Custody Transfer Measurement Systems For Gases and Vapours: Dep Specification
Custody Transfer Measurement Systems For Gases and Vapours: Dep Specification
DEP 32.32.00.12-Gen.
February 2013
ECCN EAR99
This document contains information that is classified as EAR99 and, as a consequence, can neither be exported nor re-exported to any country which is under an
embargo of the U.S. government pursuant to Part 746 of the Export Administration Regulations (15 C.F.R. Part 746) nor can be made available to any national of such
country. In addition, the information in this document cannot be exported nor re-exported to an end-user or for an end-use that is prohibited by Part 744 of the Export
Administration Regulations (15 C.F.R. Part 744).
ECCN EAR99 DEP 32.32.00.12-Gen.
February 2013
Page 2
PREFACE
DEP (Design and Engineering Practice) publications reflect the views, at the time of publication, of Shell Global Solutions
International B.V. (Shell GSI) and, in some cases, of other Shell Companies.
These views are based on the experience acquired during involvement with the design, construction, operation and
maintenance of processing units and facilities. Where deemed appropriate DEPs are based on, or reference international,
regional, national and industry standards.
The objective is to set the standard for good design and engineering practice to be applied by Shell companies in oil and
gas production, oil refining, gas handling, gasification, chemical processing, or any other such facility, and thereby to help
achieve maximum technical and economic benefit from standardization.
The information set forth in these publications is provided to Shell companies for their consideration and decision to
implement. This is of particular importance where DEPs may not cover every requirement or diversity of condition at each
locality. The system of DEPs is expected to be sufficiently flexible to allow individual Operating Units to adapt the
information set forth in DEPs to their own environment and requirements.
When Contractors or Manufacturers/Suppliers use DEPs, they shall be solely responsible for such use, including the
quality of their work and the attainment of the required design and engineering standards. In particular, for those
requirements not specifically covered, the Principal will typically expect them to follow those design and engineering
practices that will achieve at least the same level of integrity as reflected in the DEPs. If in doubt, the Contractor or
Manufacturer/Supplier shall, without detracting from his own responsibility, consult the Principal.
The right to obtain and to use DEPs is restricted, and is typically granted by Shell GSI (and in some cases by other Shell
Companies) under a Service Agreement or a License Agreement. This right is granted primarily to Shell companies and
other companies receiving technical advice and services from Shell GSI or another Shell Company. Consequently, three
categories of users of DEPs can be distinguished:
1) Operating Units having a Service Agreement with Shell GSI or another Shell Company. The use of DEPs by these
Operating Units is subject in all respects to the terms and conditions of the relevant Service Agreement.
2) Other parties who are authorised to use DEPs subject to appropriate contractual arrangements (whether as part of
a Service Agreement or otherwise).
3) Contractors/subcontractors and Manufacturers/Suppliers under a contract with users referred to under 1) or 2)
which requires that tenders for projects, materials supplied or - generally - work performed on behalf of the said
users comply with the relevant standards.
Subject to any particular terms and conditions as may be set forth in specific agreements with users, Shell GSI disclaims
any liability of whatsoever nature for any damage (including injury or death) suffered by any company or person
whomsoever as a result of or in connection with the use, application or implementation of any DEP, combination of DEPs
or any part thereof, even if it is wholly or partly caused by negligence on the part of Shell GSI or other Shell Company. The
benefit of this disclaimer shall inure in all respects to Shell GSI and/or any Shell Company, or companies affiliated to these
companies, that may issue DEPs or advise or require the use of DEPs.
Without prejudice to any specific terms in respect of confidentiality under relevant contractual arrangements, DEPs shall
not, without the prior written consent of Shell GSI, be disclosed by users to any company or person whomsoever and the
DEPs shall be used exclusively for the purpose for which they have been provided to the user. They shall be returned after
use, including any copies which shall only be made by users with the express prior written consent of Shell GSI. The
copyright of DEPs vests in Shell Group of companies. Users shall arrange for DEPs to be held in safe custody and Shell
GSI may at any time require information satisfactory to them in order to ascertain how users implement this requirement.
All administrative queries should be directed to the DEP Administrator in Shell GSI.
ECCN EAR99 DEP 32.32.00.12-Gen.
February 2013
Page 3
TABLE OF CONTENTS
1. INTRODUCTION ........................................................................................................ 5
1.1 SCOPE........................................................................................................................ 5
1.2 DISTRIBUTION, INTENDED USE AND REGULATORY CONSIDERATIONS ......... 5
1.3 DEFINITIONS ............................................................................................................. 5
1.4 CROSS-REFERENCES ............................................................................................. 7
1.5 SUMMARY OF MAIN CHANGES ............................................................................... 8
1.6 COMMENTS ON THIS DEP ....................................................................................... 8
1.7 DUAL UNITS ............................................................................................................... 8
2. COMMON SYSTEM REQUIREMENTS ..................................................................... 9
2.1 INTRODUCTION ........................................................................................................ 9
2.2 REQUIREMENT HIERARCHY ................................................................................... 9
2.3 AGREEMENTS ........................................................................................................... 9
2.4 MEASUREMENT STANDARD SELECTION.............................................................. 9
2.5 ENGINEERING UNITS ............................................................................................... 9
2.6 BASE CONDITIONS ................................................................................................. 10
2.7 RESPONSIBILITIES ................................................................................................. 10
3. SYSTEM DESIGN .................................................................................................... 11
3.1 INTRODUCTION ...................................................................................................... 11
3.2 APPROVALS ............................................................................................................ 11
3.3 MEASUREMENT UNCERTAINTY ........................................................................... 12
3.4 GENERAL DESIGN REQUIREMENTS .................................................................... 12
3.5 SYSTEM AVAILABILITY........................................................................................... 13
3.6 RANGEABILITY ........................................................................................................ 14
3.7 TRACEABILITY ........................................................................................................ 15
3.8 DEVICE VALIDATION CAPABILITY ........................................................................ 15
3.9 OPERATING ENVELOPE ........................................................................................ 16
3.10 MATERIALS .............................................................................................................. 16
3.11 ELECTRICAL ............................................................................................................ 17
3.12 ENVIRONMENTAL PROTECTION .......................................................................... 18
3.13 SKID, STRUCTURAL AND BASEPLATE................................................................. 18
3.14 PIPING AND VALVING ............................................................................................. 19
3.15 FLOW CONDITIONING ............................................................................................ 21
3.16 STRAINERS.............................................................................................................. 21
3.17 FLUID COMPOSITION DETERMINATION .............................................................. 22
3.18 COMPUTATIONAL DEVICES .................................................................................. 23
4. SPECIFIC APPLICATION REQUIREMENTS .......................................................... 23
4.1 MASS MEASUREMENT ........................................................................................... 23
4.2 VOLUMETRIC MEASUREMENT ............................................................................. 24
4.3 ENERGY MEASUREMENT ...................................................................................... 24
5. METER REQUIREMENTS ....................................................................................... 25
5.1 GENERAL REQUIREMENTS ................................................................................... 25
5.2 MULTI-PATH ULTRASONIC METERS .................................................................... 25
5.3 CORIOLIS METERS ................................................................................................. 26
5.4 ORIFICE METERS ................................................................................................... 27
5.5 TURBINE METERS .................................................................................................. 28
5.6 VENTURI METERS .................................................................................................. 28
6. SECONDARY INSTRUMENTS ................................................................................ 29
6.1 INTRODUCTION ...................................................................................................... 29
6.2 TEMPERATURE ....................................................................................................... 29
6.3 PRESSURE .............................................................................................................. 29
6.4 QUALITY MEASUREMENT INSTRUMENTS .......................................................... 30
7. COMPUTATIONAL DEVICES.................................................................................. 31
7.1 GENERAL REQUIREMENTS ................................................................................... 31
7.2 COMPUTATIONS ..................................................................................................... 31
ECCN EAR99 DEP 32.32.00.12-Gen.
