TEST REPORT ATL/FMT/7.
8
SRF NO:ALT/849 ULR No: T C 9 8 9 0 2 3 0 0 0 0 0 2 8 2 0 F
Customer Name and Address: Report No: ATL/CHEM/0401-24/2820
Mittal Construction Laboratory Mark: Dec 2330/03
Project Name: PepsiCo Project Nalbari, Assam Date of Receiving: 30.12.2023
Date of Completion: 04.01.2024
Date of Report: 04.01.2024
Period of Testing 30-12-2023 to 04-01-2024
Sample Description: SikaPlast 4111 NS Brand: Sika India Pvt. Ltd Batch No.: KP23004869 Location Of testing: Inhouse
RESULTS
REQUIREMENT As Per IS
SL. No. TEST PARAMETERS TEST METHOD OBSERVED VALUE CONFORMITY
9103:1999
1 pH Value IS 9103:1999 6.78 6 Min. Yes
2 Dry Material Content,% IS 9103:1999 26.22 0.95 T ≤ DMC < 1.05 T Yes
Within 0.02 of the value stated by the
3 Relative Density IS 9103:1999 1.07 Yes
manufacturer
Within 10 percent of the value or
within 0.2 percent
4 Chloride Content, % IS 6925:1973 0.01 Yes
whichever is greater as stated by the
manufacturer
where,
T= manufacturer's stated value, in percent by mass
DMC= Dry Material Content, in percent by mass= 26.10
Relative Density= 1.08
Chloride Content= 0.03
pH= 6.55
⁎⁎⁎End of Test Report⁎⁎⁎
Checked By
Alok Kumar Jha
Perfomed By Authorized Signatory
Remarks:
(1) The results listed refer only to tested samples and applicable parameters. Endorsement of product is neither inferred nor implied.
(2) Total liability of our Lab is limited to the invoiced amount.
(3) Samples will be destroyed after 90 days from the date of test certificate unless otherwise specified.
(4) This report is not to be reproduced wholly or in part and can not be used as an evidence in the court of Law and should not be
used in any advertising media without our special permission in writing.
(5) Report refer to the sample submitted to us and not drawn by us unless mentioned otherwise.
(6)Sample Received in good condition. Page : 01 of 01
TEST REPORT ATL/FMT/7.8
SRF NO:ALT/849 ULR No: T C 9 8 9 0 2 3 0 0 0 0 0 2 8 1 8 F
Customer Name and Address: Report No: ATL/MECH/0401-24/2818
Mittal Construction Laboratory Mark: Dec 2330/01
Project Name: PepsiCo Project Nalbari, Assam Date of Receiving: 30.12.2023
Date of Completion: 04.01.2024
Date of Report: 04.01.2024
Period of Testing 30-12-2023 to 04-01-2024
Sample Description: Soil Source: NA Location: Inhouse
RESULTS
SL. No. TEST PARAMETERS TEST METHOD OBSERVED VALUE
1 (a) IS Sieve Size (mm) Weight retained (gm) Cum wt. ret (gm) % Retained % Passing
75 0.00 0.00 0.00 100
19 1032 1032 6.88 93.12
4.75 1510 2542 16.95 83.05
2 2215 4757 31.71 68.29
0.425 4311 9068 60.45 39.55
0.075 4450 13518 90.12 9.88
2 Proctor Test:
i. Maximum dry density , gm/cc 1.940
IS 2720 (P-8):1983
ii. Optimum Moisture Content , % 11.63
3 Atterberg,s Limit:
i. Liquid Limit, % 18.50
ii. Plastic Limit, % IS 2720 (P-5):1985 Non Plastic
iii. Plasticity Index, % NA
4 CBR (Soaked for 96 hours),% IS 2720(P-16):1983 RA 2011 16.33
5 Free Swell Index, % IS 2720 (P-40):1983 RA2011 15
⁎⁎⁎End of Test Report⁎⁎⁎
Checked By
Alok Kumar Jha
Performed by Authorized Signatory
Remarks: Page : 01 of 01
(1) The results listed refer only to tested samples and applicable parameters. Endorsement of product is neither inferred nor implied.
(2) Total liability of our Lab is limited to the invoiced amount.
(3) Samples will be destroyed after 90 days from the date of test certificate unless otherwise specified.
(4) Sample received in good condition.
(5) This report is not to be reproduced wholly or in part and can not be used as an evidence in the court of Law and should not be
used in any advertising media without our special permission in writing.
(6) Report refer to the sample submitted to us and not drawn by us unless mentioned otherwise.
TEST REPORT ATL/FMT/7.8
SRF NO:ALT/849 ULR No: T C 9 8 9 0 2 3 0 0 0 0 0 2 8 1 9 F
Customer Name and Address: Report No: ATL/MECH/0401-24/2819
Mittal Construction Laboratory Mark: Dec 2330/02
Project Name: PepsiCo Project Nalbari, Assam Date of Receiving: 30.12.2023
Date of Completion: 04.01.2024
Date of Report: 04.01.2024
Period of Testing 30-12-2023 to 04-01-2024
Sample Description: Soil Source: NA Location: Inhouse
RESULTS
SL. No. TEST PARAMETERS TEST METHOD OBSERVED VALUE
1 (a) IS Sieve Size (mm) Weight retained (gm) Cum wt. ret (gm) % Retained % Passing
75 0.00 0.00 0.00 100
19 1022 1022 6.81 93.19
4.75 1636 2658 17.72 82.28
2 2615 5273 35.15 64.85
0.425 4833 10106 67.37 32.63
0.075 3485 13591 90.61 9.39
2 Proctor Test:
i. Maximum dry density , gm/cc 1.950
IS 2720 (P-8):1983
ii. Optimum Moisture Content , % 11.31
3 Atterberg,s Limit:
i. Liquid Limit, % 17.50
ii. Plastic Limit, % IS 2720 (P-5):1985 Non Plastic
iii. Plasticity Index, % NA
4 CBR (Soaked for 96 hours),% IS 2720(P-16):1983 RA 2011 17.11
5 Free Swell Index, % IS 2720 (P-40):1983 RA2011 15
⁎⁎⁎End of Test Report⁎⁎⁎
Checked By
Alok Kumar Jha
Performed by Authorized Signatory
Remarks: Page : 01 of 01
(1) The results listed refer only to tested samples and applicable parameters. Endorsement of product is neither inferred nor implied.
(2) Total liability of our Lab is limited to the invoiced amount.
(3) Samples will be destroyed after 90 days from the date of test certificate unless otherwise specified.
(4) Sample received in good condition.
(5) This report is not to be reproduced wholly or in part and can not be used as an evidence in the court of Law and should not be
used in any advertising media without our special permission in writing.
(6) Report refer to the sample submitted to us and not drawn by us unless mentioned otherwise.