Informit
Informit
Downloaded from search.informit.org/doi/10.3316/informit.987977016171898. Griffith University, on 04/20/2024 09:00 PM AEST; UTC+10:00. © Road & Transport Research , 2011.
INTRODUCTION
Sydney, as Australia’s largest city with a population
of 4.5 million faces similar challenges to other
large, car-oriented cities in transitioning to more
sustainable urban transport. Despite the addition of
110 km of new motorways in the last two decades,
Sydney remains Australia’s road congestion capital.
While Sydney still has the most heavily used public
transport system in the country, and the lowest
levels of car dependence, its public transport system
has under-performed in the last decade, and it is
lagging other Australian cities in the use of cycling
as well.
As shown in Table 1, there is a very substantial list
of public transport-related projects for Sydney,
particularly rail projects, which have been
announced and subsequently cancelled (and in a
59
Table 1
Key transport projects cancelled or delayed in Sydney
Originally Original Subsequent
Project announced completion date Fate developments
Integrated ticketing 1996 2000 Contract New process
Terminated 2008 restarted in 2008
CBD light rail line 1996 Extensive EIS Not proceeded with Re-announced
Downloaded from search.informit.org/doi/10.3316/informit.987977016171898. Griffith University, on 04/20/2024 09:00 PM AEST; UTC+10:00. © Road & Transport Research , 2011.
few cases re-announced), totalling over $33 billion. Even before the axing of the CBD Metro, there was
The most recent and spectacular example was the widespread cynicism by the public and key decision
decision by the State Government to cancel the makers in Sydney about how the city is ever to
$5.3 billion CBD Metro project in February 2010, move forward with a comprehensive, believable
which was to have been the beginning of a new and affordable transport plan. It is against that
metro rail network for the city. background that a unique experiment in civic
60
action was initiated by the Sydney Morning Herald 5. Key environmental sustainability issues.
in August 2009 – the holding of an Independent
6. Key social and economic issues.
Public Inquiry into a Long Term Public Transport
Plan for Sydney. 7. Proposals for short term and long term funding.
8. The cost-effectiveness of solutions, taking into
THE INDEPENDENT PUBLIC INQUIRY account short term financial costs and benefits,
The poor state of Sydney’s transport planning and longer term environmental, congestion
was already evident in 2007, and led to a range and other external costs and land use and
of community responses. Several independent
Downloaded from search.informit.org/doi/10.3316/informit.987977016171898. Griffith University, on 04/20/2024 09:00 PM AEST; UTC+10:00. © Road & Transport Research , 2011.
accessibility benefits.
alternative plans for Sydney emerged (FROGS 2007;
Glazebrook 2009). By August 2009, it was apparent Process adopted by the Inquiry
to many people, including the Sydney Morning The process adopted by the Inquiry was similar to
Herald editorial staff, that the NSW government that used by many Public Inquiries, with calls for
was struggling to develop and implement a sensible submissions from the public and from interested
and believable transport plan. The Herald had a long groups and organisations. A total of eight public
tradition, extending back before the introduction of meetings were also held across the Sydney
democracy in the State, of raising issues of public Metropolitan Area during September-October
concern. With the strong support of a former editor 2009, and three documents were put on the Inquiry’s
who just happened to have a particular interest in website to provide useful background information
transport and planning issues, the Herald agreed to for the public.2
hold an Independent Public Inquiry to develop a
Long Term Public Transport Plan for Sydney. However, the Inquiry also adopted some unusual
approaches. In particular, it was agreed that
Ron Christie, AM., a former co-ordinator-general specific market research should be conducted
of rail, head of the Olympic Roads and Transport into the public’s preferences for investment in
Authority, Director of the Roads and Traffic transport infrastructure and services as well as
Authority and Director of Public Works, agreed to their willingness to pay for such investments. This
Chair the Inquiry. The Inquiry was assisted by a research was conducted using choice modelling
range of individuals1, mostly on an unpaid basis, techniques, in order to avoid the limitations of
together with consultant assistance in market conventional market research. It was conducted
research, financing and other areas. The terms of for a total sample of 2400 residents of Sydney, by
reference for the Inquiry were as follows: the CENSOC group at the University of Technology,
1. The Independent Public Inquiry will create a Sydney.
Long Term Public Transport Plan for Sydney A second unusual approach was to use the results
after receiving public submissions. The plan is of the research on willingness to pay to provide a
designed to assist both the public and future limit on the level of improvement in public transport
governments to make informed decisions which would be included in the proposed long term
about priorities for transport investment. The plan. It was decided that any plan must not only
plan will cover the following topics: be desirable in terms of enhancing Sydney’s public
2. The optimisation and integration of existing transport system, but also affordable. Consequently
public transport operations (including ferry, it was agreed that the full costs of capital, additional
bus, light rail and heavy rail). services and interest for the plan needed to be
funded over 30 years within the community’s
3. The expansion of public transport services
willingness to pay, as determined by the market
and infrastructure, as well as cycle commuting
research. This placed important limits on what could
infrastructure, over a 30-year planning
be proposed in the plan by way of improvements.
horizon, taking into account existing transport
accessibility problems and integration with A third aspect was also somewhat unusual in
future land use changes. the context of previous attempts by the NSW
Government. Instead of proposing a single plan,
4. The most appropriate governance arrangements
it was decided to develop a number of alternative
to guarantee the plan’s longevity to remove the
land use – transport scenarios for Sydney, and to
negative impact of single-term party politics
include these in the Inquiry’s Preliminary report.
and to optimise investments.
