Notore Chemical Industries Plc               GE / P / 02
Rev. No.1
                                                                            Title :Process For Rotary
                 General Engineering                                                                                              Rev Date :17.08.16
                                                                                    Inspection
                                                                                                                                  Page : 1 of 7
    1.0 OBJECTIVE: To ensure rotating equipment reliability,eliminate breakdown through the application of
    modern inspection techniques, to detect equipment problems at an early stage,for accurate failure prediction and
    application of sound corrective measures.
    2.0 SCOPE:
    Start:To carry out ECM schedule checks on rotating equipment.
    End:Send reports / recommendation based on machinery acquired data.
    3.0 RESPONSIBILITY & AUTORITY: General Engineering Manager is accountable for establishing, managing and continous improvement of this process.
    4.0 PROCESS DEFINITION: SIPOC DIAGRAM
                                                                      Process
                                     Knowledge /       Resources /                             Criteria / Method
     Supplier        Inputs            Skills          Technology       Critical Activities       for Control          Output       Customer       Requirements
                                  Machine            CSI -2130 /                               Calibrate the CSI- Machinery
               Critical / non-    vibration          Dynamix 2500, Data monitoring ,          2130 machine health health
               critical           monitoring         Machinery       acquisition &            analyzer on a yearly assessment
    Production equipment.         techniques.        health analyzer analysis .                      basis.        reports        Production      Timely response
                                                    AMS /
                                  Vibration         Emonitor -
                                  Parameters and    Machinery          Data monitoring &        ECM schedule / Abnormality             Accurate feed
    Production Work permit        analysis skills.  health manager     analysis .              review of schedule. report  Maintenance back
                                                    The CSI 5200
                                                    Machinery
                                   Complementary Health Oil
                                  Technology ,like Analyzer (Mini-                                                 Machinery
                 Operation /      Lube oil          Oil Laboratory)    Spectrographic &       Calibrate the CSI-   health
    Technical    Maintenance      analysis,Infrared and Infrared       Thermographic          5200 and Infrared    assessment                 equipment
     Services    Manual           thermography. Thermography           analysis               Camera.              reports        Maintenance availability.
                                                     Knowledge of
                                                     operating
                                  Operation /        parameters /                        Machinery health          Condition
            Instrument            Maintenance        equipment         Equipment history monitoring                Monitoring                     Accurate feed
Procurement Specifications        Manual             history.          and trending.     techniques.               Equipment      Warehouse       back
                                                     Knowledge of      Report /
                                                     operating         Recommendation of      Regular review of
            Equipment               Basic rotating   parameters /      checks carried out     set alarm criteria
            Condition                equipment       equipment         on rotating            specific to each     Abnormality Maintenance
Maintenance Assessment               principles.     history.          equipment.             equipment.           report      / Production Timely response
                                   Rotating
                                  equipment
                                  principles,
                                  Condition
                                Monitoring and
     Human       Information on   Reliability                                                 Regular review of                                   Accurate feed
    Resources       Training     Engineering. Dept.Budget              Fund allocation        Training Calendar    Certification Inspection       back
                                                                                                                                  GE/ P / 02
                                                                       Notore Chemical Industries Plc
                                                                                                                                  Rev. No.1
                                                                                Title :Process For Rotary
                                                                                        Inspection
                 General Engineering                                                                                              Rev Date :17.08.16
                                                                                                                                  Page :2 of 7
5.0 INTERESTED PARTIES AND THEIR EXPECTATION:
Serial No.           INTERESTED PARTIES                  INTERNAL / EXTERNAL                                NEEDS / EXPECTATION                            MONITORING / REVIEW
1                             Production                             Internal                         Equipment availability / Reliabilty               Ref. Process Performer Matrix 6.0
2                          Maintenance                               Internal                    Analysis Report / Trouble shooting support             Ref. Process Performer Matrix 6.0
3                       Third Parties                       External                       Equipment data / Performance report               Ref. Process Performer Matrix 6.0
                                                               Notore Chemical Industries Plc                         GE/ P / 02
                                                                                                                      Rev. No.1
                                                                       Title :Process For Rotary
              General Engineering                                              Inspection                             Rev Date :17.08.16
                                                                                                                      Page :3 of   7
6.0 PROCESS MEASUREMENT MATRIX:
Measurement
                                                                                                                                                         Review
                              Type (Efficiency /                 Method of           Record of
Serial No.    Parameter       Effectiveness)     Unit of Measure Measurement         Measurement         Frequency     Target          Responsibility    Frequency   Forum
                                                               1 - Total list of
                                                               rotary equipment
                                                               covered in
                                                               schedule ,
                                                               2 -Total number of
                                                               equipment schedule
                                                               comprises
                                                               equipment in                                                                                           Unit meeting
                                                               running and idle
                                                               mode , as against
                                                               the plan,Calculated
                                                               on weekly basis.
