Arbitration Moot: Claimant's Case
Arbitration Moot: Claimant's Case
5th NLIU JUSTICE R.K. TANKHA MEMORIAL INTERNATIONAL ARBITRATION MOOT, 2020
                                          Before
                                 THE ARBITRAL TRIBUNAL
                         BARATHEON CITY, STARK PROVINCE
v.
                                          UNDER
      ARBITRATION RULES OF THE SINGAPORE INTERNATIONAL ARBITRATION CENTRE
                                (6th EDITION, 1 AUGUST 2016)
                                    CASE CONCERNING
     THE PART SUPPLY CONTRACT BETWEEN ARCEBOR POWER PRIVATE LIMITED AND
                   RENVIDORA NATIONAL POWER COMPANY LIMITED
TABLE OF CONTENTS
TABLE OF CONTENTS................................................................................................................ I
B. The Act Of The Respondent Violates The Principle Of Good Faith. .......................... 8
   III.        THE CLAIMANT IS UNDER NO OBLIGATION TO DISCLOSE ITS SOURCE OF FUNDING FOR
   PURSUING THESE ARBITRATION PROCEEDINGS AND THE TRIBUNAL SHOULD NOT ORDER
   SECURITY FOR LEGAL COSTS. ................................................................................................. 9
         A. The Newspaper Report Of Third Party Funding Submitted by the Respondent Does
         Not Have Probative Value. ................................................................................................. 9
B. The Claimant Is Not Bound to Disclose the Third Party Funding Under Any Law. 10
B. The Respondent And Ministry Of Power Form A Single Economic Entity. .............. 15
      C. The Respondent Is The Agent Of The Ministry Of Power And Thus Should Be Joined
      As It Is The Principal. ....................................................................................................... 16
   V.        THE CLAIMANT’S CONDUCT DID NOT BREACH THE AGREEMENT AND THE
   RESPONDENT WAS NOT JUSTIFIED IN TERMINATING THE AGREEMENT. ............................... 17
      A. The Claimant’s Failure To Supply The Parts On Time Is Not The Fundamental Breach
      Of The Contract. ............................................................................................................... 17
      B. The Claimant’s Failure To Perform As Per The Terms Of The Agreement Is Exempted
      From Liability Under Article 79(1) Of CISG. .................................................................. 20
      C. The Respondent Was Not Justified In Terminating The Agreement By The Virtue Of
      Article 49 Of CISG. .......................................................................................................... 21
PRAYER .................................................................................................................................XVI
TABLE OF ABBREVIATIONS
INDEX OF AUTHORITIES
     CLOUT case No. 846 [U.S. Court of Appeals (3rd Circuit), United States, 19 July 2007]
        .......................................................................................................................... 13, 20, 23
     CLOUT case No. 846 [U.S. Court of Appeals (3rd Circuit), United States, 19 July
        2007]. ........................................................................................................................... 23
     CLOUT case No. 90 [Pretura circondariale di Parma, Italy, 24 November 1989] ...... 20
     Copperweld Corp. v. Independence Tube Corp, 467 U.S. 752 (1984). ....................... 16
     Dow Chemical Co. v. United States, 476 U.S. 227 (1986). ........................................ 16
     FirstLink Investments Corp Ltd v. GT Payment Pte Ltd and others [2014] SGHCR 12
        ........................................................................................................................................ 4
     Gianelli Money Purchase Plan & Trust v. ADM Inv. Servs., Inc., 146 F.3d 1309, 1313
        (11th Cir. 1998) ............................................................................................................ 12
     Guaracachi America, Inc. and Rurelec PLC v. The Plurinational State of Bolivia
        ,UNCITRAL, PCA Case No. 2011-17, Award of January 31, 2014, at 22, ¶ 66 ........ 12
     Guaracachi America, Inc. and Rurelec PLC v. The Plurinational State of Bolivia
        ,UNCITRAL, PCA Case No. 2011-17, Procedural Order No. 13 of February 21, 2013,
        at 3, ¶8. ......................................................................................................................... 12
     Heyman v. Darwins Ltd [1942] AC 35.......................................................................... 3
     HKL Group Co Ltd v. Rizq International Holdings Pte Ltd, [2013] SGHCR 8............ 2
     Hof van Cassatie, Belgium, 19 June 2009 (Scafom International BV v. Lorraine Tubes
        S.A.S.) .................................................................................................................... 21, 22
     Insigma Technology Co Ltd v. Alstom Technology Ltd, [2009] SGCA 24.................. 2
     Interocean Shipping Co. v. National Shipping and Trading Corp. and Hellenic
        International Shipping, S.A, 523 F.2d 527, (2nd Cir 1975)......................................... 17
     Ioannis Kardassopoulos & Ron Fuchs v. Georgia, ICSID Case No. ARB/05/18 and
        ARB/07/15, Award of March 3, 2010, at 215, ¶691. ................................................... 12
     Jharkhand Bijli Vitran Nigam Limited v IVRCL Ltd.,                                                          [Company Appeal
        (AT)(Insolvency) No. 285 of 2018]. .............................................................................. 8
     K. K. Modi v. K. N. Modi, AIR 1998 SC 1297 ............................................................. 1
     Kirke La Shelle Company v. The Paul Armstrong Company et al., 263 N.Y. 79. ........ 8
     Konkan Railway Corporation Ltd. & Anr. v. Rani Construction Pvt. Ltd 2005 (8) SCC
        618.................................................................................................................................. 6
     Kvaerner Cementation India Ltd. v. Bajranglal Agarwal (2012) 5 SCC 214. ............... 6
     Landgericht Oldenburg, 27 March 1996, 12 O 2541/95. See University of Freiburg
        Database, http://www.cisg-online.ch/cisg/urteile/188.htm .................................... 13, 19
     Robert Koch, ‘The Concept of Fundamental Breach of Contract under the United
        Nations Convention on Contracts for the International Sale of Goods (CISG)’, in:
        Review of the Convention on Contracts for the International Sale of Goods (CISG)
        1998 (1999) 177, 236. .................................................................................................. 19
SIAC DOCUMENTS
     Singapore International Arbitration Centre Practice Note, PN – 01/17 (31 March 2017),
        Administered Cases under the arbitration rules of the Singapore International
        Arbitration Centre, On Arbitrator Conduct in Cases Involving External Funding ...... 14
STATEMENT OF FACTS
                                            PARTIES
1. Acrebor Power Private Limited, hereinafter referred to as the CLAIMANT is a
    multinational company and a leader in market energy in Xanier. It has a major
    manufacturing unit in Xanier, which produces, sells and distributes industrial products. It
    sources most of its raw material from Zorastra. It is incorporated under the laws of Xanier
    and has its principal office in Joeville, Xanier.
2. Renvindora National Power Company Limited, hereinafter referred to as the
    RESPONDENT is wholly owned by the Government of Yevadu. It is incorporated under the
    laws of Yevadu. It owns and operates thermal power plants in remote Yevadu. One such
    thermal power plant is located in Tullyland, Yevadu [“Tullyland Power Plant], for which
    this agreement was entered into. It works under the authority and direction of the Ministry
    of Power of the Government of Yevadu.
                             THE PART SUPPLY AGREEMENT
3. The CLAIMANT and the RESPONDENT entered into an agreement in 2015 for the supply of
    parts and components of the repair and maintenance Frame 15X turbines for a period of 15
    years.
4. The Agreement was devised with the purpose of ensuring that the obsolete parts of the
    Frame 15X Turbines are to be inspected and identified by the CLAIMANT and replaced with
    new parts. For the same reason Clause 3 in the Agreement stated at the commencement of
    each year, there would be an annual inspection by the CLAIMANT. The CLAIMANT for three
    years honoured the agreement and sent a designated official to inspect, test and monitor the
    turbines and the whole Tullyland Power Plant.
5. Through this Annual Inspection, a Requisition List was prepared by the CLAIMANT’s
    officials, which contains a list of parts that are required to be supplied by the CLAIMANT.
    These parts, according to Clause 3 would be supplied in installments by the CLAIMANT to
    the RESPONDENT after the end of each quarter, i.e., on the 31st of March, June, September
    and December. The RESPONDENT was to issue a formal purchase order in the name of the
    CLAIMANT for the specified parts requisitioned for the particular quarter, fifteen days prior
    to such delivery. The Clause also specified that the CLAIMANT is to maintain at least 85%
    of Plant availability.
