PRC 0009 Current
PRC 0009 Current
Engineering Directorate
December 2019
Page 1 of 24
PRC-0009 Rev. E
Page 2 of 24
PRC-0009 Rev. E
REVISIONS
VERSION CHANGES DATE
-- Original version 04/01/1996
A Expanded content throughout. Re-specify qualification 10/29/1997
requirements.
B Formatting changed process owner, rewrite numerous 07/22/1999
sections for clarification, deleted requirement for WIR,
deleted section 8.2 on audits, and added section 8.3 on
WOPQ.
C Add tolerance range to base material component 03/24/2000
thickness(es), remove requirement for certification of
welding inspectors by the AWS, remove NASA/MSFC
reference documents in 4.0, add item 21 to Table 1,
revise 6.1, 7.0, 7.1, 7.3, 8.1, 8.2, and 8.3.
D Routine ISO review. 02/17/2004
Page 3 of 24
PRC-0009 Rev. E
1.0 SCOPE
This process specification provides the requirements that govern the Resistance Spot
Welding (RSW) of battery tabs and component wires/leads to batteries, battery tabs, or
other associated electronic components. Procedural and quality assurance requirements
are given. All work instructions and Weld Procedure Specifications (WPSs) used during
welding shall satisfy the requirements of this process specification and its applicable
documents.
2.0 APPLICABILITY
This process specification applies to the RSW of battery assemblies and associated
electronic flight and non-flight hardware fabricated under the control of the
NASA/Johnson Space Center (JSC). RSW with opposed electrodes (i.e., referred to
herein as "opposed welding") is considered as well as RSW with gapped electrodes (i.e.,
referred to herein as "series welding"). Battery assemblies are considered to be non-
structural with no load carrying capacity and shall be either potted, taped, shrink
wrapped, or installed in a rigid containment to preclude stressing the tabs and lead
wires.
3.0 USAGE
This process specification shall be called out on the engineering drawing by a drawing
note with the following general format:
a) The design of welded joints shall conform to the applicable hardware design
handbooks contained in the Engineering Standards Library.
b) All engineering drawings shall depict welded joints using the applicable symbols
described in AWS A2.4.
c) As required, all engineering drawings shall specify the minimum number and
maximum number of resistance welded spots required for each connection. In any
case, there shall be no less than two weld spots per connection. Connections
which will accommodate only one spot shall be avoided where possible.
Page 4 of 24
PRC-0009 Rev. E
e) When welding occurs onto battery cells, the parts list shall contain the battery
manufacturer, size, model/type no., and voltage rating.
f) The parts list shall contain the tab or contact material, specification, thickness,
width, metallurgical condition (e.g., ¼ hard, ½ hard, etc.) and surface finish as
applicable.
g) The parts list shall contain component leads (i.e., diode leads) gage, material,
and metallurgical condition (e.g., metallurgical, surface finish, etc.) and surface
finish as applicable.
Work instructions shall be generated for implementing this process specification. The
work instructions shall contain sufficient detail to ensure that the manufacturing
process produces consistent, repeatable products that comply with this specification.
At JSC, these work instructions are approved as Detailed Process Instructions (DPls)
that describe in a detailed, step-by-step format the required procedures, equipment,
and materials to be used for conducting a given process.
4.0 REFERENCES
The standards listed below shall be considered a part of this specification to the extent
specified herein. Unless otherwise indicated, the revision that is in effect on the date
of invitation for bids or the date of request for proposals shall apply.
Page 5 of 24
PRC-0009 Rev. E
Materials used in the welding of electronically related flight hardware should meet the
requirements of an applicable material specification unless otherwise specified on a
drawing. An applicable commercial material specification or a manufacturer's material
specification shall be used. Mills test reports {MTRs) are required when purchasing the
nickel battery tab material. The tabs shall be commercially pure nickel alloy made of
either nickel 201 (preferred) or nickel 200.
5.1 EQUIPMENT
The equipment used to produce the welds shall consist of an electrical energy source,
electrodes, and a means of applying mechanical pressure to the materials to be welded.
