Section 01-Introduction
Section 01-Introduction
INTRODUCTION
ENTER HERE
BACK TO CONTENTS
Arrow Bowen Gas Project EIS
1 Introduction
1.1 Overview
Arrow Energy Pty Ltd (Arrow) is seeking to develop gas reserves in the Bowen Basin for growing
overseas gas markets. The Bowen Gas Project (the Project) petroleum tenures cover an area of
approximately 8,000 square kilometres (km2) within the gas exploration acreage. The tenures are
located approximately 150 km south-west of Mackay, with the bulk of the area extending from
Glenden in the north to Blackwater in the south (Figure 1-1).
The reference case generated for the development of the EIS assumes that up to 6,625 production
wells are expected to be drilled throughout the Project area over its 40 year project life
(approximately). The Project area will be divided into development areas or gas fields allowing a
staged approach to development. Further developments are planned by Arrow as domestic and export
expansion opportunities arise in the energy market. In addition to providing ongoing supply to the
Queensland domestic gas market, Arrow is presently pursuing an export liquefied natural gas (LNG)
market opportunity, through the Arrow LNG Project on Curtis Island near Gladstone. It is expected that
much of the gas produced by the Project will be piped to the proposed LNG Plant. This LNG plant and
the transmission pipeline are subject to separate environmental approval processes and are not within
the scope of the Project.
Before the Project can proceed, Arrow must gain approval from the Queensland and Commonwealth
governments. Regulatory authorities must be satisfied that Arrow’s activities have been properly
assessed, to ensure that all potential impacts, direct and indirect, particularly environmental, social
and economic impacts, are fully examined and addressed. To do this, Arrow has prepared this
Environmental Impact Statement (EIS), which examines the entire Project development.
This EIS has been prepared to inform decision makers, affected parties, interest groups, and the
public about potential issues relating to the development and operation of the Project and how these
issues will be managed. The content of the EIS addresses those matters identified in the Terms of
Reference (ToR) (Appendix A of this EIS) issued by the Department of Environment and Heritage
Protection (EHP). A cross reference to the locations where each of the requirements of the ToR has
been addressed is given in Appendix B which references both the study chapters (Sections 1 through
34) and/or Appendices (A through EE).
This EIS has been made publicly available for comment, and submissions are sought from individuals
and organisations. After consideration of this EIS and submissions received, EHP will review the
Project EIS to identify any uncertainties or omissions. A supplementary report may be necessary to
cover any additional matters of concern and address stakeholder submissions. A final decision on the
overall acceptability of the Project will then be made on the basis of the information provided.
COLLINSVILLE
!
BR
U
C
E
-21
-21
H
W
Y
MACKAY
!
ATPA742
GLENDEN
! Y
HW
NS
ATPA749 DO
W
AK
PE
ATP1103
ATP1103
NEBO
!
BR
MORANBAH
U
-22
-22
CE
!
HWY
GR VELO
DE
EG
ATP759
OR MEN
Y
P
TA
LR
D
Y ATP1031
HW
NS
W DYSART
DO !
AK
PE
CLERMONT MIDDLEMOUNT
!
ATP1031 ! MARLBOROUGH
!
ATP1103
-23
-23
TIERI
!
GR
EGO
RY
H WY
CAIRNS! ATP1025
EMERALD
! BLACKWATER
WY
CAPRICORN HWY !
TOWNSVILLE!
ORY H
!
!
ROCKHAMPTON
!
GLADSTONE!
BUNDABERG!
MARYBOROUGH!
-24
-24
BRISBANE
TOOWOOMBA! ! !
IPSWICH !
COOLANGATTA
ARMIDALE!