                                     RESTRUCTURING POLICY
6. In December, the CLAIMANT notified the RESPONDENT of the new support structure as a
    part of the new restructuring policy to improve the technical support and customer service
    to its clients globally. Due to this change, the CLAIMANT would be unable to send an official
    for the annual inspection of the Tullyland Power Plant in January. However, the CLAIMANT
    ensured assistance to the RESPONDENT’s team in finalizing the Requisition List. The
    RESPONDENT welcomed this decision and acknowledged the shift in the customer policy,
    and agreed to undertake the inspection itself. Subsequently, the RESPONDENT issued the
    Requisition List to the CLAIMANT for the year 2018.
                           UNFAVOURABLE CIRCUMSTANCES
7. Xanier alleged that Zorastra was indulging in unfair trade practices, which subsequently
    led to Xanier imposing high tariffs on raw material sourced from Zorastra. The CLAIMANT
    due to increased tariffs and an intensifying trade war between the two states incurred huge
    losses in its business operations globally as there was an increase in the working capital of
    the CLAIMANT and the cost of the manufactured parts. As a result, the CLAIMANT requested
    the senior management of the RESPONDENT to renegotiate the terms and conditions of the
    Agreement due to the setback. The discussion was specifically on the consideration for the
    performance of the CLAIMANT’s obligations, as it was becoming commercially unviable for
    the CLAIMANT to continue with the Agreement
                              TERMINATION OF AGREEMENT
8. The CLAIMANT continued to communicate with the RESPONDENT with the aim of arriving
    at a reasonable business proposition. However, the RESPONDENT stopped all the
    communication channels with the CLAIMANT.
9. On 14 December 2018, The RESPONDENT wrote a letter to the CLAIMANT wherein it refused
    to renegotiate the Agreement and directed the CLAIMANT to supply the parts for the quarter
    ending in December 2018, failing which it would terminate the Agreement.
10. The RESPONDENT did not assist the CLAIMANT, and despite incurring huge losses, the
    CLAIMANT delivered the parts in the second week of January 2019 with an additional claim
    of USD 100,000. RESPONDENT alleging late delivery by breach of stipulated time and that
    the CLAIMANT had failed to perform its obligations, refused to accept the delivery of the
    consignment. On 20 January 2019, the CLAIMANT received a termination notice from the
    RESPONDENT. Aggrieved by this termination of the Agreement, the CLAIMANT filed a
    Notice of Arbitration and Statement of Claim under Rule 3 of the SIAC Rules stating that
    the termination of the Agreement is wrongful, illegal, arbitrary and mala fide.
ISSUES RAISED
~I~
~ II ~
~ III ~
~ IV ~
~V~
   WHETHER THE CLAIMANT’S CONDUCT BREACHED THE AGREEMENT AND WHETHER THE
               RESPONDENT WAS JUSTIFIED IN TERMINATING THE AGREEMENT?
SUMMARY OF ARGUMENTS
V. THE CLAIMANT’S CONDUCT DID NOT BREACH THE AGREEMENT AND THE
    RESPONDENT WAS NOT JUSTIFIED IN TERMINATING THE AGREEMENT.
    It is humbly submitted before this Tribunal that, the Claimant’s conduct does not the
    breach the Agreement. Firstly, it is contended that the Claimant’s failure to supply the
    parts on time is not the fundamental breach of the contract. Secondly, it is further
    submitted that the Claimant’s failure to perform as per the terms of the Agreement is
    exempted from liability under Art. 79 of CISG. Thirdly, the Claimant also contends that
    the Respondent was not justified in terminating the Agreement under Art. 49 of CISG.
ARGUMENTS ADVANCED
1
  Bihar State Mineral Development Corporation & Anr. v. Encon Builders (I) (P) Ltd., (2003) 7 SCC 418.
2
  ANDREA MARCO STEINGRUBER, CONSENT IN INTERNATIONAL ARBITRATION (OUP, 1st ed., 2012).
3
  K. K. Modi v. K. N. Modi, AIR 1998 SC 1297.
4
  Andrea Marco Steingruber, The Mutable and Evolving Concept of ‘Consent’ in International Arbitration-
Comparing rules, laws, treaties, and types of arbitration for a better understanding of the concept of ‘Consent’,
OXFORD UNIVERSITY COMPARATIVE LAW FORUM, (Jan. 15, 2020, 2:05 AM), https://ouclf.iuscomp.org/the-
mutable-and-evolving-concept-of-consent-in-international-arbitration-comparing-rules-laws-treaties-and-types-
of-arbitration-for-a-better-understanding-of-the-concept-of/#a5.
5
  Cl. Ex. C5.
6
  Cl. Ex. C2.
7
  Parts Supply Agreement, clause 11.0
8
  Addendum to the agreement dated 14.01.2015, clause 1.0
    5. The act of both the parties of signing the contract along with the addendum on the same
        date implies their consent to submit to arbitration under the aegis of SIAC. In addition,
        the act of not raising any reservation regarding the addendum on the part of respondent
        exhibits a clear manifestation of an unequivocal consent to submit to arbitration.
    6. Therefore, the CLAIMANT condemns the act of the RESPONDENT of submitting to an
        anti-arbitration injunction issued by its national court to bar the jurisdiction this arbitral
        tribunal. Hence, the RESPONDENT is not justified in contesting the jurisdiction of this
        arbitral tribunal.
        B. THE EFFECTIVE INTERPRETATION OF THE ARBITRATION CLAUSE CLEARLY
             INDICATES TO SUBMIT TO SIAC.
    7. It is humbly submitted that the modern trend in international arbitration law is to apply
        an interpretation that favours arbitration and gives meaning and effect to the clause even
        if the arbitration agreement has a pathological appearance. This very principle in French
        is called ‘effet utile’ (effective interpretation).9 There must be an effective interpretation
        of the arbitration clause to give effect to the terms than to deprive some of them.10 This
        principle stands incorporated in many international instruments like the Romanian Civil
        Code11 and the Trans-Lex principles.12
    8. The Singapore High Court also held in the case of HKL Group Co Ltd v. Rizq
        International Holdings Pte Ltd, that it will ‘give effect to that clause, preferring an
        interpretation, which does so over one, which does not’.13 The Singapore Court of
        Appeal in the landmark case of Insigma Technology Co Ltd v. Alstom Technology Ltd
        explained that if the parties, in an arbitration agreement, have evinced a clear intention
        and the arbitration can thereupon be performed without prejudice to any party then it
        should be performed.14 Moreover, refusing to give effect to the arbitration clause will
        delay the process of arbitration and violates the right of parties to a speedy trial.15
    9. Further, the Lithuanian Supreme Court in the case of UAB Kistela Shareholders v. UAB
        Kistela16 ruled that failure to correctly specify the arbitral institution does not render
9
  SIMON GREENBERG et al., INTERNATIONAL COMMERCIAL ARBITRATION: AN ASIA-PACIFIC PERSPECTIVE 199 (1st
ed. 2011).
10
   UNIDROIT Principles of International Commercial Contracts 2016, Art. 4.5.
11
    Law no. 287/2009 of the Civil Code, published in the Romanian Official Journal no. 409/2011.
12
   Trans-Lex Principle No. XIII. 1.2.
13
   HKL Group Co Ltd v. Rizq International Holdings Pte Ltd, [2013] SGHCR 8.
14
   Insigma Technology Co Ltd v. Alstom Technology Ltd, [2009] SGCA 24.
15
   Paul Comsa, At a crossroads: the case of ‘pathological arbitration clauses’ which determine a jurisdictional
fight, CHALLENGES OF THE KNOWLEDGE SOCIETY PRIVATE LAW 219 (2018).
