm of the same specification
concrete on the bottom. In totality the height of the surge shaft is 55m.
For rock support grouted rock bolts of 200mm diameter and 3m long have been used. These
have been bolted at a spacing of 1.5m and placed with 100mm shotcrete of grade C28/35.
Description Values(amsl)
Minimum Downsurge Level 2164.42
Normal Water Level 2183.43
Static Water Level 2187.00
Maximum Upsurge Level 2198.29
In SHEP the size of main valve chamber is larger than that of tunnel size. The entrance of
valve chamber is of dimension 4.2m(in width)*7.25m(in height) and the main valve chamber
is of dimension 5.28m (in width)* 8m(in height).
The main valve chamber has been placed with and inverts lining of 20cm thickness of
concrete of grade C20/25. For support of the valve camber 10cm fibre shotcrete of C28/35
30 | P a g e
INTERNSHIP REPORT AT SANJEN HEP 2019
has been placed and has been reinforced with rock bolt of 3m length of 20m diameter at a
spacing of 1.5m.
The penstock will be inclined shaft at two places at 50-degree angle with almost equal length
and middle part connecting with horizontal penstock. The lower part of penstock including
manifold is proposed to be horizontal, some part of it will be constructed as cut and cover
type. The total length of the penstock including manifolds will be 1018 m.
The Penstock Tunnel starts at the chainage of 3+635.16m to the chainage of 4+405.15m
chainage taken from the start of HRT with the length of 1020m. It consists 2 inclined
sections. The inlet diameter of the penstock tunnel is 2.5m varying to 2.3m and that of outlet
is 2.2m. Excavation is Circular in inclined sections and D shaped in the horizontal sections.
The Tunnel is completely backfilled with concrete in order to support the Penstock pipe with
concrete of C12/15 grade. It is also supported by steel lining and shotcrete of 5cm thickness
of grade C28/35 with permanent grouted rock bolts of 20mm diameter which is 1.5m long a
spacing of 1.5m. The excavation diameter is 3.2m in circular sections and for the inverted D
sections with 3.2m height and spring line of 1.60m and crown height of 1.60m.
Table 6: Detail of Bends in Penstock Tunnel
Bend Start of Bend in End of Bend in Radius of Bend(m)
chainage (m) Chainage (m)
Bend 1 3+674.95 3+684.53 12.50
Bend 2 3+845.28 3+854.86 12.50
Bend 3 3+951.78 3+961.35 12.50
Bend 4 4+107.84 4+117.32 12.50
There are two Adit tunnels in SHEP, namely Adit 1 and Adit 3.
31 | P a g e
INTERNSHIP REPORT AT SANJEN HEP 2019
2.3.7.1 Adit 1
The length of Adit 1 is 129.89m with 1 bend of Radius 30m. The width of adit tunnel is 3.5m
and height is 3.75m. The rock support of grouted rock bolts of 3m long and 20mm diameter
in 1.5m spacing and 5 to 10 cm shotcrete. The adit 1 is to be plugged after the completion of
the HRT by C20/25 grade concrete. The steel reinforcement of 20mm diameter with 200mm
spacing is used along the length and in the entrance its 25mm diameter with 200mm spacing.
2.3.7.2 Adit 2
The length of Adit 3 is 179.81m with 1 bend of Radius 50m. It provides an access to the
valve chamber. The width of adit tunnel is 4.2m and the height is 3.75m with spring line
height of 1.65 ma and crown height of 2.10m. The rock support of grouted rock bolts of 3m
long and 20mm diameter in 1.5m spacing and 5 to 10 cm shotcrete.
SHEP consists a tunnel for siphon pipe from balancing pond to HRT inlet of 110m, HRT of
3628.46m and a penstock tunnel of 770m in length.
For the process of rock excavation Drill and Blast Method has been for the tunnels and for
inclined excavation in penstock tunnel Alimak has been used.
Drill and blast tunneling is a method of excavation involving the controlled use of explosives
to break rock.
2.4.1 Drilling
For the purpose of drilling in SHEP jackhammers have been used. They are air driven. The
drill holes are drilled using sufficient circulation of water in order to remove sediments and
also dust from the drill site which is known as hole flushing thus, this type of drilling is
32 | P a g e
INTERNSHIP REPORT AT SANJEN HEP 2019
known as Wet Drilling. The drill bit for drilling is 38mm in diameter. Holes 7 ft deep are drill
on to which explosives are to be loaded. The drill pattern used is wedge pattern.
Figure 8: Jackhammer
2.4.2 Charging
It is the process of insertion of the explosives into the drill holes. Here emulsion type
explosives were being used as explosives. Explosives of 32 mm diameter and of 200 gm were
being used. Explosive named SUPERPOWER-90 was being used in the case of SHEP. The
quantity of explosive used is determined by the type of rock increasing with the hardness of
the rock.
33 | P a g e
INTERNSHIP REPORT AT SANJEN HEP 2019
2.4.5 Ventilation
In tunnel excavation, a ventilation system is required to provide an acceptable working
environment for the people of the tunnel. The environment is affected by the concentration of
impurities in the tunnel air. The impurities are mostly created by blasting and traffic in the
tunnel.Ventilation is done by using so-called air-ducting systems, long steel or plastic pipes,
which are attached to the roof of the tunnel and blow fresh air onto the working face. This
gives rise to localized excess pressure and the bad air is pushed towards the tunnel exit. In
case of SHEP, blowing ventilation has been used to dilute the explosion gas so that toxic gas
concentration is of the acceptable value.
2.4.6 Mucking
Mucking can be defined as cleaning of the excavated materials as well as its transportation
out of the tunnel. For this purpose the loaders are used on to which the material is loaded and
transferred out of the tunnel. In case of SHEP, the muck from Audit 1 was transported to PH
area for the purpose of filling.
2.4.7 Scaling
Scaling is defined as the process of scraping off the loose or jointed rock from the surface of
the walls of tunnel to prevent the injury from the falling rock pieces while the working on
tunnel. Scaling is performed prior to applying the rock reinforcement and support. Normal
scaling requires the prying without loosening adjoining rock, substantially locked in place,
and/or the use of the air-water flushing. Scaling is first performed by mechanical equipment
then is done by control manual control scaling is performed.
34 | P a g e
INTERNSHIP REPORT AT SANJEN HEP 2019
out which is vital for determining rock type, excavation class which in turn gives the rock
support classification.
35 | P a g e
INTERNSHIP REPORT AT SANJEN HEP 2019
36 | P a g e
INTERNSHIP REPORT AT SANJEN HEP 2019
In case of SHEP, steel ribs are provided in HRT in class VI rock type i.e. Q<0.01 and in
zones with high seepage zones. Steel ribs of (I-section) have been used in SHEP at spacing of
1m. Such steel ribs are fabricated in pieces to be tied to each other by plates and nut bolts
(four pieces, two legs below spring level and two arches). For further support the ribs are
bolted to the rocks via anchor rods of 1m long, 20mm diameter steel rod and two consecutive
ribs are connected with 16mm diameter, 1m long steel rods placed as per the drawings.