1 For full list see Preliminary Report at www.transportpublicinquiry. 2 These were Christie (2001), NSW Department of Planning
com.au (2005) and Glazebrook (2009).
61
Although such approaches have been adopted in of public submissions and hearings, the Inquiry’s
some other States as part of their metropolitan own research into experience elsewhere, and the
planning exercises, this approach is not common need to address short term improvements, long
in NSW where only one potential option is ever term enhancement and funding.
put forward for subsequent consultation/comment.
Another intriguing aspect of the Inquiry is that it
Finally, it was recognised early on, when the paralleled the Government’s own development
Inquiry’s terms of reference were being framed, that of a ‘Transport Blueprint’, undertaken by the
a physical plan, even with appropriate funding, was relevant departments and with the support of an
Downloaded from search.informit.org/doi/10.3316/informit.987977016171898. Griffith University, on 04/20/2024 09:00 PM AEST; UTC+10:00. © Road & Transport Research , 2011.
not likely to succeed without major changes to the independent ‘Reference Panel’. The Government,
way in which urban transport is governed in NSW. too, requested submissions from the public and
Thus the Inquiry spent roughly equal amounts of interested organisations for its ‘Blueprint’ exercise.
effort in four key areas: Suddenly Sydneysiders had a range of options
for expressing their views on Sydney’s transport
•• Governance
problems and how best to fix them.
•• Funding
•• Developing a Long Term Plan The Public Inquiry’s 450 page Preliminary Report
•• Short term and ongoing enhancements to the was released on 5 February 2010. Among its other
public transport system recommendations were delays to the CBD and other
metros, acceleration of the NW rail link and other
The initial round of public consultation elicited heavy and light rail projects, and major changes to
almost 500 submissions, mostly from individuals governance and funding arrangements. These will
but also from a range of local governments, regional be examined in more detail below.
organisations of councils, professional associations,
community groups, unions and other organisations. Two weeks later, a modified ‘blueprint’, relabelled
As expected there was almost no input from the State as the Metropolitan Transport Plan (NSW
Government – a two page letter – but a more serious Government 2010), finally emerged. This was a
submission was received from the State Opposition. 44 page document, reputedly a ‘cut down’ version
In addition to the submissions the Inquiry held a of a much more substantial document which had
number of hearings with individuals and groups to failed to gain Treasury endorsement. Key features
further explore their ideas or proposals for reform. of the Plan included indefinite deferment of the
CBD and other metros, re-instatement of the NW
Figure 1 shows diagrammatically the logic behind the rail link, and inclusion of two light rail projects.
Inquiry’s approach. In practice all streams of work
were closely integrated – for example the market Details of the Inquiry’s recommendations
research informed the financial analysis which in The Inquiry subsequently released its 528 page
turn limited the options included in the long term Final Report on 26 May 2010, following additional
plan, while the analysis of governance took account submissions and discussions on its Preliminary
Figure 1
The Inquiry process
62
Report. Key findings and recommendations are period from within the limits of what the community
outlined below: indicated it was willing to pay.
To measure this, an extensive market research
Governance
exercise was undertaken, across a sample of 2400
After reviewing the history of public transport people, to identify what combinations of revenue
governance in Sydney and reviewing arrangements sources people were prepared to accept in relation
in cities such as Perth, London, Singapore, Vancouver to different combinations of upgrades to public
and Zurich, a number of key principles were transport and/or roads. The market research
established as desirable for any new governance
Downloaded from search.informit.org/doi/10.3316/informit.987977016171898. Griffith University, on 04/20/2024 09:00 PM AEST; UTC+10:00. © Road & Transport Research , 2011.
63
Downloaded from search.informit.org/doi/10.3316/informit.987977016171898. Griffith University, on 04/20/2024 09:00 PM AEST; UTC+10:00. © Road & Transport Research , 2011.
Figure 2
Support for alternative
future transport scenarios
for Sydney by household
income
Table 2
Alternative long term scenarios for Sydney
Scenario ‘US’ ‘European’ ‘East Asian’
Population (2040) 6 million 6 million 6 million
% of Future Growth in:
‘Greenfield areas’ 40% 28% 22%
‘Established Areas’ 60% 72% 78%
Jobs Focus Dispersed Multi-centred CBD
Transport focus Motorways Heavy rail, Light rail, Metros
Metro, Bus
64
regional bus services, extension of the light rail REFERENCES
system, better passenger information and the like Alford, G & Whiteman, J 2009, Macro-Urban Form, Transport
(see Chapters 4 and 5). Energy Use and Greenhouse Gas Emissions: An Investigation for
Melbourne, Victorian Department of Transport, Transport
There is clearly scope for major enhancements in Policy Analysis and Research Unit.
many areas at relatively modest cost. For example,
the extension of light rail into the CBD and into the Christie, R 2001, Long Term Strategic Plan for Rail – Overview
Report, prepared for the NSW Government, June 2001,
inner western suburbs coupled with re-arranging
viewed 7 February 2011, <http://www.aptnsw.org.au/
bus routes through the CBD could enhance capacity, christie/index.html>.
Downloaded from search.informit.org/doi/10.3316/informit.987977016171898. Griffith University, on 04/20/2024 09:00 PM AEST; UTC+10:00. © Road & Transport Research , 2011.