16
   UAB Kistela shareholders v. UAB Kistela, 3K-3-666/2013.
        the arbitration clause null and void as long as there is a clear intention visible to opt the
        desired institution and rule out others17 and Francis Russel in his book, ‘Russel on
        arbitration’, notes that English Courts would seek to interpret the clause in consonance
        with the intention of parties except in cases of ‘hopeless confusion’.18
     10. In the present case, an effective interpretation of the arbitration clause contained in the
        addendum would direct the tribunal to find that the mention of the terms ‘in accordance
        with the recent rules’19 i.e. The 2016 rules, expressly states that the parties intended to
        refer to a Singaporean Arbitral Institute which updated its rules in 2016 i.e. Singapore
        International Arbitration Centre. This interpretation would clear confusion and specify
        the intention of the parties to opt SIAC and not any other arbitral institute.
        C. THE PRINCIPLE OF SEPARABILITY STANDS UPHELD.
     11. It is humbly submitted that an arbitration clause is to be treated independent of the
        contract and the declaration of a contract null and void by an arbitral tribunal does not
        dissolve the arbitration clause.20 It would defeat the purpose of arbitration if the
        termination of the contract, for whose adjudication an arbitration agreement is entered
        into, were enough to terminate the arbitration agreement.21 Unless otherwise agreed,
        the arbitration clause, which forms or was intended to form part of another agreement,
        will not be rendered invalid, non-existent or ineffective by the termination of that other
        agreement and will be considered as a distinct agreement.
     12. The English apex court in the case of Heyman v. Darwins Ltd,22 explained the concept
        of separability by stating that even though a party claims that the contract has
        terminated but the arbitration clause remains for determination of the mode of
        settlement of the dispute. Several pro-arbitration countries have adopted the same
        approach.23
17
   Denis Parchajev, Pathological Arbitration Clauses in Lithuanian Case Law, CIS ARBITRATION FORUM (Jan.
16, 2020, 8:09 AM), http://www.cisarbitration.com/2016/01/28/pathological-arbitration-clauses-in-lithuanian-
case-law/.
18
   Jae Hee Suh, Interpretation of pathological clauses: a cautionary tale?, THOMSON REUTERS, ( Jan. 16, 2020,
8:19 AM) http://arbitrationblog.practicallaw.com/interpretation-of-pathological-clauses-a-cautionary-tale/.
19
   Addendum to the Agreement, 14 January 2015, Cl. Ex. C2, Clause 1.0, p.14.
20
   UNCITRAL Model Law on International Commercial Arbitration, 1985 without Amendment, Art. 16(1).
21
    NIGEL BLACKBAY, et al., REDFERN & HUNTER: LAW AND PRACTICE OF INTERNATIONAL COMMERCIAL
ARBITRATION 108 (6th ed. 2015).
22
   Heyman v. Darwins Ltd [1942] AC 35
23
   CIETAC Arbitration Rules, 2005 Art. 5(4); Arbitration and Conciliation Act, 1996, Section 16(1) (a); English
Arbitration Act, 1996, Section 7; Code of Civil Procedure (CCP), 1887 (Germany) Section 1040(1).
      13. In the present case, clause 2.0 of the Addendum,24 states, “the addendum to the
         agreement shall stay effective on the date of signing the addendum to the agreement
         and shall be valid for the duration of the agreement”. One can clearly infer from the
         clause that it nowhere expressly bars the validity of the arbitral agreement after the
         termination of the power purchase agreement.
      14. Hence, the CLAIMANT reiterates its claim that the separability of the arbitration clause
         should be upheld.
24
   Cl. Ex. C2.
25
   Arbitration Rules of Singapore International Arbitration Centre SIAC Rules, 2016, Rule 19.
26
   Filip De Ly, The Place of Arbitration in the Conflict of Laws of International Commercial Arbitration: An
Exercise in Arbitration Planning, 12 NW. J. INT’L L. & BUS. 62, (1991).
27
   Simon Greenberg et al., INTERNATIONAL COMMERCIAL ARBITRATION: AN ASIA-PACIFIC PERSPECTIVE 58 (1st
ed. 2011).
28
   FirstLink Investments Corp Ltd v. GT Payment Pte Ltd and others [2014] SGHCR 12.
        the parties chosen substantive governing law. The Singapore Court of Appeal also gave
        a judgement to a similar effect in PT Garuda Indonesia v. Birgen Air. 29
     18. The seat of arbitration in the present case, Baratheon City, Stark Province has adopted
        the UNCITRAL Model Law thereby making it the lex arbitri. The UNCITRAL Model
        Law has a power to decide whether arbitration is barred or not, while any parallel
        insolvency, proceedings are underway in any foreign state.
     19. In the case,30 involving a Syrian and a French party that went bankrupt and pleaded for
        the arbitration proceedings to be set aside, the arbitrators held -‘regardless of French
        law, the arbitral tribunal, sitting in Damascus and applying Syrian law, considers that
        its mission is not to be affected by a Court’s decision rendered subsequently in France
        which is not intended to produce effects in Syria.’31 The present case resonates with
        this case in as much as this
     20. Similarly, in another award rendered by the ICC tribunal in the case (ICC Case 5996,
        unpublished award rendered in 1991)             involving a Cameroon client and French
        defendant wherein the defendant was declared bankrupt, it was held that ‘the arbitral
        tribunal, amiable compositeur, sitting in Tunis in an international arbitration, is not
        bound by a particular (substantive or procedural) national law.’32
     21. It is also submitted that the arbitrators have not, in most of the cases involving parallel
        insolvency, resorted to the territorial effects of insolvency and consistent to the
        dominant trend rejected the request of parties to suspend arbitral proceedings.33
     22. The CLAIMANT thus submits before the honourable tribunal that it should not consider
        the foreign legislations and is requested to apply the lex arbitri i.e. UNCITRAL Model
        Law on International Commercial Arbitration which nowhere bars the continuance of
        arbitration while insolvency proceedings that are ongoing in parallel.
        B. INSOLVENCY PROCEEDINGS, IF ALLOWED, WILL RENDER THE ‘COMPETENCE-
            COMPETENCE’ PRINCIPLE FUTILE.
     23. It is humbly submitted that Article 16 of the UNCITRAL Model Law on International
        Commercial Arbitration states that the arbitral tribunal may rule on its own jurisdiction,
        including any objections with respect to the existence or validity of the arbitration
29
   PT Garuda Indonesia v. Birgen Air [2002] 1SLR 393.
30
   Fernando Mantilla-Serrano, International Arbitration and Insolvency Proceedings, 11 ARBITR. INT. 51, 58
(1995).
31
   See Ibid.
32
   Fernando Mantilla-Serrano, International Arbitration and Insolvency Proceedings, 11 ARBITR. INT. 51, 58
(1995).
33
   See Ibid at 57-58
        agreement. Jurists have also defined the principle of competence-competence as the one
        which allows arbitrators’ themselves to decide on their own jurisdiction
        notwithstanding that their jurisdiction is challenged.34
     24. The doctrine of ‘competence-competence’ is a fundamental pillar and it is hard to
        imagine international arbitration being developed in the absence of this doctrine.35 This
        principle has been justified on two grounds: first, there is a rebuttable presumption that
        such jurisdictional power has been conferred by the will of the parties when they
        entered into an arbitration agreement, and second, the competence-competence power
        is innate in all judicial bodies and integral to let them function.36
     25. The Supreme Court of India in the case of Konkan Railway Corporation Ltd. & Anr. v.
        Rani Construction Pvt. Ltd 37 ruled that the courts cannot interfere in the matters of an
        arbitral tribunal and article 16 of the Arbitration and Conciliation Act, 1996, adapted
        from Article 16 of UNITRAL Model Law on International Commercial Arbitration,
        gave the arbitral tribunals the competence to rule on its jurisdiction. Similarly, in the
        case of Kvaerner Cementation India Ltd. v. Bajranglal Agarwal,38 the Bombay High
        Court set aside the order passed by a civil court declining the jurisdiction of the arbitral
        tribunal.
     26. Thus, the application of a moratorium, backed by the non-obstante provision of Section
        238,39 gives an over-riding effect to the moratorium over any other law inconsistent
        with it, including arbitration. This over-riding effect thereby interferes with the
        jurisdiction of the arbitral tribunal, obstructs the power of arbitrators to rule on their
        own jurisdiction, and renders the principle of ‘competence-competence’ void.
     27. The CLAIMANT thereby submits before the honourable tribunal that, international
        arbitration is an entirely autonomous process, functions independent of any national
        law, and has a life of its own 40 and any anti-arbitration injunction issued by a national
34
   Jurgita Petkutė-Gurienė, The Competence-Competence Principle In Commercial Arbitration: A Comparative
Analysis, SITICS, 91 (2017).