37 | P a g e
INTERNSHIP REPORT AT SANJEN HEP 2019
For SHEP the grade of concrete used for backfill was C12/15. The concrete mix was prepared
outside the tunnel and was transported in the required site via a loader. Then the concrete was
placed on a concrete pump which utilized compressed air for pumping the concrete. Water
was added in the concrete to make it pumpable and thus backfilling was done. During the
preparation of concrete mix for backfilling the observed value of slump was not in the region
of that specified however due to presence of seepage in the tunnel and complying to the fact
that water was still to be added to the mix in the tunnel for pumping, it was informed to us
that the w/c ratio had been decreased taking into consideration site conditions, thus no
modification was made to the concrete mix.
2.4.11.3 Shotcreting
Shotcreting orSprayed concreting refers to the process of spraying a mix of cement, sand and
fine aggregate through a hose projected at a very high velocity on the surface of the rock face.
Shotcreting may be of types plain or fibres reinforced or wire mesh reinforced. Shotcrete in
SHEP contained Micro silica as admixture and Sikament 170 as plasticizer to reduce the
quantity of water and to improve the pump ability of concrete.
In the field,fibreof 3cm in length and 0.25 mm in diameter has been used for fibre shotcrete.
Fibre shotcrete has been used in rock types of HRT and also penstock tunnel except Rock
Class I,II,III. In class III plain shotcrete has been used. Welded wire fabric of dimension
150mm x 150mm x 6 mm have been used for wire mesh reinforced shotcrete as required.
For the process of shotcreting concrete mix is prepared outside of the tunnel, where concrete
mixer prepares the mix, which is then loaded upon a loader and transported in to the required
site where it is placed in to the shotcrete machine and is sprayed. The thickness of shotcrete
varies according to the site condition and the rock type.
38 | P a g e
INTERNSHIP REPORT AT SANJEN HEP 2019
Invert lining has been done on the entirety of the HRT. Concrete lining is only done for
sections with weak zones, shear zones, areas prone to squeezing.
For the test of Rock Bolts, pull out test is carried out on the bolts. In a predefined section of
tunnel 50 rock bolts are tested and if 3 of those fail to meet the required criteria the rock bolts
fail the pull out test. The pull out test is carried out by the use of the hydraulic jack with a pull
force of 127 kN.If applying this creates the displacement of 8 mm then the rock said to be
failed. The hydraulic jack presses the face plate and pulls the bolt.
However we were not able to test for the rock bolts due to lack of concrete padding on the
base plates of the rock bolts.
We were to see grouting carried out in rock bolts for consolidation. This grout fills these
voids, thus stabilizing and strengthening the soil. Pressure Grouting favors control of the
amount of grout and has many applications. The purpose of grouting can be either to
strengthen a formation or to reduce water flow through it.
For the purpose of rock bolt grouting cement slurry with compressive strength of 45MPa at
28 days must be used.
Material
Cement Agrakanchi OPC
Plasticizer Sikament 1016 NS-0.9% by wt. of cement
Admixture Intraplast-0.25%
Table 11: Composition of Grout Mix
Material(kg) Cement(kg) Water(kg) Plasticizer(kg) Admixture(kg)
Wt for trial mix 3.5 1.229 0.0315 0.0087
Wt per bag 50 17.5 0.45 0.125
The rock bolts bolted onto the tunnel have been tied up with two pipes, one of which reaches
the end of the bolt whereas another one reaches 50 cm inside the bolt.
Grouting Procedure:
(Detail Drawings of rock support in HRT and penstock tunnel have been provided in
ANNEX I)
40 | P a g e
INTERNSHIP REPORT AT SANJEN HEP 2019
We observed over break in audit 1 leading towards the HRT. This was due to presence of
cavity in the rock mass. Due to this presence of cavity the weak rock mass fell onto the base
of tunnel which required for mucking.
For this problem of over break, the measures that were taken are listed below:
1. Shotcreting on the rock mass fallen from the cavity and around the cavity.
However even though shotcreting was carried out the falling of rock mass continued
leading a huge cavity.
2. During rib installation it was decided that additional ribs would be provided for
additional support.
3. Spilling dowels of 25mm diameter,2.5m in length and 15 in no. were provided for
support and control of overbreak
4. Backfilling of the cavity is to be done using concrete of grade C12/15 after
construction of remaining tunnel. The amount of backfill required was calculated by
survey.
2.4.12.3 Lack of concrete padding for rock bolt pull out test
Though pull out test was intended to be carried out in the surge shaft, it could not be carried
out due lack of concrete padding on the base of rock bolts. Rock bolts had been marked
previously which required concrete padding for rock bolt pull out test, but it had not been
done thus rock bolt pull out test had been cancelled until concrete padding was done.
41 | P a g e
INTERNSHIP REPORT AT SANJEN HEP 2019
2.6 Powerhouse
The structural complex where all the equipment’s for providing electricity are suitably
arranged is a powerhouse. Two basic requirement of powerhouse planning are functional
efficiency and aesthetic beauty. One of the choices is whether to locate the powerhouse in a
building above ground called as surface powerhouse or to locate it as the underground
powerhouse situated in caverns, excavated below the ground.
The powerhouse of Sanjen HEP is proposed in the right bank of the ChilimeKhola very
close to the headworks of existing Chilime Power Plant at Chilime Village.
The powerhouse will be equipped with three units of Vertical Pelton turbines and matching
synchronous generators.The surface penstock, with the C L at an elevation of 1745.00 m,
enters the powerhouse and the penstock is bifurcated at chainage of 4+515.304 m changing
the penstock diameter from Ф1.8m to Ф1.5m at 1st unit. Second bifurcation is done at
chainage of 4+529.674m changing Ф1.5m to Ф1.06m at 2nd unit and 3rd unit. Each of these
penstock pipes are attached with manifold pipe provided with 4 nozzles each which rounds
the turbine unit in order to hit the turbine from every direction. These arrangements are all
covered with mass concreting of strength C25/30 with total volume of 480 m3.
The sizing of the powerhouse is done in such a way that it encompasses all the machines
equipment and provides sufficient space for maintenance and easy installation. Entrance to
the powerhouse building is through a 2m wide rolling shutter gate and the service bay is
immediately after the entrance gate.
42 | P a g e
INTERNSHIP REPORT AT SANJEN HEP 2019
The Sanjen HEP underwent mass concreting in the area covering the bifurcated penstock
pipe as shown in the plan below. The whole mass concreting was carried out in 3 stages. First
the concreting was done upto the height of 1.3m enclosing the volume of 200m 3 which
almost covered the penstock pipe. After the completion of the concreting, the concrete was
allowed to set and cured for 7 days. The shear wall at sides and the top of mass concrete were
chipped for good second stage concreting. The second stage concreting was performed after 7
days which was of height 0.8m enclosing volume of 90m 3. Similarly, the third stage
concreting enclosed the volume of 190m 3 with depth of 1.2m. The total volume of the mass
concrete was 580m3 and the strength of the concrete was C25/30.
