Break 1

break down volume 1
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
14 views1 page

Break 1

break down volume 1
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 1

VOLUME PONDASI TOWER 394 TYPE DD+0 KELAS 6

PEMBANGUNAN SUTET 275 KV 2CCT QUADRUPLE ZEBRA GITET GUMAWANG - GITET LAMPUNG I (PAKET GGL-01)
0056.PJ/KON.02.01/UIP SUMBAGSEL/2017, TANGGAL 22 DESEMBER 2017
KSO. PT. HASTA PRAJATAMA - PT. SEJAHTERA INTERCON - PT. KMI WIRE AND CABLE TBK

PAD CHIMNEY TIE BEAM BOR PILE t1 t2


p l t t p t p l t d t jmlh Leg 4,00 Unit
8,70 8,70 0,90 1,20 1,20 1,60 14,41 0,30 0,50 0,60 9,90 8,00 0,05 0,10

1 Galian Tanah Biasa (PAD) = 8,70 x 8,70 x 1,95 x 4,00 = 590,38 m³

2 Galian Tanah Biasa (Tie Beam) = 12,59 x 0,30 x 0,35 x 4,00 = 5,29 m³

3 Urugan Pasir = 8,70 x 8,70 x 0,10 x 4,00 = 30,28 m³

Lantai Kerja PAD = 8,70 x 8,70 x 0,05 x 4,00 = 15,14 m³


4
Beton Adukan 1:3:5(B.O),t=5cm Tie Beam = 12,59 x 0,30 x 0,05 x 4,00 = 0,76 m³

Beton K225 = 220,57 m³

a. BorPile = 8,70 x µ x0,28


0,3² x 5,00 x 4,00 = 49,17 m³

6 b. Bottom Pad = 8,70 x 8,70 x 0,50 x 4,00 = 151,38 m³


c. Tie Beam = 12,59 x 0,30 x 0,50 x 4,00 = 7,55 m³
d. Mata Intan = ( 0.75 x 0.75 + 0.15 x 0.15 ) x 0.5 x 0.15 x 4.00 = 0,18 m³
e. Chimney = 1,20 x 1,60 x 1,60 x 4,00 = 12,29 m³
Bekisting = 271,25 m²
a. Bottom Pad = 8,70 x 4,00 x 0,90 x 4,00 = 125,28 m²
7
b. Tie Beam = 4,00 x 0,50 x 14,41 x 4,00 = 115,25 m²
c. Chimney = 1,60 x 4,00 x 1,20 x 4,00 = 30,72 m²
Besi Tulangan' = 39993,72 kg
8 a. Besi Ulir BJTD 32 = Sesuai Pembesian Pondasi = 39.107,43 kg
b. Besi Polos BJTP 24 = Sesuai Pembesian Pondasi = 886,29 kg

9 Urugan Tanah dan Perataan Tanah = (Sama dengan Volume Galian) = 590,38 m³

10 Transport Material Pondasi ke Lokasi Tower = 220,57 + 15,14 = 235,71 m³

Total Kebutuhan Consumable Material untuk 1 Pondasi Tower :

SEMEN BATURAJA : 1744,23 ZAK SOLAR : 294,6 ltr

PASIR : 168,61 m3 PERTALITE : 265,17 ltr

KORAL : 178,16 m3

BESI Ø16 ULIR "LS" : 979,021 batang

BESI Ø19 ULIR "LS" 766,612 batang

BESI Ø13 ULIR "LS" 13,5333 batang

BESI Ø10 POLOS "LS" : 137,451 batang

Triplek 12mm : 26,9097 lembar

Kayu 5/7 : 121,094 batang

Paku 1,5" : 13,3203 kg

Paku 2" : 13,3203 kg

Paku 3" : 13,3203 kg

Bendrat @25kg : 14,2246 roll