Signed Hia Contract 1
Signed Hia Contract 1
(THIS CONTRACT HAS BEEN DEVELOPED IN CONJUNCTION WITH THE HIA AND
IS AVAILABLE FOR USE ONLY BY SIMONDS HOMES)
NOTICE TO BUILDING OWNER: YOU MAY END THIS CONTRACT WITHIN FIVE CLEAR
BUSINESS DAYS AFTER RECEIPT BY YOU OF A SIGNED COPY OF THE CONTRACT
BY FILLING IN THE NOTICE BELOW AND GIVING IT TO THE BUILDER IN ONE OF THE
FOLLOWING WAYS:
(1) PERSONALLY;
(2) LEAVING IT AT HIS OR HER ADDRESS SET OUT IN THE CONTRACT WITH A
PERSON WHO APPEARS TO BE AT LEAST 16 YEARS OLD;
(3) SENDING IT BY PRE-PAID CERTIFIED MAIL TO THE ADDRESS SET OUT IN
THIS CONTRACT;
(4) SENDING IT BY FACSIMILE TO THE FACSIMILE NUMBER (IF ANY) SET OUT IN
THIS CONTRACT.
……
………………………………………………………………………………………………………………………………………………………………
DETACH ALONG DOTTED LINE
A Building Owner cannot withdraw from a contract under the Act if:
1. The Builder and the Building Owner have previously entered into a major
domestic building contract that is in substantially the same terms for the
carrying out of the work in relation to the same home or land; OR
To ................................................................................................................................. (Builder)
I/We ............................................................................................................................................
.....................................................................................................
Date: .....................................................................................................
DocuSign Envelope ID: 581FCECD-960B-497F-8A42-883C9BFB6473
DocuSign Envelope ID: 581FCECD-960B-497F-8A42-883C9BFB6473
This checklist must be included in major domestic building contracts entered into from 1 September 2016
in substantially the same form or to the same effect as follows.
If you answer ‘NO’ to any of the following questions that apply to your building project, you are not
ready to sign the contract:*
Have you had this contract long enough to read and understand it? Yes X No
Have you been provided with evidence that the builder named in
Yes X No
this contract is registered with the Victorian Building Authority?
Do you understand how the price is calculated and may be varied? Yes X No
Has the builder assessed the suitability of the site for the proposed
Yes X No
works? If tests are necessary, have they been carried out?
Is the work shown and described clearly in the contract, plans and
specifications and any other relevant documents (such as Yes X No
engineering computations or soil report)?
Page 1 of 2
DocuSign Envelope ID: 581FCECD-960B-497F-8A42-883C9BFB6473
Are any ‘provisional sums’ or ‘prime cost items’ clearly stated in the
Yes X No
schedules and understood by you?
If yes, insert the date on which you were given a copy of this guide
23/03/2021
dd/mm/yyyy
Have you read the Domestic Building Consumer Guide and the
Yes X No
related information at consumer.vic.gov.au/buildingguide?
Signature/s
Date
dd/mm/yyyy
* Note: Not all of these questions will apply to a domestic building contract that covers a limited scope of
work, for example, a contract that is limited to the preparation of building plans and specifications.
(4 August 2016)
consumer.vic.gov.au/buildingindustry Page 2 of 2
DocuSign Envelope ID: 581FCECD-960B-497F-8A42-883C9BFB6473
Particulars of contract 1
Date 1
Owners 1
Builder 1
The Building Works 1
Building Surveyor 2
Lending details 2
Domestic building insurer 2
The land 2
Schedule 1 4
Time for completion 4
Contract Price 4
Deposit 5
Planning approval 5
Building permit 5
Percentage if contract is ended 5
Number of days to make Progress Payments after stage completed and notice
5
received
Agreed interest for late Progress payments 6
Agreed damages for late completion of the Building Works 6
Percentage applicable to extra work 6
Lending body finance 6
Agreed damages for delays 6
Schedule 2 7
Prime cost items and provisional sum items and allowances 7
Schedule 3 8
Schedule 3 Method 1 9
Schedule 3 Method 2 Acknowledgment 10
Schedule 3 Method 2 Progress Payments 11
Schedule 4 13
Schedule 5 17
Signatures 18
Deed of guarantee and indemnity 19
GENERAL CONDITIONS 21
Clause 1. Definitions 21
Clause 2. Headings, footnotes, etc. 22
Clause 3. Contract complete in itself 23
Clause 4. Joint and several obligations 23
Clause 5. Assignment and sub-letting 23
Clause 6. Notices 23
Clause 7. Building Act 1993 insurance 24
Clause 8. Finance 24
DocuSign Envelope ID: 581FCECD-960B-497F-8A42-883C9BFB6473
Clause 9. Deposit 24
Clause 10. Commencement and Building period 25
Clause 11. Statutory warranties 25
Clause 12. Owner must pay the Contract Price 25
Clause 13. Owner must provide essential information 27
Clause 14. Owner to supply documents 27
Clause 15. Copyright 27
Clause 16. Interpretation of Contract Documents 28
Clause 17. Owner must identify the Land 28
Clause 18. Building permit fees 28