February 2013
Page 4
APPENDICES
APPENDIX A BLACK AND WHITE LIST .............................................................................. 45
APPENDIX B COMMON ENGINEERING UNITS .................................................................. 50
APPENDIX C BASE CONDITIONS ....................................................................................... 51
APPENDIX D TYPICAL SINGLE METER RUN CTM GAS APPLICATION EXAMPLE ....... 52
APPENDIX E ANALYTICAL METHODS ............................................................................... 53
APPENDIX F “Z” MASTER METER CONFIGURATION EXAMPLE ................................... 54
APPENDIX G LINING UP OF DENSITOMETERS IN ORIFICE METER RUNS
(POCKET STYLE) ........................................................................................... 55
APPENDIX H THERMAL INSULATION FOR DENSITOMETERS AND
TEMPERATURE SENSORS ........................................................................... 56
APPENDIX I FLOW COMPUTATION TYPICAL EXAMPLES ............................................. 57
APPENDIX J EXAMPLE OF MEASUREMENT SYSTEM ARCHITECTURE....................... 59
APPENDIX K DATA ACQUISITION AND CONTROL ARCHITECTURE ............................. 60
APPENDIX L FLOW COMPUTER DETAILED REQUIREMENTS ....................................... 61
APPENDIX M TYPICAL MULTI METER RUN WITH MASTER METER ............................... 63
ECCN EAR99 DEP 32.32.00.12-Gen.
February 2013
Page 5
1. INTRODUCTION
1.1 SCOPE
This DEP specifies requirements and gives recommendations for the design, fabrication,
installation and commissioning of custody transfer measurement systems. Application of
this DEP is limited to single phase homogenous fluids, which are gases or vapours at the
measurement conditions such as natural gas, steam and hydrogen.
Custody transfer measurement systems associated with pipeline receipt or delivery
applications are included in the scope of this DEP. Custody transfer measurement systems
at the retail level of trade (e.g., residential gas meters) are outside the scope of this DEP.
LNG custody transfer measurement is also outside the scope of this DEP, see
DEP 32.32.00.11-Gen.
Metering requirements associated with allocation meters upstream of the natural gas
custody transfer meters are outside the scope of this DEP, see DEP 32.00.00.12-Gen.
This DEP encompasses mass, volumetric and energy measurement.
This DEP shall be used in conjunction with requisition sheet DEP 32.32.00.95-Gen.
This is a revision of the DEP of the same number dated September 2007; see (1.5)
regarding the changes.
1.3 DEFINITIONS
1.3.1 General definitions
The Contractor is the party that carries out all or part of the design, engineering,
procurement, construction, commissioning or management of a project or operation of a
facility. The Principal may undertake all or part of the duties of the Contractor.
The Manufacturer/Supplier is the party that manufactures or supplies equipment and
services to perform the duties specified by the Contractor.
The Principal is the party that initiates the project and ultimately pays for it. The Principal
may also include an agent or consultant authorised to act for, and on behalf of, the
Principal.
The word shall indicates a requirement.
The word should indicates a recommendation.
ECCN EAR99 DEP 32.32.00.12-Gen.
February 2013
Page 6
Term Definition
Base Standard reference, base or standard conditions; henceforth, base
Conditions conditions are the reference conditions of temperature and pressure to
which measured volumes are to be corrected for reporting purposes. See
(2.6) and (Appendix C) for details.
Custody Custody transfer measurement provides highest accuracy quantity and
Transfer quality information used for the physical and fiscal documentation of a
change in ownership and/or a change in responsibility for feed stocks, fuel,
products, etc. Synonymous with fiscal measurement, with the exclusion of
government implications such as taxation and royalties.
Fiscal Measurement pertaining to government income and revenues such as
Measurement taxation and royalties.
Validation In jurisdictions where API MPMS terminology is utilized, measurement
equipment performance assurance is denoted by the terms verification
(i.e., assessment of the as-found state of the device relative to a reference
standard) and calibration (i.e., device output adjustment to conform to
reference standard value).
In jurisdictions where OIML/ISO terminology is utilized, measurement
equipment performance assurance is denoted by the terms calibration (i.e.,
verification as defined above) and adjustment (i.e., calibration as defined
above).
In this DEP, the term “validation” shall be used to denote the process of
verification followed by calibration if required.
Meter validation is typically termed meter proving.
Master Meter A meter of comparable or lower uncertainty used to verify/calibrate a
custody transfer meter.
N+1 Number of required runs plus spare.
Pay and A redundant measurement system whereby one system produces the fiscal
Check data and the other checks the outcome of the previous.
Reference Reference conditions are a specified temperature and pressure at which
Conditions physicals properties or volumes are reported. See (2.6) and (Appendix C)
for details.
1.3.3 Abbreviations
Term Definition
AGA American Gas Association
AMS Asset Management System
API American Petroleum Institute
ATEX European Union directives describing explosive atmosphere equipment
requirements
BIPM Bureau International des Poids et Mesures
BPCS Basic Process Control System
CCR Central Control Room
CSA Canadian Standards Association
CTM Custody Transfer Measurement
D Nominal Pipe Internal Diameter
ECCN EAR99 DEP 32.32.00.12-Gen.
February 2013
Page 7
Term Definition
DB&B Double block and bleed
FAT Factory Acceptance Test
TM
FF FOUNDATION FIELDBUS
FGS Fire and Gas System
GC Gas Chromatograph
GPA Gas Processors Association
HART® Highway Addressable Remote Transducer
HPIMS Hydrocarbon Production Information Management System
HFE Human Factors Engineering
IAPWS International Association for the Properties of Water and Steam
IPS Instrument Protective System
ISO International Organization for Standardization
IUPAC International Union of Pure and Applied Chemistry
LCR Local Control Room
MESC Materials, Equipment, Standards and Code
MID European Measuring Instruments Directive
MPMS API Manual of Petroleum Measurement Standards
NDI Non-Destructive Inspection
NIST National Institute of Standards and Technology
NMI National Metrology Institute
NPL National Physical Laboratory
NTEP National Type Evaluation Program
PEFS Process Engineering Flow Scheme (i.e., P&ID)
P&ID Piping and Instrumentation Diagram (i.e., PEFS)
QMI Quality Measurement Instrument
RTD Resistance Temperature Detector
PLC Programmable Logic Controller
SAT Site Acceptance Test
SCADA Supervisory Control and Data Acquisition
STP IUPAC Standard Temperature and Pressure
TCoO Total Cost of Ownership
UL Underwriters Laboratories Inc.
1.4 CROSS-REFERENCES
Where cross-references to other parts of this DEP are made, the referenced section
number is shown in brackets ( ). Other documents referenced by this DEP are listed in (14).
ECCN EAR99 DEP 32.32.00.12-Gen.
February 2013
Page 8
Section Change
All Major DEP revision to include fluids other than natural gas and
North American measurement standards.
Document was restructured to harmonize with DEP for custody
transfer measurement of liquids.
All run and maintain activities, which are outside the scope of a
DEP Specification, were removed.
Feedback that has been registered in the DEP Feedback System by using one of the above
options will be reviewed by the DEP Custodian for potential improvements to the DEP.
