Msasani Project.
Msasani Project.
1 1
Ensuite
Bedroom 2
1'
2 2
Living room
Bedroom 1
3 3
Balcony
19
18
17
MR HASHAM
13 14 15 P.O.Box ......
DAR ES SALAAM
12
11
A A B C PROPOSED EXTENSION OF APARTMENT BUILDING
10 TO BE BUILT AT BLOCK ... PLOT NO ...
MSASANI - DAR ES SALAAM
9
7
GROUND FLOOR LAYOUT PLAN
GROUND FLOOR PLAN
6
1 1
Ensuite
Bedroom 2
1'
2 2
Living room
Bedroom 1
3 3
Balcony
4 4
19
18
17
13 14 15 MR HASHAM
P.O.Box ......
DAR ES SALAAM
12
11
A A B C
PROPOSED EXTENSION OF APARTMENT BUILDING
10
TO BE BUILT AT BLOCK ... PLOT NO ...
9 MSASANI - DAR ES SALAAM
8
FIRST FLOOR LAYOUT PLAN
7
4
Designed By: Checked By:
3
Drawn By: Scale: As Shown
2
Approved By: Date: April.-2024
1
Contact: Dwg No: 02
A'' A A' B B' C
1 1
Ensuite
M/Bedroom 2
M/Bedroom 1
2 2
3 3
Balcony
4 4
MR HASHAM
P.O.Box ......
DAR ES SALAAM
A A B C
MR HASHAM
P.O.Box ......
DAR ES SALAAM
ELEVATIONS
1 1
F
O
RO
A T
FL
A B
SL
T E
2 RE 2
NC
CO
m
m
150
3 3
Balcony
4 4 MR HASHAM
P.O.Box ......
DAR ES SALAAM
+12.600 +12.600
4 Story 4 Story
+9.450 +9.450
3 Story 3 Story
+6.300 +6.300
2 Story 2 Story
LIVING ROOM
BEDROOM CLOSET
+3.150 +3.150
1 Storey 1 Storey
Skirting
400x400 mm floor tiles finish
40mm cement mortar
SECTION AA
Damp proof mebrane
150mm well compacted earth
foundation by engineering details
Designed By: Checked By:
SECTION AA Drawn By: Scale: As Shown
A A
25mm FOR SLAB
50mm FOR FOUNDATION
F2 F2 B F2
B.S. 666.2000.
12. ALL BLOCKS FOR LOAD BEARING WALLS SHALL HAVE THE
MIN.COMP. STRENGTH OF 10N/m² AT THE AGE OF 28 DAYS.
C1 C1 C1
2 2
F1 F1 F1
C2 C2 C2
3 3
A B C
ISSUED FOR
FOUNDATION PLAN
PERMIT
SECTION A SECTION B
STG-001
GRID GRID
GRID GRID
05 05 SECTION 05-05 10 10 6. THE CONTRACTOR SHALL BE RESPONSIBLE FOR THE DESIGN AND DETAIL OF
ALL CHAIRS ,STOOLS AND TEMPORARY SUPPORT FOR THE REINFORCEMENT.
SECTION 10-10 7. CONCRETE FOR ALL STRUCTURE MEMBER TO BE GADE C25, TO BS 8110
WITH CUBE STRENGTH 25N/M² AND FOR BLINDING GRADE C15.
12. ALL BLOCKS FOR LOAD BEARING WALLS SHALL HAVE THE
MIN.COMP. STRENGTH OF 10N/m² AT THE AGE OF 28 DAYS.
04 04 09 09
SECTION 04-04 SECTION 09-09 GRID
750
1500
GRID
02 02
750
750 750
03 03 08 08
1500
ISSUED FOR
PERMIT
02 02 07 07 GRID
900
1800
GRID
07 07
900
01 01 06 06
STG-002
A B C
1. ALL DIMENSIONS ARE IN mm UNLESS NOTED OTHERWISE
1 1 7.
ALL CHAIRS ,STOOLS AND TEMPORARY SUPPORT FOR THE REINFORCEMENT.
GB03(300x230)
GB03(300x230)
GB03(300x230)
OF BAR UNLESS OTHERWISE NOTED.
12. ALL BLOCKS FOR LOAD BEARING WALLS SHALL HAVE THE
MIN.COMP. STRENGTH OF 10N/m² AT THE AGE OF 28 DAYS.
GB02(300x230)
2 2
GB01(300x230)
3 3
ISSUED FOR
A B C PERMIT
GROUND FLOOR BEAMS LAYOUT PLAN
STG-003
A'' A B C
1. ALL DIMENSIONS ARE IN mm UNLESS NOTED OTHERWISE
FB03(450x230)
FB04(450x230)
FB04(450x230)
10. MIN. LAP SPLICE TO REINFORCING BARS SHALL BE 50xDIA,
150mm THCK 150mm THCK OF BAR UNLESS OTHERWISE NOTED.
12. ALL BLOCKS FOR LOAD BEARING WALLS SHALL HAVE THE
MIN.COMP. STRENGTH OF 10N/m² AT THE AGE OF 28 DAYS.
