TPL 001 4
TPL 001 4
A. Introduction
1. Title: Transmission System Planning Performance Requirements
2. Number: TPL-001-4
3. Purpose: Establish Transmission system planning performance requirements within the
planning horizon to develop a Bulk Electric System (BES) that will operate reliably over a
broad spectrum of System conditions and following a wide range of probable Contingencies.
4. Applicability:
4.1. Functional Entity
4.1.1. Planning Coordinator.
4.1.2. Transmission Planner.
5. Effective Date: Requirements R1 and R7 as well as the definitions shall become effective on
the first day of the first calendar quarter, 12 months after applicable regulatory approval. In
those jurisdictions where regulatory approval is not required, Requirements R1 and R7 become
effective on the first day of the first calendar quarter, 12 months after Board of Trustees
adoption or as otherwise made effective pursuant to the laws applicable to such ERO
governmental authorities.
Except as indicated below, Requirements R2 through R6 and Requirement R8 shall become
effective on the first day of the first calendar quarter, 24 months after applicable regulatory
approval. In those jurisdictions where regulatory approval is not required, all requirements,
except as noted below, go into effect on the first day of the first calendar quarter, 24 months
after Board of Trustees adoption or as otherwise made effective pursuant to the laws
applicable to such ERO governmental authorities.
For 84 calendar months beginning the first day of the first calendar quarter following applicable
regulatory approval, or in those jurisdictions where regulatory approval is not required on the
first day of the first calendar quarter 84 months after Board of Trustees adoption or as
otherwise made effective pursuant to the laws applicable to such ERO governmental
authorities, Corrective Action Plans applying to the following categories of Contingencies and
events identified in TPL-001-4, Table 1 are allowed to include Non-Consequential Load Loss
and curtailment of Firm Transmission Service (in accordance with Requirement R2, Part 2.7.3.)
that would not otherwise be permitted by the requirements of TPL-001-4:
P1-2 (for controlled interruption of electric supply to local network customers
connected to or supplied by the Faulted element)
P1-3 (for controlled interruption of electric supply to local network customers
connected to or supplied by the Faulted element)
P2-1
P2-2 (above 300 kV)
P2-3 (above 300 kV)
P3-1 through P3-5
P4-1 through P4-5 (above 300 kV)
P5 (above 300 kV)
1
Standard TPL-001-4 — Transmission System Planning Performance Requirements
B. Requirements
R1. Each Transmission Planner and Planning Coordinator shall maintain System models within its
respective area for performing the studies needed to complete its Planning Assessment. The
models shall use data consistent with that provided in accordance with the MOD-010 and
MOD-012 standards, supplemented by other sources as needed, including items represented in
the Corrective Action Plan, and shall represent projected System conditions. This establishes
Category P0 as the normal System condition in Table 1. [Violation Risk Factor: High] [Time
Horizon: Long-term Planning]
1.1. System models shall represent:
1.1.1. Existing Facilities
1.1.2. Known outage(s) of generation or Transmission Facility(ies) with a duration
of at least six months.
1.1.3. New planned Facilities and changes to existing Facilities
1.1.4. Real and reactive Load forecasts
1.1.5. Known commitments for Firm Transmission Service and Interchange
1.1.6. Resources (supply or demand side) required for Load
R2. Each Transmission Planner and Planning Coordinator shall prepare an annual Planning
Assessment of its portion of the BES. This Planning Assessment shall use current or qualified
past studies (as indicated in Requirement R2, Part 2.6), document assumptions, and document
summarized results of the steady state analyses, short circuit analyses, and Stability analyses.
[Violation Risk Factor: High] [Time Horizon: Long-term Planning]
2.1. For the Planning Assessment, the Near-Term Transmission Planning Horizon portion
of the steady state analysis shall be assessed annually and be supported by current
annual studies or qualified past studies as indicated in Requirement R2, Part 2.6.
Qualifying studies need to include the following conditions:
2.1.1. System peak Load for either Year One or year two, and for year five.
2.1.2. System Off-Peak Load for one of the five years.
2.1.3. P1 events in Table 1, with known outages modeled as in Requirement R1,
Part 1.1.2, under those System peak or Off-Peak conditions when known
outages are scheduled.