Clause 19. Planning approvals and building permits 29
Clause 20. Insurance 30
Clause 21. Variations to statutory laws 31
Clause 22. Variations to State or Commonwealth tax laws 32
Clause 23. Requested variations 32
Clause 24. Effect of variations 32
Clause 25. Possession 33
Clause 26. All Weather Access 33
Clause 27. Owner must not direct Builder's workers 33
Clause 28. Owner must arrange Lending Body inspections 33
Clause 29. Builder to claim Progress Payments 34
Clause 30. Owner must make Progress Payment 34
Clause 31. Builder's right to agreed damages 34
Clause 32. Unfixed materials on Site 34
Clause 33. Prime Cost Items and Provisional Sum Items 35
Clause 34. Builder's right to extensions of time 36
Clause 35. Suspension of work 36
Clause 36. Final inspection 37
Clause 37. List of defects and Final Payment 37
Clause 38. Handover and Final Payment 38
Clause 39. Defects within the 3 month period 38
Clause 40. Owner's claim for agreed damages 39
Clause 41. Ending this Contract under bankruptcy or liquidation 39
Clause 42. Builder's right to end this Contract 39
Clause 43. Owner's right to end this Contract 40
Clause 44. Owner may get another Builder to finish work 41
Clause 45. Subcontracting 41
Clause 46. No waiver 41
Clause 47. Severance 41
Clause 48. Excluded items 41
Clause 49. Disputes 42
DocuSign Envelope ID: 581FCECD-960B-497F-8A42-883C9BFB6473
Particulars of contract
Date
Insert date when contract is signed by both parties
Owners
If the Owner is a company, a Director's Guarantee must be signed before this Contract is signed. See Deed of Guarantee and
Indemnity
Builder
NAME
ADDRESS
SUBURB Melbourne STATE VIC POSTCODE 3004
ABN 35 050 197 610 ACN 050 197 610
WORK 03 9682 0700 HOME 03 9682 0800
FAX MOBILE
EMAIL
BUILDER'S REGISTRATION NUMBER CDB-U 49491
REGISTERED BUILDING PRACTITIONER HOMES VICTORIA PTY LTD (ACN 050 197 610)
HIA MEMBER NUMBER HIA MEMBERSHIP EXPIRY 27/09/2023
The Building Works (Brief description) as set out in the Specifications and Plans
These documents must be signed and dated with the Contract.
Double Brick veneer Dwelling as set out in the specification and plans
The Specifications include 5 pages that were prepared and supplied by the builder
There are 18 sheets of Plans that were prepared by and supplied by the builder
There are sheets in the Engineer's Design/s and it/they was/were, prepared by for the Builder
Page 1 of 42
DocuSign Envelope ID: 581FCECD-960B-497F-8A42-883C9BFB6473
EMAIL adminnorth@northpointbs.com.au
REG. NO. BS-U20159
I/we acknowledge that the building surveyor was appointed by me/us before this contract was signed.
Owner
NAME Mr Muneeb Ahmed
SIGNATURE sig
NOTE: Under the Building Act 1993 the owner of the land on which domestic work is to be carried out
must choose and appoint the building surveyor.
Lending details
Any lender
Lender 1
LENDER
ADDRESS
SUBURB STATE POSTCODE
1. (a) Except for the Builder's interest in this Contract and the legal requirement for it to be
arranged in respect of the Building Works, the Builder receives no benefits in relation to
arranging such insurance.
(b) The Builder further confirms that such insurance may be arranged with an insurer of the
Owner's choice.
2. The cost to the Owner for this insurance is $774.40
Page 2 of 42
DocuSign Envelope ID: 581FCECD-960B-497F-8A42-883C9BFB6473
The land
LOT NO (IF APPLICABLE) 1148
Street Address
ADDRESS Heggart Crescent
SUBURB OFFICER SOUTH STATE VIC POSTCODE 3809
Page 3 of 42
DocuSign Envelope ID: 581FCECD-960B-497F-8A42-883C9BFB6473
Schedule 1
Note - the building period is the total of the days of actual building work and the estimates for delays.
The Builder has excluded from the Contract Price amounts payable to third parties in relation to the
Building Works. The work or things listed below are not included in the Contract Price and the
Builder's reasonable estimate of the amount payable in respect to them are listed as follows:
Item Estimate
1. Conveying connection or installation of
4. Other
The price of this Contract is not fixed, and may be altered as a result of:
• additional costs caused by any deficiency or conflict within the Contract Documents (Refer to
Clause 16);
• additional building permit fees (Refer to Clause 18);
• variations including those required by the council/registered building surveyor (Refer to
Clause 21);
• the cost of providing access where applicable (Refer to Clause 26);
Page 4 of 42
DocuSign Envelope ID: 581FCECD-960B-497F-8A42-883C9BFB6473
Ensure that you fully understand how the clauses dealing with these matters affect
the Contract Price
It is always better to get a fixed price for all work, However, some fixtures and fittings may need to be
selected after the contract is signed e.g. a stove, type of taps etc. If these items are specified as
Prime Cost Items the Builder will allow an amount in the Contract Price which should cover the
expected cost of the item.