43 | P a g e
INTERNSHIP REPORT AT SANJEN HEP 2019
Table 13: Source of material of bifurcation area in Power House For elevation 1743.40m –
1744.70m
Material
Cement 410 kg (Agrakhanchi OPC)
Coarse Aggregate (25 mm down) 876.96 kg (HH Cruher Plant (80%))
Coarse Aggregate (10mm down) 219.24 kg (HH Crusher Plant (20%))
Sand 643.8 kg (Powerhouse area sand washing plant)
Admixture 3.28 kg (Hind Plast Super-160-0.8%)
Retarder 2.05 kg (Hind Plast Super-R-0.5%)
Water 157.44 kg
W/C ratio 0.384
Table 14: Compressive Strength of 7 days concrete of bifurcation area in Power House for
elevation 1744.70m – 1745.50m
Table 15: Source of material of bifurcation area in Power House for elevation 1744.70m –
1745.50m
Material
Cement 410 kg (Agrakhanchi OPC)
Coarse Aggregate (25 mm down) 876.46 kg (HH Cruher Plant (80%))
Coarse Aggregate (10mm down) 219.24 kg (HH Crusher Plant (20%))
Sand 643.8 kg (Powerhouse area sand washing plant)
Admixture 3.28 kg (Hind Plast Super-160-0.8%)
Retarder 2.05 kg (Hind Plast Super-R-0.5%)
Water 157.44 kg
W/C ratio 0.384
Table 16: Compressive Strength of 7 days concrete of bifurcation area in Power House for
elevation 1744.70m – 1745.50m
44 | P a g e
INTERNSHIP REPORT AT SANJEN HEP 2019
Table 17: Source of material of bifurcation area in Power House for elevation 1744.70m –
1745.50m
Material
Cement 410 kg (Agrakhanchi OPC)
Coarse Aggregate (25 mm down) 876.96 kg (HH Cruher Plant (80%))
Coarse Aggregate (10mm down) 219.24 kg (HH Crusher Plant (20%))
Sand 643.8 kg (Powerhouse area sand washing plant)
Admixture 3.28 kg (Hind Plast Super-160-0.8%)
Retarder 2.05 kg (Hind Plast Super-R-0.5%)
Water 157.44 kg
W/C ratio 0.384
Table 18: Compressive Strength of 7 days concrete of bifurcation area in Power House for
elevation 1744.70m – 1745.50m
First the materials ( sand, aggregate ) are loaded in the batching plant by the help of
excavator.
Then, the plant automatically batches the materials by weight which is controlled
from the control panel.
The mix is transferred to the mixer above where cement, water, admixtures and
retarders are mixed.
The final concrete mix is passed to the Transit Mixer.
The concrete is maintained in the liquid through rotation of the drum about its own
axis.
The concrete is discharged to the concrete pump which was outside the powerhouse.
The concrete placed in the pump is pumped through piston mechanism.
The concrete pumped is reached to places required with the hose pipe connected to
the concrete pump.
The hoses are interconnected or detached as per the length required to reach the
destination.
The concrete placed in the powerhouse are spread to the corners and places where the
reinforcements are compact with the help of vibrator.
The concrete is allowed to set once the whole concreting is finished.
Problem in batching plant like the chain problem was encountered, which resulted in
delay in completion of concreting.
Choking of the concrete in the concrete pump was encountered.
Due to lesser w/c ratio, the workability of the concrete was decreased due to which
the concrete was stuck in the hose pipe than to reach the concreting place.
Due to complex reinforcement design of the staircase, there was difficulty in using the
vibrator properly in the staircase.
While concreting of the slab was carried out, the surface was to be levelled. But due
to the shear wall the difficulty in the work was increased for the surveyor.
46 | P a g e
INTERNSHIP REPORT AT SANJEN HEP 2019
CHAPTER 3
CONSTRUCTION EQUIPMENTS
Application
Grouting is the process of pumping a cement or chemical grout into soft or weak strata of soil
or interconnected pore or voids whose neither configuration nor volume is known. This grout
fills these voids, thus stabilizing and strengthening the soil. Pressure Grouting favors control
of the amount of grout and has many applications. One of these includes support for existing
structures or where foundations have shifted. The greatest use of pressure grouting is to
improve geomaterials (soil and rock).The purpose of grouting can be either to strengthen a
formation or to reduce water flow through it. It is also used to correct faults in concrete and
masonry structures. It is also a key procedure in the creation of post-tensioned prestressed
concrete, a material used in many concrete bridge designs, among other places.
47 | P a g e
INTERNSHIP REPORT AT SANJEN HEP 2019
Among the two types of excavator namely Crawler and Wheel, Crawler Excavator was
equipped in the construction site. The Crawler runs in two endless tracks (chain wheel
system). It was preferred to wheel system in case of poor soil due to the large contact of
tracks and in hilly areas.
Wet Mix Plant was the one equipped at the construction site. The inputs provided were
cement, sand, crushed stone, water, admixture and retarder. Hind Plast Super was the
admixture and the retarder used. The calculated amount of the required materials is fed into
the plant and mixed by the agitator. The volume of the agitator is 0.35 m 3. After the mixing
done in the ready-mix, the mixed material is transported to the TM for further agitation till
the material reaches the site for concreting the structure.
48 | P a g e
INTERNSHIP REPORT AT SANJEN HEP 2019
There were 2 TM equipped for transporting the concrete from the batching plant at the site
for rapid concreting process. The capacity of the TM was about 6 m3.
In Sanjen HEP, there is the traditional sand washing plant in use. In the plant, the materials
are placed over the sieve with the excavator and are washed with the water for sand to pass
through the sieve and separate out the aggregates. The water mix is passed through a
constructed canal to a pool where the washed sand is collected and deposited.
49 | P a g e
INTERNSHIP REPORT AT SANJEN HEP 2019
The plant equipped at Sanjen HEP can produce the aggregates of size ranges like………….
The one used at Sanjen HEP site is Line pump. This pump required steel or flexible concrete
placing hoses to be manually attached to the outlet of the machine. Those hoses are linked
together and lead to wherever the concrete needs to be placed. The concrete is placed on the
pump from the Transit Mixer and the placed concrete is pumped with piston pump through
the hoses to the point.
50 | P a g e
INTERNSHIP REPORT AT SANJEN HEP 2019
The roller used in Sanjen HEP was Single Drum Vibratory Roller for the compaction of soil
in the power house is upto the elevation of 1749.80 m amsl.
