REPORT
OF ELECTRICAL EQUIPMENT INSTALLATION
PROJECT: CHAU THON HYDROELECTRIC POWER PLANT
REPORT DATE: 28th Jan 2024
Page 1
I. Supervision work on the site:
1. Main activity.
No Time Contents Notes
- Solving the issue with cables termination with
generator connection box.
22nd Jan
- Solving the cable termination with the ground
1 From 8AM-12AM
switchgear generator A11 & A21
From 1:30PM-5:30PM
- Contractor pulled the MV cables from Generators
G01, G02 to the cabinets A11, A21, A10, A20.
- Checking the termination for the cables at the Diesel
generator.
23th Jan
- Found some issues in the design drawing
2 From 8AM-12AM
termination for cables at the site.
From 1:30PM-5:30PM
- Contractor install cable tray, termination the MV
cables, LV cables and control cables.
- Inspection the MV cables termination at the cabinet
24th Jan
A11, A21.
3 From 8AM-12AM
- Contractor terminates the MV cables, LV cables and
From 1:30PM-5:30PM
control cables.
- Checking the conduit installation and pulling cables
th
25 Jan at the Song Quang to the connection box.
4 From 8AM-12AM - Checking the MV cables termination.
From 1:30PM-5:30PM - Contractor install cable conduit at Song Quang
substation, termination the MV cables.
- Checking the MV cables termination.
th
26 Jan - Contractor terminate the MV cables
5 From 8AM-12AM - Instruction to the contractor the solving issue for
From 1:30PM-5:30PM cables connection to the Generators connecting
boxes.
27th Jan
- Checking the MV cables termination.
6 From 8AM-12AM
- Contractor terminate the MV cables
From 1:30PM-5:30PM
2. Estimation the schedule of installation.
Currently, the constractor did not submit the installation schedule to Ingeteam. In the owner
progress the project will be energyzing on 30th April 2024.
Status of works at the site:
Page 2
Content of works Installation Notes
+A01 SWITCHGEAR OUTLET (10,5kV) Installed Not yet connected the cable
to the grounding system,
not yet did the bolting work
to the foundation.
+A02 SWITCHGEAR AUX. SERV. Installed Not yet connected the cable
(10,5kV) to the grounding system,
not yet did the bolting work
to the foundation.
+A05 SWITCHGEAR_LOCAL GRID Owner would like to use
(35kV) the existing 35kV system
and would not install this
equipment.
+A10 SWITCHGEAR GENERATOR 1 Installed Not yet connected the cable
(10,5kV) to the grounding system,
not yet did the bolting work
to the foundation.
+A11 GROUND SWITCHGEAR Installed Not yet connected the cable
GENERATOR 1 (10,5kV) to the grounding system,
not yet did the bolting work
to the foundation.
+A20 SWITCHGEAR GENERATOR 2 Installed Not yet connected the cable
(10,5kV) to the grounding system,
not yet did the bolting work
to the foundation.
+A21 GROUND SWITCHGEAR Installed Not yet connected the cable
GENERATOR 2 (10,5kV) to the grounding system,
not yet did the bolting work
to the foundation.
+A40
SWITCHGEAR_INTAKE&SPILLWAY
(35kV)
+C01 POWER METER CABINET Installed Not yet connected the cable
to the grounding system,
not yet did the bolting work
to the foundation.
+T01 POWER TRANSFORMER Installed Not yet connected the cable
110/10,5kV to the grounding system,
not yet did the bolting work
Page 3
to the foundation.
+C02 SUBSTATION CONTROL Installed Not yet connected the cable
CABINET to the grounding system,
not yet did the bolting work
to the foundation.
+C05 AUX. SERV. A.C. CABINET Installed Not yet connected the cable
to the grounding system,
not yet did the bolting work
to the foundation.
+C06 EMERG. SERV. A.C. CABINET Installed Not yet connected the cable
to the grounding system,
not yet did the bolting work
to the foundation.
+C07 AUX. SERV. DC/SAI CABINET Installed Not yet connected the cable
to the grounding system,
not yet did the bolting work
to the foundation.