NOTE: If the actual cost is more than the amount allowed you will have to pay the extra amount. You
may also have to pay the Builder's margin in the extra amount. If this is intended, the margin should
be specified, or cannot be claimed unless the Owner agrees in writing to such additional amount. If
the Prime Cost is less than that allowed for in the Contract, the difference should be deducted from
the Contract Price.
3. Deposit (Clause 9)
$21,541.60 (5.00 % of Contract Price)
30.00%
Page 5 of 42
DocuSign Envelope ID: 581FCECD-960B-497F-8A42-883C9BFB6473
30.00%
Page 6 of 42
DocuSign Envelope ID: 581FCECD-960B-497F-8A42-883C9BFB6473
Schedule 2
Page 7 of 42
DocuSign Envelope ID: 581FCECD-960B-497F-8A42-883C9BFB6473
Schedule 3
CONSTRUCTION STAGES APPLICABLE TO METHOD 1 PROGRESS
PAYMENTS
'Base Stage' (a) in the case of a home with a timber floor, the stage when the concrete footings for
means the floor are poured and the base brickwork is built to floor level;
(b) in the case of a home with a timber floor with no base brickwork, the stage when the
stumps, piers or columns are completed;
(c) in the case of a home with a suspended concrete slab floor, the stage when the
concrete footings are poured;
(d) in the case of a home with a concrete floor, the stage when the floor is completed;
(e) in the case of a home for which the exterior walls and roof are constructed before
the floor is constructed, the stage when the concrete footings are poured;
'Frame stage'
the stage when a home's frame is completed and approved by a building surveyor;
means
'Lock-up stage' the stage when a home's external wall cladding and roof covering is fixed, the flooring is
means laid and external doors and external windows are fixed (even if those doors or windows
are only temporary);
'Fixing stage' the stage when all internal cladding, architraves, skirting, doors, built-in shelves, baths,
means basins, troughs, sinks, cabinets and cupboards of a home are fitted and fixed in
position;
'Completion'
the Building Works are complete in accordance with the Contract Documents.
means
NOTE: This table is prescribed by Section 40 of the Domestic Building Contracts Act 1995. In the case of a
Domestic Building Contract that is not listed in the Table, a Builder must not demand or receive any amount
or instalment that is not directly related to the progress of the Building Works being carried out under the
Contract.
TABLE
Type of contract Percentage of Contract Price Stage
Page 8 of 42
DocuSign Envelope ID: 581FCECD-960B-497F-8A42-883C9BFB6473
Schedule 3 Method 1
PROGRESS PAYMENTS
NOTE: Use Method 1 unless the Building Works differ from the usual. If Method 2 is to be used the Owner
must read and sign Form 1 and Form 2 in Schedule 3 Method 2. Delete whichever method is inapplicable.
Method 1
There are five stages in Method 1. These are described below. Fill in the percentage if the Contract Price
and the amount payable for each of the stages applicable to your Contract (for example, if the Contract is to
build to lock-up stage, fill in only the first 3 stages and delete the last 2 stages; if the Contract is to complete
the Building Works complete all 5 stages).
There are five different types of construction for the Base Stage - refer to Schedule 3. In the space *
provided below fill in (a), (b), (c), (d) or (e) to indicate which type will be used under this Contract.
Stage Percent
Deposit
Completion
* Base stage: in the case of a home with a timber floor, the stage when the concrete footings for the floor
are poured and the base brickwork is built to floor level
Page 9 of 42
DocuSign Envelope ID: 581FCECD-960B-497F-8A42-883C9BFB6473
/s1/\\signer1_sig
Page 10 of 42
DocuSign Envelope ID: 581FCECD-960B-497F-8A42-883C9BFB6473
FORM 2
Regulation 13(1)(b)
The parties agree -
(i) that the Progress Payments fixed by Section 40 of the Domestic Building Contracts Act 1995
do not apply; and
(ii) instead the stages and percentages of the Contract Price and amounts payable are as follows:
/s
Page 11 of 42
DocuSign Envelope ID: 581FCECD-960B-497F-8A42-883C9BFB6473
23-Mar-2021
Date:
AND
Page 12 of 42
DocuSign Envelope ID: 581FCECD-960B-497F-8A42-883C9BFB6473
Schedule 4
SPECIAL CONDITIONS
SPECIAL CONDITIONS
Unless otherwise stated, references to clauses numbers in these Special Conditions below are to clauses in
the General Conditions of this Contract.
1. Completion – Installation of Appliances
1.1 The Building Works will be deemed to have reached Completion even if the following appliances (if
included in the Building Works) are yet to be installed in the Building Works:
(a) Cook Top;
(b) Range Hood;
(c) Oven;
(d) Hot Water Service;
(e) External heating and/or cooling units;
(f) Products associated with the Darwin package; and
(g) Dishwasher.
1.2 The abovementioned appliances will be installed after Completion in consultation with the Owner and
upon installation will be the Owner’s responsibility to insure against damage and theft. The Owner will have
no claim for loss or damage against the Builder if the above-mentioned appliances are damaged or stolen
after they have been installed.