3.9. Alimak
The Alimak method is based on a lift type climber, which has a platform, safety canopy, lift
basket and motor. The climber travels on rails that are fixed onto the rock wall and is driven
by air, or an electric or diesel motor. The water and air lines are attached to the rail. The
Alimak method represents the first mechanized form of raise building. It is more efficient
than the traditional raise building and is much safer as the work is always performed under
protective canopy. The Alimak method is a relatively inexpensive alternative for construction
sites that have a few variable length raises.
The Alimak method raises between levels in a safe and effective manner. Drilling, loading
and blasting are all performed from the platform of the Raise Climber, which is adapted to fit
the precise dimensions and shape of the raise.
It runs on a guide rail anchored to the hanging wall. Using curved guide rails the direction
of travel can be changed at any time; forward, backward, or sideways.
51 | P a g e
INTERNSHIP REPORT AT SANJEN HEP 2019
Figure 26:
Alimak Method
Generally, the loader without backhoe is being used for transporting concrete mix into the
tunnel and for mucking purpose while the loader with backhoe is being equipped for the
surface construction works ( i.e, placing materials on batching plant, placing materials on
tippers for transporting to the site, etc )
52 | P a g e
INTERNSHIP REPORT AT SANJEN HEP 2019
CHAPTER 4
QUALITY CONTROL/ASSURANCETESTS
The trial mixes shall be deemed as approved if the characteristic strength fck so determined is
greater than the specified compressive strength. Based on the results of the tests on the trial
mixes, the Contractor shall submit full details of his proposals for mix design to the Engineer,
including the type and source of each ingredient, the proposed proportions of each mix and
the results of the tests on the trial mixes.
This new trial fix was formulated since aggregates from a different crusher site were intended
to be used. This trial mix was for strength of C16/20.
53 | P a g e
INTERNSHIP REPORT AT SANJEN HEP 2019
Material
Cement Agrakhanchi OPC
Coarse Aggregate (25 mm down) HH Cruher Plant (80%)
Coarse Aggregate (10mm down) HH Crusher Plant (20%)
Sand Powerhouse area sand washing plant
Admixture Sikament 1016 N/S
After preparation of the concrete mix 9 cubes were prepared in a standard mouldof
150mm*150mm*150mm. Slump test was consequently carried out for the concrete mix
which resulted in a slump of 75 mm which was to be obtained between 50mm-100mm. Then
compressive strength test was to be carried out for 3, 7 and 28 days.
Table 21: Compressive Strength of 7 days concrete for PCC in Power House
54 | P a g e
INTERNSHIP REPORT AT SANJEN HEP 2019
The standard moulds vary for concrete and for grout mix. For concrete mix the standard
mould size is 150mm*150mm*150mm whereas for grout mix the mould size is
50mm*50mm*50mm.
For the purpose of the test an analogue compression test machine of capacity 1500 KN was
present in the lab. This compressive testing machine is needed to be calibrated after one year
which is done by Pulchowk Campus which was last calibrated on 13 August 2018.
55 | P a g e
INTERNSHIP REPORT AT SANJEN HEP 2019
Compressive test of concrete for Power House Shear Wall-C25/30 (E.L. 1747.50-1748.00m)
(C-256)
Table 22: Source of Materials of concrete for Power House Shear Wall(E.L. 1747.50-
1748.00m)
Material
Cement Agrakhanchi OPC
Coarse Aggregate (25 mm down) HH Cruher Plant (80%)
Coarse Aggregate (10mm down) HH Crusher Plant (20%)
Sand Powerhouse area sand washing plant
Admixture Hind Plast Super-160 (0.8% by wt. of cement)
Retarder Hind Plast Super-R (0.5% by wt. of cement)
Table 23: Composition of concrete for Power House Shear Wall(E.L. 1747.50-1748.00m)
Table 24: Compressive Strength of 7 days concrete for Power House Shear Wall(E.L.
1747.50-1748.00m)
Table 25: Compressive Strength of 28 days concrete for Power House Shear Wall(E.L.
1747.50-1748.00m)
56 | P a g e
INTERNSHIP REPORT AT SANJEN HEP 2019
Table 26: Source of Materials of concrete for EDV Power House in SUHEP
Material
Cement Agrakhanchi OPC
Coarse Aggregate (30 mm down) Quarry, Cruher Plant
Sand Quarry, Headwork Site
Plasticizer Markplast SP-10
Table 27: Composition of concrete for EDV Power House in SUHEP
Fine Water
Batch Admixtu
Water Cement Coarse Aggre Cement Slump
volume re
(kg) (kg) Aggregate (kg) gate Ratio (mm)
(m3) (kg)
(kg) (%)
1 164 437 1095 730 7 0.375 140
Table 28: Compressive Strength of 7 days concrete for EDV Power House in SUHEP
Table 29: Compressive Strength of 28 days concrete for EDV Power House in SUHEP
57 | P a g e
INTERNSHIP REPORT AT SANJEN HEP 2019
Compressive test of concrete for Fiber Shotcrete in HRT Inlet Tunnel d/s (0+274 to 0+294)m
-C28/35( C-260)
Table 30: Source of Materials of concrete for Fiber Shotcrete in HRT Inlet Tunnel d/s (0+274
to 0+294)m
Material
Cement Sagarmatha OPC
Coarse Aggregate (10 mm down) SUHEP Cruher Plant
Sand Powerhouse area sand washing plant
Admixture Micro silica (10% by wt. of cement)
Plasticizer Sikament 170(1.5% by wt. of cement)
Fine Water
Batch Admixt
Water Cement Coarse Aggre Plasticier Cement Fiber Slump
volume ure
(kg) (kg) Aggregate (kg) gate (kg) Ratio (kg) (mm)
(m3) (kg)
(kg) (%)
1 247 540 334 1094 54 8.10 0.416 48.6 175
Table 31: Composition of concrete for Fiber Shotcrete in HRT Inlet Tunnel d/s (0+274 to
0+294)m
Table 32: Compressive Strength of 7 days concrete for Fiber Shotcrete in HRT Inlet Tunnel
d/s (0+274 to 0+294)m
Table 33: Compressive Strength of 28 days concrete for Fiber Shotcrete in HRT Inlet Tunnel
d/s (0+274 to 0+294)m
58 | P a g e
INTERNSHIP REPORT AT SANJEN HEP 2019
Compressive test of concrete for Power House Shear Wall-C25/30 (E.L. 1748.00-1749.00m)
(C-262)
Material
Cement Agrakhanchi OPC
Coarse Aggregate (25 mm down) HH Cruher Plant (80%)
Coarse Aggregate (10mm down) HH Crusher Plant (20%)
Sand Powerhouse area sand washing plant
Admixture Hind Plast Super-160 (0.8% by wt. of cement)
Retarder Hind Plast Super-R (0.5% by wt. of cement)
Table 34: Source of Materials for Power House Shear Wall(E.L. 1748.00-1749.00m)
Table 35: Composition of concrete for Power House Shear Wall(E.L. 1748.00-1749.00m)
Table 36: Compressive Strength of 7 days concrete for Power House Shear Wall(E.L.