35
   Luciano Timm & Isabela Popolizio Morales, Competence-Competence Doctrine: An Absolute Principle?,
INTERNATIONAL              LAW           OFFICE           (Jan.        16,2020,            8:15         PM)
https://www.internationallawoffice.com/Newsletters/Arbitration-ADR/Brazil/Carvalho-Machado-e-Timm-
Advogados/Competence-competence-doctrine-an-absolute-principle.
36
   Janet A. Rosen, Arbitration Under Private International Law: The Doctrines of Separability and Competence
De La Competence, 17 FORDHAM. INT’L. L.J. 599,608 (1993).
37
   Konkan Railway Corporation Ltd. & Anr. v. Rani Construction Pvt. Ltd 2005 (8) SCC 618.
38
   Kvaerner Cementation India Ltd. v. Bajranglal Agarwal (2012) 5 SCC 214.
39
   The Insolvency and Bankruptcy Code, 2016, Section 238.
40
   Julian D M Lew, Does National Court Involvement Undermine the International Arbitration Processes?, 24
AUILR 488 (2009).
        court renders the ‘competence-competence’ principle futile and undermines the spirit
        of arbitration.
     28. Therefore, the CLAIMANT condemns the act of the respondent of submitting to an anti-
        arbitration injunction issued by its national court to bar the jurisdiction this arbitral
        tribunal. Hence, the RESPONDENT is not justified in contesting the jurisdiction of this
        arbitral tribunal.
        C. YEVADU INSOLVENCY LAW DOES NOT BAR ARBITRAL PROCEEDINGS.
     29. The claimant contends that section 14 of IBC when read with the non-obstante
        provision contained in section 23841 gives an over-riding effect to the Insolvency and
        bankruptcy code over anything inconsistent therewith contained in any other law.
        Thereby the moratorium also gains an over-riding to anything inconsistent with the law.
        However, it is brought to the notice of the tribunal that section 14 of the code, which
        imposes moratorium on the corporate debtor, does not bar arbitration proceedings.
     30. Section 14 (1) (a)42 of the Insolvency and Bankruptcy Code, 2016 declares and imposes
        a moratorium on the corporate and thereby bars the institution or pendency of any
        pending suit or proceeding. The word ‘proceedings’ or ‘pending suits’ in section
        14(1)(a) does not include arbitral proceedings as the IBC in section 5(6) expressly states
        that “dispute” includes a suit or arbitration proceeding and thereby makes a clear
        distinction between a suit and an arbitration.
     31. Further, in section 8(2) (a) of the code, again a differentiation is made between a suit
        and an arbitration proceeding. Thereafter, again in the section 25(2)(b) ‘arbitration
        proceedings’ find a separate mention beside ‘judicial’ and ‘quasi-judicial’ proceedings.
     32. Thus, it can be construed that whenever a reference is made to arbitration, the word
        ‘arbitration proceedings’ is specifically used. Therefore, had arbitration proceedings
        been barred under section 14 of the code , the word ‘arbitration proceedings’ would
        have been used but contrarily these words find no mention and hence imply that
        arbitration proceedings are excluded from the ambit of moratorium.
     33. The claimant further contend that the prior-cited arguments are backed by the judgment
        of Delhi High Court in the case of Power Grid Corporation of India Ltd. v. Jyoti
        Structures Ltd,43 in which the court held that the word ‘proceedings’ in section 14(1)
        (a) is not preceded by the word ‘all’, implying that not all proceedings are barred against
41
   The Insolvency and Bankruptcy Code, 2016, Section 238.
42
   The Insolvency and Bankruptcy Code, 2016. Section 14(1) (a).
43
   Power Grid Corporation of India Ltd. v. Jyoti Structures Ltd, O.M.P (COMM) 397/2016.
        the corporate debtor. Subsequently, the National Company Law Appellate Tribunal of
        Hyderabad, India in the case of Jharkhand Bijli Vitran Nigam Limited v. IVRCL Ltd.44
        allowed continuance of arbitral proceedings while insolvency proceedings were
        underway and affirmed that ‘the claims of a corporate debtor can only be determined
        after the counter-claims are filed.’
     34. The claimant thus contends that there is a clear distinction made between ‘proceedings’
        and ‘arbitration proceedings’ in the code and thus the institution of or continuance of
        the arbitration proceedings, as opposed to the respondent’s contention, are not barred
        under section 14 of the code.
     35. In addition, the CLAIMANT requests the tribunal to set aside the counter-claims filed by
        the RESPONDENT and exercise its own jurisdiction in adjudicating the issue.
        D. THE ACT OF THE RESPONDENT BY NOT CONFORMING TO BE BEING BOUND BY
            ARBITRATION VIOLATES THE PRINCIPLE OF GOOD FAITH.
     36. It is humbly submitted that the principle of good faith imposes a positive obligation on
        both parties to co-operate and maintain transparency in dealings. It places an obligation
        on parties to a contract to act with fairness, reasonableness, and decency in the
        formation and performance of the contract.45 The New York Court of Appeals while
        explaining the concept of good faith ruled that there is an implied covenant that neither
        party shall do anything, which will have the effect of destroying or injuring the right of
        the other party, to receive the fruits of the contract.
     37. In other words, every contract has an implied covenant of good faith and fair dealing.46
        Further, numerous international treaties and conventions talk of the necessity principle
        of ‘good faith’. Reference can be made here to Art. 26 of VCLT, 47 which talks about
        the principle of Pacta Sunt Servanda, which creates an obligation on the parties of the
        treaty to carry out its provisions in good faith. Hence it is an established principle of
        international law as well, that agreements need to be carried out in good faith.
     38. In the present case, the act of the RESPONDENT of not being bound to arbitration
        proceedings impinges upon the right of the CLAIMANT to continue the proceeding and
        to enforce the Award.
44
   Jharkhand Bijli Vitran Nigam Limited v IVRCL Ltd., [Company Appeal (AT) (Insolvency) No. 285 of 2018].
45
   Brendan J. Reilly, Procedural Good Faith In International Arbitration, SQUIRE PATTON BOGGS (January 16,
2020, 7:26 PM), https://www.lexology.com/library/detail.aspx?g=76181d62-5604-4c82-a0e5-f13411e56678.
46
    Kirke La Shelle Company v. The Paul Armstrong Company et al., 263 N.Y. 79.
47
   Vienna Convention on Law of Treaties, Art. 26, May 23, 1969, 1155 U.N.T.S. 331.
     39. Hence, the CLAIMANT requests the Tribunal to Proceed with the Arbitration and wants
        the RESPONDENT to affirm to its obligation of maintaining Good Faith in international
        trade Under Art 7 of CISG.
48
   Resp. Ex. R3.
49
   See Ibid.
50
   Konstantin Pilkov, Evidence in International Arbitration: Criteria for Admission and Evaluation, 80 INT’L. J.
ARB.147-155 (2014).
51
   Aceris Law LLC, The Admissibility of Evidence In International Arbitration, ACERIS LAW LLC (Dec.30, 2019,
7:30 PM) https://www.acerislaw.com/admissibility-evidence-international-arbitration/.
52
   Arbitration Rules of Singapore International Arbitration Centre Rules. 6 th ed. 2016, Rule 19.2.
     43. It is further submitted, that, the materiality of any evidence in international arbitration
        is connected with its sufficiency of the evidence. The reliability of the evidence
        becomes doubtful when it is not sufficient to prove what it is offered to prove.53 In this
        situation, the Tribunal may ask the parties concerned to present additional evidence to
        support its claim. At the admissibility stage the evidence is required to be prima facie
        credible, that is, it must have sufficient indicia of reliability and authenticity to establish
        that it appears to show what it is offered to prove.54 Moreover, when a party submits
        evidence the opposing party should be provided with an opportunity to comment on the
        relevance, materiality, admissibility or probative value of that evidence. 55
     44. It is further humbly submitted that the disclosure of third party funding frivolously
        challenges the arbitrators and is unfounded requests for security for costs especially
        when it is based on some non-credible sources. It is perceived to be procedural and
        strategic consequences of disclosure by many funders. These funders also suggest that
        the response to disclosure may not simply be a matter of case strategy, but an intentional
        effort to drive up the cost of the case.56
     45. The CLAIMANT contends that the Evidence Exhibit R3 is not credible and is not enough
        to be considered by the Tribunal for evaluating the issue. The information provided in
        the newspaper report is based on some unconfirmed reports. Moreover, any official
        statement of CLAIMANT’S law firm does not support the very evidence of the existence
        of the third party to the CLAIMANT. The RESPONDENT, in this case, is trying to draw
        Tribunal’s attention to a baseless claim of the existence of any third party to this
        arbitration proceeding. Therefore, this evidence is unsuitable to proof the
        RESPONDENT’S contention and hence, does not have probative value in the present case.
