FIDIC CLAIM SERIES #01
FIDIC YELLOW
BOOK 2017:
CONTRACTOR
CLAIM EVENT
SCENARIOS
parithi
Ilam
01 FIDIC YELLOW BOOK 2017: CONTRACTOR CLAIM EVENT SCENARIOS
CLAUSE 1.9: ERROR IN
EMPLOYER’S SPECIFICATION
Cause of Claim: Error in Employer’s
specification not discovered before
Contract Award.
Contractor Entitlement:
Extension of Time (EOT): YES
Cost: YES
Profit: YES
parithi
Ilam
02 FIDIC YELLOW BOOK 2017: CONTRACTOR CLAIM EVENT SCENARIOS
CLAUSE 1.13: DELAY IN
WORK PERMIT
Cause of Claim: Delay in Work
permit by Employer.
Contractor Entitlement:
EOT: YES
Cost: YES
Profit: YES
parithi
Ilam
03 FIDIC YELLOW BOOK 2017: CONTRACTOR CLAIM EVENT SCENARIOS
CLAUSE 2.1: DELAY IN
ACCESS TO SITE
Cause of Claim: Delay in Access to site
by Employer.
Contractor Entitlement:
EOT: YES
Cost: YES
Profit: YES
parithi
Ilam
04 FIDIC YELLOW BOOK 2017: CONTRACTOR CLAIM EVENT SCENARIOS
CLAUSE 4.6:
UNFORESEEABLE
ADDITIONAL COOPERATION
Cause of Claim: Instruction for
unforeseeable additional cooperation
with other agencies of Employer or
Government.
Contractor Entitlement:
EOT: YES
Cost: YES
Profit: YES
parithi
Ilam
05 FIDIC YELLOW BOOK 2017: CONTRACTOR CLAIM EVENT SCENARIOS
CLAUSE 4.7: ERROR IN
SETTING-OUT DATA
Cause of Claim: Error in setting-out data.
Contractor Entitlement:
EOT: YES
Cost: YES
Profit: YES
parithi
Ilam
06 FIDIC YELLOW BOOK 2017: CONTRACTOR CLAIM EVENT SCENARIOS
CLAUSE 4.12:
UNFORESEEABLE PHYSICAL
CONDITIONS
Cause of Claim: Unforeseeable physical
conditions at Site.
Contractor Entitlement:
EOT: YES
Cost: YES
Profit: NO
parithi
Ilam
07 FIDIC YELLOW BOOK 2017: CONTRACTOR CLAIM EVENT SCENARIOS
CLAUSE 4.15: CHANGES TO
ACCESS ROUTE
Cause of Claim: Changes to an access
route.
Contractor Entitlement:
EOT: YES
Cost: YES
Profit: NO
parithi
Ilam
08 FIDIC YELLOW BOOK 2017: CONTRACTOR CLAIM EVENT SCENARIOS
CLAUSE 4.23: DISCOVERY OF
FOSSILS ETC.
Cause of Claim: Discovery of fossils etc.
Contractor Entitlement:
EOT: YES
Cost: YES
Profit: NO
parithi
Ilam
09 FIDIC YELLOW BOOK 2017: CONTRACTOR CLAIM EVENT SCENARIOS
CLAUSE 7.4: DELAY IN
TESTS/INSPECTION
Cause of Claim: Delay in tests/inspection
due to Employer.
Contractor Entitlement:
EOT: YES
Cost: YES
Profit: YES
parithi
Ilam
10 FIDIC YELLOW BOOK 2017: CONTRACTOR CLAIM EVENT SCENARIOS
CLAUSE 7.6: REMEDIAL
WORK PRIOR TO TAKING-
OVER
Cause of Claim: Remedial work prior to
Taking-Over due to Employer.
Contractor Entitlement:
EOT: YES
Cost: YES
Profit: YES
parithi
Ilam
11 FIDIC YELLOW BOOK 2017: CONTRACTOR CLAIM EVENT SCENARIOS
CLAUSE 8.5: EXCEPTIONAL
CLIMATIC
CONDITIONS/FORCE
MAJEURE
Cause of Claim: Exceptional climatic
conditions/Force Majeure.
Contractor Entitlement:
EOT: YES
Cost: NO
Profit: NO
parithi
Ilam
12 FIDIC YELLOW BOOK 2017: CONTRACTOR CLAIM EVENT SCENARIOS
CLAUSE 8.10: SUSPENSION
BY EMPLOYER
Cause of Claim: Suspension by Employer
unless Contractor default.