2.1 INTRODUCTION
Custody transfer measurement systems are designed to provide accurate, equitable and
reliable measurements. This is achieved by pre-establishing and then meeting the
regulatory, contractual and the Principal’s requirements. This mitigates the risk of breach of
contract, financial loss or non-compliance. The use of industry measurement standards lays
the foundation for appropriate custody transfer measurement system design.
2.3 AGREEMENTS
The measurement sections of contracts (e.g., tariffs, connection agreements, sales and
purchase agreements) should refer to general custody transfer measurement requirements.
Measurement requirements should be expanded in an addendum (i.e., exhibit, attachment)
to the contract thus avoiding undue revision of the contract if only technical requirements
change. Measurement details such as procedures and measurement uncertainty
calculations should be addressed in a Measurement Manual. The “Black and White List”
(Appendix A) should be reviewed when preparing the contract.
2.7 RESPONSIBILITIES
The Contractor’s scope of work shall include system design, equipment selection, and
documentation of the measurement system and oversight of the Supplier. The Supplier’s
scope of work shall include fabrication, inspection, testing, delivery, and the initial
calibration of the complete gas metering system.
The Contractor shall assume full system responsibility. This means that the Contractor shall
have, as a minimum, single point responsibility for the following:
a) designing the custody transfer measurement system in accordance with this DEP
and all applicable codes and standards,
b) the operability, accuracy and quality of all components including those of sub-
suppliers,
c) obtaining written approvals from the Principal, regulatory authorities and all
interested parties for the design prior to procurement and fabrication,
d) all performance based testing,
e) obtaining all permits, certifications and calibrations (e.g., meters),
f) demonstrating satisfactory system performance via a FAT, SAT and site
commissioning,
g) timely notification of upcoming shop and field testing to permit witnessing (Principal,
authorities, interested parties),
h) providing appropriate documentation,
i) fabrication, delivery and installation oversight.
The Supplier shall prepare a preliminary design with appropriate documentation (13.2) for
approval by the Principal in writing prior to equipment procurement.
Where applicable, the Supplier shall be required to liaise with the main data acquisition
system Supplier (to be advised by the Principal) to arrange the data links and protocols
necessary for monitoring and control of the metering system and the data transfer required
for accounting purposes.
The Supplier shall immediately inform the Contractor and the Principal if there is doubt
regarding the specified requirements. The Supplier shall not proceed with any aspect of the
work until the Principal gives the necessary written approval.
ECCN EAR99 DEP 32.32.00.12-Gen.
February 2013
Page 11
3. SYSTEM DESIGN
3.1 INTRODUCTION
The measurement system shall be designed to meet all applicable agreements, codes and
standards using field proven methods and devices (i.e., no prototypes). Products shall be
technically qualified to the satisfaction of the Principal and shall be sourced from
Manufacturers acceptable to the Principal.
NOTE: For this purpose, Shell Companies may use the list of Technically Acceptable Manufacturers and
Products (i.e., TAMAP) maintained by Shell.
The total life cycle costs of ownership (TCoO) of the measurement station shall be
optimised against the requirements stated below. A method for calculating the TCoO is
given in DEP 32.31.09.31-Gen.
Prior to the design of custody transfer measurement systems, the following shall be defined
and documented (13):
a) target uncertainty for measurement system,
b) applicable codes, regulations, agreements and standards,
c) ownership of measurement equipment,
d) responsible party for measurement system,
e) measurement basis (mass, volume or energy),
f) acceptable flow meter types,
g) range of process conditions (e.g., fluid types, fluid contaminants, density,
pressures, temperatures, flow rate range, etc.),
h) acceptable validation techniques (e.g., in-situ or remote),
i) base conditions for volumetric techniques,
j) target system availability,
k) third party data transfer connection requirements,
l) engineering units,
m) fluid quality specifications.
n) rangeability factor (3.6), and,
o) measurement system operational control philosophy (consistent with the facility
operational control philosophy).
Selecting the industry measurement standards to be applied in combination with defining
what validation techniques are to be applied will largely determine the potential
measurement uncertainty (3.3).
Where applicable (2.2), the requirements of OIML R140 shall apply.
3.2 APPROVALS
Custody transfer metering installations are usually subject to approval by local authorities or
other interested parties (e.g., JV partners, other producers or refiners, pipeline companies).
These approvals typically extend from the design stage through to final installation and
eventually to the operating stage. Those authorities/interested parties shall be consulted at
the earliest possible stage and thereafter, in order to gain acceptance of the metering
philosophy, approval of the system design (where required) and to simplify final approval of
the installation.
In some cases, local authorities require that devices (e.g., meters, flow computers,
transmitters) have individual approvals (e.g., NMI, NTEP or other Notified Bodies).
ECCN EAR99 DEP 32.32.00.12-Gen.
February 2013
Page 12
However, the fact that a device has such an approval does not negate the necessity to
ensure the devices’ suitability for the application under consideration.
The preliminary design shall be submitted to the Principal for approval prior to detailed
engineering (2.7).
For meters which are to be calibrated elsewhere, provision shall be made to permit removal
of the meter run without disassembly (i.e., transport meter, upstream and downstream
straight pipe lengths including flow conditioner without unbolting).
Note: Local safety requirements regard lifting of equipment should be taken into account in the design (e.g.,
potential lifting above pressurized lines).
Where required, meter runs shall be thermally insulated in order to reduce heat transfer
from ambient via the piping to avoid hydrocarbon or water condensation and temperature
stratification at low gas flow rates. For volumetric measurements, the length of the insulated
section shall at least satisfy the straight length requirements and shall include the
temperature element and the primary device.
A typical meter run flow scheme for a custody transfer application is illustrated in
(Appendix D) while a redundant custody transfer measurement system architecture is
illustrated in (Appendix I) and (Appendix J). The examples presented in these two
appendices detail a “highly” redundant system whereas typical designs need only meet the
availability requirements detailed in (3.5).
The design shall meet the process control domain security requirements as detailed in
DEP 32.01.20.12-Gen.
3.5 SYSTEM AVAILABILITY
The required system availability and rangeability shall be defined prior to design and
specified in DEP 32.32.00.95-Gen. The design shall incorporate the degree of redundancy
to meet the defined system availability considering the documented reliability of the system
components and subsystems based on the Principal’s experience with similar devices or
Manufacturer’s reliability data. Local availability of spares and expertise to repair equipment
failures in a timely manner shall be considered a part of the availability assessment as well
as continuity of supply.
Subject to (2.2), redundancy computations shall consider any allowance for brief outages or
flow reductions in multi meter designs to accommodate the replacement of faulty
components or for the purposes of verification and/or calibration. In such circumstances,
the maximum flow rate through any of the remaining meters shall not exceed their
calibrated range.
Redundancy shall cover the following elements as a minimum:
a) the meters.
b) the power supply of the measurement system. The means of back up shall be by
UPS.
c) pressure and temperature measurements (where applicable) and for differential
producers the differential pressure measurements.
d) the flow computer and its ticket printer, the latter if installed to meet legal
requirements.
e) In some cases legislation may require a turbine meter to be equipped with a
mechanical counter.
f) on-line measurements of fluid properties or samplers. Redundancy does not require
diverse physical property measurements.
Appendices I.1 and M illustrate an all encompassing degree of redundancy including
diverse measurement techniques (e.g., density and GC analyzers). This degree of
redundancy is not normally required. However, the unavailability of a single component of
the custody gas measurement system due to failure or maintenance shall result neither in
the interruption of ongoing measurements nor in the loss or invalidation of contractually
required data.
When high (> 99 %) availability is required, the metering system shall be arranged in such
a way that a single device failure does not result in a complete loss of measurement. This
means that:
ECCN EAR99 DEP 32.32.00.12-Gen.