        B. THE CLAIMANT IS NOT BOUND TO DISCLOSE THE THIRD PARTY FUNDING UNDER
             ANY LAW.
     46. It is most humbly submitted before this Tribunal, that, the CLAIMANT is not bound to
        disclose the Third Party Funding under any law applicable. It is contended by the
        CLAIMANT that the CLAIMANT did not opt for third party funding in this arbitral
53
   Konstantin Pilkov, Evidence in International Arbitration: Criteria for Admission and Evaluation, 80 INT’L. J.
ARB.147-155 (2014), p.6.
54
   Konstantin Pilkov, Evidence in International Arbitration: Criteria for Admission and Evaluation, 80 INT’L. J.
ARB.147-155 (2014), p.7.
55
   Konstantin Pilkov, Evidence in International Arbitration: Criteria for Admission and Evaluation, 80 INT’L. J.
ARB.147-155 (2014), p.9.
56
   The Report of the ICCA-Queen Mary Task Force On Third-Party Funding In International Arbitration, 86 (31
Oct.                                       2017),                                       https://www.arbitration-
icca.org/media/10/40280243154551/icca_reports_4_tpf_final_for_print_5_april.pdf.
        proceedings. The RESPONDENT’S request for disclosure of third party funding based on
        some non-credible source is frivolous. The RESPONDENT’S contention of conflict of
        interest of the arbitrator and any third party is unknown, and could not challenge the
        arbitrator in a sense to order for the disclosure of third party funding.
     47. It is humbly submitted that the RESPONDENT claims, the existence of the third party is
        against the arbitrator’s conduct in terms of conflict of interest. Contrary to the
        RESPONDENT’S contention, the CLAIMANT submits that unknown conflicts of interest
        cannot be a basis for an effective challenge to an arbitrator or an Arbitral Award. Some
        of the US Courts have found that unknown conflicts cannot be a basis for refusing
        enforcement of arbitral awards. US Courts while, considering the issue of conflict of
        interest stated that absence of knowledge about a conflict, discourages arbitrators from
        fulfilling their duty to investigate. It also imposes on the aggrieved party the
        unreasonable burden of having to prove actual knowledge about a conflict on the part
        of an arbitrator.57 There are no standard rules and regulations set up in International
        Arbitration, which specifically says that disclosure of third party funding is mandatory.
     48. In the case of Guaracachi America, Inc. and Rurelec PLC v. The Plurinational State of
        Bolivia,58 the PCA confirmed it that, there was no conflict of interest whatsoever
        between the parties based on the given documents and the Tribunal requires no further
        documents.       The     Tribunal      in Ioannis     Kardassopoulos         &     Ron     Fuchs     v.
        Georgia,59 declared that the third-party funding arrangement was irrelevant to
        determining the amount of recovery of CLAIMANT’S costs. The two annulment
        committees in the two ICSID cases, RSM v. Grenada,60 and ATA v. Jordan,61 applied
        the same reasoning.
     49. In the present case, the CLAIMANT was alleged to be funded by the Third Party, the
        RESPONDENT received the information of which by some unconfirmed news report.62
        There is no existence of any third party funding to the CLAIMANT in this Arbitration
57
    In the United States, the approach of U.S. courts is summarized in the Reporters’ Notes to the Restatement:
“Some courts have taken the view that an absence of knowledge about a conflict per se precludes a finding of
evident partiality. See Gianelli Money Purchase Plan & Trust v. ADM Inv. Servs., Inc., 146 F.3d 1309, 1313 (11th
Cir. 1998);
58
   Guaracachi America, Inc. and Rurelec PLC v. The Plurinational State of Bolivia ,UNCITRAL, PCA Case No.
2011-17, Award of January 31, 2014, at 22, ¶ 66.
59
    Ioannis Kardassopoulos & Ron Fuchs v. Georgia, ICSID Case No. ARB/05/18 and ARB/07/15, Award of
March 3, 2010, at 215, ¶691.
60
   RSM v. Grenada, ICSID Case No. ARB/05/14, Award of March 13, 2009.
61
   ATA v. Jordan, ICSID Case No. ARB/08/2, Award of May 18, 2010.
62
   See Resp. Ex. R3.
63
    The Report of the ICCA-Queen Mary Task Force On Third-Party Funding In International Arbitration, at 146,
https://www.arbitration-icca.org/media/10/40280243154551/icca_reports_4_tpf_final_for_print_5_april.pdf.;
Chris Parker, A Global Perspective On Availability Of Security For Costs And Claim In International Arbitration
Mirage        Or       Oasis?,    HERBERT        SMITH       FREEHILLS        (Jan.20,2020,     07:30       AM)
https://www.herbertsmithfreehills.com/latest-thinking/a-global-perspective-on-availability-of-security-for-costs-
and-claim-in.
64
    The United Nations Convention on Contracts for the International Sale of Goods, 1980, Art. 25.
65
   INGEBORG SCHLECHTRIEM AND PETER SCHWENZER, COMMENTARY ON THE UN CONVENTION ON THE
INTERNATIONAL SALE OF GOODS 431 (Ingeborg Schwenzer ed., 4th ed., 2016).
66
   CLOUT case No. 846 [U.S. Court of Appeals (3rd Circuit), United States, 19 July 2007] (a two-day delay that
did not impede the use of the delivery regarded as a non-fundamental breach); CLOUT case No. 275
[Oberlandesgericht Düsseldorf, Germany, 24 April 1997]; CLOUT case No. 681 [China International Economic
and Trade Arbitration Commission, People’s Republic of China, 18 August 1997]; Landgericht Oldenburg, 27
March 1996, 12 O 2541/95. See University of Freiburg Database, http://www.cisg-online.ch/cisg/urteile/188.htm;
Amtsgericht Ludwigsburg, 21 December 1990, 4 C 549/90; See University of Freiburg Database,
http://www.cisg-online.ch/cisg/urteile/134.htm (affirmed by Landgericht Stuttgart, 30 August 1991, 16 S 14/91.
67
   CLOUT case No. 275 [Oberlandesgericht Düsseldorf, Germany, 24 April 1997]; also Brandenburgisches
Oberlandesgericht, Germany, 18 November 2008 Internationales Handelsrecht 2009, 105.
         constitutes a fundamental breach of contract unless the seller has justifying reasons to
         withhold its performance.68
     52. In the present case, the CLAIMANT’S delayed delivery of the 3rd Quarterly instalment
         was accepted by the RESPONDENT, which shows that the time of delivery was not of
         significant importance to the RESPONDENT. Thus, failure on the part of the CLAIMANT
         does not substantially deprive the buyer. Also, the imposition of tariffs and declaring
         of the trade war by the Government of the CLAIMANT’S country to another country
         where from the raw material for the CLAIMANT is a justifying reason to withhold its
         performance. Therefore, the CLAIMANT did not fundamentally breach the agreement.
         Hence, the RESPONDENT’S conduct to terminate the agreement based on fundamental
         breach of agreement is invalid and the claim of the CLAIMANT is genuine.