1748.00-1749.00m)
Table 37: Compressive Strength of28 days concrete for Power House Shear Wall(E.L.
1748.00-1749.00m)
59 | P a g e
INTERNSHIP REPORT AT SANJEN HEP 2019
Compressive test of concrete for Power House Shear Wall-C25/30 (E.L. 1748.00-1749.00m)
(C-261)
Table 38: Source of Materials for Power House Shear Wall(E.L. 1748.00-1749.00m)
Material
Cement Agrakhanchi OPC
Coarse Aggregate (25 mm down) HH Cruher Plant (80%)
Coarse Aggregate (10mm down) HH Crusher Plant (20%)
Sand Powerhouse area sand washing plant
Admixture Hind Plast Super-160 (0.8% by wt. of cement)
Retarder Hind Plast Super-R (0.5% by wt. of cement)
Table 39: Composition of concrete for Power House Shear Wall(E.L. 1748.00-1749.00m)
Table 40: Compressive Strength of 7 days concrete for Power House Shear Wall(E.L.
1748.00-1749.00m)
Table 41: Compressive Strength of 28 days concrete for Power House Shear Wall(E.L.
1748.00-1749.00m)
60 | P a g e
INTERNSHIP REPORT AT SANJEN HEP 2019
Compressive test of concrete for Fiber Shotcrete in HRT Inlet Tunnel d/s (0+409 to 0+417)m
-C28/35( C-274)
Material
Cement Sagarmatha OPC
Coarse Aggregate (10 mm down) SUHEP Cruher Plant
Sand Powerhouse area sand washing plant
Admixture Micro silica (10% by wt. of cement)
Plasticizer Sikament 170(1.5% by wt. of cement)
Table 42: Source of Materials of concrete for Fiber Shotcrete in HRT Inlet Tunnel d/s(0+409
to 0+417)m
Table 43: Composition of Fiber Shotcrete in HRT Inlet Tunnel d/s(0+409 to 0+417)m
Fine Water
Batch Admixt
Water Cement Coarse Aggre Plasticier Cement Fiber Slump
volume ure
(kg) (kg) Aggregate (kg) gate (kg) Ratio (kg) (mm)
(m3) (kg)
(kg) (%)
1 247 540 334 1094 54 8.10 0.416 48.6 175
Table 44: Compressive Strength of 7 days Fiber Shotcrete in HRT Inlet Tunnel d/s(0+409 to
0+417)m
61 | P a g e
INTERNSHIP REPORT AT SANJEN HEP 2019
Table 45: Source of Materials of concrete for Adit 1 Backfill –C12/15 (0+595.0m)
Material
Cement Sagarmatha OPC
Coarse Aggregate (25 mm down) HH Cruher Plant (80%)
Coarse Aggregate (10mm down) HH Crusher Plant (20%)
Sand Powerhouse area sand washing plant
Table 47: Compressive Strength of 7 concrete for Adit 1 Backfill –C12/15 (0+595.0m)
62 | P a g e
INTERNSHIP REPORT AT SANJEN HEP 2019
Slump tests carried out in the site are done after the concrete mix has been prepared by the
batching plant. Thus some concrete mix was taken out from the batching plant for the slump
test to be carried out while the remaining was poured on to a transit mixer to be taken to the
concreting site.
Mold for slump test i.e. slump cone, non porous base plate, measuring scale, temping rod.
The mold for the test is in the form of the frustum of a cone having height 30 cm, bottom
diameter 20 cm and top diameter 10 cm. The tamping rod is of steel 16 mm diameter and
60cm long and rounded at one end.
The internal surface of the mouldis cleaned and greased. The mouldis placed on a smooth
horizontal non- porous base plate. The mould is filled in approximately 4 layers by tamping
each layer 25 times. The excess concrete Remove and the surface is level with a trowel.The
mortar or water leaked out between the mould and the base plate is to be cleaned. The mould
is raised from the concrete immediately and slowly in vertical direction.The slump is
Measure as the difference between the height of the mould and that of height point of the
specimen being tested.
63 | P a g e
INTERNSHIP REPORT AT SANJEN HEP 2019
64 | P a g e
INTERNSHIP REPORT AT SANJEN HEP 2019
In our case, a hole of 15 cm diameter hole and of 15 cm depth was dug in the site. The
compacted soil extracted from the hole was then weighed.Then it was passed through a
20mm sieve and the aggregate retained in 20mm sieve size were weighed. The standard sand
sample weighing 16 kg was kept in the sand pouring cylinder of diameter 15cm and height 45
cm and poured into the hole through the cone arrangement in the cylinder. The remaining
sand in the cylinder was weighed and in the site the wet soil moisture content is calculated.
The wet density as well as dry density of soil was calculated. Then samples of the compacted
soil were taken in can to be dried and finally calculate the moisture content and the relative
compactness. The test was done for two iterations.
Table 50: Summary of Result of Field Density Test of compacted soil of powerhouse from
EL 1746 to 1747m
66 | P a g e
INTERNSHIP REPORT AT SANJEN HEP 2019
Table 51: Result of Field Density Test of compacted soil of powerhouse from 1747 to
1749.80m
Table 52: Summary of Result of Field Density Test of compacted soil of powerhouse from
EL 1747 to 1749.80m
67 | P a g e
INTERNSHIP REPORT AT SANJEN HEP 2019
CHAPTER 5
OFFICE WORK
5.1. Introduction
For the remaining two weeks of our internship, we were mainly focusing on carrying out the
office work. We performed the following activities in the office,
The report should meet the questions raised during the project appraisals, i.e. the
various types of analyses should also be taken care.
Report should be with sufficient details to indicate the possible fate of the project
when implemented.
To understand importance of optimization of the schemes, detailed cost estimate,
payback period and return on investment.
The report should assure performance for reliable quality with in optimum cost.
68 | P a g e
INTERNSHIP REPORT AT SANJEN HEP 2019
Executive Summary
Introduction Background
Main technical and financial analysis
Recommended action plan
Appendices
Technical Specification is developed for a particular construction which specifies the quality
of the final product, production process, the inspection and tests methods, which should be
conducted during construction. The technical specification is of the following types
(b) Specification for the performance: This part specifies quality and performance
the end product. Method of testing as per NS or IS are also mentioned
(d) Safety, Public health Requirement: Safety and public health and environment
protection if needed are also mentioned.
69 | P a g e
INTERNSHIP REPORT AT SANJEN HEP 2019
Scope
o Scope of specification as what a particular specification covers.
Definition
o Definitions of the works, materials for which specifications are written.