/
0 10 20 40 60 Bowen Gas Project Tenements
km
1:2,000,000
Projection: Geographic (GDA94)
Source: This product may contain information that is © Mapinfo Australia Pty Ltd and PSMA Australia Ltd., © Copyright Commonwealth of Australia (Geoscience Australia) 2006 , © Copyright The State of Queensland (Department of Natural Resources and Water) 2008,
© The State of Queensland (Department of Mines and Energy) 2006-2008,© The State of Queensland (Department of Environment and Resource Management) 2010, Bing Maps © Microsoft Corporation and its data suppliers, Images from Client Feb 2012.
Whilst every care is taken by URS to ensure the accuracy of the digital data, URS makes no representation or warranties about its accuracy, reliability, completeness, suitability for any particular purpose and disclaims all responsibility and liability (including without limitation, liability in negligence) for any expenses,
losses, damages (including indirect or consequential damage) and costs which may be incurred as a result of data being inaccurate in any way for any reason. Electronic files are provided for information only. The data in these files is not controlled or subject to automatic updates for users outside of URS.
Section 1 Introduction
Section 1 Introduction
Email: bowengas@arrowenergy.com.au
Whilst every care is taken by URS to ensure the accuracy of the digital data, URS makes no representation or warranties about its accuracy, reliability, completeness, suitability for any particular purpose and disclaims all responsibility and liability (including without limitation, liability in negligence) for any expenses,
losses, damages (including indirect or consequential damage) and costs which may be incurred as a result of data being inaccurate in any way for any reason. Electronic files are provided for information only. The data in these files is not controlled or subject to automatic updates for users outside of URS.
Section 1 Introduction
1.3.1 Location
The Project’s petroleum tenures currently cover an area of approximately 8,000 km2 within Arrow's
gas exploration acreage. These tenures are located approximately 150 km south-west of Mackay, with
the bulk of the area extending from Glenden in the north to Blackwater in the south (see Figure 1-1).
The Project area follows the Connors Range to the east and the Denham Range to the west and is
located within the Isaac River and Mackenzie River sub-catchments of the Fitzroy River catchment
and the Belyando Suttor sub-catchment of the Burdekin catchment.
A number of towns and built up areas fall within or adjacent to the Project area. These include the
towns of Moranbah, Glenden, Dysart, Middlemount and Blackwater. Project infrastructure, including
CSG wells, gas and water gathering systems and production facilities will be located throughout the
development area but not in any of the towns.
The Project area comprises Authorities to Prospect (ATPs) 1103, 1031, 1025, and a small portion of
759; and Authority to Prospect Applications (ATPAs) 742 and 749 (see Figure 1-1).
1.3.2 Scope
The EIS will assess the impacts from the construction, operational and decommissioning stages of the
Project, which includes the drilling of CSG wells and construction of associated infrastructure to treat
and transport the gas and associated water. For the first phase of development, supply is expected to
be approximately 520 terajoules per day (TJ/d) (inclusive of infield gas usage, which is approximately
10%). This is approximately equal to 35% of the total daily demand (plateau) flowrate required by the
Arrow LNG plant.
For Arrow to realise the potential of the Project as a viable commercial development, exploration has
been conducted across the Project area to identify and define the gas resource. Exploration is
governed under existing approvals (environmental authorities) and is therefore outside the scope of
this EIS. Exploration and appraisal pilots are ongoing and are at different stages of maturity across the
Project area.
Development of the Project will require significant infrastructure and facilities for the construction,
operations and decommissioning phases of the Project. Table 1-1 describes the facilities to be
constructed as part of the Project. Further details are provided in the Project Description chapter
(Section 4) of this EIS.
Section 1 Introduction
Section 1 Introduction
Arrow will stagger the development of subsequent resource areas to sustain the required production
rate, and increase it subject to the LNG plant demand. Production well installation, facility construction,
operation, decommissioning and rehabilitation will therefore occur concurrently at different locations
throughout the Project life.
The life of a production well will vary in accordance with the density of wells, the gas extraction rate
and the production performance of the well. Production performance is predominately dependent on
the physical characteristics of the coal. Modelling of well life is based on probabilities and averages.