     53. It is further humbly submitted that owing to the high-risk involved with respect to non-
         fulfilment of the Award and the Cost, the evidence required by requesting party for an
         order of security cost should be firm enough to justify the application. Evidence may
         involve CLAIMANT’S financial records.69
     54. The RESPONDENT has no evidence of the CLAIMANT’S financial condition besides an
         allegation of the Third Party Funding. According to SIAC rules on Arbitrator Conduct
         in cases involving external funding, “the involvement of an external Funder alone shall
         not be taken as an indication of the financial status of a Disputant Party. The Tribunal
         may take into account factors other than the involvement of an external funder in order
         for security for legal or other costs”.70
     55. In the present case, CLAIMANT is a successful business. The CLAIMANT successfully
         completed its entire obligation in the first three years of the agreement. In the 4th year,
         the CLAIMANT, even after price surge, after 2nd quarterly instalment delivered, was able
         to manage its production due to the availability of sufficient funds. For the 3rd quarter,
         the CLAIMANT supplied the parts within a week of the scheduled delivery even after
         multiple emphases put forth by the CLAIMANT with respect to its lack of viability to
68
   CLOUT case No. 846 [U.S. Court of Appeals (3rd Circuit), United States, 19 July 2007] (a two-day delay that
did not impede the use of the delivery regarded as a non-fundamental breach).
69
   Chris Parker, A Global Perspective On Availability Of Security For Costs And Claim In International
Arbitration Mirage Or Oasis?, HERBERT SMITH FREEHILLS (Jan.20,2020,                               07:30 AM)
https://www.herbertsmithfreehills.com/latest-thinking/a-global-perspective-on-availability-of-security-for-costs-
and-claim-in.
70
   Singapore International Arbitration Centre Practice Note, PN – 01/17 (31 March 2017), Administered Cases
under the arbitration rules of the Singapore International Arbitration Centre, On Arbitrator Conduct in Cases
Involving External Funding (Jan. 10, 2020, 12:45 PM), https://www.international-arbitration-attorney.com/wp-
content/uploads/2018/11/Practice-Note-on-Arbitrator-Conduct-in-Cases-Involving-External-Funding.pdf.
        perform the contract and incurring losses. The given circumstances clearly indicate that
        the CLAIMANT has sufficient assets to continue with this arbitration proceeding and that
        CLAIMANT’S financial situation is not bad.
     56. Thus, the CLAIMANT has a meritorious claim and the RESPONDENT does not have
        sufficient evidence to prove the poor financial status of the CLAIMANT other than an
        alleged third party funding. Therefore, there is no need for the Tribunal to order security
        costs in this arbitration proceeding. Hence, the RESPONDENT’S request to order security
        costs is futile and may be dismissed.
71
   Arbitration Rules of Singapore International Arbitration Centre Rules. 6 th ed. 2016, Rule 7.1(a) and 7.1(b).
72
   N. Voser, Multi-Party Disputes and Joinder of Third Parties, in 50 Years of the New York Convention: ICCA
International Arbitration Conference, 14 ICCA CONGRESS SERIES, 343, 358 (2009).
73
   Karyna Loban, Extension of the Arbitration Agreement to the Third Parties, C.E.U., 19 (2009).
        dominion and control’ over the decisions over the signatory party. 74 Thus, if the
        signatory party is an alter ego of the non-signatory, the non-signatory may come under
        the arbitration clause and further be joined in the arbitration proceedings.75
     61. In the present case, it is clear that RESPONDENT is acting as the alter ego of the Ministry
        of Power as it has a close relationship i.e. being wholly owned by the Government of
        Yevadu to which Ministry of Power is a part and thus, controls it. Further, it exercises
        its control through making the company seek permission for business matters over
        which company should have full autonomy e.g. requirement to seek permission to
        change the contract76 and terminating the contract on the instruction of the Ministry of
        Power.77 In addition, the RESPONDENT terminated the contract on undue justifications,
        which are not valid for terminating a contract thus committing a wrong against the
        Claimant.
     62. Thus it is humbly submitted that the corporate veil should be lifted and the Ministry of
        Power who is the real power behind the RESPONDENT’S company should be joined to
        the arbitral proceeding as RESPONDENT’s company is nothing but an alter ego of
        Ministry of Power through which it operates.
        B. THE RESPONDENT AND MINISTRY OF POWER FORM A SINGLE ECONOMIC ENTITY.
     63. When a company exercises deep and pervasive control on the functioning of other, they
        are said to be part of a single economic entity.78 It is an established affair that a company
        and its subsidy are separate legal entities but if the subsidy has no autonomy and has to
        consult the parent body for taking every decision then they are claimed to be part of a
        single economic entity.79
     64. Brekoulakis particularly suggests, “What matters is not whether a non-signatory can
        demonstrate consent for arbitration, but whether it is inextricably implicated in a dispute
        which is the subject matter of the arbitration.”80 In the present case, the Ministry of
        Power is inextricably implicated in the dispute regarding the contract as the Respondent
        and Ministry form a Single Economic Entity. The American case of Copperweld Corp.
        v. Independence Tube Corp,81 held that a parent corporation and a subsidiary wholly
74
   Thomson-CSF, S.A. v. American Arbitration Association 64 F.3d 773 (2 nd Cir 1995) (U.S.A.).
75
   Bridas S.A.P.I.C. v. Government of Turkmenistan, 447 F.3d 411 (5 thCir 2006) (U.S.A.).
76
   Cl. Ex. C4.
77
   Cl. Ex. C18.
78
   Dow Chemical Co. v. United States, 476 U.S. 227 (1986).
79
   Mahwesh Buland, A Study of Single Economic Entity Doctrine in Context of India, 2 IJLMH (2018).
80
   Benson Lim & Andriana Uson, Relooking At Consent In Arbitration, KLUWER ARBITRATION BLOG, (Jan.
23,2020, 1:08 PM) http://arbitrationblog.kluwerarbitration.com/2019/02/12/relooking-at-consent-in-arbitration/.
81
   Copperweld Corp. v. Independence Tube Corp, 467 U.S. 752 (1984).
        owned by it would constitute a single entity. Therefore, any subsidiary, which have
        been administered by its parent corporation in decision-making and has no complete
        autonomy, said to be a part of the parent, and together they would comprise of a single
        entity.
     65. The RESPONDENT has often mentioned consulting the Ministry before executing any
        administrative function. Instances such as taking assistance of the Ministry of Power
        before issuing of a purchase order,82 mentioning of the ministry as its higher managerial
        body83 and the argument put forth by RESPONDENT that consulting the Ministry of
        Power was a procedural requirement84 elucidate that RESPONDENT lacks autonomy and
        it functions under the aegis and governance of Ministry of Power, Government of
        Yevadu and hence, these two form a single economic entity. Therefore, Ministry of
        Power may be joined, as RESPONDENT has no clear autonomy over itself without the
        authority of Ministry.
        C. THE RESPONDENT IS THE AGENT OF THE MINISTRY OF POWER AND THUS SHOULD
             BE JOINED AS IT IS THE PRINCIPAL.
     66. An agency is “fiduciary relationship created by express or implied contract or by law,
        in which one party (the agent)” that is subject to principal’s control “may act on behalf
        of another party (the principal) and bind that other party by words or actions”.85 In the
        case of Interocean Shipping Co. v. National Shipping and Trading Corp. and Hellenic
        International Shipping the court asserted that “agency is a legal concept which depends
        on the manifest conduct of the parties, not on their intentions or beliefs” and thus
        decided that the acts of the agent bound his agent in the contract.86
     67. Further, the Swiss Federal Supreme Court in China National Machinery & Equipment
        Import & Export Corporation v. Loebersdorfer Maschinenfabrik AG (Austria) decided
        that both principal and agent are bound to arbitrate when they are “one indistinguishable
        entity…mutually connected, with a uniform purpose and a mere geographical
        separation of tasks”.87
82
   Parts Supply Agreement, Clause 3.0 (2), Cl. Ex. C1.
83
   Cl. Ex. C4.
84
   Opposition to Request for Joinder of Parties, at 39.
85
   Black’s Law Dictionary, 7th ed.(1999), “Agency”.
86
   Interocean Shipping Co. v. National Shipping and Trading Corp. and Hellenic International Shipping, S.A, 523
F.2d 527, (2nd Cir 1975).
87
   China National Machinery & Equipment Import & Export Corporation v. Loebersdorfer Maschinenfabrik AG
(Austria), (1996) 4 ASA Bull 623, 629.
