SCHEDULE-A
1 The Site
1.1 Site of the Four-Lane Project Highway shall include the land, buildings, structures
and road works as described in Annex-I of this Schedule-A.
1.2 An inventory of the Site including the land, buildings, structures, road works, trees and
any other immovable property on, or attached to, the Site shall be prepared jointly by the
Authority Representative and the Concessionaire, and such inventory shall form part of
the memorandum referred to in Clause 10.3.1 of the Agreement.
1.3 Additional land required for Toll Plazas, Traffic Aid Posts, Medical Aid Posts and
vehicle rescue posts or for construction of works specified in the Change of Scope Order
issued under Clause 16.2.3 of this Agreement shall be acquired in accordance with
the provisions of Clause 10.3.6 of this Agreement. Upon acquisition, such land shall
form part of the Site and vest in the Authority.
4-laning of Lucknow-Sultanpur section of NH-56 from km 11.500 to km 134.700 in the State of Uttar Pradesh under
NHDP Phase IV through Public Private Partnership (PPP) on Design, Build, Finance, Operate and Transfer (DBFOT)
Toll Basis
National Highways Authority of India Request for Proposal – Bid Document
Volume-III: Schedules
Annex – I
(Schedule-A)
1. Site
The Site of the Four-Lane divided Project Highway comprises the section of National
Highway 56 commencing from Km 11.500 to Km 134.700 i.e. the Lucknow-Sultanpur
section in the State of Uttar Pradesh..
The start point is at km 11.500 of NH 56 and end point of the project is 134.700 of NH 56.
2. Land
The site of the Project Highway comprises the land described below.
4-laning of Lucknow-Sultanpur section of NH-56 from km 11.500 to km 134.700 in the State of Uttar Pradesh under
NHDP Phase IV through Public Private Partnership (PPP) on Design, Build, Finance, Operate and Transfer (DBFOT)
Toll Basis
National Highways Authority of India Request for Proposal – Bid Document
Volume-III: Schedules
3. Carriageway
The present carriageway of the Project Highway is a 2-lane carriageway with paved
shoulders in isolated length. Details of the existing carriageway of the project highway is
given here.
4-laning of Lucknow-Sultanpur section of NH-56 from km 11.500 to km 134.700 in the State of Uttar Pradesh under
NHDP Phase IV through Public Private Partnership (PPP) on Design, Build, Finance, Operate and Transfer (DBFOT)
Toll Basis
National Highways Authority of India Request for Proposal – Bid Document
Volume-III: Schedules
5 46 47 7 1.5 1
6 47 48 7 - 1
7 48 50 7 1.5 2
8 50 52 7 - 2
9 52 63 7 1.5 11
10 63 70 7 - 7
11 70 85 7 1.5 15
12 85 86 7 - 1
13 86 101 7 1.5 15
14 101 102 7 - 1
15 102 117 7 1.5 15
16 117 118 7 - 1
17 118 119 7 1.5 1
18 119 133 7 - 14
19 133 134.70 7 1.5 1.7
Total Length 123.2
4. Major Bridges
The Site includes the following Major Bridges:
Existing Span Type of structure
S. Width
Chainage arrangement Super
No. (m) Foundation Sub structure
(km) (m) structure
Spill Through
PSC T-Beam
1 31+601 9.0 3 x 26.5(m) Well Abutment &
Girder
Circular Pier
Type of structure
Existing Span
S. ROB / Width
Chainage arrangement
No. RUB (m) Sub Super
(km) (m) Foundation
structure structure
NIL
4-laning of Lucknow-Sultanpur section of NH-56 from km 11.500 to km 134.700 in the State of Uttar Pradesh under
NHDP Phase IV through Public Private Partnership (PPP) on Design, Build, Finance, Operate and Transfer (DBFOT)
Toll Basis
National Highways Authority of India Request for Proposal – Bid Document
Volume-III: Schedules
6. Grade Separators
The Site includes the following Grade Separators:
S. Chainage
Type of structure No. of Spans Width (m)
No. km)
Nil
7. Minor Bridges
The Site includes the following Minor Bridges:
4-laning of Lucknow-Sultanpur section of NH-56 from km 11.500 to km 134.700 in the State of Uttar Pradesh under
NHDP Phase IV through Public Private Partnership (PPP) on Design, Build, Finance, Operate and Transfer (DBFOT)
Toll Basis
National Highways Authority of India Request for Proposal – Bid Document
Volume-III: Schedules
The total number of bus bays and truck lay byes on the Project Highway is noted
below:
4-laning of Lucknow-Sultanpur section of NH-56 from km 11.500 to km 134.700 in the State of Uttar Pradesh under
NHDP Phase IV through Public Private Partnership (PPP) on Design, Build, Finance, Operate and Transfer (DBFOT)
Toll Basis
National Highways Authority of India Request for Proposal – Bid Document
Volume-III: Schedules
The Site includes the following permanent bridge/ bypass/ tunnel which was
constructed at the cost noted below:
NIL
4-laning of Lucknow-Sultanpur section of NH-56 from km 11.500 to km 134.700 in the State of Uttar Pradesh under
NHDP Phase IV through Public Private Partnership (PPP) on Design, Build, Finance, Operate and Transfer (DBFOT)
Toll Basis
National Highways Authority of India Request for Proposal – Bid Document
Volume-III: Schedules
4-laning of Lucknow-Sultanpur section of NH-56 from km 11.500 to km 134.700 in the State of Uttar Pradesh under
NHDP Phase IV through Public Private Partnership (PPP) on Design, Build, Finance, Operate and Transfer (DBFOT)
Toll Basis
National Highways Authority of India Request for Proposal – Bid Document
Volume-III: Schedules
4-laning of Lucknow-Sultanpur section of NH-56 from km 11.500 to km 134.700 in the State of Uttar Pradesh under
NHDP Phase IV through Public Private Partnership (PPP) on Design, Build, Finance, Operate and Transfer (DBFOT)
Toll Basis
National Highways Authority of India Request for Proposal – Bid Document
Volume-III: Schedules
4-laning of Lucknow-Sultanpur section of NH-56 from km 11.500 to km 134.700 in the State of Uttar Pradesh under
NHDP Phase IV through Public Private Partnership (PPP) on Design, Build, Finance, Operate and Transfer (DBFOT)
Toll Basis