ITP - Erection

The document outlines an inspection test plan for steel erection of a factory building. It details activities like erection, welding, painting, and decking work. Inspection criteria, frequency, responsibility and acceptance are defined for each activity.

Uploaded by

Tech 5
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
18 views2 pages

ITP - Erection

The document outlines an inspection test plan for steel erection of a factory building. It details activities like erection, welding, painting, and decking work. Inspection criteria, frequency, responsibility and acceptance are defined for each activity.

Uploaded by

Tech 5
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 2

Document No: KRYFS/ERE/ITP/2024-25/01

INSPECTION TEST PLAN FOR STRUCTURE STEEL ERECTION


Date: 26-03-2024
Client: KRYFS Power Components Ltd. Contractor: Desai Construction Revision No: 00
Structural Consultant: Mahimtura Consultant Pvt. Ltd. Sub Contractor: Gayatri Engineering Date: NA
Ref Quality IS, ASME, AWS & Structural
Project: Factory Building Unit 5 TPI: Aavishkar Group
Documents: Project Documents
Inspection Acceptance Scope of Inspection
Activity
Structural Remark
No Activity Detail of Activity Frequency Reference Document Criteria Verify Documents Contactor TPI Client / PMC
Consultant
1 Erection Activities

Check anchor bolts Approved Drawings / IS Survey / Inspection


1.1 100% Base plate GA drawings P1 P2 R R Verify as per actual site condition
setting out 12843 Report

Alignment After Approved Drawings / IS Survey / Inspection


1.2 Survey Works 100% Erection GA drawings P1 P2 R R Verify as per actual site condition
Erection 12843 Report

Approved Drawings / IS Survey / Inspection


1.3 Check top of steel level 100% Erection GA drawings P1 H R R Verify as per actual site condition
12843 Report

Approved Drawings / IS Survey / Inspection


1.4 Visual Inspection 100% Erection GA drawings P1 P2 R R Verify as per actual site condition
12843 Report
Bolting
Approved Drawings / IS Survey / Inspection
1.5 Bolt Tightening 100% Design Requirement P1 H R R
12843 / Bolting Procedure Report
2 Site Welding
TPI will support contractor to
Site Weld Approved Drawings / AWS WPS, PQR & WPQ
2.1 Submission 100% AWS D1.1/ ASME Sec IX P W&A R R establish WPS, PQR & WPQ
(WPS/PQR/WPQ) D1.1/ ASME Sec IX records
record for the project
Monitoring Welding
2.2 Welding Process Random WPS WPS Range WPS P1 P2 R R QAP guideline to be followed
Process variables
Approved Shop Drawings & Approved drawing & IS 12843 to
2.3 Dimension Check-up 100% Approved Shop Drawings Inspection Report P1 P2 R R
Welding Inspection & AWS D 1.1 be followed
Testing
2.4 Weld Visual Inspection 100% Approved NDT Procedure AWS D 1.1 Inspection Report P1 P2 R R

2.5 NDT - CJP Groove Weld Ultrasonic Testing 100% Approved NDT Procedure AWS D 1.1 NDT Report S P R R
Magnetic Particle
2.6 NDT - PJP Groove Inspection / Dye 100% Approved NDT Procedure AWS D 1.1 NDT Report S P R R
Penetrant Testing
Magnetic Particle
2.7 NDT - Fillet Weld Inspection / Dye 25% Approved NDT Procedure AWS D 1.1 NDT Report S P R R
Penetrant Testing
3 Painting
Painting Procedure guideline to
3.1 Paint Touch-up Visual Inspection 100% painting procedure Project Specification Painting Reports P1 H R R
be followed
4 Decking Work

4.1 Decking Visual Examination Random Decking Layout Structural Inputs Inspection Report P1 P2 R R As per decking layout
Visual & Quality
Follow AWS D 1.1 requirement &
4.2 Verification (WPS / PQR 100% Decking Layout AWS D 1.1 / Structural Inputs Inspection Report P W&A R R
acceptance
Shear Stud Welding / WPQ)
Follow AWS D 1.1 requirement &
4.3 Bend Test Random Stud welding procedure AWS D1.1 Inspection Report P W&A R R
acceptance
5 Final Area Handing Over
Erection methodology / Erection methodology / follow Erection methodology /
5.1 Visual Examination 100% Inspection Report P1 P2 R R
project specification project specification project specification
Final Area Handing Over
Phase / Floor Final Inspection
5.2 Final Documentation Inspection Report Project Specification P H A A Final Quality Dossier
wise report
6 Final Documentation
Preparation of quality
6.1 Quality Dossier One Time NA NA NA S P R&A R&A Final Quality Dossier
dossier

Legends:

Method of Inspection Extent of inspection Others Testing

S - Submission / offer 1 - 100% / Full Scope TPI - Third Party Inspection VT - Visual Inspection
P - Perform 2 - Random / Sample MTC - Material Test Certificate UT - Ultrasonic Test
R - Review QAP - Quality Assurance Plan RT - Radiography Test
H - Hold ITP - Inspection Test Plan PT - Dye Penetrant Test
W - Witness IRN - Inspection Release note MT - Magnetic Particle test
A - Approve