2.1.4. For each of the studies described in Requirement R2, Parts 2.1.1 and 2.1.2,
sensitivity case(s) shall be utilized to demonstrate the impact of changes to
the basic assumptions used in the model. To accomplish this, the sensitivity
analysis in the Planning Assessment must vary one or more of the following
conditions by a sufficient amount to stress the System within a range of
credible conditions that demonstrate a measurable change in System
response :
Real and reactive forecasted Load.
Expected transfers.
Expected in service dates of new or modified Transmission Facilities.
Reactive resource capability.
Generation additions, retirements, or other dispatch scenarios.
2
Standard TPL-001-4 — Transmission System Planning Performance Requirements
3
Standard TPL-001-4 — Transmission System Planning Performance Requirements
2.5. For the Planning Assessment, the Long-Term Transmission Planning Horizon portion
of the Stability analysis shall be assessed to address the impact of proposed material
generation additions or changes in that timeframe and be supported by current or past
studies as qualified in Requirement R2, Part2.6 and shall include documentation to
support the technical rationale for determining material changes.
2.6. Past studies may be used to support the Planning Assessment if they meet the
following requirements:
2.6.1. For steady state, short circuit, or Stability analysis: the study shall be five
calendar years old or less, unless a technical rationale can be provided to
demonstrate that the results of an older study are still valid.
2.6.2. For steady state, short circuit, or Stability analysis: no material changes have
occurred to the System represented in the study. Documentation to support
the technical rationale for determining material changes shall be included.
2.7. For planning events shown in Table 1, when the analysis indicates an inability of the
System to meet the performance requirements in Table 1, the Planning Assessment
shall include Corrective Action Plan(s) addressing how the performance requirements
will be met. Revisions to the Corrective Action Plan(s) are allowed in subsequent
Planning Assessments but the planned System shall continue to meet the performance
requirements in Table 1. Corrective Action Plan(s) do not need to be developed solely
to meet the performance requirements for a single sensitivity case analyzed in
accordance with Requirements R2, Parts 2.1.4 and 2.4.3. The Corrective Action
Plan(s) shall:
2.7.1. List System deficiencies and the associated actions needed to achieve
required System performance. Examples of such actions include:
Installation, modification, retirement, or removal of Transmission and
generation Facilities and any associated equipment.
Installation, modification, or removal of Protection Systems or Special
Protection Systems
Installation or modification of automatic generation tripping as a
response to a single or multiple Contingency to mitigate Stability
performance violations.
Installation or modification of manual and automatic generation
runback/tripping as a response to a single or multiple Contingency to
mitigate steady state performance violations.
Use of Operating Procedures specifying how long they will be needed
as part of the Corrective Action Plan.
Use of rate applications, DSM, new technologies, or other initiatives.
2.7.2. Include actions to resolve performance deficiencies identified in multiple
sensitivity studies or provide a rationale for why actions were not necessary.
2.7.3. If situations arise that are beyond the control of the Transmission Planner or
Planning Coordinator that prevent the implementation of a Corrective Action
Plan in the required timeframe, then the Transmission Planner or Planning
Coordinator is permitted to utilize Non-Consequential Load Loss and
curtailment of Firm Transmission Service to correct the situation that would
normally not be permitted in Table 1, provided that the Transmission Planner
4
Standard TPL-001-4 — Transmission System Planning Performance Requirements
or Planning Coordinator documents that they are taking actions to resolve the
situation. The Transmission Planner or Planning Coordinator shall
document the situation causing the problem, alternatives evaluated, and the
use of Non-Consequential Load Loss or curtailment of Firm Transmission
Service.
2.7.4. Be reviewed in subsequent annual Planning Assessments for continued
validity and implementation status of identified System Facilities and
Operating Procedures.
2.8. For short circuit analysis, if the short circuit current interrupting duty on circuit
breakers determined in Requirement R2, Part 2.3 exceeds their Equipment Rating, the
Planning Assessment shall include a Corrective Action Plan to address the Equipment
Rating violations. The Corrective Action Plan shall:
2.8.1. List System deficiencies and the associated actions needed to achieve
required System performance.
2.8.2. Be reviewed in subsequent annual Planning Assessments for continued
validity and implementation status of identified System Facilities and
Operating Procedures.
R3. For the steady state portion of the Planning Assessment, each Transmission Planner and
Planning Coordinator shall perform studies for the Near-Term and Long-Term Transmission
Planning Horizons in Requirement R2, Parts 2.1, and 2.2. The studies shall be based on
computer simulation models using data provided in Requirement R1. [Violation Risk Factor:
Medium] [Time Horizon: Long-term Planning]
3.1. Studies shall be performed for planning events to determine whether the BES meets
the performance requirements in Table 1 based on the Contingency list created in
Requirement R3, Part 3.4.