The power supply shall have an adequate means of controlling and indicating the energy
applied to the weld zone. The power supply shall have means for internal voltage
regulation if there is no such regulation on the primary AC power line source. Regulation
shall be within ±2% for line voltage variations of ±10%. Energy source meters shall have
a minimum accuracy of ±2%.
The welding head shall be of low-inertia design and provide a means of efficiently
controlling electrode force. The electrode force shall be repeatable to within ±5%.
5.1.3 ELECTRODES
Page 6 of 24
PRC-0009 Rev. E
essential variable.
The welding equipment shall be qualified as a system that includes at a minimum, the
power supply, weld head, electrodes, and interconnecting cables. Qualification of a
Welding Procedure Specification also qualifies the system. Otherwise, qualification of a
system shall be per 6.2.2.
Devices used to determine electrode force shall have a minimum accuracy of ±5%.
Page 7 of 24
PRC-0009 Rev. E
gauge and adjusted. For applications where each electrode is controlled individually
(e.g., series welding), the force of each electrode shall be determined and adjusted
individually.
A Welding Procedure Specification (WPS) shall be qualified for each unique weld type to
be produced by conforming to the requirements below, before the production welds are
made. An existing qualified WPS for one unique weld type may be used for a new
engineering drawing provided the resistivity determined during qualification meet the
requirements of the new drawing as applicable, and it is demonstrated that the essential
weld variables will be met. Demonstration shall constitute all the requirements of Section
7.4.2 except that no additional documentation is required (existing PQR and WPS
records shall be acceptable documentation).
The actual welding variables, methods, practices, specific tooling requirements, and test
results used during WPS qualification shall be recorded on a Procedure Qualification
Record (PQR).
Requalification of the WPS shall be required when any of the following conditions exist:
a) The weld system has been placed on a different external power source
except when the power supply has a means for internal power regulation,
b) A WPS is proposed to be used on a weld system or systems other than
that used for the initial qualification,
c) Major maintenance has been performed on the weld system. Major
maintenance includes replacement of the power supply, major repair of the
power supply requiring entrance into the controller or transformer cabinet,
replacement of the weld head, or replacement or change in length by more
than 10% of any of the interconnecting cables,
d) Preproduction weld samples do not meet requirements and no assignable
cause for the failure can be determined.
Requalification may be performed with less total test sample requirements than that
required for an initial qualification for a unique weld type. For requalification, 5 total weld
samples shall be produced and submitted as a lot. All 5 samples shall be subjected to
visual inspection and conductivity and destructive peel testing and shall meet the
applicable requirements specified herein. No requalification specimens from the 5
submitted shall fail any of the requirements as stated herein. Requalification results shall
be documented on a PQR with a specific notation made indicating "requalification". If the
requalification activities result in any welding parameter deviations that exceed the range
specified in Table 1 for that parameter, then the level of testing in 7.4.4 shall be required.
Page 8 of 24
PRC-0009 Rev. E
All essential variables shall be addressed and identified on a qualified WPS and the
supporting PQR. These essential variables are listed in Table 1. Other variables
determined to be essential to maintaining the quality of the process output may be
required to be controlled, as determined by the M&P organization.
(1) Unless the power supply has internally regulated voltage capability .