     68. In the present case, the RESPONDENT is clearly in a fiduciary relationship with the
        Ministry of Power, as the RESPONDENT has to take permissions from the Ministry and
        act on the instructions of the Ministry of Power. Hence, the RESPONDENT acts on behalf
        of the Ministry as it produces power from its thermal power plant for parts of Yevadu
        and acts an agent of Government and Ministry of Power to produce and supply the
        power.
     69. Since RESPONDENT acts as an agent and is mutually connected as it is a company wholly
        owned by the government and both the Ministry and RESPONDENT have the same
        purpose of producing and supplying Power in Yevadu they should be joined in the
        arbitral proceeding.
 V.     THE CLAIMANT’S CONDUCT DID NOT BREACH THE AGREEMENT AND THE
        RESPONDENT WAS NOT JUSTIFIED IN TERMINATING THE AGREEMENT.
     70. As per the terms of the Agreement88, the CLAIMANT was supposed to supply parts based
        on the requisition list and purchase order. However, due to the intensified trade war
        between the countries of Xanier and Zorastra, the country supplying raw materials to
        the CLAIMANT, the working capital and cost of manufacturing of the CLAIMANT
        increased to a considerable amount. Due to this, the CLAIMANT was incurring huge
        losses and was unable to supply parts on earlier negotiated prices. This delayed the
        manufacturing process and prevented the CLAIMANT from performing its obligations to
        its full extent.
     71. The CLAIMANT asserts that, Firstly, [A] the CLAIMANT’S failure to supply the parts on
        time is not the fundamental breach of the contract; secondly, [B] the CLAIMANT’S failure
        to perform as per the terms of the Agreement is exempted from liability under Art. 79;
        thirdly, [C] the RESPONDENT was not justified in terminating the Agreement under Art.
        49 of CISG.
        A. THE CLAIMANT’S FAILURE TO SUPPLY THE PARTS ON TIME IS NOT THE
            FUNDAMENTAL BREACH OF THE CONTRACT.
     72. It is humbly submitted that for fundamental breach of Contract under Art. 2589 , there
        are two limbs tests for that.90 First, it ought to have caused substantial deprivation to
88
   Part Supply Agreement, Clause 3.0.
89
   The United Nations Convention on Contracts for the International Sale of Goods, 1980, Art. 25.
90
   JOHN O. HONNOLD & HARRY M. FLECHTNER (ED.), UNIFORM LAW FOR INTERNATIONAL SALES UNDER THE 1980
UNITED NATIONS CONVENTION, 276 (4th ed, 2009); Andrew Babiak, ‘Defining “Fundamental Breach” Under
        the other party of what it is entitled to expect out of the contract91 and second, this
        deprivation caused to the party ought to have been reasonably foreseeable by a
        reasonable person of the same kind in the same circumstances.92 Both of these
        conditions have to be fulfilled for the contract to be fundamentally breached. It shows
        that the aggrieved party is willing to perform its part of contractual obligation.
    73. The aggrieved party must have suffered such detriment as to substantially deprive it of
        what it was entitled to expect under the contract. The breach must, therefore, nullify or
        essentially depreciate the aggrieved party’s justified contract expectations. Art. 25
        provides further that a breach is fundamental only if the substantial deprivation of
        expectations caused by the breach was reasonably foreseeable to the breaching party.
        However, the provision does not mention the time at which the consequences of the
        breach must have been foreseeable. It has been expressly stated that the time of the
        conclusion of a contract is the relevant time.93
    74. The Court denied fundamental breach in a dispute between a German buyer and an
        Italian seller, where the seller had dispatched summer clothes one day later than the
        stipulated time.94 The Ludwigsberg Court concluded from the fact that the buyer took
        delivery of the goods instead of rejecting them that time was not of the essence of the
        contract. The Ludwigsburg Petty District Court held that the inconvenience caused by
        the delay was only of minor importance to the German buyer and thus did not amount
        to a fundamental breach.95
    75. The Dusseldorf Court of Appeals rejected the buyer’s arguments and held that mere
        non- or late delivery does not constitute a fundamental breach under Art. 25 provided
        that delivery is objectively possible and the seller was willing to deliver.96 Although the
the United Nations Convention on Contracts for the International Sale of Goods’ 6 Temple Int’l & Comp. L. J.,
113, 118 (1992).
91
   INGEBORG SCHLECHTRIEM AND PETER SCHWENZER, COMMENTARY ON THE UN CONVENTION ON THE
INTERNATIONAL SALE OF GOODS 431 (Ingeborg Schwenzer ed., 4th ed., 2016).
92
   Ibid.; Alysha Salinger, The United Nations Convention On Contracts For The International Sale Of Goods
(CISG): What Is The Relevant Time Of Foreseeability In Article 25?, PACE LAW SCHOOL INSTITUTE OF
INTERNATIONAL            COMMERCIAL          LAW,          (Jan.       15,      2020,        4:15       PM)
https://www.cisg.law.pace.edu/cisg/biblio/salinger.pdf.
93
    CLOUT case No. 275 [Oberlandesgericht Düsseldorf, Germany, 24 April 1997]; CLOUT case No. 681 [China
International Economic and Trade Arbitration Commission, People’s Republic of China, 18 August 1997].
94
    Landgericht Oldenburg, 27 March 1996, 12 O 2541/95. See University of Freiburg Database, http://www.cisg-
online.ch/cisg/urteile/188.htm; See Robert Koch, ‘The Concept of Fundamental Breach of Contract under the
United Nations Convention on Contracts for the International Sale of Goods (CISG)’, in: Review of the
Convention on Contracts for the International Sale of Goods (CISG) 1998 (1999) 177, 236.
95
     Amtsgericht Ludwigsburg, 21 December 1990, 4 C 549/90; See University of Freiburg Database,
http://www.cisg-online.ch/cisg/urteile/134.htm; See Ibid. Koch at 237.
96
     Oberlandesgericht Dusseldorf, 18 November 1993, 6 U 228/92, See University of Freiburg Database,
http://www.cisg-online.ch/cisg/urteile/92.htm.
        date for delivery may be fixed by agreement, a short delay may nonetheless not
        constitute a fundamental breach if the buyer’s interests are not impaired.97
     76. In the present case, the RESPONDENT duly accepted the delayed delivery of goods by
        the CLAIMANT for the 3rd Quarterly Instalment in the year 2018.98 Therefore, it is
        evident that adherence to the delivery date was not of significant importance for the
        RESPONDENT. If only a minor part of the contract is finally not performed i.e. one
        delivery out of several deliveries is not made, then the failure to perform is simply not
        a fundamental breach of contract.99
     77. Moreover, the detriment, if any, caused to the RESPONDENT could not be reasonably
        foreseeable by the CLAIMANT. The CLAIMANT could not foresee the trade war between
        its country and Zorastra at the time of the conclusion of the contract, which would
        become a predicament to complete its obligation on time. Since both of the above-
        mentioned conditions have not been fulfilled in the present case, the CLAIMANT did not
        commit any fundamental breach of the contract.
     78. Complete failure to perform a contractual duty constitutes a Fundamental Breach unless
        the party has justifying reason to withhold its performance. It is also decided in cases
        of final Non-delivery.100 The CLAIMANT was supposed to perform its obligation in such
        a way that it achieves 85% plant availability. As of August 2018, the CLAIMANT was
        successful in maintaining the plant availability averaging to about 93% until the Second
        Quarter of the Year 2018. As contended by the RESPONDENT, it was not a complete
        failure on the part of CLAIMANT to perform its obligation.
     79. It is further humbly submitted that change in the country’s tariff policies and price hike
        for the raw materials is the justifying reason to withhold the performance by the
        CLAIMANT. The CLAIMANT was willing and ready to complete its part of the contract
        and tried to communicate to RESPONDENT to re-negotiate the contractual prices. But,
        besides continuous efforts of the CLAIMANT to have a meeting with the senior
        management of the RESPONDENT, based on emails dated August 20,2018, September
        27, 2018, October 17, 2018, and November 11, 2018,101 all the channels of
97
   CLOUT case No. 846 [U.S. Court of Appeals (3rd Circuit), United States, 19 July 2007] (a two-day delay that
did not impede the use of the delivery regarded as a non-fundamental breach).
98
   Cl. Ex. C.13 at 25; Notice of Arbitration, at 7, ¶ 14.
