Bidding Documents 2
Bidding Documents 2
     Construction of
     Motor Pool and
      Parking Area
Government of the Republic of the Philippines
                         Sixth Edition
                           July 2020
                                        Preface
         The PBDs are intended as a model for admeasurements (unit prices or unit rates in a
bill of quantities) types of contract, which are the most common in Works contracting.
         The Bidding Documents shall clearly and adequately define, among others: (i) the
objectives, scope, and expected outputs and/or results of the proposed contract; (ii) the
eligibility requirements of Bidders; (iii) the expected contract duration; and (iv) the
obligations, duties, and/or functions of the winning Bidder.
       Care should be taken to check the relevance of the provisions of the PBDs against the
requirements of the specific Works to be procured. If duplication of a subject is inevitable in
other sections of the document prepared by the Procuring Entity, care must be exercised to
avoid contradictions between clauses dealing with the same matter.
        Moreover, each section is prepared with notes intended only as information for the
Procuring Entity or the person drafting the Bidding Documents. They shall not be included in
the final documents. The following general directions should be observed when using the
documents:
       a.      All the documents listed in the Table of Contents are normally required for the
               procurement of Infrastructure Projects. However, they should be adapted as
               necessary to the circumstances of the particular Project.
       b.      Specific details, such as the “name of the Procuring Entity” and “address for
               bid submission,” should be furnished in the Instructions to Bidders, Bid Data
               Sheet, and Special Conditions of Contract. The final documents should
               contain neither blank spaces nor options.
       c.      This Preface and the footnotes or notes in italics included in the Invitation to
               Bid, BDS, General Conditions of Contract, Special Conditions of Contract,
               Specifications, Drawings, and Bill of Quantities are not part of the text of the
               final document, although they contain instructions that the Procuring Entity
               should strictly follow.
                                               1
e.   Modifications for specific Procurement Project details should be provided in
     the Special Conditions of Contract as amendments to the Conditions of
     Contract. For easy completion, whenever reference has to be made to specific
     clauses in the Bid Data Sheet or Special Conditions of Contract, these terms
     shall be printed in bold typeface on Sections I (Instructions to Bidders) and III
     (General Conditions of Contract), respectively.
f.   For guidelines on the use of Bidding Forms and the procurement of Foreign-
     Assisted Projects, these will be covered by a separate issuance of the
     Government Procurement Policy Board.
                                     2
                                       TABLE OF CONTENTS
                                                                  3
     7.     Warranty..................................................................................................................23
     8.     Liability of the Contractor .......................................................................................23
     9.     Termination for Other Causes .................................................................................23
     10.    Dayworks ................................................................................................................24
     11.    Program of Work.....................................................................................................24
     12.    Instructions, Inspections and Audits .......................................................................24
     13.    Advance Payment....................................................................................................24
     14.    Progress Payments ..................................................................................................24
     15.    Operating and Maintenance Manuals......................................................................25
Section V. Special Conditions of Contract .................................................... 26
Section VI. Specifications .............................................................................. 28
Section VII. Drawings .................................................................................... 30
Section VIII. Bill of Quantities ...................................................................... 31
Section IX. Checklist of Technical and Financial Documents ..................... 33
                                                                 4
                       Glossary of
            Terms, Abbreviations, and Acronyms
Bidding Documents – The documents issued by the Procuring Entity as the bases for bids,
furnishing all information necessary for a prospective bidder to prepare a bid for the Goods,
Infrastructure Projects, and/or Consulting Services required by the Procuring Entity. (2016
revised IRR, Section 5[e])
Consulting Services – Refer to services for Infrastructure Projects and other types of projects
or activities of the GOP requiring adequate external technical and professional expertise that
are beyond the capability and/or capacity of the GOP to undertake such as, but not limited to:
(i) advisory and review services; (ii) pre-investment or feasibility studies; (iii) design; (iv)
construction supervision; (v) management and related services; and (vi) other technical
services or special studies. (2016 revised IRR, Section 5[i])
Contract – Refers to the agreement entered into between the Procuring Entity and the
Supplier or Manufacturer or Distributor or Service Provider for procurement of Goods and
Services; Contractor for Procurement of Infrastructure Projects; or Consultant or Consulting
Firm for Procurement of Consulting Services; as the case may be, as recorded in the Contract
Form signed by the parties, including all attachments and appendices thereto and all
documents incorporated by reference therein.
