Warehouse Office Construction BOM

The document provides a bill of materials for the construction of a warehouse office including drywall, doors and windows, ceiling works, electrical work, and painting work. It lists the required materials, quantities, and costs for each item and section. The total cost of materials is PHP 236,594 with a total labor cost of PHP 104,101.36 and overall project cost of PHP 352,619.70.

Uploaded by

rheyjc09
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as XLSX, PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
74 views5 pages

Warehouse Office Construction BOM

The document provides a bill of materials for the construction of a warehouse office including drywall, doors and windows, ceiling works, electrical work, and painting work. It lists the required materials, quantities, and costs for each item and section. The total cost of materials is PHP 236,594 with a total labor cost of PHP 104,101.36 and overall project cost of PHP 352,619.70.

Uploaded by

rheyjc09
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as XLSX, PDF, TXT or read online on Scribd
You are on page 1/ 5

CONSTRUCTION OF WAREHOUSE OFFICE

BILL OF MATERIALS
A. DRYWALL (Double wall)
Material Description QTY.
Metal stud 119.00 pcs
5 mm Fiber Cement Board 53.00 sheets
Blindrivets 4.00 box
Concrete nail 3.00 kgs
Blackscrew 7.00 box
Drill bit 5.00 pcs
Total Amount :
B. DOOR AND WINDOWS
Material Description QTY.
D1 Panel Door (45mm thick) with 1.0 set
Jamb(.90mx2.10m)(Tanguile Panel
Door)
Brown aluminum dark gray glass sliding 1.0 set
window
Four way sliding window 1.0 set
Total Amount :
C. CEILING WORKS
Material Description QTY.
9mm thk Gypsum board 24 pcs
25mm x 25mm Wall Angle 39 pcs
19mm x 38mm x 5m Metal furring 34 pcs
12.5mm x 38mm x 5m Carrying Channel 24 pcs
1 1/2" Concrete Nails 4 kgs
1 1/2"Self tapping screw 2 box
5/32" x 1/4" Blind Rivet 7 box
#16 Tie wire 6 kgs
Metal Furring Clip 33 pcs
Miscellaneous/Furring Accessories 1 lot
Total Amount :
D. ELECTRICAL ANG LIGHTING
Material Description QTY.
LED Weather proof T-8 Flourescent 3 set
Light 2-18w w/ fixtures
3 Gang Switch w/ Plate and Cover 1 set
3-gang Convenience Outlet 14 set
Aircon Outlet 1 set
15mm Ø PVC Flexible Conduit 5 roll
3.5mm² THHN Stranded Copper Wire 2 box
5.5mm² THHN Stranded Copper Wire 2 box
G.I. Wire #16 5 kgs
Electrical Tape big 5 pc
Utility Box 2 pc
Junction Box 2 pc
Panel Board 1 pc

Total Amount :
E. PAINTING WORKS
Material Description QTY.
Skim Coat 12.00 bags
Flat Wall Latex Paint 15.00 gals
Flat Wall Enamel 15.00 gals
Paint Thinner 3.00 bot
Paint Brush 3", 2" and 1" 3.00 pcs
11" Paint Roller with Pan 3.00 pcs
Baby Paint Roller 5.00 pcs
Assorted Sand Paper #80 /#120 15.00 sheets
Paint Rug 5.00 kgs
Masking Tape 5.00 rolls
Total Amount :

Material Cost 236,594.00


Labor Cost 104,101.36
340,695.36
Ovehead Exp. Misc. and Conting. 3.5% 11,924.34

Total 352,619.70

CONSTRUCTION OF WAREHOUSE OFFICE


Brgy. Banago, Circumferential Road, Bacolod City

BILL OF MATERIALS

Description Material Cost Labor Cost


A. DRYWALL (Double wall) 74,341.00 32,710.04
B. DOOR AND WINDOWS 45,000.00 19,800.00
C. CEILING WORKS 40,200.00 17,688.00
D. ELECTRICAL ANG LIGHTING 35,465.00 15,604.60
E. PAINTING WORKS 41,588.00 18,298.72
236,594.00 104,101.36

Prepared by
Cresmer J. Catarong
Contractor
`
ferential Road, Bacolod City

RIALS
Overhead Ex. And Conting.
Total
3.5%
3,746.79 110,797.83
2,268.00 67,068.00
2,026.08 59,914.08
1,787.44 52,857.04
2,096.04 61,982.76
11,924.34 352,619.70