2. Building Surveyor
2.1 The Owner’s nomination of the Private Building Surveyor is noted in clause 4 of the Preliminary
Agreement.
(a) If the Owner has selected a Building Surveyor in the Preliminary Agreement (and not appointed a
Building Surveyor under “Other”) and the Builder is identified in item 5 of Schedule 1 as the party
responsible for obtaining building permit, then the Builder is responsible for paying for fees of the Building
Surveyor appointed by the Owner and this cost is included in the contract price. The Owner authorises the
Builder to make applications, appeals or referrals under the Building Act 1993 for the Building Works.
(b) If the Owner has selected a “Other” Building Surveyor in the Preliminary Agreement and the Builder is
identified in item 5 of Schedule 1 as the party responsible for obtaining building permit, then the Owner is
responsible for paying any cost difference in the fees of the building surveyor appointed by the Owner
(compared to the named Building Surveyor for the relevant Region in the Preliminary Agreement). The
Owner acknowledges that this additional cost is not included in the contract price. The Owner authorises the
Builder to make applications, appeals or referrals under the Building Act 1993 for the Building Works.
2.2 The Owner must sign all documents and do all the acts required by the Builder to obtain all permits,
consents and certificates from the Building Surveyor or any Statutory or other authority that has the power
to affect the Building Works.
3. Variations
Prior to the Builder being required to give effect to any variation to the Building Works under clause 23, the
Owner must:
(a) Provide the Builder with satisfactory evidence of the Owner’s capacity to pay the sum of the variation in
the form of a bank statement dated no older than 1 week prior to finalising the variation request; or
(b) If the Contract is subject to finance, satisfactory written evidence by the Lending Body that such further
monies are available to the Owner prior to finalising the variation request.
4. Interpretation of Contract Documents
Delete the bullet points in clause 16.0 and replace them with the following:
Page 13 of 42
DocuSign Envelope ID: 581FCECD-960B-497F-8A42-883C9BFB6473
Page 14 of 42
DocuSign Envelope ID: 581FCECD-960B-497F-8A42-883C9BFB6473
under this Contract to carry out the Building Works or any maintenance works required to satisfy the
Builder’s warranty obligations).
8. Owner as trustee
If the Owner is a trustee of a trust, the Owner (where the Owner is a real person) or the Directors of the
trustee (where the trustee is a company) must before executing this contract, execute a Deed of Guarantee
and Indemnity in the same form as included with this contract, save for the following amendments:
8.1 “Operative” is amended by adding a new clause 1A:
1A. Owner
“The Owner has executed this contract as trustee of a trust. The guarantor is a trustee of the trust, or a
director of a trustee of the trust, and gives this guarantee and indemnity in his or her personal capacity.”
8.2 Clause 4 of the Guarantee is amended by the addition of the following words at the end of the clause:
“or if a trustee of a trust, the trustee or the trust is wound up or declared insolvent or bankrupt, or the trust
is dissolved for any reason.”
9. Contract Complete in itself
Clause 3.0 is deleted and replaced with the following clause:
“3.0 The parties have not relied on any representation or warranty in entering into this Contract, except
those expressly set out in this Contract and the signed Preliminary Agreement.”
10. Builder’s right to Terminate this Contract
The first dot point in clause 42.1 is to be amended to be:
“Does not give the Builder any of the essential information required by Clause 13 (and if at the time of this
Contract the Owner provides proof of its right to be Owner of the Land but is not the registered owner of the
Land, the Owner failed to provide the essential information required by Clause 13 within 90 days of the
Owner being the registered proprietor of the Land).”
11. Lifetime Structural Guarantee
The Owner acknowledges and agrees to the terms and conditions of the lifetime structural guarantee,
attached to this Contract, in Schedule 4 Annexure A (Lifetime Structural Guarantee).
12. Bank Statement
A new clause 8.3 is to be added:
“If this Contract is not subject to finance, the Owner must provide the Builder with a bank statement, no older
than 1 week prior to Commencement, to confirm the Owner’s capacity to pay the Contract Price.”
13. Commencement
13.1 Clause 1.0 is amended by insertion of the following definition:
“‘Final Version Construction Documents’ means the Specification, Plans (including but not limited to floor
plans, elevation plans, sections and details and selections schedules) and any other drawings associated
with the Building Works, accepted by the relevant building surveyor for the purposes of issuing the
necessary building permits.”
13.2 Clause 13.0 is amended by insertion of the following last dot:
“. Final Version Construction Documents signed by the Owner.”
Other changes to the HIA Contract
Schedule 1 – the table in Item 1 regarding third party costs
(a) Gas (including both connection and any usage costs)
(b) Electricity (including both connection and any usage costs)
(c) Water (including both connection and any usage costs)
(d) Telephone (to one point)
(e) Sewerage
Schedule 1 – Item 2
Page 15 of 42
DocuSign Envelope ID: 581FCECD-960B-497F-8A42-883C9BFB6473
Page 16 of 42
DocuSign Envelope ID: 581FCECD-960B-497F-8A42-883C9BFB6473
Schedule 5
EXCLUDED ITEMS (Clause 48)
The Owner acknowledges that the Contract Building Works do not include those items of building work
and materials listed below and accepts full responsibility for this work and building materials.