Description of materials
o The quantity and quality of each material/ constituent required should be
clearly mentioned. For examples for Concreted Works, Cements, Sand, (fine
aggregate), Coarse Aggregate, water and formwork etc
o Quality testing for (acceptance of materials as per accepted code) for each
material like Cement, Sand (sieve analysis) and Aggregates (e.g. Grading
Requirements in accordance with IS 2386 Part 1, Flakiness index, Water
Absorption Test as set out in IS: 2386 Part 3., Los Angeles Abrasion (LAA)
tested in accordance with IS: 2386 Part 4, Aggregate Crushing Value (ACV)
in accordance with IS: 2486 Part 4) are should also be mentioned. Similarly
Compliance Testing/Process Control Testing is also mentioned.
o The quality of equipments to be used must be specified
Workmanship
o Transportation and storage of materials
o Method of mixing proportions / fabricating/ Erecting etc.
o Method of laying/ preparation of surface
o Compaction, finishing / curing,/ welding / painting etc. should be clearly
mentioned
Quality Control of production
Methods of measurement and payment
o For particularly new materials or works etc the methods of measurement and
the payment is also specified.
o If needed, tolerance for product measurement is also mentioned.
Equipments
o The equipment, tools and plant along with their capacities and performance
should be described clearly to carry out the work.
o The method of operation also should be stated in the specification.
70 | P a g e
INTERNSHIP REPORT AT SANJEN HEP 2019
If the performance of the works required is the same as that of standard specification,
we should make it our project specific by simply mentioning the clause of the
Standard Specification. (i.e. No need of rewriting whole description)
Should be Fair to all parties.
Hazards/ Risks/ Safety Requirements should be specified properly.
Specification is a part of contract which become a legal document (when contract is
signed, so they should be prepared keeping in mind constitution, prevailing Acts and
Regulations in mind.
The estimate is the probable cost of a work and is determined theoretically by mathematical
calculation based on the plans and drawing and current rates.
71 | P a g e
INTERNSHIP REPORT AT SANJEN HEP 2019
list of reinforcement bars in a tabular form and the following essential details are generally
given for a bar bending schedule in RCC works:
72 | P a g e
INTERNSHIP REPORT AT SANJEN HEP 2019
This leads to an estimation of the quantity of steel, which translates to the cost requirements
for steel work. Hence, BBS is used by the contractor who orders the reinforcements as well.
Unit cost of steel is charged by weight of steel purchased.
5.1.5.1. Introduction
A topographic map is a two-dimensional representation of a three-dimensional land surface.
Topographic maps are differentiated from other maps in that they show both the horizontal
and vertical positions of the terrain.
Through a combination of contour lines, colors, symbols, labels, and other graphical
representations, topographic maps portray the shapes and locations of mountains, forests,
rivers, lakes, cities, roads, bridges, and many other natural and man-made features. They also
contain valuable reference information for surveyors and map makers, including bench
marks, base lines and meridians, and magnetic declinations.
Topographic maps are used by civil engineers, environmental managers, and urban planners,
as well as by outdoor enthusiasts, emergency services agencies, and historians.
5.1.5.2. Procedure
The software is grouped into menus based on the similarity of functions.
73 | P a g e
INTERNSHIP REPORT AT SANJEN HEP 2019
74 | P a g e
INTERNSHIP REPORT AT SANJEN HEP 2019
α, the angle of the sloped side from vertical. The side slope is usually specified as
horizontal: vertical = z: 1.
The cross sectional area of flow is the trapezoid area:
A = y(b + B)/2, or
A = (y/2)(b + b + 2zy), because B = b + 2zy, as can be seen from the diagram.
75 | P a g e
INTERNSHIP REPORT AT SANJEN HEP 2019
These two methods are in use for the estimation ofthe flow conditions for various medium-
small scal ewater resource projects at the ungauged locations. When WECS/DHM method
was developed, thecountry had only 54 hydrological stations whichwere insufficient to
completely represent thecountry in terms of hydrological regime. So it has made several
recommendations of updating themethod every five years, developing hydrometricnetwork
review and plans, making extensiveprecipitation study including the Himalayan region and
Siwaliks etc.
WECS/DHM has inferred the MIP method asless comprehensive study. This design manual
is intended for guidance only and consequently it is not as complete, nor as rigorous, as
theWECS (1982) study (WECS/DHM, 1990). The hydrograph developed should be checked
orupdated so that the prediction made on the basisof the hydrograph is accurate and the
dischargepredicted could be used.
But these recommendations have not been realized and the method is in use since they are
developed. Since there is no other choice for the ungauged locations; these methods are
widely relied upon by the water resource projects. As these tools didn’t meet the
recommendations, it isnot wise to fully depend upon their predictions. So this study is to
76 | P a g e
INTERNSHIP REPORT AT SANJEN HEP 2019
check the anomaly andreliability so that the risk associated with theirpredictions will be
timely avoided.
Ϭ =ln (𝐐𝟏𝟎𝟎/𝐐𝟐)/2.326
where, S is the standard normal variant.
Table 54: Value of Standard Normal Variant for Corresponding Return Period
Standard
Return
Normal
Period T
Variant
(yrs)
(ϭ)
2 0
5 0.842
10 1.282
20 1.645
50 2.054
100 2.326
200 2.576
500 2.876
1000 3.09
5000 3.54
10000 3.719
77 | P a g e
INTERNSHIP REPORT AT SANJEN HEP 2019
Suffix ‘b’ stand for base station (ungauged station) and ‘i’ stands for index station (gauged
station).
Advantages
This method is useful if the hydro-meteorological data of the index station having
similar catchment characteristics with the base station are available for the data
extension.
Easy to excess the data.
Mostly preferable
Purpose:
To enable all contractors tendering for a contract to price on exactly the same
information. Subsequent to this, it is widely used for post-tender work such as:
material scheduling; construction planning; cost analysis; and cost planning.
Importance of BOQ
It provides basic idea of the project by giving the quantities to tenderers.
It defines the extent of the work. (But it should be identified in line with drawings&
specification as well).
It gives estimated or anticipated contract sum. (very important to client)
It provides a basis for valuation of variation. (Variation is to be discussed in detail).