3.2. Studies shall be performed to assess the impact of the extreme events which are
identified by the list created in Requirement R3, Part 3.5.
3.3. Contingency analyses for Requirement R3, Parts 3.1 & 3.2 shall:
3.3.1. Simulate the removal of all elements that the Protection System and other
automatic controls are expected to disconnect for each Contingency without
operator intervention. The analyses shall include the impact of subsequent:
3.3.1.1. Tripping of generators where simulations show generator bus
voltages or high side of the generation step up (GSU) voltages
are less than known or assumed minimum generator steady state
or ride through voltage limitations. Include in the assessment
any assumptions made.
3.3.1.2. Tripping of Transmission elements where relay loadability limits
are exceeded.
3.3.2. Simulate the expected automatic operation of existing and planned devices
designed to provide steady state control of electrical system quantities when
such devices impact the study area. These devices may include equipment
such as phase-shifting transformers, load tap changing transformers, and
switched capacitors and inductors.
3.4. Those planning events in Table 1, that are expected to produce more severe System
impacts on its portion of the BES, shall be identified and a list of those Contingencies
5
Standard TPL-001-4 — Transmission System Planning Performance Requirements
to be evaluated for System performance in Requirement R3, Part 3.1 created. The
rationale for those Contingencies selected for evaluation shall be available as
supporting information.
3.4.1. The Planning Coordinator and Transmission Planner shall coordinate with
adjacent Planning Coordinators and Transmission Planners to ensure that
Contingencies on adjacent Systems which may impact their Systems are
included in the Contingency list.
3.5. Those extreme events in Table 1 that are expected to produce more severe System
impacts shall be identified and a list created of those events to be evaluated in
Requirement R3, Part 3.2. The rationale for those Contingencies selected for
evaluation shall be available as supporting information. If the analysis concludes
there is Cascading caused by the occurrence of extreme events, an evaluation of
possible actions designed to reduce the likelihood or mitigate the consequences and
adverse impacts of the event(s) shall be conducted.
R4. For the Stability portion of the Planning Assessment, as described in Requirement R2, Parts 2.4
and 2.5, each Transmission Planner and Planning Coordinator shall perform the Contingency
analyses listed in Table 1. The studies shall be based on computer simulation models using
data provided in Requirement R1. [Violation Risk Factor: Medium] [Time Horizon: Long-
term Planning]
4.1. Studies shall be performed for planning events to determine whether the BES meets
the performance requirements in Table 1 based on the Contingency list created in
Requirement R4, Part 4.4.
4.1.1. For planning event P1: No generating unit shall pull out of synchronism. A
generator being disconnected from the System by fault clearing action or by
a Special Protection System is not considered pulling out of synchronism.
4.1.2. For planning events P2 through P7: When a generator pulls out of
synchronism in the simulations, the resulting apparent impedance swings
shall not result in the tripping of any Transmission system elements other
than the generating unit and its directly connected Facilities.
4.1.3. For planning events P1 through P7: Power oscillations shall exhibit
acceptable damping as established by the Planning Coordinator and
Transmission Planner.
4.2. Studies shall be performed to assess the impact of the extreme events which are
identified by the list created in Requirement R4, Part 4.5.
4.3. Contingency analyses for Requirement R4, Parts 4.1 and 4.2 shall :
4.3.1. Simulate the removal of all elements that the Protection System and other
automatic controls are expected to disconnect for each Contingency without
operator intervention. The analyses shall include the impact of subsequent:
4.3.1.1. Successful high speed (less than one second) reclosing and
unsuccessful high speed reclosing into a Fault where high speed
reclosing is utilized.
4.3.1.2. Tripping of generators where simulations show generator bus
voltages or high side of the GSU voltages are less than known or
assumed generator low voltage ride through capability. Include
in the assessment any assumptions made.