Contractor – is a natural or juridical entity whose proposal was accepted by the Procuring
Entity and to whom the Contract to execute the Work was awarded. Contractor as used in
these Bidding Documents may likewise refer to a supplier, distributor, manufacturer, or
consultant.
                                               5
DOLE – Department of Labor and Employment.
Goods – Refer to all items, supplies, materials and general support services, except
Consulting Services and Infrastructure Projects, which may be needed in the transaction of
public businesses or in the pursuit of any government undertaking, project or activity,
whether in the nature of equipment, furniture, stationery, materials for construction, or
personal property of any kind, including non-personal or contractual services such as the
repair and maintenance of equipment and furniture, as well as trucking, hauling, janitorial,
security, and related or analogous services, as well as procurement of materials and supplies
provided by the Procuring Entity for such services. The term “related” or “analogous
services” shall include, but is not limited to, lease or purchase of office space, media
advertisements, health maintenance services, and other services essential to the operation of
the Procuring Entity. (2016 revised IRR, Section 5[r])
UN – United Nations.
                                            7
                    Section I. Invitation to Bid
Apart from the essential items listed in the Bidding Documents, the IB should also indicate
the following:
  a.   The date of availability of the Bidding Documents, which shall be from the time the
       IB is first advertised/posted until the deadline for the submission and receipt of
       bids;
  b.   The place where the Bidding Documents may be acquired or the website where it
       may be downloaded;
The IB should be incorporated into the Bidding Documents. The information contained in
the IB must conform to the Bidding Documents and in particular to the relevant
information in the Bid Data Sheet.
                                                8
                                    Republic of the Philippines
                              Department of Science and Technology
               PHILIPPINE SCIENCE HIGH SCHOOL - CENTRAL MINDANAO CAMPUS
                                 BIDS AND AWARDS COMMITTEE (BAC)
                                            Nangka, Balo-i, Lanao del Norte
                                            Telephone Nos. (063) 836-0098
      2.    The Philippine Science High School – Central Mindanao Campus now invites bids
            for the above Procurement Project. Completion of the Works is required one hundred
            fifty (150) calendar days. Bidders should have completed a contract similar to the
            Project. The description of an eligible bidder is contained in the Bidding Documents,
            particularly, in Section II (Instructions to Bidders).
      3.    Bidding will be conducted through open competitive bidding procedures using non-
            discretionary “pass/fail” criterion as specified in the 2016 revised Implementing Rules
            and Regulations (IRR) of Republic Act (RA) No. 9184.
      4.    Interested bidders may obtain further information from Philippine Science High
            School – Central Mindanao Campus and inspect the Bidding Documents at the
            address given below from 7:00am to 4:00am, Monday to Friday.
      6.    The Philippine Science High School – Central Mindanao Campus will hold a Pre-Bid
            Conference1 on November 24, 2020 @ 1:00pm through videoconferencing/webcasting
            via Google Meet with this link meet.google.com/vuo-kkwj-yvw, which shall be open to
            prospective bidders.
      7.    Bids must be duly received by the BAC Secretariat through (i) manual submission at
            the office address as indicated below, (ii) online or electronic submission as
1
    May be deleted in case the ABC is less than One Million Pesos (PhP1,000,000) where the Procuring Entity may not hold a
    pre-bid conference.
                                                             9
       indicated below, or (iii) both} on or before December 7, 2020 @ 10:00am. Late bids
       shall not be accepted.
  8.   All bids must be accompanied by a bid security in any of the acceptable forms and in
       the amount stated in ITB Clause 16.
  9.   Bid opening shall be on December 7, 2020 @10:01am at the given address below or
       through electronic mail address given below. Bids will be opened in the presence of
       the bidders’ representatives who choose to attend the activity through Google Meet
       with this link meet.google.com/hup-nkkr-prm.
  10. The prospective bidders may also submit their bids through online or electronic mail
      in an archive format compression and password protection to ensure the security,
      integrity and confidentiality of the bids submitted.