+D01 DC CHARGER CABINET Installed Not yet connected the cable
to the grounding system.
+C04 COMMUNICATION CABINET Installed Not yet connected the cable
to the grounding system,
not yet did the bolting work
to the foundation.
+C03 COMMON CONTROL CABINET Installed Not yet connected the cable
to the grounding system,
not yet did the bolting work
to the foundation.
+C10 CONTROL CABINET UNIT 1 Installed Not yet connected the cable
to the grounding system,
not yet did the bolting work
to the foundation.
+E10 HYDRAULIC OIL UNIT 1 Not in the Ingeteam scope
+G10 GENERATOR 1 Not in the Ingeteam scope
+C11 TURBINE GOVERNOR CABINET
UNIT 1
+C20 CONTROL CABINET UNIT 2 Installed Not yet connected the cable
to the grounding system,
not yet did the bolting work
Page 4
to the foundation.
+E20 HYDRAULIC OIL UNIT 2 Not in the Ingeteam scope
+G20 GENERATOR 2 Not in the Ingeteam scope
+C21 TURBINE GOVERNOR CABINET
UNIT 2
+C31 POWER METER CABINET Not in the Ingeteam scope
(SONG-QUANG)
+C32 SUBSTATION CONTROL Installed Not yet connected the cable
CABINET (SONG-QUANG) to the grounding system,
not yet did the bolting work
to the foundation.
+C40 AUX SERV. A.C. CABINET
(INTAKE&SPILLWAY)
+D02 BATTERIES Changing the installation
location
+H10 COOLING SYSTEM UNIT 1
+F01 SURGE ARRESTER-1 110kV Installed Not yet connected the cable
to the grounding system,
not yet poured the grouting
for the structure
foundation.
+F02 SURGE ARRESTER-2 110kV Installed Not yet connected the cable
to the grounding system,
not yet poured the grouting
for the structure
foundation.
+F31 SURGE ARRESTER 110kV Installed Not yet connected the cable
(SONG-QUANG) to the grounding system,
not yet poured the grouting
for the structure
foundation.
+G01 DIESEL GENERATOR AUX Installed Not yet connected the cable
to the grounding system,
not yet did the bolting work
to the foundation.
+G40 DIESEL GENERATOR
(INTAKE&SPILLWAY)
+I01 LINE CIRCUIT BREAKER 110kV Installed Not yet connected the cable
Page 5
(52L1) to the grounding system,
not yet poured the grouting
for the structure
foundation.
+I31 CIRCUIT BREAKER 110kV Installed Not yet connected the cable
(SONG-QUANG) to the grounding system,
not yet poured the grouting
for the structure
foundation.
+S01 DISCONNECTOR 110kV (89L1) Installed Not yet connected the cable
to the grounding system,
not yet poured the grouting
for the structure
foundation.
+S30 DISCONNECTOR-1 110kV Installed Not yet connected the cable
(89B2) (SONG-QUANG) to the grounding system,
not yet poured the grouting
for the structure
foundation.
+S31 DISCONNECTOR-2 110kV Installed Not yet connected the cable
(89L2) (SONG-QUANG) to the grounding system,
not yet poured the grouting
for the structure
foundation.
+T02 VOLTAGE TRANSFORMER Installed Not yet connected the cable
110kV to the grounding system,
not yet poured the grouting
for the structure
foundation.
+T02A VOLTAGE TRANSFORMER Installed Not yet connected the cable
110kV Phase A to the grounding system,
not yet poured the grouting
for the structure
foundation.
+T02B VOLTAGE TRANSFORMER Installed Not yet connected the cable
110kV Phase B to the grounding system,
not yet poured the grouting
for the structure
foundation.
Page 6
+T02C VOLTAGE TRANSFORMER Installed Not yet connected the cable
110kV Phase C to the grounding system,
not yet poured the grouting
for the structure
foundation.
+T03 CURRENT TRANSFORMER Installed Not yet connected the cable
110kV to the grounding system,
not yet poured the grouting
for the structure
foundation.
+T03A CURRENT TRANSFORMER Installed Not yet connected the cable
110kV Phase A to the grounding system,
not yet poured the grouting
for the structure
foundation.
