CONTRACT ( FINISHING WORK )
የክፍያ ምሥክር ወረቀት ቁጥር - 04
CERTIFICATE OF PAYMENT NO. 04
Date 25/07/2023 G.C.
ሥራዉ :- የገንዘቡ ልክ /ብር/ Amount
/Birr/
ADDIS LIFE REAL ESTATE PLC APARTMENT PROJECT
Project :- ዋናዉ ዉል (ከተ.እ.ታ. በፊት)
2,815,012.57
ቦታዉ :- Main Contract (Before VAT)
ADDIS ABABA , AROUND AFRICA UNION
Location :- ዋናዉ ዉል (ተ.እ.ታ. ጨምሮ)
አሰሪዉ መ/ቤት :- Main Contract (Inc VAT)
ADDIS LIFE REAL ESTATE PLC
Client :- የተሻሻለ ዉል (ተ.እ.ታ. ጨምሮ)
የሥራ ተቐራጭ :- Amended Contract (Inc VAT)
Contractor :-
Atsokia Building Finishing works ተጨማሪ ዉል (ተ.እ.ታ.ጨምሮ)
አማካሪ መሐንዲስ :- Supplementary Con. (Inc VATT)
Consultant :- የለዉጥ ትዕዛዞች
Variation Order
አባሪ በሆነዉ የክፍያ ሰነድ ጥያቄ እስከ ዛሬ ድረስ ተቐራጩ የሰራዉ ሥራና/ ያቀረበዉ ዕቃ ዋጋ
ጠቅላላ ድምር (ተ.እ.ታ. ጨምሮ)
3,237,264.46
As per the attached statement the value of work executed and /or materials supplied to date is: Total Sum (Inc VAT.)
የቅድሚያ ክፍያ /ADVANCE PAYMENT/
የገንዘብ ልክ ከተ.እ.ታ. በፊት
ተ.ቁ. ቀን /ብር/ .የተ.እታ. (A) Total Amount of work Excuted to Date (Excl.VAT) 1,532,814.20
Amount Before (B) Supplementary agreement Executed
No. Date VAT [ Birr ] VAT [15%]
-
- (C) Material on site
-
ድምር /Total/ - - (D) Total Amount of Work Executed =A+B+C 1,532,814.20
አስቀድሞ የተከፈለ ክፍያ/PREVIOUS PAYMENTS/ DEDUCTIONS
E Previous payments 1,095,610.53
የገንዘብ ልክ ከተ.እ.ታ.
ተ.ቁ. ቀን በፊት /ብር/ .የተ.እ.ታ.
Amount Before F Adv.Recovery (VaxD)/(Vtx0.8) -
No. Date VAT [ Birr ] VAT [15%]
1st G Retention 5% 76,640.71
434,865.68 65,229.85
2nd H Deduction for material on site
257,718.99 38,657.85
3rd 403,025.86 60,453.88
I Total Deduction (I) 1,172,251.24
4th (J) Sum Due to The Contractor=D-I 360,562.97
5th
ድምር /Total/ 1,095,610.53 164,341.58
VAT on Retention
(K) VAT on Total Retention Todate=15%xG 11,496.11
Deductions
(L) Previously Collected VAT on Retention 8,649.56
(M) VAT on Retention at this payment=K-L 2,846.55
(N) Sum Due to The Contractor=J 360,562.97
(O) VAT on Sum Due to The Contractor=15%xN 54,084.45
ADVANCE PAYMENT HISTORY (P) VAT on Retention at this payment=M 2,846.55
(Q) Total VAT Payable at this Payment =O+P 56,930.99
Amount of Advance Taken with V.A.T. - (R) Total Payment to the Contractor (Including 15 % VAT)=N+Q 417,493.96
Amount of Advance Repaid With V.A.T. - Four Hundred Seventeen thousand Four hundred Ninety Three birr and 96/100
Outstanding Advance Repayment With V.A.T. - WE have entitled to a sum of Birr:
Requested By:( The Contractor) Approved By: (Project manager) Endorsed By: ( The Client)
Name: __________________________ Name: ___________________________ Name: __________________________
Sign. and Date: __________________ Sign. and Date: ____________________ Sign. and Date: __________________