TROJAN GENERAL CONTRACTING L.L.C REF: ITP-01 Rev.
01
DATE: 28-May-2024
INSPECTION & TEST PLAN FOR THE INSTALLATION OF UNDERGROUND UPVC DUCT PIPE & ACCESSORIES
PAGES: 1 OF 1
Project : REEM HILLS-REEM MAINLAND TOWNHOUSE&SEMI-DETACHED VILLAS(412) -PHASE 1B & 1C
LEGENDS:
Employer : Reem Hills Sole Properietorship LLC
I= Inspection H=Hold SC=Sub-Contractor
Royal Development Company and
Employer Project Manager :
Rapm Architect Project Management W =Witness C=Contractor E/A =Engineer / Client
Consultant : Aecom Middle East – Abu Dhabi
R =Review Records P = Preform ITL=Independent Testing lab
Main Contractor : Trojan General Contracting LLC
S =Surveillance
MEP Contractor Royal Advance Electro Mechanical Works LLC
A =Approval
VERIFYING RESPONSIBILITY
SPECIFICATION/DRAWIN RESPONSIBLE PERSON AT
SL.NO ACTIVITY DESCRIPTION INSPECTION/TEST METHOD MODE OF CHECK STAGE/FREQUENCY DOCUMENTS/ACCEPTANCE
G REFERENCE LOCATION SC /ITL C E/A
CRITERIA
1 Document Verification Check Drawings are approved & at correct revision By reviewing the documents Prior to start activities Approved Drawing R P R&A
obtained. Project Engineer
QA/QC Engineer
2 Material Inspection Check that material is approved through MIR By Visual Prior to start activities Approved Material Submittal P P R
3 Preliminary activities Check Civil clearance is obtained. By reviewing the documents Prior to start activities Permits of Excavation P P R
Q.C Check list Surveyor , Forman, Project
4 Level and dimension Ensure all sizes, locations and elevations are By Visual Before and during Engineer , QA/QC Engineer P P W
accordance with relevent drawing
General requirement
5 Installation of UPVC Duct Pipes Location, Size, joints By Measuring Tape, Level After Installation Inspection Request P S I&A
marker Q.C Check list QA/QC Engineer
Project Engineer
6 Removal of Waste material Check the removal and disposal of all unsuitable By Visual After Installation NA
materials to designated site. P P S
7 Final Acceptance Visual By Visual After Work Completion Signed WIR P P S
TGC/QAQC/FRM/PR/14 Rev.00 Prepared by : QA/QC EngineerReviewed by : QA/QC Manager