TABLE A - ABSTRACT OF COST STATEMENT
Modified Amount as per
Rate as per
S. No. Description Unit Quantity as per PWD (in Rs.) Remarks
PWD
AE (2023-24)
1 Earth work cum 519.13 114.00 59,181
2 Plain Cement Concrete M-15 cum 13.92 6,006.75 83,609
3 Pile Cap (RCC grade M35) cum 358.34 7,850.45 2,813,162 Currnt rats of NH Circle Prayagraj
4 Substructure (RCC M-35) cum 177.19 7,850.45 1,390,996 based on MoRT&H Standard
Bored cast-in-situ M35 grade R.C.C. data book
5 m 721.20 20,014.00 14,434,097
Pile
6 HYSD bar Reinforcement MT 164.16 107,363.00 17,624,789
540.87-355.94=184.93
Fabrication & Erection of Bow string Currnt rats of NH Circle Prayagraj
7 MT 184.93 176,386.00 32,619,063
girder (New) based on MoRT&H Standard
data book
Fabrication of Bow String Girder
(Old). The Qty of old Bow String
Girder has been varified after joint Rate is based on IR USSOR-
8 MT 355.66 104,936.00 37,321,538
measurement vide EE office order 2019
no. 484 dated 22.06.2023 & 483
dated 27.06.2023 (Copy enclosed)
13 Bearings
13.1 POT-cum -PTFE Bearing (Free end) Nos. 1.00 86,500.96 86,501
13.2 POT Bearing-Fixed Type Nos. 1.00 121,527.03 121,527 Railways 2019 rates
Rates to be chaged for 2023-24
13.3 POT-cum -PTFE Guided (L)Bearing Nos. 1.00 146,775.31 146,775
13.4 POT-cum -PTFE Guided (T) Bearing Nos. 1.00 140,658.10 140,658
14 Additional RCC Qty in Deck Slab cum 38.09 7,850.45
Not payable as overall width of
Additional HYSD bar Reinforcement the ROB has not been changed
15 MT 4.95 107,363.00
in Deck Slab
Total COS Amount for ROB Work 106,841,896
The contractor quoted rate of
Deduct cost of old bow string Girder
scrap material @ 35 per Kg vide
16 (Scrap value as per meeting with MT 355.66 35,000.000 12,448,100
his letter no. 477-1 dated
CE NH)
08.07.2023.
Total COS Amount for ROB Work 94,393,796