  11. The Philippine Science High School – Central Mindanao Canpus reserves the right to
      reject any and all bids, declare a failure of bidding, or not award the contract at any
      time prior to contract award in accordance with Sections 35.6 and 41 of the 2016
      revised Implementing Rules and Regulations (IRR) of RA No. 9184, without thereby
      incurring any liability to the affected bidder or bidders.
                                             ______________________________________
                                                      CARLITO C. LARIOSA
                                                   Chairperson, BAC PSHS-CMC
                                              10
             Section II. Instructions to Bidders
This Section on the Instruction to Bidders (ITB) provides the information necessary for
bidders to prepare responsive bids, in accordance with the requirements of the Procuring
Entity. It also provides information on bid submission, eligibility check, opening and
evaluation of bids, post-qualification, and on the award of contract.
                                           11
1.   Scope of Bid
     The Procuring Entity, Philippine Science High School – Central Mindanao Campus
     invites Bids for the Construction of Motor Pool and Parking Area, with Project
     Identification Number CMC INFRA 2020-11-013.
     [Note: The Project Identification Number is assigned by the Procuring Entity based
     on its own coding scheme and is not the same as the PhilGEPS reference number,
     which is generated after the posting of the bid opportunity on the PhilGEPS website.]
2.   Funding Information
     2.1.   The GOP through the source of funding as indicated below for National
            Expenditure Program for CY 2021 in the amount of One Million Nine
            Hundred Forty Thousand & 00/100 (Php 1,940,000.00).
3.   Bidding Requirements
     The Bidding for the Project shall be governed by all the provisions of RA No. 9184
     and its 2016 revised IRR, including its Generic Procurement Manual and associated
     policies, rules and regulations as the primary source thereof, while the herein clauses
     shall serve as the secondary source thereof.
     Any amendments made to the IRR and other GPPB issuances shall be applicable only
     to the ongoing posting, advertisement, or invitation to bid by the BAC through the
     issuance of a supplemental or bid bulletin.
     The Bidder, by the act of submitting its Bid, shall be deemed to have inspected the
     site, determined the general characteristics of the contracted Works and the conditions
     for this Project, such as the location and the nature of the work; (b) climatic
     conditions; (c) transportation facilities; (c) nature and condition of the terrain,
     geological conditions at the site communication facilities, requirements, location and
     availability of construction aggregates and other materials, labor, water, electric
     power and access roads; and (d) other factors that may affect the cost, duration and
     execution or implementation of the contract, project, or work and examine all
     instructions, forms, terms, and project requirements in the Bidding Documents.
                                           12
     obstructive practices defined under Annex “I” of the 2016 revised IRR of RA No.
     9184 or other integrity violations in competing for the Project.
5.   Eligible Bidders
     5.1.   Only Bids of Bidders found to be legally, technically, and financially capable
            will be evaluated.
     5.2.   The Bidder must have an experience of having completed a Single Largest
            Completed Contract (SLCC) that is similar to this Project, equivalent to at
            least fifty percent (50%) of the ABC adjusted, if necessary, by the Bidder to
            current prices using the PSA’s CPI, except under conditions provided for in
            Section 23.4.2.4 of the 2016 revised IRR of RA No. 9184.
     5.3.   For Foreign-funded Procurement, the Procuring Entity and the foreign
            government/foreign or international financing institution may agree on another
            track record requirement, as specified in the Bidding Document prepared for
            this purpose.
     5.4.   The Bidders shall comply with the eligibility criteria under Section 23.4.2 of
            the 2016 IRR of RA No. 9184.
7.   Subcontracts
     7.1.   The Bidder may subcontract portions of the Project to the extent allowed by
            the Procuring Entity as stated herein, but in no case more than fifty percent
            (50%) of the Project.
     7.1.   [If Procuring Entity has determined that subcontracting is allowed during the
            bidding , state:] The Bidder must submit together with its Bid the
            documentary requirements of the subcontractor(s) complying with the
            eligibility criterial stated in ITB Clause 5 in accordance with Section 23.4 of
            the 2016 revised IRR of RA No. 9184 pursuant to Section 23.1 thereof.