+T03B CURRENT TRANSFORMER Installed Not yet connected the cable
110kV Phase B to the grounding system,
not yet poured the grouting
for the structure
foundation.
+T03C CURRENT TRANSFORMER Installed Not yet connected the cable
110kV Phase C to the grounding system,
not yet poured the grouting
for the structure
foundation.
+T04 AUX. TRANSFORMER 1 Installed Not yet connected the cable
10,5/0,4kV to the grounding system,
not yet poured the grouting
for the structure
foundation.
+T05 AUX. TRANSFORMER 2 Owner would like to use
35/0,4kV the existing 35kV system
and would not install this
equipment.
+T32 VOLTAGE TRANSFORMER Installed Not yet connected the cable
110kV (SONG-QUANG) to the grounding system,
not yet poured the grouting
for the structure
foundation.
Page 7
+T32A VOLTAGE TRANSFORMER Installed Not yet connected the cable
110kV Phase A (SONG-QUANG) to the grounding system,
not yet poured the grouting
for the structure
foundation.
+T32B VOLTAGE TRANSFORMER Installed Not yet connected the cable
110kV Phase B (SONG-QUANG) to the grounding system,
not yet poured the grouting
for the structure
foundation.
+T32C VOLTAGE TRANSFORMER Installed Not yet connected the cable
110kV Phase C (SONG-QUANG) to the grounding system,
not yet poured the grouting
for the structure
foundation.
+T33 CURRENT TRANSFORMER Installed Not yet connected the cable
110kV (SONG-QUANG) to the grounding system,
not yet poured the grouting
for the structure
foundation.
+T33A CURRENT TRANSFORMER Installed Not yet connected the cable
110kV Phase A (SONG-QUANG) to the grounding system,
not yet poured the grouting
for the structure
foundation.
+T33B CURRENT TRANSFORMER Installed Not yet connected the cable
110kV Phase B (SONG-QUANG) to the grounding system,
not yet poured the grouting
for the structure
foundation.
+T33C CURRENT TRANSFORMER Installed Not yet connected the cable
110kV Phase C (SONG-QUANG) to the grounding system,
not yet poured the grouting
for the structure
foundation.
+T40 AUX. TRANSFORMER 35/0,4kV
(INTAKE&SPILLWAY)
+X01 POWER TRANSFORMER Installed Not yet connected the cable
CONNECTION BOX to the grounding system.
Page 8
+X02 VOLTAGE TRANSFORMERS Installed Not yet connected the cable
110kV CONNECTION BOX to the grounding system.
+X03 CURRENT TRANSFORMERS Installed Not yet connected the cable
110kV CONNECTION BOX to the grounding system.
+X10 TERMINAL BOX1 GENERATOR Not in the Ingeteam scope
U1 (ACB0)
+X10A TERMINAL BOX2 GENERATOR Not in the Ingeteam scope
U1 (ACB2)
+X10B TERMINAL BOX3 GENERATOR Not in the Ingeteam scope
U1 (ACBH)
+X11 TERMINAL BOX TURBINE U1 Not in the Ingeteam scope
+X11A TERMINAL BOX 1 TURBINE Not in the Ingeteam scope
U1
+X11B TERMINAL BOX 2 TURBINE Not in the Ingeteam scope
U1
+X11C TERMINAL BOX 3 TURBINE Not in the Ingeteam scope
U1
+X11D TERMINAL BOX 4 TURBINE Not in the Ingeteam scope
U1
+X11E TERMINAL BOX 5 TURBINE U1 Not in the Ingeteam scope
+X11F TERMINAL BOX 6 TURBINE U1 Not in the Ingeteam scope
+X12 TERMINAL BOX HYDRAULIC Not in the Ingeteam scope
OIL UNIT 1
+X13 TERMINAL BOX VALVES UNIT 1 Not in the Ingeteam scope
+X14 TERMINAL BOX COOLING Not in the Ingeteam scope
SYSTEM UNIT 1
+X20 TERMINAL BOX GENERATOR Not in the Ingeteam scope
U2 (ACB0)
+X20A TERMINAL BOX2 GENERATOR Not in the Ingeteam scope
U2 (ACB2)
+X20B TERMINAL BOX3 GENERATOR Not in the Ingeteam scope
U2 (ACBH)