The Owner must ensure that, when required by Victorian legislation, a person engaged by them to
complete excluded building work is registered as a building practitioner, uses a major domestic building
contract, and provides domestic building insurance.
Owner
NAME Mr Muneeb Ahmed
SIGNATURE
Page 17 of 42
DocuSign Envelope ID: 581FCECD-960B-497F-8A42-883C9BFB6473
Signatures
This contract is made between the Owner and the Builder.
The schedules form part of this contract.
The Owner has read and understood this contract.
Owner
NAME Mr Muneeb Ahmed
SIGNATURE gner1_sig
WITNESS
SIGNATURE NOT APPLICABLE
WITNESS
NAME AND
ADDRESS NOT APPLICABLE
Builder
Andrew Flanagan
NAME
SIGNATURE
Signed for and on behalf of: Simonds Homes Victoria Pty Ltd
WITNESS
NAME NOT APPLICABLE
WITNESS
SIGNATURE NOT APPLICABLE
Please note
1. Where a company is signing: 'by A. Smith, Director' or 'Signed for and on behalf of XYZ Pty Ltd'
2. Where a partnership is signing: 'B. Bloggs in partnership with A. Bloggs and C. Bloggs'
NOTES: 1. Only sign this Contract when: All the Contract Documents required including Specifications and Plans are attached and signed; All the
details in the Schedules have been filled in. 2. The Builder must give the Owner a readily legible signed copy of this Contract within 5 clear Days after
it is signed.
Page 18 of 42
DocuSign Envelope ID: 581FCECD-960B-497F-8A42-883C9BFB6473
Interpretation
BUILDER IS
OWNER IS
Guarantors
ADDRESS LINE 1
ADDRESS LINE 2
SUBURB STATE POSTCODE
Background
The Owner executed the Contract at the Guarantor's request.
The Guarantor is aware of the Owner's obligations under the Contract.
Operative
1. Guarantee
The Guarantor guarantees to the Builder, the fulfilment of the Owner's obligations under the
Contract including but not limited to the due payment of all moneys arising out of the subject matter of
the Contract.
2. Indemnity
The Guarantor indemnifies the Builder against any claim, loss or damage arising out of the subject
matter of the contract caused by or resulting from any non-fulfilment of the Owner's obligations under
the Contract.
3. Principal Debtor
The Guarantor is deemed to be principal debtor jointly and severally liable with the Owner to
discharge the Owner's obligations under the Contract.
4. No Merger
The Guarantor agrees that this Deed does not merge on completion or on the ending of the Contract
by either party and continues notwithstanding that the Owner, if a corporation, is placed in liquidation
or if a person, is declared bankrupt.
5. No Release
The Guarantor is not discharged by:
◦ any variation to the Contract including a variation to the building works;
◦ any delay or claim by the Builder to enforce a right against the Owner; and
◦ any forbearance given to the Owner to perform the Owner's obligations under the Contract.
6. Severability
Any provision of this Deed which is illegal, void or unenforceable will be ineffective to the extent only of
such illegality, voidness or unenforceability and will not invalidate any other provision of this Deed.
Page 19 of 42
DocuSign Envelope ID: 581FCECD-960B-497F-8A42-883C9BFB6473
Guarantor's Statement
I/we understand the nature, terms and extent of the guarantee and indemnity provided by me/us and further
acknowledge that I/we have obtained legal advice prior to executing this Deed.
Signed as a Deed
SIGNATURE
SIGNATURE
DATE
Page 20 of 42
DocuSign Envelope ID: 581FCECD-960B-497F-8A42-883C9BFB6473
GENERAL CONDITIONS
A. Interpretation
Clause 1. Definitions
NOTE 1.0 • 'All Weather Access' means reasonable access to the Building Site
Throughout the to enable the carrying out of the Building Works including in
Contract whenever a
defined phrase or conditions resulting from Restricted Access.
word is used it is
shown in bold print. • 'Builder' means the person, partnership or company named in the
Particulars of Contract.
• 'Building Period' means the building construction time estimated by
the Builder to carry out the Building Works as stated in Item 1 of
Schedule 1, subject to Clause 34.
• 'Building Works' means the works to be carried out and completed by
the Builder as shown in the Contract Documents and as varied in
accordance with this Contract.
• 'Building Site' means the land upon which the Building Works are to
be carried out.
• 'Building Surveyor' means the person, partnership or company
named in the Particulars of Contract.
• 'Business Day' means a day that is not a Saturday or a Sunday or a
day that is wholly or partly observed as a public holiday throughout
Victoria.
• 'Commencement' means the day on which the Building Works
commence on the Building Site.
• 'Completion' means that the Building Works to be carried out under
the Contract have been completed in accordance with the Plans and
Specifications set out in the Contract.
• 'Contract Documents' means this signed Contract and the
Conditions, signed Specifications, signed Plans and an Engineer's
Design.
• 'Contract Price' means the amount show in Item 2 of Schedule 1.
• 'Days' means calendar days.