February 2013
Page 14
a) The power supply of the measuring station up to and including the field
instrumentation shall be redundant. However, failure of the power supply in
combination with a failure of the back-up supply need not be assumed in the design.
NOTE: The autonomy time (the specified time that the battery shall be capable of supplying rated
current to the load within the specified voltage limits) of the UPS shall fulfil project
requirements. UPS is required for bridging power outages of short duration and for the safe
shutdown of the metering station in the event of a total power shut down.
3.6 RANGEABILITY
The design capacity of the metering system is determined by the maximum flow rate that
can be measured at the required uncertainty (excluding any spare meter runs provided for
reliability purposes).
The minimum design capacity is the minimum flow rate of the smallest single meter run at
the required uncertainty.
Minimum and maximum flow rate design shall consider the limitations of all components
such as the meter, flow conditioner, filter, etc. The system design shall incorporate
sufficient parallel meter runs to:
• permit the maximum and minimum system flow rates to be measured at the specified
uncertainty,
• achieve the specified availability including validation exercises when one of the
meter runs is removed for validation.
Where required by agreement or regulation, provision shall be made to stop the flow at
rates below a preset minimum value (e.g., the lowest flow calibration point of the flow meter
as specified at the metrological certificate or where uncertainty cannot be met).
ECCN EAR99 DEP 32.32.00.12-Gen.
February 2013
Page 15
When determining the maximum flow rate required, peak as well as average flow rates
shall be considered.
NOTE: For example, if gas flow rates vary significantly (e.g., in response to power demand), the average daily
throughput of a meter station would not represent the peak hourly meter flow rate.
3.7 TRACEABILITY
The system shall be designed in a manner to permit traceability to the required national
metrological standards. At the design stage, this requires:
• selecting equipment types that are traceable, and,
• providing appropriate means (e.g., access, process taps, sample points) for the
required field verifications and calibrations.
The equipment used for determining fluid and process properties shall be traceable to
national and international standards through a system of analytical procedures, reference
materials, sampling and calibration procedures (3.8.2).
3.10 MATERIALS
All pressure retaining components such as piping, valves, strainers, and meter bodies shall
comply with the piping classes specified in DEP 32.32.00.95-Gen. and with requirements of
DEP 31.38.01.11-Gen., DEP 31.38.01.12-Gen., DEP 31.38.01.15-Gen. and
DEP 39.01.10.11-Gen.
ECCN EAR99 DEP 32.32.00.12-Gen.
February 2013
Page 17
3.11 ELECTRICAL
All electrical devices shall be approved (e.g., ATEX, CSA, UL) and so marked for the area
classification and jurisdiction in which they are to be installed. See DEP 32.31.00.32-Gen.,
Section 2.5 for electrical certification requirements.
3.11.1 Measurement device outputs
In addition to the primary element signals (3.11.2) and secondary instrument signals
(3.11.3), all measurement devices shall output a fault condition (3.11.4).
Where available, device diagnostics shall be provided.
With the exception of communications downstream of the flow computer, wireless shall not
be utilized in custody transfer measurement systems.
Barriers to achieve intrinsically safe designs shall not be utilized for measurement device
analog outputs.
For custody transfer measurement devices, meter wiring design shall utilize a minimum
number of connections (e.g., junction boxes). Continuous conductors shall be utilized
between field devices and the skid junction box and between the skid junction box and the
computational device. Other wiring practices are as per DEP 32.31.00.32-Gen.
3.11.2 Primary element outputs
The primary output of linear meters shall be pulses where each pulse represents a discrete
volume or mass. Specifically, analog signals (e.g., 4-20 mA) or digital communications
TM
such as FOUNDATION FIELDBUS (FF) shall not be utilized as the primary output for
linear custody transfer meters.
3.11.3 Secondary device signals
Where practical and provided compatibility has been proven through interoperability testing
between transmitter and flow computer, secondary instruments such as static pressure,
differential pressure, temperature and QMIs should utilize a digital communications such as
FF. With the exception of gas chromatographs, Modbus shall not be used for secondary
device signals. Where digital communications are not practical, analogue outputs shall be
4-20 mA.
The square root function of differential pressure meters shall be applied in the computing
device.
Temperature measurements may utilize one of the following:
• a fully characterized temperature transmitter combined with an RTD, or,
• 4 wire RTDs interfaced directly to the computing device (i.e., avoid temperature
transmitters).
3.11.4 Diagnostics/fault signals
In addition to the required measurement output, where practical measurement devices shall
output common (i.e., grouped) warning and fault status signals to the BPCS or SCADA.
Detailed diagnostic capability/screens shall be provided by equipment specific software and
need not be programmed into the BPCS or SCADA.
The fault status may be transmitted utilizing a set of dry contacts, over/under range analog
signals or via a digital protocol such as Modbus or digital communications such as FF.
Fault status via analog 4-20 mA type output signals shall comply with NAMUR NE-43
recommended values for abnormal signal levels. In such designs the computational device
inputs shall also comply with NAMUR NE-43. The field device shall not drive the signal
through the alarm condition to reach the fault condition value.
ECCN EAR99 DEP 32.32.00.12-Gen.
February 2013
Page 18
Contacts used for fault status shall be normally closed, open on fault detection and shall be
self resetting.
Measurement systems shall be designed to provide the capability to connect to field and
flow computation devices digitally (e.g., Modbus over Ethernet) for the purpose of
performance validation and troubleshooting utilizing fit for purpose software.
Where asset management systems are employed, the analogue output devices (i.e.,
transmitters) shall be HART® or FF compatible to enable enhanced diagnostic data to be
collected. The associated analogue input modules shall support HART® or FF without the
need for additional hardware.
Subject to (2.2) the action upon device fault detection shall be documented (e.g., decision
matrix in measurement manual or control narrative).
Single body, full port type rotating plug valves are preferred for DB&B service.
The bleed port of DB&B valves shall allow visual or electronic means of seal verification.
Unless required for HSSE reasons, vent valve connections through which leakage is clearly
visible do not require DB&B valves.
Facilities shall be designed to minimize hard-piped pressure relief and vent connections
through which flow would cause measurement error. If hard piped relief, vent or DB&B
bleed connections are necessary, the outlet of potential bypasses shall be continuously
monitored.
If vents, drains, and relief valves that discharge to the downstream side of the flow meter
absolutely cannot be avoided, associated discharge lines shall include a visual or electronic
means of determining leakage.
3.14.2 Thermal relief
Thermal expansion relief valves are required in liquid-full systems if the system can be
blocked in and subjected to heat input from atmosphere or process. For the application of
thermal expansion relief valves, see DEP 80.45.10.11-Gen.
In no case shall a thermal or pressure relief valve be located between the meter and the
check or master meter or between the sampling system and meter.
3.14.3 Master meter
Check or master meter valving/manifolds shall be provided for applications requiring in-situ
validations.
Master meter valving/manifolds shall be:
• sized to allow meter validation over the full operating range expected for the meter.
• be located downstream of the flow meters.
Where in-situ meter validation is required, DB&B valves shall be provided as follows:
• as the meter run validation bypass (i.e., divert) valve to divert the flow through the
master meter for a single meter run application,
• as the meter run validation bypass (i.e., divert) valve to divert the flow to the meter
validation supply header for a multi meter run application, and,
• to isolate individual meter runs from the validation supply header when validating
other meters,
• to isolate individual meter runs the validation return header when validating other
meters.
3.14.4 Flow control valves
Flow control valves shall be utilized where required to control the flow rate through a meter
to ensure the measured flow rate is within the calibrated portion of the meter range.