     7.2.   [If subcontracting is allowed during the contract implementation stage, state:]
            The Supplier may identify its subcontractor during the contract
            implementation stage. Subcontractors identified during the bidding may be
                                           13
               changed during the implementation of this Contract. Subcontractors must
               submit the documentary requirements under Section 23.1 of the 2016 revised
               IRR of RA No. 9184 and comply with the eligibility criteria specified in ITB
               Clause 5 to the implementing or end-user unit.
       7.3.    Subcontracting of any portion of the Project does not relieve the Contractor of
               any liability or obligation under the Contract. The Supplier will be responsible
               for the acts, defaults, and negligence of any subcontractor, its agents, servants,
               or workmen as fully as if these were the Contractor’s own acts, defaults, or
               negligence, or those of its agents, servants, or workmen.
8.     Pre-Bid Conference
       The Procuring Entity will hold a pre-bid conference for this Project on the specified
       date   and     time    and     either    at    its   physical     address    through
       videoconferencing/webcasting} as indicated in paragraph 6 of the IB.
       10.2.   If the eligibility requirements or statements, the bids, and all other documents
               for submission to the BAC are in foreign language other than English, it must
               be accompanied by a translation in English, which shall be authenticated by
               the appropriate Philippine foreign service establishment, post, or the
               equivalent office having jurisdiction over the foreign bidder’s affairs in the
               Philippines. For Contracting Parties to the Apostille Convention, only the
               translated documents shall be authenticated through an apostille pursuant to
               GPPB Resolution No. 13-2019 dated 23 May 2019. The English translation
               shall govern, for purposes of interpretation of the bid.
       10.3.   A valid PCAB License is required, and in case of joint ventures, a valid
               special PCAB License, and registration for the type and cost of the contract for
               this Project. Any additional type of Contractor license or permit shall be
               indicated in the BDS.
                                               14
              These key personnel must meet the required minimum years of experience set
              in the BDS.
      10.5.   A List of Contractor’s major equipment units, which are owned, leased, and/or
              under purchase agreements, supported by proof of ownership, certification of
              availability of equipment from the equipment lessor/vendor for the duration of
              the project, as the case may be, must meet the minimum requirements for the
              contract set in the BDS.
      11.2.   Any bid exceeding the ABC indicated in paragraph 1 of the IB shall not be
              accepted.
a. Philippine Pesos.
                                            15
15.   Bid Security
      15.1.   The Bidder shall submit a Bid Securing Declaration or any form of Bid
              Security in the amount indicated in the BDS, which shall be not less than the
              percentage of the ABC in accordance with the schedule in the BDS.
      15.2.   The Bid and bid security shall be valid until one hundred twenty calendar days
              after the scheduled bid opening. Any bid not accompanied by an acceptable
              bid security shall be rejected by the Procuring Entity as non-responsive.
      The Procuring Entity may request additional hard copies and/or electronic copies of
      the Bid. However, failure of the Bidders to comply with the said request shall not be a
      ground for disqualification.
      If the Procuring Entity allows the submission of bids through online submission to the
      given website or any other electronic means, the Bidder shall submit an electronic
      copy of its Bid, which must be digitally signed. An electronic copy that cannot be
      opened or is corrupted shall be considered non-responsive and, thus, automatically
      disqualified.
              In case the Bids cannot be opened as scheduled due to justifiable reasons, the
              rescheduling requirements under Section 29 of the 2016 revised IRR of RA
              No. 9184 shall prevail.
                                            16
              shall consider the conditions in the evaluation of Bids under Section 32.2 of
              2016 revised IRR of RA No. 9184.
      19.2.   If the Project allows partial bids, all Bids and combinations of Bids as
              indicated in the BDS shall be received by the same deadline and opened and
              evaluated simultaneously so as to determine the Bid or combination of Bids
              offering the lowest calculated cost to the Procuring Entity. Bid Security as
              required by ITB Clause 16 shall be submitted for each contract (lot)
              separately.
      19.3.   In all cases, the NFCC computation pursuant to Section 23.4.2.6 of the 2016
              revised IRR of RA No. 9184 must be sufficient for the total of the ABCs for
              all the lots participated in by the prospective Bidder.