6
Standard TPL-001-4 — Transmission System Planning Performance Requirements
7
Standard TPL-001-4 — Transmission System Planning Performance Requirements
8
Standard TPL-001-4 — Transmission System Planning Performance Requirements
Interruption of Firm
Non-Consequential
Category Initial Condition Event 1 Fault Type 2 BES Level 3 Transmission
Load Loss Allowed
Service Allowed 4
9
Standard TPL-001-4 — Transmission System Planning Performance Requirements
Interruption of Firm
Non-Consequential
Category Initial Condition Event 1 Fault Type 2 BES Level 3 Transmission
Load Loss Allowed
Service Allowed 4
P7 The loss of:
Multiple 1. Any two adjacent (vertically or
Contingency Normal System horizontally) circuits on common SLG EHV, HV Yes Yes
(Common structure 11
Structure) 2. Loss of a bipolar DC line
10
Standard TPL-001-4 — Transmission System Planning Performance Requirements
11
Standard TPL-001-4 — Transmission System Planning Performance Requirements
12
Standard TPL-001-4 — Transmission System Planning Performance Requirements
13
Standard TPL-001-4 — Transmission System Planning Performance Requirements
Attachment 1
I. Stakeholder Process
During each Planning Assessment before the use of Non-Consequential Load Loss under
footnote 12 is allowed as an element of a Corrective Action Plan in the Near-Term Transmission
Planning Horizon of the Planning Assessment, the Transmission Planner or Planning
Coordinator shall ensure that the utilization of footnote 12 is reviewed through an open and
transparent stakeholder process. The responsible entity can utilize an existing process or develop
a new process. .The process must include the following:
1. Meetings must be open to affected stakeholders including applicable regulatory
authorities or governing bodies responsible for retail electric service issues
2. Notice must be provided in advance of meetings to affected stakeholders including
applicable regulatory authorities or governing bodies responsible for retail electric service
issues and include an agenda with:
a. Date, time, and location for the meeting
b. Specific location(s) of the planned Non-Consequential Load Loss under footnote
12
c. Provisions for a stakeholder comment period
3. Information regarding the intended purpose and scope of the proposed Non-
Consequential Load Loss under footnote 12 (as shown in Section II below) must be made
available to meeting participants
4. A procedure for stakeholders to submit written questions or concerns and to receive
written responses to the submitted questions and concerns
5. A dispute resolution process for any question or concern raised in #4 above that is not
resolved to the stakeholder’s satisfaction
An entity does not have to repeat the stakeholder process for a specific application of footnote 12
utilization with respect to subsequent Planning Assessments unless conditions spelled out in
Section II below have materially changed for that specific application.
III. Instances for which Regulatory Review of Non-Consequential Load Loss under Footnote 12
is Required
Before a Non-Consequential Load Loss under footnote 12 is allowed as an element of a
Corrective Action Plan in Year One of the Planning Assessment, the Transmission Planner or
Planning Coordinator must ensure that the applicable regulatory authorities or governing bodies
responsible for retail electric service issues do not object to the use of Non-Consequential Load
Loss under footnote 12 if either:
1. The voltage level of the Contingency is greater than 300 kV
a. If the Contingency analyzed involves BES Elements at multiple System voltage
levels, the lowest System voltage level of the element(s) removed for the
analyzed Contingency determines the stated performance criteria regarding
allowances for Non-Consequential Load Loss under footnote 12, or
b. For a non-generator step up transformer outage Contingency, the 300 kV limit
applies to the low-side winding (excluding tertiary windings). For a generator or
generator step up transformer outage Contingency, the 300 kV limit applies to the
BES connected voltage (high-side of the Generator Step Up transformer)
2. The planned Non-Consequential Load Loss under footnote 12 is greater than or equal to
25 MW
Once assurance has been received that the applicable regulatory authorities or governing bodies
responsible for retail electric service issues do not object to the use of Non-Consequential Load
Loss under footnote 12, the Planning Coordinator or Transmission Planner must submit the
information outlined in items II.1 through II.8 above to the ERO for a determination of whether
there are any Adverse Reliability Impacts caused by the request to utilize footnote 12 for Non-
Consequential Load Loss.
Standard TPL-001-4 — Transmission System Planning Performance Requirements
C. Measures
M1. Each Transmission Planner and Planning Coordinator shall provide evidence, in electronic or
hard copy format, that it is maintaining System models within their respective area, using data
consistent with MOD-010 and MOD-012, including items represented in the Corrective Action
Plan, representing projected System conditions, and that the models represent the required
information in accordance with Requirement R1.
M2. Each Transmission Planner and Planning Coordinator shall provide dated evidence, such as
electronic or hard copies of its annual Planning Assessment, that it has prepared an annual
Planning Assessment of its portion of the BES in accordance with Requirement R2.