Flow control valves are normally not required for single meter run applications. For multi-
run flow measurement systems, one flow control valve shall be provided per meter run to
balance flow rates during operation and when performing meter validations (where
applicable).
Flow control valves associated with meter runs shall be installed outside the downstream
straight length required by a meter (i.e., typically 5D downstream).
Flow control valves shall be selected, sized and installed as per the requirements of
DEP 32.36.01.17-Gen.
ECCN EAR99 DEP 32.32.00.12-Gen.
February 2013
Page 21
Straight run lengths shall be as per the most stringent of the local authority or as per
Industry standard. For CTM applications for which the straight length requirements are not
defined by local authority or industry standard, the Manufacturer’s straight length
recommendations are acceptable provided the Manufacturer supplies supporting test data
to substantiate the recommendations.
Meter applications without the provision for in-situ verifications (e.g., master meters) shall
be provided with a perforated plate type flow conditioner installed according to the
Manufacturer’s recommendations. Exceptions to this requirement are orifice meters and
meters which are not sensitive to upstream piping disturbances such as Coriolis meters and
where the operating and calibration upstream piping configurations meet the minimum
straight requirements of the applicable standard.
Tube bundle style flow conditioners including those referenced in ISO 9951 or AGA 7 shall
not be utilized.
For meters sensitive to flow profile disturbances, the upstream and downstream meter runs
shall be free of protruding gaskets, weld beads, etc.
Eccentric pipe reducers shall not be utilized upstream or downstream of meters sensitive to
flow profile disturbances.
The straight length/flow conditioner requirements stated above do not apply to meters
insensitive to upstream flow disturbances (e.g., Coriolis).
For bidirectional flow applications, flow conditioning should meet these requirements
regardless of direction of flow.
3.16 STRAINERS
Strainers shall only be provided for turbine meters. Application of strainers for other types
of meters requires the approval of the Principal.
When strainers are required, they shall be selected and installed as per the strainer and
meter Manufacturer’s recommendations and as per the requirements of the applicable
standard.
The strainers shall have the following characteristics:
a) for meter protection applications, located upstream of the meter,
b) for sampler only applications, located upstream of the sampling system
c) pipeline vertical basket type with top entry
d) In the clean condition, the strainer should have a pressure drop of not more than
20 kPa (2.9 psi), and in a dirty condition the strainer internals shall be capable of
withstanding a pressure drop of at least 35 kPa (5 psi). This requirement is more
stringent than that specified by most Suppliers, but is considered necessary to
prevent the collapse of a dirty strainer.
e) Strainers should have ports to accommodate the installation of a differential pressure
indicator or transmitter across the strainer body.
f) A differential pressure transmitter with alarm should be provided where frequent
fouling of the strainer is expected.
ECCN EAR99 DEP 32.32.00.12-Gen.
February 2013
Page 22
g) The strainer enclosure shall be of the quick-opening type with valved vent and drain
connections.
h) The strainer shall have replaceable stainless steel inserts.
i) The strainer screen shall be supported by a strainer basket having much larger
openings than those of the screen.
j) The mesh size for the screen shall be as recommended by the meter Manufacturer.
For the purposes of selecting an analysis scheme, the fluid is deemed to have a constant
composition (Group 2) if the variability in its composition contributes less than 0.5 %
ECCN EAR99 DEP 32.32.00.12-Gen.
February 2013
Page 23
increased uncertainty to the parameter of interest (e.g., mass, energy, volume). In all other
cases the gas has, by definition, a variable composition (Group 1).
Composition variability shall consider the source of the gas (e.g., process, reservoir),
similar applications and the results of representative spot sampling.
For fluid properties for custody transfer gas measurements, the following methodology
should be made available:
In addition to the above, the selection of analysis scheme shall consider the implementation
cost and technical feasibility of the required quality measurements. For example, moisture
content, hydrogen sulphide and fluid composition can generally be reliably determined by
on-line analyser systems provided that contaminants are absent from the fluid matrix.
Properties required to meet contractual or regulatory requirements but which are less
suitable for determination by on-line analysers should be determined via sampling and
analysis. The method selected should meet local needs and encompass all requirements,
e.g., logistics and training of local staff.
For QMI requirements, see (6.4).
For sampler requirements, see (10).
For inferred property determinations from compositional data, see (7.2.4).
For indirect mass measurement, a densitometer should be utilized (6.4.2). Where use of a
densitometer is not practical or cost effective, a computed density (7.2.4) may be utilized
using fluid composition. In such cases, the uncertainty of the fluid composition
measurement (6.4), the density computation algorithm (7.2.4) and volumetric meter (5)
shall be considered to ensure the required uncertainty of the overall mass measurement is
achievable.
Where in-situ validations are required for mass measurements using Coriolis meters, the
means of meter validation shall be considered (9) as part of the meter type selection
process. For example, a Coriolis meter outputting mass, which requires in-situ meter
verification, requires that the meter skid design is capable of either:
• master meter proving using another Coriolis meter, or,
• master meter proving using a volumetric meter and a densitometer, or,
• master meter proving using a volumetric meter and a compositional analyzer.
• for line sizes > 100 mm (4 NPS), multi-path ultrasonic (5.2) or Coriolis meters (5.3),
• orifice (5.4)
• turbine (5.5)
Coriolis meters shall not be used for direct measurement of gas or vapours on a volumetric
at flowing condition basis.
NOTE: The uncertainty of the density measurement of a Coriolis meter relative to the flowing density is such
that it precludes using the measured flowing density to convert the measured mass to a volumetric
flow rate for gas applications.
5. METER REQUIREMENTS
Where applicable (2.2), the requirements of OIML R137 – Parts 1 and 2 shall apply.
With the exception of orifice meters, all gas meters used for custody transfer shall be flow
calibrated as per (9).
All meters shall be installed so that they are well supported (i.e., adjacent piping shall not
exert any stress on the meter body).
Adequate filtering shall be provided where necessary.
Failure of one of the acoustic paths of an ultrasonic flow transmitter shall not invalidate its
measurement.
can affect the performance of the Coriolis meter. Care should be taken to ensure that no
forces are exerted on the meter from clamping arrangements.
Measures should also be taken to prevent excessive stresses from being exerted on the
Coriolis meter by connecting pipes. Under no circumstances should the Coriolis meter be
used to align the pipe work. Alignment of the instrument shall be in accordance with the
Manufacturer’s specification, i.e., typically within 1 % of the internal pipe diameter.
Common piping practice for the supporting of adjacent piping should be sufficient to
suspend the meter and no additional supports are generally required. Arrangements shall
be in accordance with the Manufacturer's recommendations.
Venturi meter tubes shall be individually calibrated for custody transfer applications.
ECCN EAR99 DEP 32.32.00.12-Gen.
February 2013
Page 29
6. SECONDARY INSTRUMENTS
6.1 INTRODUCTION
Temperature, pressure and differential pressure transmitters shall be selected and installed
as per the requirements of DEP 32.31.00.32-Gen.
6.2 TEMPERATURE
Temperature measurement shall be performed using RTDs mounted in flanged
thermowells (refer to Standard Drawing S 38.113). Meter skin or meter body temperature
measurements may only be used to correct for temperature effects on the meter body but
not to compute physical properties or correct volumes.
The temperature measurement shall accurately present the gas temperature in the line.
The effects of heat transfer from the piping or thermowell attachment to ambient shall be
limited and the temperature misreading for this reason should be limited to 0.5 °C (0.9 °F)
under steady state conditions. Refer to (Appendix H) for construction details.
