ID Task Task Name Duration Start Finish Predecessors Resource Names Qtr 1, 2024 Qtr 2, 2024
Mode Dec Jan Feb Mar Apr May
1 Project Proposal 5 days Mon 1/15/24Fri 1/19/24 1/19
2 Draft project 2 days Mon Tue 1/16/24
proposal 1/15/24
3 Review project 1 day Wed Wed 2
proposal 1/17/24 1/17/24
4 Finalize project 2 days Thu 1/18/24 Fri 1/19/24 3
proposal
5 Project Approval 3 days Sat 1/20/24 Tue 1/23/24 1 1/23
6 Present proposal 1 day Sat 1/20/24 Sat 1/20/24
to managers
7 Obtain approval 2 days Sun 1/21/24 Mon 1/22/246
8 Requirements 7 days Tue 1/23/24 Wed 5 1/31
Gathering 1/31/24
9 Identify network 2 days Tue 1/23/24 Wed
infrastructure 1/24/24
requirements
10 Define hardware 5 days Thu 1/25/24 Wed 9
and software 1/31/24
needs
11 Design 10 days Thu 2/1/24 Wed 2/14/248 2/14
12 Design network 3 days Thu 2/1/24 Mon 2/5/24
architecture
Task Inactive Summary External Tasks
Split Manual Task External Milestone
Milestone Duration-only Deadline
Project: MicrosoftProjectMarch
Summary Manual Summary Rollup Progress
Date: Fri 3/29/24
Project Summary Manual Summary Manual Progress
Inactive Task Start-only
Inactive Milestone Finish-only
Page 1
ID Task Task Name Duration Start Finish Predecessors Resource Names Qtr 1, 2024 Qtr 2, 2024
Mode Dec Jan Feb Mar Apr May
13 Select hardware 4 days Tue 2/6/24 Fri 2/9/24 12
and software
vendors
14 Develop 3 days Sat 2/10/24 Tue 2/13/24 13
implementation
plan
15 Hardware 5 days Thu 2/15/24 Wed 11 2/21
Procurement 2/21/24
16 Research hardware 2 days Thu 2/15/24 Fri 2/16/24
options
17 Procure routers, 3 days Sat 2/17/24 Tue 2/20/24 16
switches, and
servers
18 Software 7 days Thu 2/22/24 Fri 3/1/24 15 3/1
Development
19 Develop or acquire 7 days Thu 2/22/24 Fri 3/1/24
timekeeping and
workflow
management
software
Task Inactive Summary External Tasks
Split Manual Task External Milestone
Milestone Duration-only Deadline
Project: MicrosoftProjectMarch
Summary Manual Summary Rollup Progress
Date: Fri 3/29/24
Project Summary Manual Summary Manual Progress
Inactive Task Start-only
Inactive Milestone Finish-only
Page 2
ID Task Task Name Duration Start Finish Predecessors Resource Names Qtr 1, 2024 Qtr 2, 2024
Mode Dec Jan Feb Mar Apr May
20 Installation 7 days Sat 3/2/24 Mon 18 3/11
3/11/24
21 Install new 3 days Sat 3/2/24 Tue 3/5/24
hardware
components
22 Deploy software 4 days Wed 3/6/24 Mon 21
systems 3/11/24
23 Testing 10 days Tue 3/12/24 Mon 3/25/2420 3/25
24 Conduct hardware 3 days Tue 3/12/24 Thu 3/14/24
testing
25 Perform software 4 days Fri 3/15/24 Wed 24
testing 3/20/24
26 User acceptance 3 days Thu 3/21/24 Mon 25
testing 3/25/24
27 Training 5 days Tue 3/26/24 Mon 4/1/24 23 4/1
28 Subtask 1: Develop 2 days Tue 3/26/24 Wed
training materials 3/27/24
29 Subtask 2: Train 3 days Thu 3/28/24 Mon 4/1/24 28
staff on new
systems
Task Inactive Summary External Tasks
Split Manual Task External Milestone
Milestone Duration-only Deadline
Project: MicrosoftProjectMarch
Summary Manual Summary Rollup Progress
Date: Fri 3/29/24
Project Summary Manual Summary Manual Progress
Inactive Task Start-only
Inactive Milestone Finish-only
Page 3
ID Task Task Name Duration Start Finish Predecessors Resource Names Qtr 1, 2024 Qtr 2, 2024
Mode Dec Jan Feb Mar Apr May
30 Transition 5 days Tue 4/2/24 Mon 4/8/24 27 4/8
31 Transition from old 2 days Tue 4/2/24 Wed 4/3/24
to new systems
32 Provide ongoing 2 days Thu 4/4/24 Fri 4/5/24 31
support
33 Monitor system 1 day Sat 4/6/24 Sat 4/6/24 32
performance
34 Maintenance 7 days Tue 4/9/24 Wed 4/17/2430 4/17
35 Regular 5 days Tue 4/9/24 Mon
maintenance 4/15/24
checks
36 Address any issues 2 days Tue 4/16/24 Wed 35
or updates 4/17/24
Task Inactive Summary External Tasks
Split Manual Task External Milestone
Milestone Duration-only Deadline
Project: MicrosoftProjectMarch
Summary Manual Summary Rollup Progress
Date: Fri 3/29/24
Project Summary Manual Summary Manual Progress
Inactive Task Start-only
Inactive Milestone Finish-only
Page 4