M3. Each Transmission Planner and Planning Coordinator shall provide dated evidence, such as
electronic or hard copies of the studies utilized in preparing the Planning Assessment, in
accordance with Requirement R3.
M4. Each Transmission Planner and Planning Coordinator shall provide dated evidence, such as
electronic or hard copies of the studies utilized in preparing the Planning Assessment in
accordance with Requirement R4.
M5. Each Transmission Planner and Planning Coordinator shall provide dated evidence such as
electronic or hard copies of the documentation specifying the criteria for acceptable System
steady state voltage limits, post-Contingency voltage deviations, and the transient voltage
response for its System in accordance with Requirement R5.
M6. Each Transmission Planner and Planning Coordinator shall provide dated evidence, such as
electronic or hard copies of documentation specifying the criteria or methodology used in the
analysis to identify System instability for conditions such as Cascading, voltage instability, or
uncontrolled islanding that was utilized in preparing the Planning Assessment in accordance
with Requirement R6.
M7. Each Planning Coordinator, in conjunction with each of its Transmission Planners, shall
provide dated documentation on roles and responsibilities, such as meeting minutes,
agreements, and e-mail correspondence that identifies that agreement has been reached on
individual and joint responsibilities for performing the required studies and Assessments in
accordance with Requirement R7.
M8. Each Planning Coordinator and Transmission Planner shall provide evidence, such as email
notices, documentation of updated web pages, postal receipts showing recipient and date; or a
demonstration of a public posting, that it has distributed its Planning Assessment results to
adjacent Planning Coordinators and adjacent Transmission Planners within 90 days of having
completed its Planning Assessment, and to any functional entity who has indicated a reliability
need within 30 days of a written request and that the Planning Coordinator or Transmission
Planner has provided a documented response to comments received on Planning Assessment
results within 90 calendar days of receipt of those comments in accordance with Requirement
R8.
D. Compliance
1. Compliance Monitoring Process
1.1 Compliance Enforcement Authority
Regional Entity
1.2 Compliance Monitoring Period and Reset Timeframe
Not applicable.
Standard TPL-001-4 — Transmission System Planning Performance Requirements
1.3 Compliance Monitoring and Enforcement Processes:
Compliance Audits
Self-Certifications
Spot Checking
Compliance Violation Investigations
Self-Reporting
Complaints
1.4 Data Retention
The Transmission Planner and Planning Coordinator shall each retain data or evidence to
show compliance as identified unless directed by its Compliance Enforcement Authority
to retain specific evidence for a longer period of time as part of an investigation:
The models utilized in the current in-force Planning Assessment and one
previous Planning Assessment in accordance with Requirement R1 and Measure
M1.
The Planning Assessments performed since the last compliance audit in
accordance with Requirement R2 and Measure M2.
The studies performed in support of its Planning Assessments since the last
compliance audit in accordance with Requirement R3 and Measure M3.
The studies performed in support of its Planning Assessments since the last
compliance audit in accordance with Requirement R4 and Measure M4.
The documentation specifying the criteria for acceptable System steady state
voltage limits, post-Contingency voltage deviations, and transient voltage
response since the last compliance audit in accordance with Requirement R5 and
Measure M5.
The documentation specifying the criteria or methodology utilized in the analysis
to identify System instability for conditions such as Cascading, voltage
instability, or uncontrolled islanding in support of its Planning Assessments since
the last compliance audit in accordance with Requirement R6 and Measure M6.
The current, in force documentation for the agreement(s) on roles and
responsibilities, as well as documentation for the agreements in force since the
last compliance audit, in accordance with Requirement R7 and Measure M7.
The Planning Coordinator shall retain data or evidence to show compliance as identified
unless directed by its Compliance Enforcement Authority to retain specific evidence for a
longer period of time as part of an investigation:
Three calendar years of the notifications employed in accordance with
Requirement R8 and Measure M8.
If a Transmission Planner or Planning Coordinator is found non-compliant, it shall keep
information related to the non-compliance until found compliant or the time periods
specified above, whichever is longer.
R1 The responsible entity’s System The responsible entity’s System The responsible entity’s System The responsible entity’s System model
model failed to represent one of the model failed to represent two of the model failed to represent three of the failed to represent four or more of the
Requirement R1, Parts 1.1.1 Requirement R1, Parts 1.1.1 through Requirement R1, Parts 1.1.1 through Requirement R1, Parts 1.1.1 through
through 1.1.6. 1.1.6. 1.1.6. 1.1.6.