FB01(450x230)
2 2
FB02(450x230)
3 3
BALCONY
4 4
A'' A B C
ISSUED FOR
PERMIT
FIRST FLOOR BEAMS LAYOUT PLAN
STG-004
A B C
12. ALL BLOCKS FOR LOAD BEARING WALLS SHALL HAVE THE
MIN.COMP. STRENGTH OF 10N/m² AT THE AGE OF 28 DAYS.
SECTION 2
BEAM FB2 - 1 No.
1 2 3 3
3
ISSUED FOR
SECTION
PERMIT
BEAM FB3 - 1 No.
1 2 3
4
FIRST FLOOR BEAM
RC DETAILS
SECTION 4
BEAM FB4 - 2 No.
STG-005
A'' A B C
1. ALL DIMENSIONS ARE IN mm UNLESS NOTED OTHERWISE
12. ALL BLOCKS FOR LOAD BEARING WALLS SHALL HAVE THE
MIN.COMP. STRENGTH OF 10N/m² AT THE AGE OF 28 DAYS.
2 2
3 3
4 4
A'' A B C
ISSUED FOR
TYPICAL
PERMIT
1st ,2nd AND 3rd FLOOR SLAB
BOTTOM REINFORCEMENTS
STG-006
1. ALL DIMENSIONS ARE IN mm UNLESS NOTED OTHERWISE
A'' A B C 2. THIS DRAWING IS TO BE READ IN CONJUNCTION WITH ALL RELEVANT
DRAWINGS AND SPECIFICATIONS. ANY DISCREPANCIES TO BE BROUGHT TO
THE ATTENTION OF THE PROJECT ENGINEER.
12. ALL BLOCKS FOR LOAD BEARING WALLS SHALL HAVE THE
MIN.COMP. STRENGTH OF 10N/m² AT THE AGE OF 28 DAYS.
2 2
3 3
4 4
ISSUED FOR
A'' A B C PERMIT
TYPICAL
1st ,2nd AND 3rd FLOOR SLAB
TOP REINFORCEMENTS
STG-007
A'' A B C
1. ALL DIMENSIONS ARE IN mm UNLESS NOTED OTHERWISE
RB01(450x230)
1 1 5. REINFORCEMENT TO BE HOT ROLLED HIGH YIELD GRADE 460 TYPE 2
DEFORMED BARS TO B.S. 4449:1986 (DESIGNATED T).
RB03(450x230)
RB04(450x230)
RB05(450x230)
150mm THCK 150mm THCK 9. IN. CONCRETE COVER FOR THE REINFORCEMENTS
SHALL BE:- 40mm FOR COLUMN
SLAB SLAB 30mm FOR BEAMS
25mm FOR SLAB
50mm FOR FOUNDATION
RB02(450x230)
3 3
BALCONY
4 4
A'' A B C
ISSUED FOR
PERMIT
STG-008
A'' A B C 1. ALL DIMENSIONS ARE IN mm UNLESS NOTED OTHERWISE
FB03(450x230)
FB04(450x230)
FB05(450x230)
10. MIN. LAP SPLICE TO REINFORCING BARS SHALL BE 50xDIA,
150mm THCK 150mm THCK OF BAR UNLESS OTHERWISE NOTED.
12. ALL BLOCKS FOR LOAD BEARING WALLS SHALL HAVE THE
MIN.COMP. STRENGTH OF 10N/m² AT THE AGE OF 28 DAYS.
FB01(450x230)
2 2
FB02(450x230)
3 3
BALCONY
4 4
ISSUED FOR
A'' A B C
PERMIT
TYPICAL 2nd & 3rd FLOOR BEAMS LAYOUT PLAN
STG-009
A B C 1 2 3
1. ALL DIMENSIONS ARE IN mm UNLESS NOTED OTHERWISE
BEAM FB1 - 2 No. BEAM FB5 - 1 No. 9. IN. CONCRETE COVER FOR THE REINFORCEMENTS
SHALL BE:- 40mm FOR COLUMN
30mm FOR BEAMS
25mm FOR SLAB
50mm FOR FOUNDATION
12. ALL BLOCKS FOR LOAD BEARING WALLS SHALL HAVE THE
MIN.COMP. STRENGTH OF 10N/m² AT THE AGE OF 28 DAYS.
SECTION 6 SECTION 9
BEAM FB2 - 1 No.
1 2 3 3
ISSUED FOR
SECTION 7 PERMIT
BEAM FB3 - 1 No.
1 2 3
8
2nd AND 3rd FLOOR BEAM
RC DETAILS
SECTION 8
BEAM FB4 - 1 No.
STG-010
GRID A''
1. ALL DIMENSIONS ARE IN mm UNLESS NOTED OTHERWISE
2
WITH CUBE STRENGTH 25N/M² AND FOR BLINDING GRADE C15.
3 8.
9.
MAX. SIZE OF AGGREGATE AS FOR ALL CONCRETE WORKS SHALL BE 20mm,
AND WELL GRADED UNLESS OTHERWISE NOTED.
12. ALL BLOCKS FOR LOAD BEARING WALLS SHALL HAVE THE
MIN.COMP. STRENGTH OF 10N/m² AT THE AGE OF 28 DAYS.
A''
A
PLAN VIEW AT FIRST,SECOND
AND THIRD FLOOR
ISSUED FOR
PERMIT
STG-011