• 'Engineer's Design' includes a footing design or other structural
design that has been prepared by a qualified engineer for the
concrete footings, stumps, piers or slab construction, or for a particular
part of the Building Works that require a structural design, drainage
design where appropriate and computations accompanying the
foregoing.
• 'Final Claim' means the Builder's claim setting out the balance of the
Contract Price due for payment by the Owner to the Builder, taking
into account all monies paid by the Owner and all other amounts to be
added to or deducted from the Contract Price under this Contract.
• 'Final Payment' means the payment of the amount of the Final Claim.
Page 21 of 42
DocuSign Envelope ID: 581FCECD-960B-497F-8A42-883C9BFB6473
Page 22 of 42
DocuSign Envelope ID: 581FCECD-960B-497F-8A42-883C9BFB6473
Clause 6. Notices
6.0 Unless otherwise stated in this Contract, a notice given under this Contract
must be in writing and in English.
6.1 Notices may be given:
• personally;
• by sending it by prepaid post to the party's address shown in the
Particulars of Contract or the address that is last notified in writing;
• by sending it by facsimile to the party's fax number shown in the
Particulars of Contract or the fax number that is last notified in writing;
or
• by sending it by email to the party's email address shown in the
Particulars of Contract or that is last notified in writing.
6.2 Notice is deemed to be received:
• if given personally, by handing it to the other party;
• if sent by prepaid post, 5 Business Days after posting;
• if sent by facsimile, at the time and on the day shown in the sender's
transmission report;
• if sent by email, at the time of transmission unless the sender's server
or email indicates a malfunction or error in transmission or the
recipient immediately notifies the sender of an incomplete or illegible
transmission.
6.3 If the notice is deemed to be received on a day which is not a Business Day
or after 5pm, it is deemed to be received at 9am on the next Business Day.
6.4 If two or more people comprise a party, notice to one is effective notice to
all.
Page 23 of 42
DocuSign Envelope ID: 581FCECD-960B-497F-8A42-883C9BFB6473
Clause 8. Finance
8.0 If an amount is inserted in Item 11 of Schedule 1 then this Contract is
conditional upon the Lending Body providing to the Owner written
approval of a loan of at least that amount in order to enable the Owner to
pay to the Builder the monies which become payable under this Contract,
such approval unless otherwise stated in Item 11 of Schedule 1 to be
provided within 14 Days of the date of this Contract. The Owner promises
diligently to pursue such written approval.
8.1 Should such written approval not be obtained within the time provided, this
Contract will be voidable within 7 Days at the option of the Owner to be
exercised by notice in writing to the Builder, whereupon all monies paid by
the Owner to the Builder, will be refunded except for a sum calculated in
accordance with Clause 19.4.
8.2 If required by the Builder, the Owner must deposit that part of the
Contract Price not being supplied by the Lending Body into a separate
bank account in the joint names of the Owner and the Builder with:
• interest received on the money in the account belonging to the
Owner; and
• withdrawals requiring the signatures of both the Owner and the
Builder.
Clause 9. Deposit
9.0 The Owner must pay to the Builder the deposit set out in Item 3 of
Schedule 1 on the later of:
• the signing of this Contract; or
• the issue of an insurance policy in relation to this Contract under
Division 3 of Part 9 of the Building Act 1993.
9.1 The amount of the deposit must not be:
• more than 5%, if the Contract Price is $20,000 or more; or
• more than 10%, if the Contract Price is less than $20,000.
Page 24 of 42
DocuSign Envelope ID: 581FCECD-960B-497F-8A42-883C9BFB6473
Page 25 of 42
DocuSign Envelope ID: 581FCECD-960B-497F-8A42-883C9BFB6473
Page 26 of 42
DocuSign Envelope ID: 581FCECD-960B-497F-8A42-883C9BFB6473
Page 27 of 42
DocuSign Envelope ID: 581FCECD-960B-497F-8A42-883C9BFB6473
Page 28 of 42
DocuSign Envelope ID: 581FCECD-960B-497F-8A42-883C9BFB6473
18.1 In the case of multiple dwellings where additional fees may be applicable,
such as for head works, open space allowances and planning fees, these
are not included in the Contract Price unless specified in Schedules 1
or 4.
18.2 If a building permit fee increases or decreases after the date of this
Contract the Owner must pay any increase and the Builder must credit
any decrease and the next Progress Payment will be varied accordingly.
19.1 Subject to the receipt of the planning approval and if the Owner has not
already obtained the necessary building permits, the Builder must apply
for them within 14 Days after receiving evidence of the Owner's title to the
Land and ability to pay under Clause 13.
19.2 If the Builder obtains the building permits, the Builder must give copies of
the permit documents to the Owner, if requested to do so.
19.3 If the necessary planning approval and/or building permits are not obtained
within the time specified in Items 4 or 5 of Schedule 1, then if:
• neither party is at fault, either party may bring this Contract to an end
by giving written notice to the other;
• the Builder is at fault, the Owner may bring this Contract to an end
by giving the Builder written notice; or
• the Owner is at fault, the Builder may bring this Contract to an end
by giving the Owner written notice,
provided that the party who wishes to end this Contract under the
conditions of this Clause must do so within 14 Days of the expiration of the
period set out in Items 4 or 5 of Schedule 1.
