0% found this document useful (0 votes)
45 views4 pages

Hot Work Permit Form

Uploaded by

Htain Linoo
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
45 views4 pages

Hot Work Permit Form

Uploaded by

Htain Linoo
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 4

Hot Work Permit to Work Template

1a2b3c / 24 Sep 2021 / Brad Smith Complete

Score 100% Failed items 0 Actions 0

This Hot Work Permit is required for any operation involving open flames or producing heat and/or sparks. This
includes, but is not limited to, Brazing, Cutting, Grinding, Soldering, Thawing Pipe, Torch-Applied Roofing, and
Welding.

Permit No. 1a2b3c

Site Location Avenue 20, Stapleton, NE 69163,


USA
(41.4876148, -100.6945613)

Conducted on 24 Sep 2021 16:07 PST

Prepared by Brad Smith

Private & Confidential 1/4


Audit 100%
Audit- 100%

Nature of Job/Object Welding of second floor railings

Required Precautions Checklist 100%


Required Precautions Checklist
- 100%
Available sprinklers in normal automatic mode and valve open. ✔

Hot Work equipment in good repair. ✔

Using the new welding equipment today.

Assess 35 ft radial “sphere” of work for potential fire hazards:

Floors, work level and below, cleaned or protected. ✔

Floor directly under the hot work also taken cared of.

All other combustibles removed or shielded from sparks. ✔

Clean horizontal surfaces (e.g. building structures, equipment, ducts, cable



trays, etc.) above and below where possible.

Remove flammable liquids, dust, lint, combustible waste, oil deposits, etc.,

where possible.

If removal/cleaning is impractical, protect with fire-retardant covers, or


N/A
shield with fire-retardant guards and/or curtains.

Transmission or conveying of sparks to adjacent areas eliminated or



protected.

Tightly cover wall/floor openings with fire-retardant material. ✔

Where openings cannot be sealed, suspend fire-retardant tarpaulins to



help protect areas beneath.

Isolate or shut down fans and conveyors to prevent the capturing and
N/A
conveying sparks to other areas.

No fans at this area.

Explosive atmosphere eliminated or potential not present. ✔

This is open air.

Work on walls, ceilings or enclosed equipment:

Construction materials verified as noncombustible and without



combustible covering or insulation.

Combustibles on another side of walls relocated or protected. ✔

Enclosed equipment cleaned and protected from all combustibles. N/A

No other equipment in the vicinity.

Private & Confidential 2/4


Containers purged of flammable liquids/vapors. N/A

No containers around.

Fire watch/hot work area monitoring requirements:

Continuous fire watch provided during and for at least 30 minutes after hot

work, including all breaks.

There is even a fire watch even on the lower floor.

Fire watch supplied with suitable extinguishers/hoses. ✔

fire extinguishers on both floors

Fire watch trained in the use of fire equipment and sounding alarm. ✔

Area to be monitored hourly for a minimum 6 hours after job is completed,



or longer if required.

we have security watching over the job site 24 hours

Other precautions that may be required:

Fire watch provided for adjoining areas, above, or below. ✔

both floors have fire watch

Confined Space or Lock-Out-Tag-Out required/used. N/A

hot work location is open air

Area smoke or heat detection disabled to eliminate false trip. ✔

disabled for the duration of the hot work

Completion
Completion
Full Name and Signature of Permit-Authorizing Personnel

Brad Smith
24 Sep 2021 16:18 PST

Click + to add names of persons doing the hot work

Employee
Employee
Employee 1
Employee 1

Private & Confidential 3/4


Full Name and Signature of Person doing the hot work

Tommy Jones
24 Sep 2021 16:21 PST

Private & Confidential 4/4