Page 9 of 24
PRC-0009 Rev. E
7.4.1 GENERAL
All weld specimens shall be visually inspected per 8.3 and tested for electrical
conductivity (resistivity). The resistivity of each connection shall meet the drawing
requirements or if not specified by the drawing, shall measure less than 1.0 𝑚Ω. If
any of the individual samples from those submitted fail to pass the visual or
resistivity requirements, an additional sample shall be allowed to be welded and
submitted to replace it, one time only. If more than 2 samples from the original lot fail
Page 10 of 24
PRC-0009 Rev. E
Fifteen (15) weld samples shall be peel tested. The edges of a spot welded sample
connection shall be gripped and pulled apart to failure. The welded connection (lap
joint) shall be pulled in tension at an approximate 90° angle to the plane of the
faying joint surfaces. See Figure 1. The length of the grip sections on the samples
shall be long enough to preclude any interference of the gripping hardware with the
welded connection. For a procedure qualification or preproduction verification
sample set to be considered acceptable, the result of the peel test must be a plug
pull-out in a minimum of 75% of the total number of individual spots in the sample
set for connections with 4 or more spots, 85% for connections with 3 spots only, and
100% for connections with 2 or less spots. If any of the individual samples from the
15 peel tests fail to result in at least 2 plug pull-outs from the total number of weld
spots on the individual connection, 2 additional welded sample connections may be
welded and submitted for inspection and testing as part of the initial sample set, one
time only. These 2 samples shall then be factored into the above acceptance
criteria. If more than 2 samples from the original lot fail the peel test as described
above, further weld parameter development or process analysis to determine the
cause for the failure(s) is required prior to submitting another 16 samples for testing to
the requirements of this specification. If the minimum plug pull-out requirement for the
total number of individual spots in the sample set (i.e., 75%, 85%, or 100% for the
respective condition) cannot be met as described above, further weld parameter
development or process analysis to determine the cause for the failure is required prior
to submitting another lot of samples for testing to the requirements of this specification.
Page 11 of 24
PRC-0009 Rev. E
Page 12 of 24
PRC-0009 Rev. E
SM is the minimum nugget size (of the welding schedule certification) & t is the
thickness
(1) The welds shall be free of cracks or voids open to any exterior surface.
(2) The penetration shall be 20 - 80 %.
(3) The nugget exhibits no intermittent fusion regions in the weld nugget (regions
where the nickel plate is not part of the weld nugget).
(4) Pores and voids in the nugget (away from the nugget edge) shall be no greater
than 25% of the thickness of the member.
(5) No sharp, notch-like anomalies shall be present near the edge of the weld
nugget. Internal anomalies shall be no closer than 15% of the nugget weld
edge radius.
(6) No anomaly or group of internal anomalies shall be greater than 10% of the
nugget diameter.
(7) The anode weld nugget size must be consistent and the cathode weld
nugget size must be consistent. The weld nugget diameter shall not vary
more than 20% in the metallographic samples (smallest anode weld nugget
is 100% & largest anode weld nugget is ≤120 %, etc.).
(8) The surface indentation shall be no greater than 30% of the member thickness.
The nugget sizes shall be reported in the metallographic report but acceptance of the
nugget size shall be based on the peel tests.
Page 13 of 24
PRC-0009 Rev. E
*Based on Group 2, Class A Resistance Spot Weld Criteria per AWS D17.2
Prior to the start of a production run, a minimum of 1 preproduction weld sample for
each unique type of weld shall be prepared using the appropriate qualified WPS.
Actual batteries and component leads or simulated ones, as described in section
7.4.1, shall be used for this preproduction weld sample. The sample shall be visually
inspected, in accordance with Section 8.3, and peel tested, in accordance with
Section 7.4.4. The preproduction sample shall be made and tested before the welding
of the production welds and under the following conditions:
Page 14 of 24
PRC-0009 Rev. E
Prior to encapsulation, potting, or any process which would preclude inspection of the
welds, all welds and workmanship shall be inspected for conformance to the requirements
of this standard and the engineering drawing. If a nonconformance is identified it shall be
documented appropriately. If the welds of a completed welded module or assembly
cannot be inspected after the assembly is complete, the module or assembly must be
inspected at selected points during assembly to assure inspection of each weld in the
module.
8.3 VISUAL INSPECTION
All welds shall be inspected visually at a magnification of 30X. The welds shall conform
to the following visual inspection criteria:
a) Cracked Weld - Any weld that exhibits a crack in the weld zone shall be rejected.
b) Pitted/Deformed Weld - Any weld that exhibits pits, holes or voids open to the
surface, in either of the materials being shall be rejected. Surface deformation or
upset from electrode contact shall not be considered unless the area in question
exhibits sharp notch like characteristics, severe oxidation due to overheating, or
where either of the elements has been deformed/upset by more than 50% of the
material thickness.
c) Metal Expulsion - Any weld that exhibits metal expulsion where the molten metal
has become separated from the weld area shall be rejected.
d) Electrode Deposit - Significant deposits of the electrode tip being left on the weld
surface shall be rejected. Topical shallow deposits and superficial marks shall not
be considered.
e) Open Weld - An open weld shall be rejected. An open weld is one in which a weld
has been attempted but no bonding has occurred.
f) Missed Weld - Any weld that has been specified on the drawings but has been
overlooked by the welding operator shall be identified and welded to meet the
drawing requirements.