19.4 If this Contract is ended under this Clause and the Builder is not at fault,
the Builder is entitled to a reasonable price for the work performed,
including the costs incurred and an amount for the Builder's profit and
overheads being the percentage shown in Item 6 of Schedule 1 applied to
the cost of that work. The price:
• may include an amount for the preparation of Plans and
Specifications, the Engineer's Design and Soil Test Report -
unless these have been allowed for in a separate contract; and
• must not include an amount for work on the Building Site for which
planning or building approval was not obtained.
Page 29 of 42
DocuSign Envelope ID: 581FCECD-960B-497F-8A42-883C9BFB6473
20.1 The Builder must maintain the insurance from the date the Owner gives
the Builder Possession of the Land under Clause 25 to the earlier of:
• the date that the Owner takes Possession of the Land or any part of
the Land; or
• the date the Builder hands over Possession of the Land.
The Owner must pay the Builder a reasonable amount to cover the pro-
rata cost of the insurance for any period during which the Final Payment is
unreasonably withheld from the date the money is due.
20.2 The Builder must provide the Owner with a current 'Certificate of
Currency' within 7 Days of Commencement of the Building Works. The
Certificate must show the names of the Builder, Owner, Lending Body
and the job address.
20.3 The cover for personal injury, death, property loss or damage arising out of
the Building Works must be for an amount which is not less than
$5 million for any one claim and the Builder must include as parties to be
insured under the policy, any Sub-Contractors who do not provide the
Builder with evidence of adequate and continuing insurance cover.
20.4 The Builder is not responsible for, and does not indemnify the Owner or
the Owner's employees or agents or any person claiming through the
Owner against any loss or liability that arises out of something done or not
done by the Owner or any person for whom the Owner is responsible. The
Owner indemnifies the Builder in relation to such claims.
20.5 The Builder must be registered with WorkCover to protect any person
employed by the Builder in carrying out the Building Works.
Page 30 of 42
DocuSign Envelope ID: 581FCECD-960B-497F-8A42-883C9BFB6473
D. During work
Page 31 of 42
DocuSign Envelope ID: 581FCECD-960B-497F-8A42-883C9BFB6473
Page 32 of 42
DocuSign Envelope ID: 581FCECD-960B-497F-8A42-883C9BFB6473
Page 33 of 42
DocuSign Envelope ID: 581FCECD-960B-497F-8A42-883C9BFB6473
Page 34 of 42
DocuSign Envelope ID: 581FCECD-960B-497F-8A42-883C9BFB6473
33.1 An allowance for a Prime Cost Item does not include amounts for
installation, Builder's profit and overheads and cartage. These are
included in the Contract Price.
33.2 An allowance for a Provisional Sum Item does not include an amount for
the Builder's profit and overheads. The amount for the Builder's profit
and overheads is included in the Contract Price.
33.3 If a Prime Cost Item selected by the Owner is unavailable, then the
Owner must specify an alternative item within 7 Days of the Builder's
request to do so, and if the Owner fails to comply the Builder shall be
entitled to select an alternative as near as practical in quality to the original
item selected by the Owner.
33.4 In relation to each Prime Cost Item and Provisional Sum Item, if the
actual price of supplying the item or providing the work is:
• less than the allowance, the difference is deducted from the Contract
Price; or
• more than the allowance, the total of the difference plus the relevant
margin or excess stated in Schedule 2 applied to that difference is
added to the Contract Price and is payable with the Progress
Payment in which the amount for that item or work is included.
33.5 Where there are no further Progress Payments to be made, the Builder
must calculate the amount and notify the Owner as soon as possible. The
amount of the difference must be paid or allowed with the Final Payment
as the case may be.
33.6 In calculating the amount spent, the Builder must pass on normal trade
discounts to the Owner. This does not include cash or special discounts
for bulk purchasing or personal reasons.
33.7 The Builder must give the Owner a copy of any invoice, receipt or other
document that shows the cost to the Builder of any Prime Cost Item or
labour and materials that relate to a Provisional Sum Item, as soon as
practicable after receiving same.
Page 35 of 42
DocuSign Envelope ID: 581FCECD-960B-497F-8A42-883C9BFB6473
33.8 The Builder warrants that any allowance for a Provisional Sum Item
included by the Builder in the Contract has been calculated with
reasonable care and skill taking account of all the information reasonably
available at the date the Contract is made, including the nature and
location of the Building Site.
34.4 The Owner must pay any delay damages with the next Progress
Payment.
Page 36 of 42
DocuSign Envelope ID: 581FCECD-960B-497F-8A42-883C9BFB6473
35.1 If the Builder suspends the Building Works, the Builder must
immediately give notice in writing by registered post to the Owner. The
Owner must remedy the breach within 7 Days after receiving the notice.
The Builder must recommence the Building Works within 21 Days after
the Owner remedies the breach and gives notice of this to the Builder.
35.2 The date on which the Building Works are to be completed is changed
and extended to cover the period of suspension.
Page 37 of 42
DocuSign Envelope ID: 581FCECD-960B-497F-8A42-883C9BFB6473
37.4 The Owner must pay the Final Claim within a further period of 7 Days
after the Owner receives the Builder's notice under Clause 37.3.
