DATE            :      APRIL 05, 2024
PROJECT         :      REHABILITATION OF ADMIN OFFICE WITH TOILET
LOCATION        :      ILOCOS NORTE
SUBJECT         :      ACCOMPLISHMENT REPORT NO, 2
                                                                                                                 ACCOMPLISHMENT
                                                                                                   WEIGHTED    PREVIOUS       THIS PERIOD   TO DATE
ITEM                                 DESCRIPTION                                    QTY     UNIT
                                                                                                      %           %
  I    GENERAL REQUIREMENT
           a. Mobilization/Demobilization                                            1.00    lot       5.86%       40.00%          25.00%     65.00%
           b. CARI and Bonds                                                         1.00    lot       2.11%       40.00%          25.00%     65.00%
           c. Water & Power Consumption                                              1.00    lot
           d. Cleaning/Housekeeping Works/Safety                                     1.00    lot       3.09%       40.00%          25.00%     65.00%
           e. TemporaryFacility/Barraks                                              1.00    lot       2.60%       40.00%          25.00%     65.00%
           f. Supervision                                                            1.00    lot       3.74%       40.00%          25.00%     65.00%
           g. Disposal of unused materials and debris                                1.00    lot       4.55%       40.00%          25.00%     65.00%
           h. Delivery and hauling                                                   1.00    lot       3.90%       40.00%          25.00%     65.00%
           i. Testing and Commissioning                                              1.00    lot       0.98%       40.00%          25.00%     65.00%
                                                                     SUB-TOTAL I                      26.84%       40.00%          25.00%     65.00%
 II    Supply Materials and Installation works
          A. ADMIN OFFICE
               For Civil and Architectural works
                1. Demolition of existing CHB partition wall including
                                                                                     1.00    lot       1.28%       80.00%          20.00%    100.00%
                restoration works
                2. Dismanling of existing steel door and jamb                        1.00   set        0.09%       80.00%          20.00%    100.00%
                3. Enclosure of wall due to dismantled of existing door
                                                                                     3.00   sq.m       0.19%       80.00%          20.00%    100.00%
                opening using chb with cement plastered finish
                4. Restoration of existing acoustic ceiling.                        11.84   sq.m       0.25%       80.00%          20.00%    100.00%
                5. Add new acoustic ceiling ( same spec of existing)                15.31   sq.m       0.83%       80.00%          20.00%    100.00%
                6. Painting works on walls and Existing steel door                  77.21   sq.m       1.30%       80.00%          15.00%     95.00%
                7. Replacement of existing vinyl tiles(6mm thickness)               27.15   sq.m       1.63%       80.00%          20.00%    100.00%
                8. Signage                                                           1.00   pcs        0.05%       80.00%                     80.00%
               For EFSl works
                8. Outlets with rough-ins and wiring(should be 3-prong)              6.00   pcs        2.39%       25.00%          65.00%     90.00%
                9. Switches with rough-ins and wiring(brand can be National
                                                                                     1.00    pc        0.25%       25.00%          65.00%     90.00%
                Panasonic or any approve. See reflected on lay-out plan)
                10. Data/Telephone with rough-ins and wiring                         5.00   pcs        2.82%       25.00%          65.00%     90.00%
                11. 600mmX600mm panel light with rough-ins and wire(used
                                                                                     6.00   pcs        3.06%       25.00%          65.00%     90.00%
                other existing/installed wiring)
                12. Adjustment of smoke detector                                     1.00   pcs        0.10%       25.00%          65.00%     90.00%
                13. Adjustment/relocate of existing sprinklers                       2.00   pcs        0.39%       25.00%          65.00%     90.00%
                14. Dismantling of existing lighting fixtures                        1.00    lot       0.25%       25.00%          75.00%    100.00%
                15. Provision of drain for wall mounted AC                           1.00    lot       0.88%       25.00%          75.00%    100.00%
                                                                   SUB-TOTAL II-A                     15.77%       44.60%          49.20%     93.80%
          B. TOILETS
               For Civil and Architectural works
                1. Laying of 5'chb wall with cement plastered finish (floor to
                                                                                    21.87   sq.m       1.43%       40.00%          60.00%    100.00%
                slab)
                2. Re-installation of existing/dismanted steel door                  1.00   set        0.14%       40.00%          60.00%    100.00%
                3. Gypsum ceiling with standard framing with shadow line on
                                                                                     3.40   sq.m       0.27%       40.00%                     40.00%
                perimeter wall including painting
                4. Painting worksi ncliuding existing steel door                    35.80   sq.m       0.63%       40.00%                     40.00%
                5. 600mmx600mm Homogeneous tile on floor and wall( 2.7m
                                                                                    21.50   sq.m       1.76%       40.00%          10.00%     50.00%
                ht)
                6. Mirror with backing                                               1.00    pc        0.13%       40.00%                     40.00%
                7. Signage                                                           1.00    pc        0.05%       40.00%                     40.00%
               For EFS works
                6. Plumbing fitures including fitting and piping
                    - lavatory                                                       1.00   set        0.23%          0.00%        60.00%     60.00%
                    - fauset                                                         1.00   set        0.23%          0.00%        60.00%     60.00%
                    - bidet                                                          1.00   set        0.11%          0.00%        60.00%     60.00%
                    - Handyer                                                        1.00   set        0.46%          0.00%        60.00%     60.00%
                    - tisue holder                                                   1.00   set        0.10%          0.00%        60.00%     60.00%
                7. New smoke detector with rough-ins and wire(use same
                                                                                     1.00    pc        0.96%          0.00%                    0.00%
                brand[notifier] of existing. See reflected on lay-out plan)
                8. Relocation/adjustment of sprinkler                                1.00    pc        0.20%          0.00%       100.00%    100.00%
                                                                                                               ACCOMPLISHMENT
                                                                                                 WEIGHTED    PREVIOUS       THIS PERIOD   TO DATE
ITEM                              DESCRIPTION                                    QTY     UNIT
                                                                                                    %           %
             9. Lighting fixtues with rough-ins and wiring(used existing pin
                                                                                  2.00    pcs        0.50%          0.00%       100.00%    100.00%
             light)
             10. Provide switch (brand can be National Panasonic or any
                                                                                  1.00    pc         0.03%          0.00%        95.00%     95.00%
             approve. See reflected on lay-out plan)
                                                           SUB-TOTAL II-B                            7.25%       24.45%          34.88%     59.32%
       C. TELCO ROOM
           For Civil and Architectural works
            1. Dismantling and re-installation of existing steel door
                                                                                  1.00    set        0.30%      100.00%                    100.00%
            including restoration works
            2. Enclosure of door opening using chb with cement
                                                                                  2.50   sq.m        0.16%      100.00%                    100.00%
            plastered finish
                                                               SUB-TOTAL II-C                        0.45%      100.00%                    100.00%
       D. Mechanical Works
            For AC works
             1. Supply and Installation of 1.5TR ceiling cassette split type
             complete with FCU, ACCU, refrigerant piping and all related
                                                                                  2.00   units      14.62%       70.00%          25.00%     95.00%
             accessories.