                                            17
                     Section III. Bid Data Sheet
This Section is intended to assist the Procuring Entity in providing the specific information in
relation to corresponding clauses in the ITB and has to be prepared for each specific
procurement.
The Procuring Entity should specify in the BDS information and requirements specific to the
circumstances of the Procuring Entity, the processing of the procurement, and the bid
evaluation criteria that will apply to the Bids. In preparing the BDS, the following aspects
should be checked:
                                              18
                             Bid Data Sheet
ITB Clause
   5.2       For this purpose, contracts similar to the Project refer to contracts which have
             the same major categories of work, which shall be:
             Construction of vertical structure/building.
   7.1       No further instructions.
   10.4      The key personnel must meet the required minimum years of experience set
             below:
             1. Civil Engineer – licensed with at least five (5) year experience in building
                construction works.
             2. Safety Officer – should be a construction occupational safety and health
                (COSH) or BOSH Certified.
             3. Master Plumber – must be registered Master Plumber with at least five (5)
                years of experience.
             4. Mechanical Engineer – licensed with at least five (5) years of experience in
                building construction works.
             5. Two (2) Welders – must have at least five (5) years of experience in similar
                and comparable projects.
   10.5      The minimum major equipment requirements are the following:
   15.1      The bid security shall be in the form of a Bid Securing Declaration or any of
             the following forms and amounts:
               a.     The amount of not less than Thirty Eight Thousand Eight Hundred
                      Pesos & 00/100 (Php 1,940,000.00), if bid security is in cash,
                      cashier’s/manager’s check, bank draft/guarantee or irrevocable letter
                      of credit;
               b.    The amount of not less than Ninety Seven Thousand Pesos & 00/100
                     (Php 97,000.00) if bid security is in Surety Bond.
   19.2      No further instructions.
    20       No Further instructions.
    21       Additional contract documents relevant to the Project that may be required by
             existing laws and/or the Procuring Entity, such as construction schedule and S-
             curve, manpower schedule, construction methods, equipment utilization
             schedule, construction safety and health program approved by the DOLE, and
                                            19
other acceptable tools of project scheduling.
                               20
      Section IV. General Conditions of Contract
Matters governing performance of the Contractor, payments under the contract, or matters
affecting the risks, rights, and obligations of the parties under the contract are included in the
GCC and Special Conditions of Contract.
Any complementary information, which may be needed, shall be introduced only through the
Special Conditions of Contract.
                                               21
1.   Scope of Contract
     This Contract shall include all such items, although not specifically mentioned, that
     can be reasonably inferred as being required for its completion as if such items were
     expressly mentioned herein. All the provisions of RA No. 9184 and its 2016 revised
     IRR, including the Generic Procurement Manual, and associated issuances, constitute
     the primary source for the terms and conditions of the Contract, and thus, applicable
     in contract implementation. Herein clauses shall serve as the secondary source for
     the terms and conditions of the Contract.
     This is without prejudice to Sections 74.1 and 74.2 of the 2016 revised IRR of RA
     No. 9184 allowing the GPPB to amend the IRR, which shall be applied to all
     procurement activities, the advertisement, posting, or invitation of which were issued
     after the effectivity of the said amendment.
3.   Possession of Site
     4.1.   The Procuring Entity shall give possession of all or parts of the Site to the
            Contractor based on the schedule of delivery indicated in the SCC, which
            corresponds to the execution of the Works. If the Contractor suffers delay or
            incurs cost from failure on the part of the Procuring Entity to give possession
            in accordance with the terms of this clause, the Procuring Entity’s
            Representative shall give the Contractor a Contract Time Extension and certify
            such sum as fair to cover the cost incurred, which sum shall be paid by
            Procuring Entity.
     4.2.   If possession of a portion is not given by the above date, the Procuring Entity
            will be deemed to have delayed the start of the relevant activities. The
            resulting adjustments in contract time to address such delay may be addressed
            through contract extension provided under Annex “E” of the 2016 revised IRR
            of RA No. 9184.