78 | P a g e
INTERNSHIP REPORT AT SANJEN HEP 2019
XT = x + K × 𝛛 (𝐧−𝟏) ……… i
Where, 𝛛 (𝐧−𝟏) = standard deviation of sample of size
2
∑ (X −x)
¿√
N−1
yt − yn
K= ………….. ii
Sn
Where, yt is reduced variant for given time T
yn is reduced mean and Sn is reduced the standard deviation
N 0 1 2 3 4 5 6 7 8 9
10 0.4952 0.4996 0.5035 0.5070 0.5100 0.5128 0.5157 0.5181 0.5202 0.5220
20 0.5236 0.5252 0.5268 0.5283 0.5296 0.5309 0.5320 0.5332 0.5343 0.5353
30 0.5362 0.5371 0.5380 0.5388 0.5396 0.5402 0.5410 0.5418 0.5424 0.5430
40 0.5436 0.5442 0.5448 0.5453 0.5458 0.5463 0.5468 0.5473 0.5477 0.5481
50 0.5485 0.5489 0.5493 0.5497 0.5501 0.5504 0.5508 0.5511 0.5515 0.5518
79 | P a g e
INTERNSHIP REPORT AT SANJEN HEP 2019
60 0.5521 0.5524 0.5527 0.5530 0.5533 0.5535 0.5538 0.5540 0.5543 0.5545
70 0.5548 0.5550 0.5552 0.5555 0.5557 0.5559 0.5561 0.5563 0.5565 0.5567
80 0.5569 0.5570 0.5572 0.5574 0.5576 0.5578 0.5580 0.5581 0.5583 0.5585
90 0.5586 0.5587 0.5589 0.5591 0.5592 0.5593 0.5595 0.5596 0.5598 0.5599
N 0 1 2 3 4 5 6 7 8 9
10 0.9496 0.9676 0.9833 0.9971 1.0095 1.0206 1.0316 1.0411 1.0493 1.0565
20 1.0628 1.0696 1.0754 1.0811 1.0864 1.0915 1.0961 1.1004 1.1047 1.1086
30 1.1124 1.1159 1.1193 1.1226 1.1255 1.1285 1.1313 1.1339 1.1363 1.1388
40 1.1413 1.1436 1.1458 1.1480 1.1499 1.1519 1.1538 1.1557 1.1574 1.1590
50 1.1607 1.1623 1.1638 1.1658 1.1667 1.1681 1.1696 1.1708 1.1721 1.1734
60 1.1747 1.1759 1.1770 1.1782 1.1793 1.1803 1.1814 1.1824 1.1834 1.1844
70 1.1854 1.1863 1.1873 1.1881 1.1890 1.1898 1.1906 1.1915 1.1923 1.1930
80 1.1938 1.1945 1.1953 1.1959 1.1967 1.1973 1.1980 1.1987 1.1994 1.2001
90 1.2007 1.2013 1.2020 1.2026 1.2032 1.2038 1.2044 1.2049 1.2055 1.2060
100 1.2065
N = Sample size
The log transferred series with base 10 are assumed to follow Log Pearson type III
distribution and then analyzed. If x is the variant of a random hydrologic series, the Z variant
is given by:
Z=log x ……………………………………………………. i
ZT =Z+ K Z σ Z………………………………………………. ii
80 | P a g e
INTERNSHIP REPORT AT SANJEN HEP 2019
Source:(Subramanya, 2013)
Table 3Kz = F (Cs, T) for use in Log Pearson type III Distribution
81 | P a g e
INTERNSHIP REPORT AT SANJEN HEP 2019
2
√ ∑ (Z−z)
σ Z= …….……. iii
N −1
3
N ∑(Z−z)
C S= ……….... iv
(N−1)(N−2)σ Z 3
82 | P a g e
INTERNSHIP REPORT AT SANJEN HEP 2019
CHAPTER 6
FIELD VISIT
During the internship period, we had the opportunity to visit another under construction
hydropower located nearby Rasuwagadhi Hydroelectric Project (111 MW)
6.1. Introduction
Rasuwagadhi Hydroelectric Project is a run of the river type project with the design discharge
of 80 m3/sec and available gross head of 168m. The source river is BhoteKoshi (Trishuli)
which flows down from Tibet, China entering Nepal at Rasuwagadhi reaches down to
Trishuli in Rasuwa District. The headworks site is located about four hundred meters
downstream from the confluence of Kerungkhola and Lendekhola which are the Boundary
Rivers of Nepal and China (Tibet).
Hydrology
Catchment Area : 3300 sq km
Average Precipitation : 2211 mm/year
100 years Design Flood : 1167 cumecs
Design Discharge : 80 cumecs
Headworks
Diversion structure : Non-gated weir
Length of weir : 61.5 m
Weir crest elevation : EL 1790.00msl
Height of weir :10 m
Under sluice : Two Radial Sluice gate along with stop log gate
83 | P a g e
INTERNSHIP REPORT AT SANJEN HEP 2019
Gravel Trap
Type : Rectangular
Particle Size to be settled : 2 mm
Length of Gravel Trap : 26.2 m length
Bed Slope : 1:50
Desander
Type : Underground Serpent Sediment Slucing System
No of Basin : 3 Nos
Particle Size to be settled : 0.2 mm
Length of Desander (Main Part) : 125m
Length of Transition : 34.36m
Size of Desander Cavern : 15m * 15.38m
Size of Desander (Width X Depth) : 15m * 17.1m
Bed Slope : 1:40
Headrace Tunnel
Conveyance Length : 4184.5m
Type : Horseshoe shaped tunnel
Internal Diameter : 7.150m * 5.162m (Class I, II and III)
: 3m diameter lining (Class IV, V and V’a’)
Average tunnel slope : 0.005409
Surge Tank
Type : Underground, restricted orifice
Size : 16m diameter and 59.15m height
Max. Upsurge EL : 1806.00 msl
FSL. EL : 1790.00 msl
Max. Downsurge EL : 1765.00 msl
Penstock Pipe
Type : Steel lined Underground penstock
Vertical Penstock Shaft:
Height without bend : 114m
Height with bend : 139.05m
Size of Pipe : 4.8m
Horizontal Penstock Pipe:
84 | P a g e
INTERNSHIP REPORT AT SANJEN HEP 2019
Length : 127.307m
Pipe Material : Mild steel
Size of Pipe : 4.8m-12.5m, 4m-14.895m, 2.9m-17.276m, 2m- 79.236m
Number of supports : 5 Nos Saddle Supports
Powerhouse Cavern
Type : Underground with outdoor Switchyard
PH Cavern dimension (l x b) : 76.3 m x 15m
Height of PH Cavern : 39.5m
Transformer Cavern
Type : Underground
Cavern dimension (l x b) : 85.7m x 12.9m
Height of Transformer Cavern : 16.1m
Tailrace Tunnel
Type : Horseshoe shape
Internal Diameter : 6m
Length : 598.55 m
Tailrace water level : EL 1615.0msl
Turbine
Number of Units :3
Type of Turbine : Francis
Shaft Arrangement : Vertical
Rated discharge for each turbine : 26.67 m3/s
Rated Head : 158.6 m
Rated Output for each unit : 37000 kW
Turbine Axis Level : 1615.2 msl
Machine Floor Level : 1625.0 msl
Generators
No of units :3
Generator Type : 3 phase AC Synchronous, 50Hz
Excitation : Brushless excitation
Layout : Vertical
Rated Output : 43.75 MVA
Transmission Line
Transmission Length : 10 km (Rasuwagadhi PH – Chilime S/S)
Transmission Voltage : 132 kV
Type of Circuit : Double circuit line
Proposed Interconnection Point : NEA 132/33 kV Proposed Substation at Switiatar
85 | P a g e
INTERNSHIP REPORT AT SANJEN HEP 2019
86 | P a g e
INTERNSHIP REPORT AT SANJEN HEP 2019
CONCLUSION
In conclusion, this internship which has been included in our course has been very beneficial
to us. We have learnt a lot during our internship period about the construction of a
Hydropower project and also the office work carried out during the construction period of
Hydropower project. We believe that the objectives of the internship activity have been met
by us during the 6 weeks spent under the Host Organization.