Arrow’s current modelling suggests an average well life of 15 to 20 years. Once the wells cease
production, the wells and well sites are to be decommissioned and rehabilitated and new wells will be
established in new development areas.
Section 1 Introduction
This has been achieved through the identification of environmental constraints to development and the
establishment of management controls that apply to Project activities in constrained areas. Known as
the environmental framework, this approach is an internal planning process developed by Arrow for
optimising site locations for its various Project activities so that the environmental values of the Project
area are protected.
Constraints mapping, an integral part of the environmental framework approach, guides site and route
selection decisions based on the known level of environmental constraints in the area and the level of
impact posed by the Project activity. In this way Project planning will seek to avoid and minimise
impacts, thereby protecting environmental values. A detailed description of the environmental
framework approach is provided in the Environmental Framework chapter (Section 7) of this EIS.
Section 1 Introduction
The regional location of the different components of the overall Arrow LNG project described above,
including the Bowen Gas Project, are depicted in Figure 1-3.
MACKAY
SARINA
MORANBAH
-22
-22
DYSART
CLERMONT MARLBOROUGH
YEPPOON
ROCKHAMPTON
EMERALD
BLACKWATER
MOUNT MORGAN
)
"
GLADSTONE
TANNUM SANDS
-24
-24
BILOELA
BUNDABERG
HERVEY BAY
MARYBOROUGH
GAYNDAH
-26
-26
GYMPIE
ROMA KINGAROY
CHINCHILLA
!
CAIRNS
! NORMANTON
TOWNSVILLE
DALBY
!
TOOWOOMBA
!
CLERMONT GATTON
ROCKHAMPTON
LONGREACH IPSWICH
!
GLADSTONE
!
!
BILOELA
BUNDABERG
!
MARYBOROUGH
!
CHARLEVILLE ST GEORGE
-28
-28
ROMA
!
!
TOOWOOMBA
IPSWICH WARWICK
! !
ST GEORGE
!
COOLANGATTA
!
GOONDIWINDI
/
0 10 20 40 60 80 100 120 Tenements
km
Surat Gas Project Tenements Main Road Arrow Surat Pipeline
1:4,000,000
Projection: Geographic (GDA94) Arrow Curtis LNG Plant Arrow Surat Header Pipeline
Project Development Area
Source: This product may contain information that is © Mapinfo Australia Pty Ltd and PSMA Australia Ltd., © Copyright Commonwealth of Australia (Geoscience Australia) 2006 , © Copyright The State of Queensland (Department of Natural Resources and Water) 2008,
© The State of Queensland (Department of Mines and Energy) 2006-2008,© The State of Queensland (Department of Environment and Resource Management) 2010, Bing Maps © Microsoft Corporation and its data suppliers, Images from Client Feb 2012.
Whilst every care is taken by URS to ensure the accuracy of the digital data, URS makes no representation or warranties about its accuracy, reliability, completeness, suitability for any particular purpose and disclaims all responsibility and liability (including without limitation, liability in negligence) for any expenses,
losses, damages (including indirect or consequential damage) and costs which may be incurred as a result of data being inaccurate in any way for any reason. Electronic files are provided for information only. The data in these files is not controlled or subject to automatic updates for users outside of URS.
Section 1 Introduction
The EIS process allows for community consultation and ensures environmental protection by
comprehensive consideration of potential impacts and management strategies. The content of the EIS
addresses the environmental, social and economic aspects of the Project as identified in the ToR
(Appendix A) of this EIS.
Following any decision on the EIS, the Project will also need to obtain a range of planning and
environmental approvals and permits before construction can begin and the Project is approved for
operation. These approvals and permits will be in accordance with local, state and federal legislation.
A full outline of the project approvals is detailed in the Project Approvals chapter (Section 2) of this
EIS.