     The Procuring Entity will approve any proposed replacement of key personnel only if
     their relevant qualifications and abilities are equal to or better than those of the
     personnel listed in the Schedule.
                                           22
5.   Performance Security
     5.1.   Within ten (10) calendar days from receipt of the Notice of Award from the
            Procuring Entity but in no case later than the signing of the contract by both
            parties, the successful Bidder shall furnish the performance security in any of
            the forms prescribed in Section 39 of the 2016 revised IRR.
     5.2.   The Contractor, by entering into the Contract with the Procuring Entity,
            acknowledges the right of the Procuring Entity to institute action pursuant to
            RA No. 3688 against any subcontractor be they an individual, firm,
            partnership, corporation, or association supplying the Contractor with labor,
            materials and/or equipment for the performance of this Contract.
7.   Warranty
     7.1.   In case the Contractor fails to undertake the repair works under Section 62.2.2
            of the 2016 revised IRR, the Procuring Entity shall forfeit its performance
            security, subject its property(ies) to attachment or garnishment proceedings,
            and perpetually disqualify it from participating in any public bidding. All
            payables of the GOP in his favor shall be offset to recover the costs.
                                             23
10.   Dayworks
      Subject to the guidelines on Variation Order in Annex “E” of the 2016 revised IRR of
      RA No. 9184, and if applicable as indicated in the SCC, the Dayworks rates in the
      Contractor’s Bid shall be used for small additional amounts of work only when the
      Procuring Entity’s Representative has given written instructions in advance for
      additional work to be paid for in that way.
      11.2. The Contractor shall submit to the Procuring Entity’s Representative for
            approval an updated Program of Work at intervals no longer than the period
            stated in the SCC. If the Contractor does not submit an updated Program of
            Work within this period, the Procuring Entity’s Representative may withhold
            the amount stated in the SCC from the next payment certificate and continue
            to withhold this amount until the next payment after the date on which the
            overdue Program of Work has been submitted.
                                            24
15.   Operating and Maintenance Manuals
      15.1. If required, the Contractor will provide “as built” Drawings and/or operating
            and maintenance manuals as specified in the SCC.
      15.2. If the Contractor does not provide the Drawings and/or manuals by the dates
            stated above, or they do not receive the Procuring Entity’s Representative’s
            approval, the Procuring Entity’s Representative may withhold the amount
            stated in the SCC from payments due to the Contractor.
                                          25
       Section V. Special Conditions of Contract
The Special Conditions of Contract (SCC) complement the GCC, specifying contractual
requirements linked to the special circumstances of the Procuring Entity, the Procuring
Entity’s country, the sector, and the Works procured. In preparing this Section, the following
aspects should be checked:
However, no special condition which defeats or negates the general intent and purpose of the
provisions of the GCC should be incorporated herein.
                                              26
          Special Conditions of Contract
GCC Clause
    2        No further instructions.
   4.1       January 22, 2020
    6        The site investigation report is Affidavit of Site Inspection
   7.2       Fifteen (15) years.
   10           a. Dayworks are applicable at the rate shown in the Contractor’s
                   original Bid.
   11.1      The Contractor shall submit the Program of Work to the Procuring
             Entity’s Representative within ten (10) calendar days of delivery of the
             Notice of Award.
   11.2      The amount to be withheld for late submission of an updated Program of
             Work is five percent (5%) of the progress billing.
    13       The amount of the advance payment is Two Hundred Ninety One
             Thousand Pesos & 00/100 (Php 291,000.00).
    14       Materials or equipment delivered on the site but not completely installed
             in place or used in the project shall not be included for payment.
   15.1       “as built” drawings and maintenance manuals are required on May 21,
             2021.
   15.2      The amount to be withheld for failing to produce “as built” drawings
             and/or operating and maintenance manuals by the date required is
             Nineteen Thousand Four Hundred Pesos & 00/100 (Php 19,400.00).
