The document provides an inspection and test plan for installing underground UPVC duct pipes and accessories for a construction project. It outlines 7 activities to be inspected including verifying documents, material inspection, installation, and final acceptance. Responsibilities for inspection and sign off are assigned.

Uploaded by

Waqar Khan
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
71 views1 page

3 Itp

The document provides an inspection and test plan for installing underground UPVC duct pipes and accessories for a construction project. It outlines 7 activities to be inspected including verifying documents, material inspection, installation, and final acceptance. Responsibilities for inspection and sign off are assigned.

Uploaded by

Waqar Khan
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 1

TROJAN GENERAL CONTRACTING L.L.C REF: ITP-01 Rev.

01

DATE: 28-May-2024
INSPECTION & TEST PLAN FOR THE INSTALLATION OF UNDERGROUND UPVC DUCT PIPE & ACCESSORIES
PAGES: 1 OF 1
Project : REEM HILLS-REEM MAINLAND TOWNHOUSE&SEMI-DETACHED VILLAS(412) -PHASE 1B & 1C
LEGENDS:

Employer : Reem Hills Sole Properietorship LLC


I= Inspection H=Hold SC=Sub-Contractor
Royal Development Company and
Employer Project Manager :
Rapm Architect Project Management W =Witness C=Contractor E/A =Engineer / Client

Consultant : Aecom Middle East – Abu Dhabi


R =Review Records P = Preform ITL=Independent Testing lab

Main Contractor : Trojan General Contracting LLC


S =Surveillance

MEP Contractor Royal Advance Electro Mechanical Works LLC


A =Approval

VERIFYING RESPONSIBILITY
SPECIFICATION/DRAWIN RESPONSIBLE PERSON AT
SL.NO ACTIVITY DESCRIPTION INSPECTION/TEST METHOD MODE OF CHECK STAGE/FREQUENCY DOCUMENTS/ACCEPTANCE
G REFERENCE LOCATION SC /ITL C E/A
CRITERIA
1 Document Verification Check Drawings are approved & at correct revision By reviewing the documents Prior to start activities Approved Drawing R P R&A
obtained. Project Engineer
QA/QC Engineer
2 Material Inspection Check that material is approved through MIR By Visual Prior to start activities Approved Material Submittal P P R

3 Preliminary activities Check Civil clearance is obtained. By reviewing the documents Prior to start activities Permits of Excavation P P R

Q.C Check list Surveyor , Forman, Project


4 Level and dimension Ensure all sizes, locations and elevations are By Visual Before and during Engineer , QA/QC Engineer P P W
accordance with relevent drawing
General requirement

5 Installation of UPVC Duct Pipes Location, Size, joints By Measuring Tape, Level After Installation Inspection Request P S I&A
marker Q.C Check list QA/QC Engineer
Project Engineer
6 Removal of Waste material Check the removal and disposal of all unsuitable By Visual After Installation NA
materials to designated site. P P S

7 Final Acceptance Visual By Visual After Work Completion Signed WIR P P S

TGC/QAQC/FRM/PR/14 Rev.00 Prepared by : QA/QC EngineerReviewed by : QA/QC Manager