99
    CLOUT case No. 275 [Oberlandesgericht Düsseldorf, Germany, 24 April 1997]; also Branden burgisches
Oberlandesgericht, Germany, 18 November 2008 Internationales Handelsrecht 2009, 105.
100
    CLOUT case No. 90 [Pretura circondariale di Parma, Italy, 24 November 1989] (only partial and very late
delivery); CLOUT case No. 136 [Oberlandesgericht Celle, Germany, 24 May 1995].
101
    Cl. Ex. C11, C14, C15, C16.
         communications were stopped from the side of RESPONDENT. Therefore, with respect
         to all the above-mentioned submissions, the CLAIMANT denies any fundamental breach
         of contract from its part.
         B. THE CLAIMANT’S FAILURE TO PERFORM AS PER THE TERMS OF THE AGREEMENT
             IS EXEMPTED FROM LIABILITY UNDER ARTICLE 79(1) OF CISG.
      80. It is humbly submitted before the tribunal that CLAIMANT’S failure to perform the part
         of its obligation as per the agreement is exempted from liability under Art. 79 of
         CISG.102 For Art. 79(1) to be applicable, there are certain requirements that are to be
         fulfilled: the party’s non-performance was ‘due to an impediment’; the impediment was
         ‘beyond his control’; the impediment is one that the party ‘could not reasonably be
         expected to have taken into account at the time of the conclusion of the contract’.103
      81. The Belgian Court of Cassation has indicated that the “impediment” referred to in Art.
         79 (1) CISG may include changed circumstances that have made a party’s performance
         a matter of economic hardship, even if performance has not been rendered literally
         impossible. The Court emphasized that, in order to qualify as an “impediment,” the
         change of circumstances ought not to have been reasonably foreseeable at the time of
         the conclusion of the contract and performing the contract must involve an
         extraordinary and disproportionate burden under the circumstances.104 This
         impediment can be an exceptional event such as economic impossibility.105
      82. In the present case, the tariffs imposed by the CLAIMANT’S country on the source
         country of raw materials are an impediment beyond its control. The tariffs imposed on
         the raw materials are as high as 60%. Materials like Cobalt, Nickel & Lithium were
         procured from this country, which were used as raw materials for the parts and
         equipment CLAIMANT supplies. This impediment of change in government import-
         export policies is impediments beyond CLAIMANT’S control. Given this situation, the
         manufacturing cost of the CLAIMANT increased tremendously. Due to this, an
         extraordinary & disproportionate burden was imposed on the CLAIMANT, and thus the
         contract became unviable for the CLAIMANT to perform.
102
    The United Nations Convention on Contracts for the International Sale of Goods, 1980, Art. 79.
103
    INGEBORG SCHLECHTRIEM AND PETER SCHWENZER, COMMENTARY ON THE UN CONVENTION ON THE
INTERNATIONAL SALE OF GOODS 431 (Ingeborg Schwenzer ed., 4th ed., 2016).
104
     Hof van Cassatie, Belgium, 19 June 2009 (Scafom International BV v. Lorraine Tubes S.A.S.),
www.cisg.law.pace.edu. The court also held that, under general principles applicable pursuant to article 7 (2)
CISG, the legal consequences of economic hardship included an obligation by the parties to renegotiate the
contract.
105
    CLOUT case No. 166 [Schiedsgericht der Handelskammer Hamburg, Germany, 21 March, 21 June 1996].
      83. Where the governmental regulations and any action by government officials prevent
         the party’s performance, it would amount to an impediment beyond the party’s
         control.106 It is further submitted that the aforementioned change was unforeseeable at
         the time of concluding the Contract and the CLAIMANT’s obligation was affected due to
         change in the government’s policy of tariffs. The CLAIMANT could not have reasonably
         foreseen the impact of the imposition of tariffs on another country and declaration of a
         trade war at the time of concluding the contract.
      84. The Belgian Court of Cassation, applying general principles pursuant to Art. 7 (2)
         CISG, has held that “under these principles, as incorporated inter alia in the UNIDROIT
         Principles of International Commercial Contracts, the party who invokes changed
         circumstances that fundamentally disturb the contractual balance...is also entitled to
         claim the renegotiation of the contract.”107
      85. In the present case, re-negotiation tried by the CLAIMANT with the RESPONDENT failed
         in every way. The RESPONDENT was not willing to re-negotiate besides many
         efforts.108The RESPONDENT, on December 14, 2018, wrote a letter to the CLAIMANT
         wherein it refused to renegotiate the agreement and directed the CLAIMANT to supply
         the parts for the quarter ending in December 2018, failing which it would terminate the
         agreement. The RESPONDENT was under an obligation to renegotiate the contract in the
         situation of economic hardship, which in this case denied by the RESPONDENT.
         C. THE RESPONDENT WAS NOT JUSTIFIED IN TERMINATING THE AGREEMENT BY THE
             VIRTUE OF ARTICLE 49 OF CISG.
      86. It is humbly submitted that the RESPONDENT was not justified in terminating the
         agreement by the virtue of Art. 49 of CISG.109 In order for the buyer to have proper
         grounds to avoid the contract under Art. 49 (1) (a), the seller must have failed to perform
         an obligation, and the seller’s non-performance must substantially deprive the buyer of
         what he was objectively entitled to expect under the contract.
      87. In Contradiction of RESPONDENT’S contention, the CLAIMANT asserts that CLAIMANT’S
         failure to perform its part of obligation is not a fundamental breach under Art. 25 of
         CISG.110 The final non-delivery by the seller constitutes a fundamental breach of
106
    Tribunal of International Commercial Arbitration at the Russian Federation Chamber of Commerce, Russian
Federation, 22 January 1997 (Arbitral award No. 155/1996), Unilex.
107
     Hof van Cassatie, Belgium, 19 June 2009 (Scafom International BV v. Lorraine Tubes S.A.S.),
www.cisg.law.pace.edu.
108
    Cl. Ex. C11, C14, C15, C16.
109
    The United Nations Convention on Contracts for the International Sale of Goods, 1980, Art. 49 (1) (a).
110
    The United Nations Convention on Contracts for the International Sale of Goods, 1980, Art. 25.
         contract unless the seller has justifying reasons to withhold its performance.111
         However, if only a small part of the contract, i.e. one of the many instalments, is not
         supplied the breach is not fundamental.112 In addition, a little late delivery does not
         amount to a fundamental breach.113
      88. In the present case, CLAIMANT’S failure to deliver the 3rd Quarterly instalment a week
         later was due to the impediment of increased manufacturing cost and trade war. In
         addition to that, the failure to deliver the 4th Quarterly Instalment is because of a
         justifying reason. The notice of which was communicated to the RESPONDENT but no
         re-negotiation of price could be possible due to RESPONDENT’S indifferent behaviour.
         The failure to deliver 4th Instalment to the RESPONDENT does not amount to a
         fundamental breach. The main objective of the Contract was to maintain the plant
         availability above 85%. The CLAIMANT completed this main obligation in all three
         years of the contract starting from January 2015 to January 2018 i.e. 94.8%-96%.114
         This availability of plants was maintained averaging to 93% until the end of the 2nd
         quarter.115 There is no chance or possibility that this plant availability reduces straight
         below the 85% threshold even after supplying the 3rd quarterly instalment. Thus, the
         CLAIMANT, in entirety, concludes that the termination of the agreement by the
         RESPONDENT is not justified.
111
    CLOUT case No. 846 [U.S. Court of Appeals (3rd Circuit), United States, 19 July 2007].
112
    CLOUT case No. 275 [Oberlandesgericht Düsseldorf, Germany, 24 April, 1997].
113
    CLOUT case No. 846 [U.S. Court of Appeals (3rd Circuit), United States, 19 July 2007].
114
    Notice of Arbitration ¶ 12.
115
    Cl. Ex. C11.
PRAYER
In the light of all the submissions made, the CLAIMANT hereby respectfully requests the
Tribunal to ADJUDGE and DECLARE that:
    1. The RESPONDENT’S counterclaim may be dismissed summarily.
    2. The Ministry of Power, Government of Yevadu shall be joined as a party to the
        proceedings.
    3. The RESPONDENT was not justified in terminating the Agreement.
    4. The CLAIMANT’S conduct did not result in a fundamental breach of the Agreement.
Sd/