A pair of thermowells, one for the measurement RTD and one for validation purposes shall
be provided outside the straight length as per the applicable standards (i.e., typically from
5D to 10D from the meter outlet flange).
If redundancy is required (3.5) a dual RTD sensor may be installed in the measurement
thermowell assembly thus avoiding the need for an additional thermowell.
Test thermowells shall have a 10 mm to 13 mm (3/8 in to 1/2 in) internal bore.
The two thermowells shall be installed on different radial axes to minimise vibration fatigue
of the downstream well by vortex shedding from its upstream partner.
Insertion depth shall be middle third of pipe or 75 mm (3 in) maximum into pipe subject to
the vibration failure avoidance constraints and length requirements detailed in
DEP 32.31.00.32-Gen. For pipe sizes 100 mm (4 in) and smaller, the pipe size shall be
increased to 150 mm (6 in) to avoid flow restriction. Eccentric reducers/expanders shall not
be used for this purpose. The thermowells shall be mounted to allow filling with a heat
conductive fluid. The test thermowell shall be provided with a threaded cap and chain.
The RTD shall be a Pt 100 RTD, 100 Ω at 0 °C, alpha coefficient 0.00385 Ω/Ω/°C as
defined in IEC 60751. Tolerance class A shall be applied.
The temperature element shall be spring loaded, installed and connected so that it can be
readily disconnected and extracted for replacement.
The temperature transmitter/direct wired RTD shall have sufficient coiled cable to facilitate
removal for verifications.
6.3 PRESSURE
For volumetric meters, pressure transmitters shall be located as per the applicable
standard.
Gauge pressure transmitters are preferred to absolute pressure transmitters because of
their ease of validation. Absolute pressure transmitters should be considered for low
pressure applications (less than 700 kPag (100 psig)).
Conversion from gauge to absolute pressure may be performed by adding the nominal
barometric pressure agreed as per (2.2) to the gauge pressure reading or by adding a
measured barometric pressure value.
To facilitate calibration, a dedicated impulse line connection to the transmitter manifold
block shall be available to allow calibration of the transmitter without the transmitter being
removed from the field.
Local pressure gauges shall be applied only by exception and shall be selected and
installed according to DEP 32.31.00.32-Gen. Indicating pressure transmitters should be
used rather than permanently mounted pressure gauges.
ECCN EAR99 DEP 32.32.00.12-Gen.
February 2013
Page 30
The temperature of the densitometer shall be kept within 0.5 °C (0.9 °F) from the process
temperature, which represents an additional density error of approximately 0.15 %. With a
pocket type of densitometer, the line pocket and protruding instrument shall be placed
inside a thermally well-insulated box that surrounds the whole pipe section over a length of
approximately 1 m (40 in) and over which length the insulation shall be stripped. Sample
take-off and flow controls of the densitometer shall be located inside the same box.
Provision shall be made for obtaining a manual sample for device validation.
6.4.3 Gas composition
Compositional analysis may be used to infer via computation parameters such as density,
heating value and compressibility (7.2).
Where required, the gas composition shall be determined according to the following:
• GPA 2261, or ,
• ISO 6974 (applicable part as per (2.2)).
• The gas chromatographs shall be calibrated using a primary gas standard
(i.e., prepared by weight), in accordance with ISO 14111 and ISO 6142.
Performance evaluation of the GC analyzer shall be as per ISO 10723.
ECCN EAR99 DEP 32.32.00.12-Gen.
February 2013
Page 31
7. COMPUTATIONAL DEVICES
7.2 COMPUTATIONS
7.2.1 Introduction
At a minimum the computations shall meet the requirements of the applicable standards
associated with the different meter types (5) and API MPMS 21.1 utilizing agreed upon flow
rate and physical property algorithms.
7.2.2 Flow rate computations
Mass and volumetric flow rates shall be computed as per the standards detailed in the
following table.
Where it is not practical to compute values for viscosity and isentropic coefficient in real
time, subject to (2.2) and uncertainty requirements, fixed values may be used for the these
parameters based on the average operating conditions.
ECCN EAR99 DEP 32.32.00.12-Gen.
February 2013
Page 32
The following equipment list identifies the minimum equipment that shall have sealing
provisions. If regulatory requirements require additional devices to be sealed, the additional
devices shall also have sealing provisions.
a) Meter covers,
b) Preamplifier housings (e.g., turbine meters),
c) Meter counter and mounting bolts,
d) Sample probe and actuator mounting connection,
e) Sample container valves and openings,
f) Measurement system field panels,
g) Electronic computational devices (i.e., flow computers),
h) Temperature and pressure probes and transmitters including write protected dip
switches for smart transmitters,
i) Any valves capable of diverting fluids around the meter,
j) Junction boxes,
k) Any valves capable of diverting fluids after the meter prior to its intended destination
l) Any valves isolating a third party from the metering skid.
9. METER VALIDATION
9.1 GENERAL
With the exception of orifice meter tubes, all meters including Venturi meters shall be
calibrated prior to shipment to site at a facility traceable to the appropriate national standard
(2.2) as per the requirements of the applicable standards in (5).
Meter system designs shall provide for subsequent verifications using a master meter,
check meter or removal to an offsite facility for calibration. Check meters are master meters
which are typically left in line. Master meters may be permanently in-line or periodically
brought in-line.
For meters subject to upstream flow disturbance effects, the design shall provide
appropriate straight lengths for check and pay meters. For meters removed for offsite
calibrations, the design and installation shall permit shipment of the upstream spool pieces
without disassembly. For bidirectional meters, shipment of upstream and downstream
spool pieces is required.
10 SAMPLING
10.1 GENERAL
Manual natural gas sampling systems shall be selected, sized, installed, verified and
operated to meet the requirements of:
• API MPMS 14.1, or,
• ISO 10715.
The requirements of these standards shall apply to fluids other than natural gas (exception
steam). Steam sampling design shall meet the requirements of ASTM D 1066.
Automated sampling systems shall be selected, sized, calibrated and operated to meet the
requirements of:
• ISO 10715.
In addition to the above standards sample systems shall meet the requirements of
DEP 32.31.50.10-Gen. in terms of sample location, sample probe requirements, phase
control and sample transport and sample disposal where required.
Sample systems shall not bypass the meter.
The sample take-off probe should be located with due consideration to meter upstream and
downstream straight length piping requirements as if it was a thermowell.
All on-line QMIs shall be provided with manual sampling stations for verifications.
11.1 GENERAL
All measurement systems installations shall be thoroughly checked and functionally tested
prior to shipment of the packaged unit. Examinations and/or tests may be reviewed
and/or witnessed by the Principal or their authorized agent at the Manufacturer's or the
Supplier’s facility as stated in the purchase order. The appropriate authority may wish to
approve the equipment design and witness calibration tests.
The Manufacturer/Supplier shall contact the Principal at the agreed schedule, i.e., six
weeks before the package delivery date, to schedule a factory acceptance test (FAT) that
will be witnessed by the Principal. The Manufacturer/Supplier shall submit a test procedure
to the Principal for approval six weeks prior to the FAT.
For meters which require calibration at the Manufacturer’s facility or an approved
independent calibration facility, the Manufacturer/Supplier shall contact the Principal at the
agreed schedule, i.e., six weeks before the meter calibration date, to provide the
opportunity for witnessing of the meter calibration by the Principal and where required by
the local authority.
The FAT procedure should test all power distribution, grounding, wiring, instrument
installation, calibration and control/measurement system configuration, functionality and
interfaces. The procedure shall include a means of documenting the results of each step of
the test, with space for approval signatures.
The Manufacturer/Supplier shall perform the test in accordance with the procedure, and
then correct any problems that are revealed by the test prior to sending to site.