                                      27
                     Section VI. Specifications
Notes on Specifications
A set of precise and clear specifications is a prerequisite for Bidders to respond
realistically and competitively to the requirements of the Procuring Entity without
qualifying or conditioning their Bids. In the context of international competitive bidding,
the specifications must be drafted to permit the widest possible competition and, at the
same time, present a clear statement of the required standards of workmanship, materials,
and performance of the goods and services to be procured. Only if this is done will the
objectives of economy, efficiency, and fairness in procurement be realized, responsiveness
of Bids be ensured, and the subsequent task of bid evaluation facilitated. The
specifications should require that all goods and materials to be incorporated in the Works
be new, unused, of the most recent or current models, and incorporate all recent
improvements in design and materials unless provided otherwise in the Contract.
Samples of specifications from previous similar projects are useful in this respect. The use
of metric units is mandatory. Most specifications are normally written specially by the
Procuring Entity or its representative to suit the Works at hand. There is no standard set of
Specifications for universal application in all sectors in all regions, but there are
established principles and practices, which are reflected in these PBDs.
Care must be taken in drafting specifications to ensure that they are not restrictive. In the
specification of standards for goods, materials, and workmanship, recognized international
standards should be used as much as possible. Where other particular standards are used,
whether national standards or other standards, the specifications should state that goods,
materials, and workmanship that meet other authoritative standards, and which ensure
substantially equal or higher quality than the standards mentioned, will also be acceptable.
The following clause may be inserted in the SCC.
Wherever reference is made in the Contract to specific standards and codes to be met by
the goods and materials to be furnished, and work performed or tested, the provisions of
the latest current edition or revision of the relevant standards and codes in effect shall
apply, unless otherwise expressly stated in the Contract. Where such standards and codes
are national, or relate to a particular country or region, other authoritative standards that
ensure a substantially equal or higher quality than the standards and codes specified will be
                                           28
accepted subject to the Procuring Entity’s Representative’s prior review and written
consent. Differences between the standards specified and the proposed alternative
standards shall be fully described in writing by the Contractor and submitted to the
Procuring Entity’s Representative at least twenty-eight (28) days prior to the date when the
Contractor desires the Procuring Entity’s Representative’s consent. In the event the
Procuring Entity’s Representative determines that such proposed deviations do not ensure
substantially equal or higher quality, the Contractor shall comply with the standards
specified in the documents.
These notes are intended only as information for the Procuring Entity or the person
drafting the Bidding Documents. They should not be included in the final Bidding
Documents.
                                           29
                       Section VII. Drawings
[Insert here a list of Drawings. The actual Drawings, including site plans, should be
attached to this section, or annexed in a separate folder.]
                                         30
                  Section VIII. Bill of Quantities
   b.   when a Contract has been entered into, to provide a priced Bill of Quantities for use in
        the periodic valuation of Works executed.
In order to attain these objectives, Works should be itemized in the Bill of Quantities in
sufficient detail to distinguish between the different classes of Works, or between Works of
the same nature carried out in different locations or in other circumstances which may give
rise to different considerations of cost. Consistent with these requirements, the layout and
content of the Bill of Quantities should be as simple and brief as possible.
Daywork Schedule
A Daywork Schedule should be included only if the probability of unforeseen work, outside
the items included in the Bill of Quantities, is high. To facilitate checking by the Entity of
the realism of rates quoted by the Bidders, the Daywork Schedule should normally comprise
the following:
   a.   A list of the various classes of labor, materials, and Constructional Plant for which
        basic daywork rates or prices are to be inserted by the Bidder, together with a
        statement of the conditions under which the Contractor will be paid for work executed
        on a daywork basis.
Provisional Sums
A general provision for physical contingencies (quantity overruns) may be made by including
a provisional sum in the Summary Bill of Quantities. Similarly, a contingency allowance for
possible price increases should be provided as a provisional sum in the Summary Bill of
Quantities. The inclusion of such provisional sums often facilitates budgetary approval by
avoiding the need to request periodic supplementary approvals as the future need arises.
Where such provisional sums or contingency allowances are used, the SCC should state the
manner in which they will be used, and under whose authority (usually the Procuring Entity’s
Representative’s).