             2. Supply and Installation of 1.5TR wall mounted split type
             complete with FCU, ACCU, refrigerant piping and all related
                                                                                  1.00   unit        5.34%       70.00%          25.00%     95.00%
             accessories.
             3. Refigerant charging complete with vacuuming, leak
             testing and all related works to run the system.
                                                                                  1.00   lot         4.05%       70.00%          25.00%     95.00%
             4. Condensate drain piping complete with fittings , insulation,
             support and all related accessories.
                                                                                  1.00   lot         1.35%       70.00%          25.00%     95.00%
             5. Dismantling of existing VRF ACCU complete with all related
             accessories including the hauling up to the designated
                                                                                  1.00   lot         0.25%       70.00%          30.00%    100.00%
             location.
             6. Supply and Installation of 70CFM ceiling exhaust fan
             complete with PVC pipe, end cap and all related
                                                                                  1.00   lot         0.74%       70.00%                     70.00%
             accessories.
             7. Equipment platform and support complete with all related
             accessories.
                                                                                  1.00   lot         0.93%       70.00%          30.00%    100.00%
             8. FCU drain piping horizontal and vertical complete with
             fittings , insulation, support and all related accessories.
                                                                                  1.00   lot         1.84%       70.00%          30.00%    100.00%
             9. Supply and Installation of Hand-portable fire extinguisher
             complete with all related accessories.
                                                                                  1.00   lot         0.92%       70.00%                     70.00%
             10. Supply and Installation of ceiling type fire extinguishers
             complete with all related accessories at CCTV Room
                                                                                  1.00   pcs         0.46%       70.00%                     70.00%
             11. Electrical materials consisting of circuit breakers,
             starters,switches, relay, wires,conduits and all related
                                                                                  1.00   lot        10.46%       70.00%          20.00%     90.00%
             accessories.
             12. Miscellaneous materials necessary to complete the
             project.
                                                                                  1.00   lot         1.37%       70.00%          20.00%     90.00%
                                                                SUB-TOTAL II-E                      42.33%       70.00%          22.71%     92.71%
            For Electrical/FDAS/Auxiliary works
             1. Supply and installation of needed new circuit breakers,
             wiring for lightings, FDAS, convenience outlets and other
             Electrical related works for Admin office, and Toilet.
                - Power provisions for all AC units (both indoor and
             outdoor) on all rooms. Refer to mechanical trade. Complete
                                                                                  3.00   sets        1.84%       60.00%          30.00%     90.00%
             circuit breakers, wires/cables, conduits/fiitings, boxes and
             other miscelaneous items.
                                                                                                               ACCOMPLISHMENT
                                                                                                 WEIGHTED    PREVIOUS     THIS PERIOD   TO DATE
ITEM                               DESCRIPTION                                    QTY     UNIT
                                                                                                    %           %
                  - Power provisions for all Exhaust units. Refer to mechanical
               trade. Complete circuit breakers, wires/cables,
                                                                                   1.00   lot        0.37%       60.00%        30.00%     90.00%
               conduits/fiitings, boxes and other miscelaneous items.
                 - Power provisions for Lighting and outlets. Complete circuit
               breakers, wires/cables, conduits/fiitings, boxes and other
                                                                                   1.00   lot        3.44%       60.00%        30.00%     90.00%
               miscelaneous items.
                 - Miscellaneous materials necessary to complete the
               project.
                                                                                   1.00   lot        1.72%       60.00%        30.00%     90.00%
                                                                SUB-TOTAL II-C                      7.37%        60.00%        30.00%     90.00%
                                                         TOTAL AMOUNT I& II)                      100.00%        54.04%        28.82%     82.86%
                                                        LESS DISCOUNT                                            54.04%        28.82%     82.86%
                                   TOTAL CONTRACT AMOUNT (DISCOUNTED)                                            54.04%        28.82%     82.86%
Prepared by:
DENNIS PINEDA CONSTRUCTION, INC.
ENGR. EFREN DELOS REYES
DPCI Head Engineer