VOLUME PONDASI TOWER 394 TYPE DD+0 KELAS 6
PEMBANGUNAN SUTET 275 KV 2CCT QUADRUPLE ZEBRA GITET GUMAWANG - GITET LAMPUNG I (PAKET GGL-01)
0056.PJ/KON.02.01/UIP SUMBAGSEL/2017, TANGGAL 22 DESEMBER 2017
KSO. PT. HASTA PRAJATAMA - PT. SEJAHTERA INTERCON - PT. KMI WIRE AND CABLE TBK
PAD CHIMNEY TIE BEAM BOR PILE t1 t2
p l t t p t p l t d t jmlh Leg 4,00 Unit
8,70 8,70 0,90 1,20 1,20 1,60 14,41 0,30 0,50 0,60 9,90 8,00 0,05 0,10
1 Galian Tanah Biasa (PAD) = 8,70 x 8,70 x 1,95 x 4,00 = 590,38 m³
2 Galian Tanah Biasa (Tie Beam) = 12,59 x 0,30 x 0,35 x 4,00 = 5,29 m³
3 Urugan Pasir = 8,70 x 8,70 x 0,10 x 4,00 = 30,28 m³
Lantai Kerja PAD = 8,70 x 8,70 x 0,05 x 4,00 = 15,14 m³
4
Beton Adukan 1:3:5(B.O),t=5cm Tie Beam = 12,59 x 0,30 x 0,05 x 4,00 = 0,76 m³
Beton K225 = 220,57 m³
a. BorPile = 8,70 x µ x0,28
0,3² x 5,00 x 4,00 = 49,17 m³
6 b. Bottom Pad = 8,70 x 8,70 x 0,50 x 4,00 = 151,38 m³
c. Tie Beam = 12,59 x 0,30 x 0,50 x 4,00 = 7,55 m³
d. Mata Intan = ( 0.75 x 0.75 + 0.15 x 0.15 ) x 0.5 x 0.15 x 4.00 = 0,18 m³
e. Chimney = 1,20 x 1,60 x 1,60 x 4,00 = 12,29 m³
Bekisting = 271,25 m²
a. Bottom Pad = 8,70 x 4,00 x 0,90 x 4,00 = 125,28 m²
7
b. Tie Beam = 4,00 x 0,50 x 14,41 x 4,00 = 115,25 m²
c. Chimney = 1,60 x 4,00 x 1,20 x 4,00 = 30,72 m²
Besi Tulangan' = 39993,72 kg
8 a. Besi Ulir BJTD 32 = Sesuai Pembesian Pondasi = 39.107,43 kg
b. Besi Polos BJTP 24 = Sesuai Pembesian Pondasi = 886,29 kg
9 Urugan Tanah dan Perataan Tanah = (Sama dengan Volume Galian) = 590,38 m³
10 Transport Material Pondasi ke Lokasi Tower = 220,57 + 15,14 = 235,71 m³
Total Kebutuhan Consumable Material untuk 1 Pondasi Tower :
SEMEN BATURAJA : 1744,23 ZAK SOLAR : 294,6 ltr
PASIR : 168,61 m3 PERTALITE : 265,17 ltr
KORAL : 178,16 m3
BESI Ø16 ULIR "LS" : 979,021 batang
BESI Ø19 ULIR "LS" 766,612 batang
BESI Ø13 ULIR "LS" 13,5333 batang
BESI Ø10 POLOS "LS" : 137,451 batang
Triplek 12mm : 26,9097 lembar
Kayu 5/7 : 121,094 batang
Paku 1,5" : 13,3203 kg
Paku 2" : 13,3203 kg
Paku 3" : 13,3203 kg
Bendrat @25kg : 14,2246 roll