                                                31
The estimated cost of specialized work to be carried out, or of special goods to be supplied,
by other contractors should be indicated in the relevant part of the Bill of Quantities as a
particular provisional sum with an appropriate brief description. A separate procurement
procedure is normally carried out by the Procuring Entity to select such specialized
contractors. To provide an element of competition among the Bidders in respect of any
facilities, amenities, attendance, etc., to be provided by the successful Bidder as prime
Contractor for the use and convenience of the specialist contractors, each related provisional
sum should be followed by an item in the Bill of Quantities inviting the Bidder to quote a
sum for such amenities, facilities, attendance, etc.
Signature Box
A signature box shall be added at the bottom of each page of the Bill of Quantities where the
authorized representative of the Bidder shall affix his signature. Failure of the authorized
representative to sign each and every page of the Bill of Quantities shall be a cause for
rejection of his bid.
These Notes for Preparing a Bill of Quantities are intended only as information for the
Procuring Entity or the person drafting the Bidding Documents. They should not be included
in the final documents.
                                            32
Section IX. Checklist of Technical and Financial
                  Documents
   b. any subsequent GPPB issuances adjusting the documentary requirements after the
      effectivity of the adoption of the PBDs.
The BAC shall be checking the submitted documents of each Bidder against this checklist
to ascertain if they are all present, using a non-discretionary “pass/fail” criterion pursuant
to Section 30 of the 2016 revised IRR of RA No. 9184.
                                             33
  Checklist of Technical and Financial Documents
I. TECHNICAL COMPONENT ENVELOPE
  Legal Documents
  ⬜ (a) Valid PhilGEPS Registration Certificate (Platinum Membership) (all pages);
            or
  ⬜ (b) Registration certificate from Securities and Exchange Commission (SEC),
           Department of Trade and Industry (DTI) for sole proprietorship, or
           Cooperative Development Authority (CDA) for cooperatives or its
           equivalent document;
            and
  ⬜ (c) Mayor’s or Business permit issued by the city or municipality where the
           principal place of business of the prospective bidder is located, or the
           equivalent document for Exclusive Economic Zones or Areas;
           and
  ⬜ (e) Tax clearance per E.O. No. 398, s. 2005, as finally reviewed and approved by
           the Bureau of Internal Revenue (BIR).
  Technical Documents
  ⬜ (f)     Statement of the prospective bidder of all its ongoing government and
            private contracts, including contracts awarded but not yet started, if any,
            whether similar or not similar in nature and complexity to the contract to be
            bid; and
  ⬜ (g) Statement of the bidder’s Single Largest Completed Contract (SLCC) similar
            to the contract to be bid, except under conditions provided under the rules;
            and
  ⬜ (h) Philippine Contractors Accreditation Board (PCAB) License;
            or
            Special PCAB License in case of Joint Ventures;
            and registration for the type and cost of the contract to be bid; and
  ⬜ (i)     Original copy of Bid Security. If in the form of a Surety Bond, submit also a
            certification issued by the Insurance Commission;
            or
            Original copy of Notarized Bid Securing Declaration; and
      (j)   Project Requirements, which shall include the following:
  ⬜           a. Organizational chart for the contract to be bid;
  ⬜           b. List of contractor’s key personnel (e.g., Project Manager, Project
                    Engineers, Materials Engineers, and Foremen), to be assigned to the
                    contract to be bid, with their complete qualification and experience
                    data;
  ⬜           c. List of contractor’s major equipment units, which are owned, leased,
                    and/or under purchase agreements, supported by proof of ownership
                    or certification of availability of equipment from the equipment
                    lessor/vendor for the duration of the project, as the case may be; and
  ⬜   (k)   Original  duly signed Omnibus Sworn Statement (OSS);
                                         34
              and if applicable, Original Notarized Secretary’s Certificate in case of a
              corporation, partnership, or cooperative; or Original Special Power of
              Attorney of all members of the joint venture giving full power and authority
              to its officer to sign the OSS and do acts to represent the Bidder.
    Financial Documents
    ⬜ (l)     The prospective bidder’s audited financial statements, showing, among
              others, the prospective bidder’s total and current assets and liabilities,
              stamped “received” by the BIR or its duly accredited and authorized
              institutions, for the preceding calendar year which should not be earlier than
              two (2) years from the date of bid submission; and
    ⬜ (m) The prospective bidder’s computation of Net Financial Contracting Capacity
              (NFCC).
                                           35
36