Republic of the Philippines
DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS
IMPLEMENTING OFFICE
Office Address
PROJECT PROFILE
Implementing Office : DPWH _________________
Contract ID/PCMA :
Project Name :
A. PROJECT DESCRIPTION
Station Limits :
Scope/Description of Works :
:
:
:
:
:
:
:
:
:
:
:
:
B. CONTRACT DATA
Province :
Region :
Project Category :
Sources of Fund :
Contractor :
Consultant :
Original Contract Amount :
Revised Contract Amount due to :
approved ___________________
(intentionally left blank for possible series of revisions) :
(intentionally left blank for possible series of revisions) :
:
Start Date :
Original Contract Duration :
Revised Contract Duration due to :
approved ___________________
(intentionally left blank for possible series of revisions) :
(intentionally left blank for possible series of revisions) :
:
Original Completion Date :
Revised Completion Date due to :
approved ___________________
(intentionally left blank for possible series of revisions) :
(intentionally left blank for possible series of revisions) :
:
C. KEY PERSONNEL
C.1 DPWH PERSONNEL :
NAME ACCREDITATION NO.
Project Engineer -
Materials Engineer -
Project Inspectors -
-
-
-
-
-
-
-
C.2 CONTRACTOR'S PLEDGED KEY PERSONNEL :
NAME ACCREDITATION/PRC NO.
Project Engineer -
Materials Engineer -
Safety Engineer/Officer -
Site Engineer/s -
-
-
-
-
-
-
D. LIST OF CONTRACTOR'S PLEDGED EQUIPMENT
NO. OF NO. OF
EQUIPMENT DESCRIPTION EQUIPMENT DESCRIPTION
UNITS UNITS
Republic of the Philippines
DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS
(IMPLEMENTING OFFICE)
(Office Address)
PROJECT PROFILE
Implementing Office : DPWH - _________________
Contract ID/PCMA :
Project Name & Address :
A. PROJECT DESCRIPTION
Station Limits :
Scope/Description of Works :
:
:
:
:
:
:
:
:
:
:
:
:
B. CONTRACT DATA
Province :
Region :
Project Category :
Sources of Fund :
Contractor :
Consultant :
Original Contract Amount :
Revised Contract Amount due to Approved
VO # ___________________ :
VO # ___________________ :
VO # ___________________ :
:
Start Date :
Original Contract Duration :
Revised Contract Duration due to Approved
TE # _____ / VO # ______ :
TE # _____ / VO # ______ :
TE # _____ / VO # ______ :
:
Original Completion Date :
Revised Completion Date due to Approved
TE # _____ / VO # ______ :
TE # _____ / VO # ______ :
TE # _____ / VO # ______ :
:
C. KEY PERSONNEL
C.1 DPWH PERSONNEL :
NAME ACCREDITATION NO.
Project Engineer -
Materials Engineer -
Project Inspectors -
-
-
-
-
-
-
-
C.2 CONTRACTOR'S PLEDGED KEY PERSONNEL :
NAME ACCREDITATION/PRC NO.
Project Engineer -
Materials Engineer -
Safety Engineer/Officer -
Site Engineer/s -
-
-
-
-
-
-
D. LIST OF CONTRACTOR'S PLEDGED EQUIPMENT
NO. OF NO. OF
EQUIPMENT DESCRIPTION EQUIPMENT DESCRIPTION
UNITS UNITS
Republic of the Philippines
DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS
(IMPLEMENTING OFFICE)
(Office Address)
CONTRACT ID NO. :
PROJECT COMPONENT ID :
PROJECT NAME :
LOCATION :
CONTRACTOR :
CONSULTANT :
DATE :
LEGEND :
WEATHER A.M. (outer circle) : FAIR
P.M. (inner circle) : CLOUDY
RAIN SHOWER
HEAVY RAIN
MANPOWER ON SITE :
MANPOWER No. MANPOWER No.
Project Manager Foreman
Project Engineer Driver
Materials Engineer Heavy Equipment Operators
Project Inspectors Laborers
Survey Engineer Mechanic
Mechanical Engineer Auto Electrician
Electrical Engineer Laboratory Technician
Plumbing/Sanitary Engineer Carpenters
Safety Officer/Safety & Health Personnel Masons
Others (specify) : Others (specify) :
EQUIPMENT ON SITE :
No. of No. of
Status TYPE OF EQUIPMENT Units
Status TYPE OF EQUIPMENT Units
STATUS OF EQUIPMENT :
Bulldozer Asphalt Paver ü Operational
Backhoe Asphalt Distributor Idle
Backhoe with Breaker Air Compressor û Breakdown
Payloader Tandem Roller n/a Not Applicable
Dump Truck Pneumatic Roller
Water Truck Electric Generator
Concrete Paver Concrete Cutter
Vibratory Roller Crawler Crane
Batching Plant, Concrete/Asphalt Submerssible Pump
Concrete Vibrator Material Testing Equipment
Screeder Others (specify) :
One Bagger Mixer
Plate Compactor
Welding Machine
CONSTRUCTION ACTIVITIES :
Continued at the back of this page.
Page No.
REMARKS :
DPWH PERSONNEL ON-SITE :
NAME TIME-IN TIME-OUT SIGNATURE
- -
- -
- -
- -
- -
- -
- -
- -
- -
VISITORS ON-SITE :
Prepared by: Concurred by:
Site Engineer /Site Inspector / Project Engineer (Contractor)
Project Inspector (DPWH/Consultant)
Noted by:
Project Engineer (DPWH)
Page No.
Republic of the Philippines
DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS
(IMPLEMENTING OFFICE)
(Office Address)
CONTRACT ID NO. :
PROJECT COMPONENT ID :
PROJECT NAME :
LOCATION :
CONTRACTOR :
CONSULTANT :
DATE :
CONSTRUCTION ACTIVITIES :
QUALITY CONTROL/ASSURANCE ACTIVITIES :
Page No.
REMARKS :
Prepared by: Concurred by:
Materials Engineer (DPWH/Consultant) Materials Engineer (Contractor)
Noted by:
Project Engineer (DPWH)
Page No.
COVER PAGE (HARDBOUND - royal blue)
Font : Times New Roman
Font Size : 16
Font Style : Bold, Italic
Republic of the Philippines
DEPARTMENT OF PUBLIC WORKS HIGHWAYS
(IMPLEMENTING OFFICE)
(Office Address)
CONSTRUCTION LOGBOOK
CONSTRUCTION
LOGBOOK
Font : Times New Roman
Font Size : 36
Font Style : Bold
Side View Front View
COVER PAGE (HARDBOUND - royal blue)
Font : Times New Roman
Font Size : 16
Font Style : Bold, Italic
Republic of the Philippines
DEPARTMENT OF PUBLIC WORKS HIGHWAYS
(IMPLEMENTING OFFICE)
(Office Address)
MATERIALS LOGBOOK
MATERIALS
LOGBOOK
Font : Times New Roman
Font Size : 36
Font Style : Bold
Side View Front View
BACK PAGE (HARDBOUND - royal blue)
Font : Times New Roman
Font Size : 10
Font Style : Regular
DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS
Rear View
Republic of the Philippines
DEPARTMENT OF PUBLIC WORKS HIGHWAYS
(IMPLEMENTING OFFICE)
(Office Address)
PROJECT LOGBOOK