PRODUCTION SUMMARY REPORT - UPDATED 16-APRIL-23
ON-GOING / PROJECTS TO CLOSE FABRICATION
Project Sn Description Qty / Area Remarks
Jubeir Annex 1 8 CW, 6 Hinge Door, 1 Sliding Window, 6 35sqm Ready, bal. openable at PP
Openable Leaf
Jubeir Resthouse 2 4pcs Door Leaf Ready
Jubeir Villa 10 3 1pc Bottom Hung Ready
Jubeir Villa 5 4 3pcs Hinge Door 9sqm Ready
Al Mousa 5 2pcs Auto.Sliding Door 13sqm Ready
Arabian Oud 6 6pcs Hinge Doors 19sqm Ready
Feras Al Madi 7 CW, Doors & Windows + 22pcs Flashings 51sqm Ready
Mahalawi Villa 8 3 Doors & 5 Windows 37sqm Ready
Mehmadi Jeddah 9 2 Skylight + 1 Auto.Sliding Door 25sqm Ready
Mehmadi Jeddah 10 Schuco Windows & Doors for Villa 39sqm at PP
Mehmadi Jeddah 11 5pcs Folding Door 69sqm at PP, waiting Powder
Ousaimi Villa 12 1 Hinge Door + 1.5mm Alum Flashing 4sqm Door Ready, Flashing at PP
Rossais Bldg 13 8pcs Hinge Door 26sqm Ready
Rossais Bldg 14 18pcs Vertical Cladding 33sqm New CL, not yet started
Tabuk Univ. 15 2pcs Fixed Windows 3sqm Ready
Metro DEPA 16 End Closure 658 LM Ready
Metro 1C2 17 Steel Skylight 5 sets on-going
Metro 1H2 18 46pcs Bal. Handrails on-going
Metro 1J2 19 Curtain Wall 450sqm Ready
Metro 1J2 20 40x80 Steel Frame for Perforated 205 units subcon
Metro 1J2 21 Perforated Sheets 1281pcs on-going
Metro 1J2 22 2mm Alum Flashings 91pcs on-going
Metro 2E1 23 Copping & Ceiling Cladding 361sqm on-going
Olaya Jarir 24 1pc Bottom Hung Windows 1sqm at PP
Olaya Jarir 25 279pcs Cladding 450sqm on-going
Olaya Jarir 26 498pcs Alum Flashings - on-going
1pcs CW, 8pcs Bottom Hung, 3pcs Arched
Abanoumay 27 Windows, 10pcs Round Shape, 20pcs Sliding 250sqm on-going
Leaf, 24pcs Hinge
CW for KGS, 58pcs leaf balance for Boys
School, 79pcs Bottom Hinge, 4pcs Fixed,
Advance School 28 556sqm on-going
16pcs Sliding Windows, 7pcs Hinge Doors,
Louvers & 206pcs End Closures
Al Mousa 29 272pcs Alum Flashing for Skylight & Staircase - on-going
Aramco MIP 30 CW, Doors & Windows, Louver Sample 180sqm on-going
Faisal Unec 31 Balance 7 CW, 2pcs Glass Leaf, 2pcs 90sqm on-going, bal. at PP
Openable Skylight, 2pcs Louver Hinge Door
Basateen 32 Cladding 167sqm on-going
Basateen 33 ACP Perforated 8sqm on-going
Basateen 34 432pcs Flyscreen 432pcs to start
Murabba 35 Flashings 378pcs at PP
Page 1 of 3
Project Sn Description Qty / Area Remarks
Murabba 36 2pcs Sliding Windows 3sqm at PP
Labor Camp 37 4pcs Sliding Windows 7sqm on-going
Marwani Villa 38 19pcs Windows 22sqm at pp
Nora Hotel 39 13pcs GI Sheet flashing for Canopy 13pcs
Obeikan Tower 40 CW w/ Auto.Sliding Door + 18pcs Alum 10sqm to start
Flashing
SABB Tower 41 2pcs Hinge Door 5sqm received at factory, to start
fab.
Shahalan 42 Alum Skylight, 4 Doors, 2 Sliding, 60pcs 10 units on-going
Flashings
Sharma Villas 43 Balance Fly Screens for W3 18pcs to start
Thalia Bldg 44 CW at Back Elev. 68sqm on-going
Thalia Bldg 45 Steel Canopy & Frame 28sqm
Thalia Bldg 46 11pcs End Closure 11pcs Ready
Theyab Villa 47 2pcs Hinge Door 10sqm stripping
Trio Plaza 48 Curtain Wall at First Floor 28sqm at PP
Trio Plaza 49 15pcs Door Leaf Bal. 15pcs waiting Glass
Trio Plaza 50 295pcs Flashings & End Closure 295pcs Ready
Trio Plaza 51 530pcs Flashings & Flooring Support 530pcs new CL
Um Nora 52 Skylight, Fixed, Hinge Door + 7pcs Flashings 25sqm to start
KACST ABV 53 1 Repair door need confirmation
Alamaria Farm 54 Bal. 183pcs Canopy Cladding 300sqm
Four Seasons 55 974 units of CW till Level 28 6136sqm on-going
La Strada 56 600sqm Curtain Wall 600sqm on-going
Res. Makkah 57 2pcs CW + 1 Skylight 74sqm on-going
Res. Makkah 58 249pcs Openable Windows + 8 glass leaf 360sqm on-going, waiting Glass
Res. Makkah 59 32pcs Sandwich panel + 41pcs Alum Flashing at pp
Spark Bldg 60 92pcs, Internal Part. Windows & Doors 570sqm on-going, bal. at PP
Total 3,812sqm
Four Seasons 6,136sqm
Grand Total 9,948sqm
NOT YET STARTED
Abanoumay 1 Shutters 650sqm
Al Madi Villas 2 123 Windows + 27pcs Bal. Leaf 250sqm awaiting bal. cl
Al Mousa 3 10pcs Hinge Doors 47sqm at PP, hinges ordered ETA
30-Mar
Al Sodais Villas 4 443pcs CW, Doors & Windows 2500sqm partially ready
Alamaria Farm 5 5pcs Schuco Sliding 154sqm
Alamaria Farm 6 45pcs Sandwich Panels
China Railwall 7 39pcs Sandwich Panel + 12pcs End Closure 44sqm
China Railwall 8 8sqm Curtain Wall 32sqm new CL
ready, waiting bal. glass
China Railwall 9 41pcs Top Hung Windows 44sqm
(4pcs mistake by supplier)
Page 2 of 3
Project Sn Description Qty / Area Remarks
Dawood Bldg 10 56pcs Doors & Windows 96sqm at PP
ETLAL Tower 11 3pcs Alum Louver + 2pcs Auto.Sliding Door 35sqm
Four Seasons 12 144pcs Sandwich Panel 144pcs
La Strada 13 15pcs Swing Doors 78sqm
Laysen Valley 14 396 Unitized Panel 2144sqm partial
Metro DEPA 15 Ver./Hor. Cover, 60x20 Alum Tubes 248 LM to send to PP
Murabba 16 664 Unitized Panel 3187sqm Partial
Murabba 17 800sqm Louver at Parking 800sqm at PP
Murabba 18 Cladding Phase 4d 1445sqm Hold
TAM Tower 19 Sandwich Panel 488pcs partially
Tamimi Al Zair 20 47pcs Windows + 107sqm Shutters 224sqm on-going bending
Yamama Hospital 21 79pcs EFP Fixed Windows 252sqm
Yamama Hospital 22 Curtain Wall at Back Elev. 397sqm
Total 10,890sqm
Page 3 of 3