WORK INSPECTION REQUEST - WIR
Construction of Townhouses & semi-detached Villas
Project Name
(412) for Phase 1B & 1C WIR Ref.No: RHP1P2-BW-TGC-4TV-00-WI-DR-00016
Contract No
Request Submission
Employer Reem Hills Sole-Proprietorship LLC 24-Jun-24
(Date & Time)
PMC Royal Development Company Inspection 25-Jun-24
PMC Royal Architect Project Management (Date & Time ) 11:00AM
Engineer AECOM Middle East LLC Rev No: 0
Main Contractor Trojan General Contracting LLC WIR Submitted By: M/s.TROJAN
MEP Contractor Royal Advance Electro Mechanical Works LLC WIR Submitted To: Consultant-AECOM
Part A: By the Contractor:
B.O.Q Ref: N/A Discipline:
B.O.Q. Description of Works to be inspected and / or tested: General MCC Works
Civil Landscaping
Storm Water Architectural
Description of Works to be inspected and /or tested: Sewer Dredging
Water Highway Bridge Works
Irrigation LRT Bridge Works
Inspection Request for Installation and leak test of Under Telephone MSE Wall
Signal Works Provisional Sum
Ground Drainage Pipes , As per Attached Highlighted Drawing
Electrical Other (state)
Street Lighting
Works Location: Villa-370 4BR (Normal) Landscape Lighting Drainage
Works Quantity: Gas Network
Drawing attached to show the location(s) Yes No Checklist attached Yes No
Attached Test Certificates Yes No
Shop Drawing Ref: PHP1P2-BW-TGC-4TV.M-00-SD-DR-0001 Method Statement Ref: RHP1P2-BW-TGC-ZZ-XX-MS-ME-00002_00
Type of Attachment: Check list ITP Ref: ITP-01-Rev-0
Eng. Dayal Pushpakumar
(QA/QC Manager )
Date & Signature
Part B: By the Engineer:
Received by Engineer on: Date: Time: Signed by:
Engineer's Comments:
1.Separate WIR shall be submitted for the remaining piping upon completion.
2.There is no surveyor marking provided for the outlets (FD/FCO/SD/WC etc.). Instead, verification is done from the
respective grid lines only.
3.All outlets (FD/FCO/WC/SD etc.) shall be matching with the approved tiling layout. The Contractor will remain responsible
for any modification, at no extra time/ cost tothe project, if the piping is not matching as per the latest approved respective
tile layout drawings.
4.The floor drain, floor clean out, WC piping and pipe riser shall be provided at floor penetration with polystyrene or any
other feasible material, for future flexibility.
5.Contractor shall maintain the water within the pipes to ensure that there are no damages occurs during the civil activities
on the site.
6.Branch piping connection from FD to main line, to be laid at max higher level, in sense to avoid reverse flow through floor
trap. Also avoid steep slope in the branch piping.
Name: Date & Signature
Discipline Engineer Decision:
A - Approved
25-06-2024
B - Approved with comments
C - Revise & Resubmit
D - Rejected
Sr.Resident Engineer / Resident Engineer :
Name : Suheib Aboamir 26/06/2024 Date & Signature