                                                               3 -Data to be
                                                               collected from
                                                               AMS/Dynamix
                                                               Rockwell
              Adherence to                                     EMONITOR
              ECM schedule                                     software,and Pdm
              of rotary                                        Trackers.
1             equipment       Efficiency       percentage                            Pdm Tracker         Weekly       80               Team Leader       Monthly
                                                               1 - Reports
                                                               generated for all
                                                               abnormal
                                                               equipment and
                                                               communicated to
                                                               internal customer
                                                               on same day.
                                                                   2 - Ratio of total                                                                                 Unit meeting
                                                               number of report
                                                               communicated on
                                                               same day to total
                                                               number of
                                                               abnormal equipmet
               Abnormality                                     identied on that
              reports                                          day.
              communicated                                       3 - Data to be
              to internal                                      collected from ECM
              customer within                                  ( abnormality)         ECM
2             24 hours        Effectiveness    percentage      report.                AbnormalityReport Weekly        100              Team Leader       Monthly
                                                               1 - Percentage of
                                                               faults detected.
                                                                                                                                                                      Unit meeting
                                                                       2 - Ration of
              Faults detected                                  faults identified on
              on the field and                                 field ,communicated
              communicated                                     immediately, as
              to internal                                      against total faults
              customer                                         detected.             ECM Log /                                         ECM Engineer
3             immediately.     Effectiveness   percentage      1 - Equipment         Production Log      Weekly       100              /Superintendent   Monthly
                                                               requiring
                                                               parameter setting.
                                                               2 - Total number of
                                                               equipment alarm                                                                                          Plant
                                                               review and setting                                                                                     management
                                                               done as against                                                                                         meeting
                                                               total number of
                                                               equipment
                                                               requiring review.
              Review and
              setting of alarm
              parameter                                             3 - AMS
              specific to each                                 machinery manager                                                       ECM
4             equipment        Efficiency      percentage      , CSI 2130 /      Alarm Review Log. Quarterly          100              Superintendent    Yearly
                                                                                                     GE / P / 02
                                               Notore Chemical Industries Plc
                                                                                                     Rev. No.1
General Engineering
                                                                                                     Rev Date :17.08.16
                                     TITLE : PROCESS FOR ROTARY INSPECTION
                                                                                                     Page : 4 of 7
7.0 PROCESS FLOW CHART:
ACTIVIT
                                              PROCESS FLOW CHART                                                                         RESPONSIBILITY
 Y No.
                                                START
                                      GET INFORMATION ON
                  ECM                                                                                  ECM
         1      SCHEDULE              EQUIPMENT SCHEDULE                                            (FIELD)               ECM TEAM LEADER/ ENGINEER
                                                                                                    LOG BOOK
                                              FOR ECM
                                     REQUEST FOR WORK                           A
         2             F                     PERMIT                                                                       ECM ENGINEER
                                 F
                                                                                                A
                                                              NO
                                          IS WORK
                                           PERMIT                                     REVISED SCHEDULED
                                         APPROVED
         3                                                                                                                ECM ENGINEER / PRODUCTION
                                       YES
              1.CSI 2130 /           SELECT PARAMETER
              2.DYNAMIX 2500                 YES                                SWOT ANALYSIS
              MACHINERY HEALTH        TO BE MEASURED
              ANALYZER 3.RISK         SPECIFIC TO EACH
              REGISTER
              4.SWOT ANALYSIS         EQUIPMENT IN THE
         4                           ANALYZER                                                                             ECM ENGINEER
                SOP FOR CSI                  SELECT
               2130 / DYNAMIX
         5     2500 ROCKWELL           MEASUREMENT                                                                        ECM ENGINEER
                 MACHINERY              LOCATION
               HEALTH
               ANALYZER