+X21 TERMINAL BOX1 TURBINE U2 Not in the Ingeteam scope
+X22 TERMINAL BOX HYDRAULIC Not in the Ingeteam scope
OIL UNIT 2
+X21A TERMINAL BOX 1 TURBINE Not in the Ingeteam scope
U2
+X21B TERMINAL BOX 2 TURBINE Not in the Ingeteam scope
Page 9
U2
+X21C TERMINAL BOX 3 TURBINE Not in the Ingeteam scope
U2
+X21D TERMINAL BOX 4 TURBINE Not in the Ingeteam scope
U2
+X21E TERMINAL BOX 5 TURBINE U2 Not in the Ingeteam scope
+X21F TERMINAL BOX 6 TURBINE U2 Not in the Ingeteam scope
+X23 TERMINAL BOX VALVES UNIT 2 Not in the Ingeteam scope
+X24 TERMINAL BOX COOLING Not in the Ingeteam scope
SYSTEM UNIT 2
+X32 JUNCTION BOX VOLTAGE Installed Not yet connected the cable
TRANSFORMER (SONG-QUANG) to the grounding system.
+X33 JUNCTION BOX CURRENT Installed Not yet connected the cable
TRANSFORMER (SONG-QUANG) to the grounding system.
+S01A DISCONNECTOR 110kV (89L1- Installed Not yet connected the cable
G-1) to the grounding system,
not yet poured the grouting
for the structure
foundation.
+S01B DISCONNECTOR 110kV (89L1- Installed Not yet connected the cable
G-2) to the grounding system,
not yet poured the grouting
for the structure
foundation.
+S31A DISCONNECTOR 110kV (89L2- Installed Not yet connected the cable
G-1) to the grounding system,
not yet poured the grouting
for the structure
foundation.
+S31B DISCONNECTOR 110kV (89L2- Installed Not yet connected the cable
G-2) to the grounding system,
not yet poured the grouting
for the structure
foundation.
+S30A DISCONNECTOR 110kV Installed Not yet connected the cable
(89B2-G-1)
to the grounding system,
not yet poured the grouting
for the structure
Page 10
foundation.
+H20 COOLING SYSTEM UNIT 2 Not in the Ingeteam scope
Grounding system The under ground system
had finished
Cable tray installation Finished
Cable pulling On going
Cable connection On going
Cable testing Not yet started
Progress Table:
Content of works Percentage Total percentage
Cabinet (Take 60% of 84% 50%
works)
Pulling and terminating 60% 18%
cable (Take 30% of works)
Testing (Take 10% of 0% 0%
works)
Total progress 68%
Estimated time to complete all the remaining works: 4.5 weeks at least not including lunar
New Year holidays.
3. Reason of delay schedule.
No comment.
4. Comment about the quality of installation.
Ingeteam has requested contractor and Chau Thon to connect the grounding cables for
installed cabinets to the grounding system, and measured the grounding system’s resistance
to ensure the safety.
5. HSE.
No comment.
6. Conclusion.
Up to now, the installation schedule for the Ingeteam’s equipment and cables is OK.
Chau Thon, 28th Jan 2024
Nguyen Manh Hung
Page 11
PICTURES OF CHECKING/INSPECTION ON
THE SITE
Page 12
Picture 1: Solving the issue with cables termination with generator connection box
Page 13
Picture 2: Contractor pulled the MV cables from Generators G01, G02 to the cabinets A11, A21,
A10, A20
Page 14
Picture 3: Cables termination
Page 15
Picture 4: Cable terminating
Page 16
Picture 5: Checking the terminal at the Diesel Generator
Page 17
Picture 6: Some cables do not have the correctly terminal for connecting at site
Page 18
Picture 7: DC Charger connecting cables
Page 19
Picture 8: MV Cable terminating
Page 20
Picture 9: Song Quang substation conduit installation and pulling cables to the cabinets
Page 21
Picture 10: MV Cables terminating for A10, A20 cabinets
Page 22