If off-skid equipment is part of the package, then it shall be temporarily wired to the junction
box on the skid for integrated testing. All connections shall be marked and tagged,
complete with installation instructions and drawings.
The Manufacturer/Supplier shall furnish all drawings, power supplies, computers, HMIs,
wiring harnesses, meters, displays and other equipment required to perform a thorough
test.
ECCN EAR99 DEP 32.32.00.12-Gen.
February 2013
Page 35
FAT wet tests using the process fluid or a suitable substitute and FAT heat soak tests shall
only be required by exception and then only with the approval of the Principal. Skids
destined for off shore applications may require wet tests as part of the FAT.
11.2 SKID
The skid shall be inspected for compliance as follows:
• Layout drawing dimensional agreement,
• General quality of workmanship,
• Equipment access for maintenance and validation.
11.3 INSTRUMENTATION
11.3.1 General
All Instruments shall be inspected, tested and calibrated as per the Manufacturer’s quality
assurance process.
Although not specifically defined as part of the Process Automation Systems (PAS),
custody transfer measurement systems shall be inspected and tested in accordance with
DEP 62.10.08.11-Gen. and the requirements of this Section.
11.3.2 Meters
In addition to the Manufacturer’s standard calibrations, custody transfer meters shall be
factory or flow loop calibrated as required as per DEP 32.32.00.95-Gen. Meter calibrations
shall be witnessed by the Principal or a representative.
As part of the inspection procedure, the upstream and downstream straight run piping
lengths and quality shall be confirmed. For differential producers, internal diameters, pipe
eccentricity, etc. shall be confirmed.
11.3.3 Samplers
Except where noted in DEP 32.32.00.95-Gen., samplers generally do not require FATs.
11.3.4 QMIs
QMIs shall be factory tested at the QMI Manufacturer’s facility as per the requirements of
DEP 32.31.50.10-Gen. As part of the skid FAT, testing shall be limited to a dry test without
process fluids to confirm correct power and signal wiring, outputs, fault indicators, sample
valves, etc. The QMI system performance test shall be performed after commissioning.
11.3.5 Computational devices
Tests of computation devices shall include, but not be limited to the following:
a) Verification of proper configuration of computational devices,
b) Verification of digital communication between all devices identified in the
measurement system architecture drawing (i.e., register mapping confirmations,
watch dog timers, etc.),
c) Functional and performance check of all conversions of analogue and frequency
measured variables into digital values,
d) Confirmation of correct flow rate and where applicable energy computation and
quantity integration operations with simulated measurement inputs,
e) Confirmation of correct input/output signals to the totalisers, analogue indicators or
recorders, meter, sampler and SCADA or BPCS systems,
f) Confirmation of correct generation of operating function alarms, e.g., high flow rate,
etc.,
g) Confirmation of computer system and health monitoring alarms,
ECCN EAR99 DEP 32.32.00.12-Gen.
February 2013
Page 36
h) Confirmation of event logging and reports (e.g., snapshot, tender, proving, end of
day),
i) Verification of all diagnostic software communications,
j) Demonstration of auto start-up and recovery after power failure,
k) Functional check of Manufacturer/Supplier supplied tools and test equipment with
the main equipment.
Dynamic tests utilizing fluids shall be performed as part of commissioning and start-up.
The programme shall include but not be limited to the following tests:
a) Verification that meter run and master meter selection valves operate correctly, that
the valves seal, and correctly signal the valve positions;
b) Verification that the meter stream flow control valves function correctly and that flow
balance between meter runs is achieved;
c) Verification that the measurement data presented at the operator's interface to the
microcomputer are correct and that commands given at the interface are executed
correctly.
In order to verify the flow computer software/firmware, duly tested and accepted flow and
uncertainty calculation programs, independent of the programs used in the flow computer,
that apply the standards cited above and are run on an off-line computer shall be available
to provide the necessary reference information.
11.5 ELECTRICAL
Custody transfer measurement systems/skids intended for use outside of North America
shall be tested and inspected as per DEP 63.10.08.11-Gen. and for those systems/skids
intended for use inside North America as per DEP 63.10.08.14-Gen.
can be calculated based on a formula from the International Association of Geodesy with
data derived from satellite orbital variations (1970) and is always to within 10-3 m/s2 and
usually within 5 x 10-4 m/s2.
Individual pieces of equipment (e.g., meters, valves) and skid packages shall be
prepared for shipment by the Manufacturer/Supplier as follows:
a) Package shall be de-pressurized, drained or blown dry of any hazardous material
and/or water prior to shipment.
b) All connection points shall be appropriately tagged.
c) Any vent lines that are capped and/or sealed for shipping shall be flagged for
removal prior to service.
d) Threaded and tube openings shall be sealed and plugged with suitable protectors to
prevent damage to threads or tubing and prevent the ingress of dirt or packing
material.
e) Flange faces, where applicable, shall be coated with a suitable rust preventative and
shall be protected with wood or plastic flange covers, securely bolted to the flange.
f) Panel and shelter exhaust vents and air intakes shall be covered with appropriately
secured plastic.
g) Fragile or sensitive pieces of equipment shall be removed and packaged separately.
h) Ancillary devices shall be crated or boxed, at the Supplier’s discretion, unless
specified on the data sheets, in such a fashion to preclude, within reason, damage in
transit.
i) Documents, tags or instructions necessary for proper unpacking and protection after
unpacking shall be enclosed and their location marked on the outer covering.
13. DOCUMENTATION
13.1 GENERAL
All drawings, manuals, datasheets shall be provided, as a minimum, in native electronic
format as specified by the Principal. Other formats and the quantity of electronic and
hardcopy copies shall be defined by the Principal for each project.
Approval of drawings by the Principal does not release the Contractor, Manufacturer or
Supplier from the responsibility for proper design, fabrication and functioning of the
equipment and systems provided.
All preliminary drawings and data sheets shall be as built (i.e., updated to reflect as
supplied condition).
ECCN EAR99 DEP 32.32.00.12-Gen.
February 2013
Page 39
Instrument data sheets shall utilize the Principal’s format or a format approval by the
Principal.
d) A listing of all electrical, instrument and control equipment supplied (by tag number),
e) An Instrument data sheet for each device (e.g., meter, transmitter, QMI, valve,
sampler, speciality piping item, flow computer) in the format approved by the
Principal,
f) Catalogue data, descriptive bulletins and installation and operating manuals for each
piece of equipment.
g) Instrument Sizing Calculation reports (e.g., valves, meters),
h) Thermowell vibration, pipe stress and pressure drop computations,
i) Configuration files in native format and paper listing for all programmable and
configurable devices (e.g., PLC programs, flow computers, transmitters, meters,
routers, switches, etc.),
j) An individually priced recommended spare parts list,
k) A list of software, special tools and/or equipment for installation, calibration, check-
out, maintenance and servicing of instruments and control systems, individually
priced,
l) FAT procedure,
m) Certified dimensional drawings for skids, shelters, major pieces of equipment,
n) Electrical power wiring diagrams,
o) Electrical signal wiring (i.e., loop) drawings,
p) Communications wiring diagrams including ports and pin-outs where applicable,
q) Piping schematics,
r) Electrical and instrument location plans,
s) Instrument installation detail,
t) Calibration certificates and test reports (13.4),
u) Instrument I/O list complete with addresses (e.g., Modbus and FF addresses),
v) I/O list for Interface with BPCS, FGS and IPS complete with addresses,
w) Alarm List (operational and diagnostic),
x) Cause and Effects,
y) Alarm and Trip Settings,
z) Spare parts list as defined in DEP 70.10.90.11-Gen.