8.4 WELD REPAIRS AND REWORK
Any weld that has been indicated as having a defect (with the exception of an Open Weld
or a Missed Weld) as listed in 8.3, or as not meeting the requirements specified on the
drawing, may be rewelded no more than 1 time at the same location where the original
weld was attempted. An Open or Missed Weld shall be reworked to provide an initial weld
Page 15 of 24
PRC-0009 Rev. E
Any deviations or waivers regarding the use of this process specification shall be
requested in writing by the outside vendor. This request shall be directed to the
NASA/JSC M&P organization with the appropriate justification and rationale. A written
response will be provided upon such a request.
9.1 TRAINING
Resistance spot welding of battery and related electronic assemblies shall be performed
by a welding operator qualified and certified in accordance with NASA/JSC PRC-0009.
Sufficiently detailed records shall be maintained by the manufacturing organization
executing the process(es). These records shall be made available to the NASA/JSC M&P
organization upon request. Minimum requirements for qualification/certification shall be
Page 16 of 24
PRC-0009 Rev. E
10. DEFINITIONS
Process Verification
The WPS, PQR, and WOPQ shall be prepared and retained as a permanent record
and made available upon request to the NASA/JSC M&P organization for review
These procedures must contain, at a minimum, all of the essential welding parameters,
an identification of the welding equipment, and include any pertinent tooling information.
One copy of the WPS shall be maintained in the vicinity of the welding station and shall
be readily accessible by the welders, inspectors, supervision, and/or engineering.
Page 17 of 24
PRC-0009 Rev. E
certifications from the approving organization. The PQR shall be approved by the
responsible M&P organization at the operating facility. Appendix A is an example of a
Procedure Qualification Record however, any format is considered acceptable provided
all the information and data necessary to accurately document the process is made
available and displayed clearly.
Opposed Welding - RSW which utilizes two electrodes positioned exactly opposite,
and in line with each other (electrodes share a common axis). See Figure 5. Each
electrode contacts a single piece of base material. Each weld cycle produces only one
fused spot.
Series Welding - RSW which utilizes two electrodes positioned adjacent to each other
but separated by an air gap or other dielectric. See Figure 5. Each electrode contacts
the same surface of base material. This type of welding is utilized where access to both
sides of the weld joint is physically restricted or if component damage would result if the
welding current were allowed to shunt through the system circuit or electrical
component. Support tooling opposing the force of the electrodes is insulated from the
welding circuit and therefore does not shunt current from the welding circuit. Each weld
cycle produces two fused spots. The electrodes can be positioned parallel or at a fixed
angle to each other.
Unique Weld Type - Those weld joint configurations that differ from one another in any
of the following respects:
Peel Test -A mechanical test in which the corners (or sides) of seam or spot welded
Page 18 of 24
PRC-0009 Rev. E
foil or sheet members are gripped and pulled apart to determine if the joint fails by
delamination, by fracture of a cleaved surface, or by tearing of a button (plug) out of the
parent material. Delamination, in contrast to fracture, is a sign of no fusion between the
two adjacent members. A button or plug, which is pulled out of the removed member, is
not necessarily equal in size to the cast nugget underlying it.
Page 19 of 24
PRC-0009 Rev. E
Appendix A
Resis
Page 20 of 24
PRC-0009 Rev. E
Page 21 of 24
PRC-0009 Rev. E
Page 22 of 24
PRC-0009 Rev. E
Appendix B
Resistance Spot Welding Procedure Qualification Record Page 2
Page 23 of 24
PRC-0009 Rev. E
Page 24 of 24