Contractor Entitlement:
EOT: YES
Cost: YES
Profit: YES
parithi
Ilam
13
CLAUSE 10.2: DELAY IN
EMPLOYER TAKING-OVER A
PART
Cause of Claim: Delay in Employer
Taking-Over a Part.
Contractor Entitlement:
EOT: YES
Cost: YES
Profit: YES
parithi
Ilam
14
CLAUSE 10.3: DELAY OR
DISRUPTION WITH TESTS
ON COMPLETION
Cause of Claim: Delay or Disruption with
Tests on Completion.
Contractor Entitlement:
EOT: YES
Cost: YES
Profit: YES
parithi
Ilam
15
CLAUSE 11.7: DELAYED
ACCESS AFTER TAKING-
OVER
Cause of Claim: Delayed access after
Taking-Over.
Contractor Entitlement:
EOT: YES
Cost: YES
Profit: YES
parithi
Ilam
16
CLAUSE 11.8: SEARCH FOR
DEFECTS NOT ITS FAULT
Cause of Claim: Search for defects not its
fault.
Contractor Entitlement:
EOT: NO
Cost: YES
Profit: YES
parithi
Ilam
17
CLAUSE 13.3.2:
CONTRACTOR REQUIRED TO
SUBMIT VARIATION
Cause of Claim: Contractor required to
submit proposal for Variation which is
not accepted.
Contractor Entitlement:
EOT: NO
Cost: YES
Profit: NO
parithi
Ilam
18
CLAUSE 13.6: CHANGE IN
LAWS/PERMITS AFTER
CONTRACT AWARD
Cause of Claim: Change in Laws/Permits
after Contract Award.
Contractor Entitlement:
EOT: YES
Cost: YES
Profit: NO
parithi
Ilam
19
CLAUSE 16.1: SUSPENSION
DUE TO PAYMENT DEFAULT
Cause of Claim: Suspension due to
Payment Default by employer.
Contractor Entitlement:
EOT: YES
Cost: YES
Profit: YES
parithi
Ilam
20
CLAUSE 16.1: SUSPENSION
DUE TO PAYMENT DEFAULT
Cause of Claim: Suspension due to
Payment Default by employer.
Contractor Entitlement:
EOT: YES
Cost: YES
Profit: YES
parithi
Ilam
21
CLAUSE 16.2.2: RIGHT TO
TERMINATE BY EMPLOYER
Cause of Claim: Right to Terminate by
Employer.
Contractor Entitlement:
EOT: YES
Cost: YES
Profit: YES
parithi
Ilam
22
CLAUSE 16.3: WORK
INSTRUCTED AFTER
TERMINATION
Cause of Claim: Work instructed after
termination.
Contractor Entitlement:
EOT: NO
Cost: YES
Profit: YES
parithi
Ilam
23
CLAUSE 16.4: TERMINATION
ON EMPLOYER DEFAULT
Cause of Claim: Termination on
Employer default.
Contractor Entitlement:
EOT: NO
Cost: YES
Profit: YES
parithi
Ilam
24
CLAUSE 17.2:
RECTIFICATION
LOSS/DAMAGE DUE TO
FORCE MAJEURE
Cause of Claim: Rectification
loss/damage to executed works due to
Force Majeure, the Employer, or other
contractors.
Contractor Entitlement:
EOT: YES
Cost: YES
Profit: YES
parithi
Ilam
25
CLAUSE 18.4: EXCEPTIONAL
EVENT
Cause of Claim: Exceptional Event.
Contractor Entitlement:
EOT: YES
Cost: YES
Profit: NO
parithi
Ilam
Was this Tip
helpful to you?
Like | Comment | Share | Follow
FOLLOW ME FOR MORE
Ilamparithi BoologaSundaraVijayan
Disclaimer: The information provided in this presentation serves as educational content and does not constitute legal
hi
advice. While efforts have been made to ensure accuracy, no warranty is provided regarding reliability or
rit
applicability. Viewers are advised to seek independent legal counsel for specific situations. The presenter and
pa
platform bear no liability for decisions made based on this information. Contractual terms may vary, and users should
lam
refer directly to their contracts for guidance. By accessing this presentation, viewers acknowledge these terms.