OR
The responsible entity’s System model
did not represent projected System
conditions as described in Requirement
R1.
OR
The responsible entity’s System model
did not use data consistent with that
provided in accordance with the MOD-
010 and MOD-012 standards and other
sources, including items represented in
the Corrective Action Plan.
R2 The responsible entity failed to The responsible entity failed to The responsible entity failed to The responsible entity failed to comply
comply with Requirement R2, Part comply with Requirement R2, Part 2.3 comply with one of the following with two or more of the following Parts
2.6. or Part 2.8. Parts of Requirement R2: Part 2.1, of Requirement R2: Part 2.1, Part 2.2,
Part 2.2, Part 2.4, Part 2.5, or Part Part 2.4, or Part 2.7.
2.7.
OR
The responsible entity does not have a
completed annual Planning
Assessment.
R3 The responsible entity did not The responsible entity did not perform The responsible entity did not The responsible entity did not perform
identify planning events as studies as specified in Requirement perform studies as specified in studies as specified in Requirement R3,
described in Requirement R3, Part R3, Part 3.1 to determine that the Requirement R3, Part 3.1 to Part 3.1 to determine that the BES
3.4 or extreme events as described BES meets the performance determine that the BES meets the meets the performance requirements
in Requirement R3, Part 3.5. requirements for one of the categories performance requirements for two of for three or more of the categories (P2
(P2 through P7) in Table 1. the categories (P2 through P7) in through P7) in Table 1.
18
Standard TPL-001-4 — Transmission System Planning Performance Requirements
R4 The responsible entity did not The responsible entity did not perform The responsible entity did not The responsible entity did not perform
identify planning events as studies as specified in Requirement perform studies as specified in studies as specified in Requirement R4,
described in Requirement R4, Part R4, Part 4.1 to determine that the Requirement R4, Part 4.1 to Part 4.1 to determine that the BES
4.4 or extreme events as described BES meets the performance determine that the BES meets the meets the performance requirements
in Requirement R4, Part 4.5. requirements for one of the categories performance requirements for two of for three or more of the categories (P1
(P1 through P7) in Table 1. the categories (P1 through P7) in through P7) in Table 1.
Table 1.
OR OR
OR
The responsible entity did not perform The responsible entity did not base its
studies as specified in Requirement The responsible entity did not studies on computer simulation models
R4, Part 4.2 to assess the impact of perform Contingency analysis as using data provided in Requirement R1.
extreme events. described in Requirement R4, Part
4.3.
19
Standard TPL-001-4 — Transmission System Planning Performance Requirements
R8 The responsible entity distributed its The responsible entity distributed its The responsible entity distributed its The responsible entity distributed its
Planning Assessment results to Planning Assessment results to Planning Assessment results to Planning Assessment results to
adjacent Planning Coordinators and adjacent Planning Coordinators and adjacent Planning Coordinators and adjacent Planning Coordinators and
adjacent Transmission Planners but adjacent Transmission Planners but it adjacent Transmission Planners but adjacent Transmission Planners but it
it was more than 90 days but less was more than 120 days but less than it was more than 130 days but less was more than 140 days following its
than or equal to 120 days following or equal to 130 days following its than or equal to 140 days following completion.
its completion. completion. its completion.
OR
OR, OR, OR,
The responsible entity did not distribute
The responsible entity distributed its The responsible entity distributed its The responsible entity distributed its its Planning Assessment results to
Planning Assessment results to Planning Assessment results to Planning Assessment results to adjacent Planning Coordinators and
functional entities having a reliability functional entities having a reliability functional entities having a reliability adjacent Transmission Planners.
related need who requested the related need who requested the related need who requested the
OR
Planning Assessment in writing but Planning Assessment in writing but it Planning Assessment in writing but it
it was more than 30 days but less was more than 40 days but less than was more than 50 days but less than The responsible entity distributed its
than or equal to 40 days following or equal to 50 days following the or equal to 60 days following the Planning Assessment results to
the request. request. request. functional entities having a reliability
related need who requested the
Planning Assessment in writing but it
was more than 60 days following the
request.
OR
The responsible entity did not distribute
its Planning Assessment results to
functional entities having a reliability
related need who requested the
Planning Assessment in writing.
20
Standard TPL-001-4 — Transmission System Planning Performance Requirements
E. Regional Variances
None.
Version History