Some of the problems that we encountered during our internship period were:
1. Entering the HRT and Audit 1 required gum boots, however we could not provided
with gum boots due to the reason that extra gum boots were not present
2. The vehicles present in the site tended to be broken down thus transportation was a
problem
Some of the problems that we were visible during our 4 week site stay are listed below:
1. Works were not carried out on the exact time according to the schedule provided by
the Contractor; there was always a delay of some sort.
2. Communication gaps could be seen between some cases; as during rib installation in
Audit I, number of tie rods and anchor rods were less than required though instruction
had been provided by the supervising engineer to the workers, another example of
such communication gap could be seen during rock bolt pull out test in surge shaft,
instructions had been given for concrete padding to be done on the marked rock bolts
however it had not been carried out as there had been a change in contractors from
Himal Hydro to Tundi constructions, thus the information had not been clearly
transferred.
Finally in conclusion, as a whole this internship period was very beneficial for us. We have
been able to experience the construction activities that occur in development of a
Hydropower project plus the office work that goes on to make it all possible.
87 | P a g e
INTERNSHIP REPORT AT SANJEN HEP 2019
REFERENCES
88 | P a g e
INTERNSHIP REPORT AT SANJEN HEP 2019
ANNEXES
89 | P a g e
INTERNSHIP REPORT AT SANJEN HEP 2019
ANNEX I
DETAIL DRAWINGS
Annex I-1
INTERNSHIP REPORT AT SANJEN HEP 2019
AnnexI-2
INTERNSHIP REPORT AT SANJEN HEP 2019
AnnexI-3
INTERNSHIP REPORT AT SANJEN HEP 2019
AnnexI-4
INTERNSHIP REPORT AT SANJEN HEP 2019
AnnexI-5
INTERNSHIP REPORT AT SANJEN HEP 2019
AnnexI-6
INTERNSHIP REPORT AT SANJEN HEP 2019
AnnexI-7
INTERNSHIP REPORT AT SANJEN HEP 2019
AnnexI-8
INTERNSHIP REPORT AT SANJEN HEP 2019
ANNEX II
The details of the office work is being attached along with this. This section mainly includes
the computation carried on MS Excel Worksheet and AutoCAD drawing of following works.
Annex II-1
INTERNSHIP REPORT AT SANJEN HEP 2019
ANNEX III
The final year internship to fulfill the undergraduate course started on 8th May, 2019.
First Week: (8th May, 2019 – 13th May, 2019)
Day 1:
Power house visit (Sanjen HEP) and Sanjen Upper HEP head works and power
house visit.
Observed compaction of soil to 2B grade for foundation for surface structures.
Field Density Test of the compacted soil by Sand Replacement Method for which
design Maximum dry density (MDD) of 2.139gm/cc and OMC of 95% and the
observed values were MDD of 2.090 gm/cc and OMC of 97.68%.
Observed compressive Strength test of powerhouse shear wall concrete ( C 25/30 )
whose 28 days strength was found to be 39.19 N/mm2.
Inspection of no. and size of rebar for mass concreting.
Day 2:
Slump test performed on site for the concrete, to be used in concreting of powerhouse,
whose slump height was observed 135mm.
Mass concreting of the powerhouse upto the depth of 1.3m (1743.40m – 1744.70m)
in the bifurcation area which covered the volume of 200 m3.
Day 3:
Site visit of Sanjen Upper HEP headrace tunnel, adits and surge shaft.
Desk study of headrace tunnel and powerhouse of Sanjen Upper HEP.
Observed chipping of the concrete in bifurcation area
Day 4:
Curing and chipping of concrete in powerhouse bifurcation area and shear wall.
7 day Compressive strength test of concrete of spillway found to be 23.77 N/mm2.
Day 5:
Site visit to Adit III and Penstock Tunnel of Sanjen HEP and surge shaft observation.
Rebar Laying in powerhouse.
Blasting at Adit I.
Day 6:
Visit HRT inlet
Observe Tunnel Cycle in audit I (Drilling, Charging, Blasting and Mucking)
Observe rebar laying and formwork at bifurcation area.
Annex III-1
INTERNSHIP REPORT AT SANJEN HEP 2019
Annex III-2
INTERNSHIP REPORT AT SANJEN HEP 2019
Day 3:
Inspection in surge shaft ( Adit III ) where the padding in the marked rock bolt were
not done properly due to which targeted rock bolt pull out test could not be
performed.
Day 4:
Rib support installation in Adit I
Inspection of cavity in tunnel face in Adit I was done and additional spilling dowels
and rib support were deemed necessary.
Required quantity of backfill concrete for the cavity seemed high.
Learn Bar Bending Schedule.
Day 5:
Curing, rebar laying at powerhouse.
Inspection of rib support installation at Adit I where steel plate laying and no. of rods
for rib support were checked.
Surveying for change of control point for estimation of backfill concrete quantity.
Observe trial mix of concrete for powerhouse.
Slump test of the trial mix (50-100 mm to be obtained) was observed to be 70 mm.
Observe compressive strength of TM-90 (30 N/ mm2 to be obtained) which was found
out to be 42.80 N/mm2.
Day 6:
Inspection of rib support installation at Adit I for concreting was done and
insufficiency in no. of tie rods and anchor rods was observed.
Supervision of concrete mix for concrete at rib till spring line which was c12/15 in
accordance with TM-99.
Slump Test for the prepared concrete (50-100mm slump) was 20mm and cubes were
prepared for compressive strength test.
28 days compressive strength fibre shotcrete (35 N/ mm2 to be obtained ) was found
to be 43.67 N/mm2.
Annex III-3
INTERNSHIP REPORT AT SANJEN HEP 2019
Fifth Week: (2th June- 9th June, 2019), holiday in 5th June.
Day 1:
Detail Project Report (DRP) study
Day 2:
Technical Specification Study
Day 3:
Quantity Workout of SHEP tailrace.
Estimation of quantities.
Day 4:
Bar bending schedule of SHEP tail race.
Literature review of bar bending schedule.
Preparationof bar bending schedule.
Day 5:
Annex III-4
INTERNSHIP REPORT AT SANJEN HEP 2019
Estimation of quantities such as excavation, structure cut, drain cut and back filling of
gabion protection wall for access road in SUHEP
Day 6:
Design of side drain at access road of SHEP balancing pond.
Annex III-5