                                                                            WRITE THE
                                                                            ACQUIRED
                                        TAKE READING                        MACHINERY
         6            CSI                  AND                              DATA ON                                       ECM ENGINEER
                 2130/DYNAM              TREND DATA.                        VIBRATION
                                                                            BOARD
                 IX2500 DATA
                 COLLECTOR
                                        DOWNLOAD THE                                  AMS SUITE
              SOP FOR CSI
              2130 / DYNAMIX              ACQUIRED                                   MACHINERY
         7                                MACHINERY                                  MANAGER /                            ECM TEAM LEADER / ENGINEER
              2500 DATA
              COLLECTOR                    DATA                                     DYNAMIX 2500
                                                                                       ALLEN
                                                                                    BRADLEY SOFT
                                                                                        WARE
                                                 B
                                                                                                                                           GE / P / 02
                                                                                                                                           Rev. No.1
General Engineering
                                                            Notore Chemical Industries Plc
                                                                                                                                           Rev Date : 17.08.16
                                                  TITLE : PROCESS FOR ROTARY INSPECTION
                                                                                                                                           Page : 7 of 7
     8.0 References:
       S.NO.                    REFERENCE TITLE                             REFERENCE
                                                                               NO
         1     SOP FOR CSI 2130 MCHINERY HEALTH ANALYSER               GE / S /35
         2     SOP FOR DYNAMIX2500 ROCKWELL DATA COLLECTOR.            GE / S/ 36
                                   SOP FOR SUPPORTIVE TECHNOLOGY
         3     SOP FOR CSI 5200 -MINI LAB. OIL ANALYSIS          GE / S / 37
         4     SOP FOR INFRARED THERMOGRAPHY                     GE / S / 38
          5    SOP FOR ALARM LIMITS OF AMMONIA EQUIPMENT        GE / S / 41
          6    SOP FOR ALARM LIMITS OF UREA SYNTHESIS EQUIPMENT GE / S / 42
          7    SOP FOR ALARM LIMIT OF GRANULATION EQUIPMENT     GE / S / 43
          8    SOP FOR ALARM LIMIT OF UTILITY EQUIPMENT         GE / S / 44
          9    SOP FOR ALARM LIMIT OF PRODUCT HANDLING EQUIPMENGE / S / 45
         10    VIBRATION SEVERITY CHART                         GE / S / 46
         11    CORRECTIVE MAINTENANCE                           MECH / P / 01
         12    RISK REGISTER                                    IAIC/F/P-02/07
         13    SWOT ANALYSIS                                    QM-9001-05
      9.0 RECORDS:
                                                                                                                                          RETENTION
                                                                                                                                          PERIOD AT
       S.NO.                      RECORD TITLE                              RECORD NO             FILE NAME/   LOCATION     MAINTAINED BY   LEAST
                                                                                                                               GENERAL
                                                                                                VIBRATION      INSPECTION    ENGINEERING
         1                      VIBRATION SCHEDULE                     GE / F / P-02 / 01       SCHEDULE         OFFICE       MANAGER          2YRS
                                                                                                                               GENERAL
                                                                                                ECM (FIELD )   INSPECTION    ENGINEERING
         2                      ECM(FIELD) LOG BOOK                       GE / F / P-02 / 02    LOG BOOK         OFFICE       MANAGER          2YRS
                                                                                                                               GENERAL
                                                                                                VIBRATION      INSPECTION    ENGINEERING
         3                  VIBRATION TRENDING REPORT                     GE / F / P-02 / 03    TREND REPORT     OFFICE       MANAGER          2YRS
                                                                                                                               GENERAL
                                                                                                ABNORMALITY    INSPECTION    ENGINEERING
         4                     ABNORMALITY REPORT                      GE / F / P-02 / 04       REPORT           OFFICE       MANAGER          2YRS
                                                                                                                               GENERAL
                                                                                                FOLLOW UP      INSPECTION    ENGINEERING
         5                       FOLLOW UP REPORT                        GE / F / P - 02 / 05   REPORT           OFFICE       MANAGER          2YRS
                                                                                                                               GENERAL
                                                                                                MONTHLY        INSPECTION    ENGINEERING
         6                       MONTHLY REPORT                          GE / F / P - 02 / 06   REPORT           OFFICE       MANAGER          2YRS
                                                                                                                               GENERAL
                                                                                                               INSPECTION    ENGINEERING
         7                       ECM DAILY REPORT                      GE / F / P -02 / 07      DAILY REPORT     OFFICE       MANAGER          2YRS
                                                                                                FAULTS
                                                                                                DETECTED &                     GENERAL
                                                                                                COMMUNICATE    INSPECTION    ENGINEERING
         8              FAULTS DETECTED AND COMMUNICATED               GE / F / P -02 / 08      D                OFFICE       MANAGER          2YRS
                                                                                                                               GENERAL
                                                                                                ALARM REVIEW   INSPECTION    ENGINEERING
         9                    ALARM REVIEW LOG BOOK                    GE / F / P -02 / 09      LOG BOOK         OFFICE       MANAGER          5YRS