Section 1 Introduction
The Project Description is a reference case generated at the early stages of Concept Select phase of
the project to inform the EIS. Upon selection of the concept and as the Project moves into the detailed
design phase (front end engineering design (FEED)) some aspects of the Project will change. While
the nature of the field development is known, details of the specific locations of wells, gathering
systems and associated infrastructure require progressive determination.
Section 1 Introduction
Section 1 Introduction
Site selection and management procedures will identify the standard management requirements for all
project activities, as well as additional environmental protection required in areas identified as having
high environmental and social sensitivity. The methodology applied in this EIS is presented in more
detail in the Impact Assessment Method chapter (Section 6).
Mitigation and management measures have been identified in the EIS sections and have also been
summarised in the draft EM Plan (Appendix Z), and the summary table of commitments (Appendix D)
of this EIS. Each mitigation and management measure has been identified consistently throughout the
EIS with a unique identifier (e.g. [B001]) to facilitate cross referencing.
Section 1 Introduction
Section 1 Introduction
Section 1 Introduction
Location Address
Isaac Regional Council
Middlemount Library Middlemount Shopping Mall, Middlemount, QLD 4746
Clermont Library Cnr. Karmoo and Herschel Streets, Clermont, QLD 4721
Dysart Library Council Premises, Shannon Crescent, Dysart, QLD 4745
Glenden Library Town Centre, Ewan Drive, Glenden, QLD 4743
Moranbah Library Grosvenor Complex, Batchelor Parade, Town Square,
Moranbah, QLD 4744
Nebo Library 10 Reynolds Street, Nebo, QLD 4742
Central Highlands Regional Council
Emerald Library 44 Borilla Street, Emerald, QLD 4720
Blackwater Library Wey Street, Blackwater, QLD 4717
Bluff Library 6 Church Street, Bluff, QLD 4702
Duaringa Library Elizabeth Street, Duaringa, QLD 4712
Whitsunday Regional Council
Section 1 Introduction
Location Address
Bowen Customer Service Centre 7 Herbert Street, Bowen, QLD 4805
Collinsville Customer Service Centre Cnr. Stanley and Conway Streets, Collinsville, QLD 4804
Proserpine Customer Service Centre 3-85 Main Street, Proserpine, QLD 4800
EHP Regional Offices
Department of Environment and Heritage Floor 3, 400 George Street, Brisbane, QLD 4000
Protection (Brisbane)
Department of Environment and Heritage 99 Hospital Road, Emerald, QLD 4720
Protection (Emerald)
Department of Environment and Heritage 22-30 Wood Street, Mackay, QLD 4740
Protection (Mackay)
1.5.10 Submissions
The public may make submissions on the EIS to the Chief Executive of EHP. The Chief Executive
must accept all properly made submissions and may accept submissions even if they are not properly
made. A properly made submission is one that:
Is written and signed by or for each person (signatory) who made the submission;
States the name and address for each signatory;
Is made to the Chief Executive; and
Is received on or before the last day of the submission period.
Please note that it is a statutory requirement that all submissions will be forwarded to the proponent
for consideration and provision of a response to EHP. Submissions should be addressed to:
The Chief Executive Department of Environment and Heritage Protection
Attention: The EIS Co-ordinator (Arrow Bowen Gas Project)
By Post GPO Box 2454, Level 8 400 George St, BRISBANE QLD 4001.
Section 1 Introduction
Following completion of the preparation of any supplementary information required, the Chief
Executive of the EHP will consider all public submissions as well as recommendations from advisory
agencies (listed below in Table 1-5) in preparing the EIS assessment report.
Subsequent to confirmation from EHP that the submissions and additional matters have been suitably
addressed; the Chief Executive (EHP) will prepare the assessment report, which will consider how
well the EIS has addressed the final ToR (and identifies any further information required). The report
may also make recommendations on the suitability of the Project and recommend conditions to be
applied to the Project should it proceed.
The report will be provided to DSEWPaC, who will approve, not approve, or approve the EIS with
conditions, under Part 9 of the EPBC Act.
Section 1 Introduction