37.5 The fact that the Owner pays the Final Claim is not evidence that there
are no defects or incomplete work nor a waiver of any rights under a
statutory warranty.
37.6 The fact that the Builder signs the list is not an admission that the defects
exist or there is incomplete Building Works.
37.7 'Defect' does not include a defect arising from the fact that something has
to be supplied or done by the Owner.
Page 38 of 42
DocuSign Envelope ID: 581FCECD-960B-497F-8A42-883C9BFB6473
39.3 The Builder must fix defects without cost to the Owner. The Builder must
do so in normal working hours or at any time agreed between the Builder
and the Owner. The Owner must provide reasonable access to the
Builder.
40.1 The Owner may deduct the amount of any such damages from the Final
Payment.
Page 39 of 42
DocuSign Envelope ID: 581FCECD-960B-497F-8A42-883C9BFB6473
Page 40 of 42
DocuSign Envelope ID: 581FCECD-960B-497F-8A42-883C9BFB6473
Page 41 of 42
DocuSign Envelope ID: 581FCECD-960B-497F-8A42-883C9BFB6473
Page 42 of 42
DocuSign Envelope ID: 581FCECD-960B-497F-8A42-883C9BFB6473
Before your building project starts Make sure you have enough time to thoroughly read
the contract. You should also consider obtaining
You will usually need to appoint building practitioners independent legal advice before you sign the
when you build, renovate or extend a house or unit, contract, even though this means you no longer have
or do other building work. Other work includes work the five-day cooling-off period to change your mind.
such as landscaping, fencing or building a swimming
pool, driveway or a garage. You may need a builder If you are asked to sign a pre-construction contract
to complete the building work, and if you need a (for example, a contract for design or specification
building permit you will need a building surveyor. work or obtaining permits) that is for more than
$10,000, it will be a major domestic building contract.
The Victorian Building Authority (VBA) registers
building practitioners. If you are concerned about the Your contract will also include a checklist, which sets
conduct of a building practitioner you should contact out the matters you must consider before signing the
the VBA. contract. You must complete and sign the contract
checklist.
You can check the registration and disciplinary
history of a building practitioner via the links at You can make a variation to a contract after it has
consumer.vic.gov.au/buildingguide. been signed by using a variation notice (for example,
to change the plans and specifications). You and
Your builder must also take out Domestic Building your builder must agree in writing to the changes and
Insurance (DBI) for your project, if the building work put the details, including the new price and
costs more than $16,000. This covers defective or completion date, in the contract before the work is
incomplete work for up to six years if your builder carried out.
dies, disappears or becomes insolvent. You can also
claim on DBI with the Victorian Managed Insurance Find more information about the contract, the
Authority if your builder fails to comply with a final checklist and contract variations via
order from the Victorian Civil and Administrative consumer.vic.gov.au/buildingguide.
Tribunal or a court.
Appointing a building surveyor
Check when you may make a claim via the links at
consumer.vic.gov.au/buildingguide. Some building projects require a building permit. A
building permit is written approval from a building
Appointing your builder surveyor that your plans and specifications comply
with the building regulations. It allows your builder to
You appoint your builder by signing a major domestic start your building project.
building contract.
If your building work requires a building permit, you
Your contract must be in writing and include details must engage a building surveyor before you apply for
such as: the permit. There are penalties for you and your
the contract price builder if a building permit is not obtained.
the deposit and progress payments required by
You can only engage one building surveyor, but you
law for completed stages of work
may choose either a private building surveyor or a
a description of the building work to be carried out municipal building surveyor. Your builder may
the plans and specifications, and recommend a building surveyor, but cannot appoint a
advice on the five-day cooling-off period. private building surveyor for you.
The contract price should be a fixed amount. Cost- You can choose a building surveyor via the links at
plus contracts, for example where your builder consumer.vic.gov.au/buildingguide.
charges you by the hour, are only allowed for
projects over $1 million, or for renovation projects in If you want to engage a municipal building surveyor,
limited circumstances. contact your local council.
(1 August 2017)
consumer.vic.gov.au/buildingguide Page 1 of 2
This guide must not be taken as legal advice.
DocuSign Envelope ID: 581FCECD-960B-497F-8A42-883C9BFB6473
During your building project supply as soon as possible (for example, materials
such as tiles, or a service such as a tiler to work
Role of your builder on the flooring)
put the details and costs of any changes in writing
Your builder is responsible for completing your – you and your builder must sign off on the
building project to the standard required by the changes before the builder starts the work, and
building regulations and your plans and only make stage payments when the building work
specifications. The builder may undertake the work for each stage is complete – do not make
or engage and manage tradespeople to do the work. payments in advance.
Your builder must also provide you with a copy of the Check everything in your contract has been delivered
DBI policy and a certificate of insurance for your and is in working order before you make the final
building project, before you pay your deposit. If you payment.
are concerned about the validity of the certificate,
you should check with the insurer. Find details at consumer.vic.gov.au/buildingguide.
consumer.vic.gov.au/buildingguide Page 2 of 2