14. REFERENCES
In this DEP, reference is made to the following publications:
NOTES: 1. Unless specifically designated by date, the latest edition of each publication shall be used,
together with any amendments/supplements/revisions thereto.
2. The DEPs and most referenced external standards are available to Shell staff on the SWW (Shell
Wide Web) at http://sww.shell.com/standards/.
SHELL STANDARDS
DEP feedback form DEP 00.00.05.80-Gen.
Standard drawings index DEP 00.00.06.06-Gen.
The use of SI quantities and units (endorsement of ISO/IEC 80000) DEP 00.00.20.10-Gen.
Protective coatings for onshore facilities DEP 30.48.00.31-Gen.
Piping classes - Basis of design DEP 31.38.01.10-Gen.
Piping - General requirements DEP 31.38.01.11-Gen.
Piping classes – Refining and chemicals DEP 31.38.01.12-Gen.
Piping classes – Exploration and production DEP 31.38.01.15-Gen.
Shop and field fabrication of piping DEP 31.38.01.31-Gen.
Fiscal and sales allocation models for upstream production systems DEP 32.00.00.12-Gen.
Process control domain – Enterprise industrial automation DEP 32.01.20.12-Gen.
information technology and security
Process control domain - Security requirements for suppliers DEP 32.01.23.17-Gen.
Instruments for measurement and control DEP 32.31.00.32-Gen.
Instrumentation for equipment packages DEP 32.31.09.31-Gen.
On-line process analysers DEP 32.31.50.10-Gen.
Analyser housing DEP 32.31.50.13-Gen.
Custody transfer measurement systems for liquids DEP 32.32.00.11-Gen.
Gas custody transfer metering system for gases and vapours DEP 32.32.00.95-Gen.
(requisition sheet)
Control valves - Selection, sizing, and specification DEP 32.36.01.17-Gen.
Static DC uninterruptible power supply (DC UPS) units DEP 33.65.50.31-Gen.
Static A.C. uninterruptible power supply unit (static A.C. UPS unit) DEP 33.65.50.32-Gen.
Selection of materials for life cycle performance (Upstream facilities) - DEP 39.01.10.11-Gen.
Materials selection process
Inspection and functional testing of instruments DEP 62.10.08.11-Gen.
Field commissioning of electrical installations and equipment DEP 63.10.08.11-Gen.
Field commissioning and testing of electrical installations and DEP 63.10.08.14-Gen.
equipment for North American application
Spare parts DEP 70.10.90.11-Gen.
Design of pressure relief, flare and vent systems DEP 80.45.10.10-Gen.
Overpressure and underpressure – Prevention and protection DEP 80.45.10.11-Gen.
ECCN EAR99 DEP 32.32.00.12-Gen.
February 2013
Page 42
STANDARD DRAWINGS
Flanged thermowell DN 40 (NPS 1-1/2), ASME classes up to S 38.113
1500 incl.
AMERICAN STANDARDS
Orifice Metering of Natural Gas and Other Related Hydrocarbon AGA Report 3-1
Fluids - Concentric, Square-edged Orifice Meters Part 1: General
Equations and Uncertainty Guidelines - Fourth Edition
Orifice Metering of Natural Gas and Other Related Hydrocarbon AGA Report 3-2
Fluids Part 2 Specification and Installation Requirements - Fourth
Edition;
Orifice Metering of Natural Gas and Other Related Hydrocarbon AGA Report 3-3
Fluids Part 3 Natural Gas Applications - Third Edition;
Natural Gas Energy Measurement AGA Report No. 5
Measurement of Natural Gas by Turbine Meters (2006) AGA Report No. 7
Compressibility Factors of Natural Gas and Other Related AGA Report No. 8
Hydrocarbon Gases
Measurement of Gas by Multipath Ultrasonic Meters AGA Report No. 9
Speed of Sound in Natural Gas and Other Related Hydrocarbon AGA Report No. 10
Gases
Measurement of natural gas by Coriolis meter AGA Report No. 11
Orifice metering of natural gas and other related hydrocarbon fluids, AGA Report No. 3, Part 2
Part 2 - Specification and installation requirements
Manual of Petroleum Measurement Standards Chapter 14—Natural API MPMS 14.1
Gas Fluids Measurement, Section 1—Collecting and Handling of
Natural Gas Samples for Custody Transfer
Manual of petroleum measurement standards, Chapter 14 - Natural API MPMS 14.3.1
gas fluids measurement, Section 3 - Concentric, square-edged orifice
meters, Part 1-General equations and uncertainty guidelines
Manual of Petroleum Measurement Standards, Chapter 14 - Natural API MPMS 14.3.2
Gas Fluids Measurement, Section 3 - Concentric, Square-Edged
Orifice Meters, Part 2-Specification and Installation Requirements
Manual of petroleum measurement standards, Chapter 14 - Natural API MPMS 14.3.3
gas fluids measurement, Section 3 - Concentric, square-edged orifice
meters, Part 3-Natural gas applications
Manual of petroleum measurement standards, Chapter 21 - Flow API MPMS 21.1
measurement using electronic metering systems, Section 1 -
Electronic gas measurement
Natural gas fluids measurement - Concentric, square-edged orifice API MPMS Chapter 14.3
meters, Part 2 – Specification and installation requirements Part 2
Properties of Saturated and Superheated Steam in U.S. Customary ASME Steam Tables
and SI Units from the IAPWS-IF97 International Standard for
Industrial Use
Malleable iron threaded fittings classes 150 and 300 ASME B16.3
Process piping ASME B31.3
Standard practice for sampling steam ASTM D 1066
ECCN EAR99 DEP 32.32.00.12-Gen.
February 2013
Page 43
Standard test method for determination of total volatile sulfur in ASTM D 6667
gaseous hydrocarbons and liquefied petroleum gases by ultraviolet
fluorescence
Analysis for natural gas and similar gaseous mixtures by gas GPA 2261
chromatography
Issued by:
Gas Processors Association
GERMAN STANDARDS
Standardization of the signal level for the failure information of digital NAMUR NE-43
transmitters
Issued by:
NAMUR Geschäftsstelle
INTERNATIONAL STANDARDS
IAPWS Formulation 1995 for the Thermodynamic Properties of IAPWS-95
Ordinary Water Substance for General and Scientific Use
Issued by:
International Association for the Properties of Water and Steam (IAPWS)
A.1.10 The system of all measurements, the type of instruments used, the use of derived
measurement values instead of direct measurements, the procedures for maintenance and
calibration, the methods and criteria by which measurement corrections will be made and
ECCN EAR99 DEP 32.32.00.12-Gen.
February 2013
Page 46
other items relevant to the measurement of the (insert fluid name(s)) at the Delivery Point
shall be mutually agreed upon between Sellers and Buyer and shall be specified in a
Measurement Manual.
A.1.11 A draft of the Measurement Manual shall be prepared prior to start-up. Within a period of
3 months after start-up of the measuring station at the Delivery Point, the Measurement
Manual shall be finalized, reviewed and approved by appropriate parties. This Manual shall
specify the detailed methods and instruments for measuring and/or calculating the quantity,
composition and physical properties of the (fluid) delivered, the calibration and maintenance
procedures and the inaccuracies of the instruments.
A.1.12 The Measurement Manual is subject to Buyer's approval.
A.1.13 This manual shall give a detailed description of the flow measurement system(s) and
methodology followed to achieve the required results. The following information shall be
specified in detail:
a) Complete description of measurement system including operating principles of
instrumentation and the methodology of determining mass, volume and energy flow.
b) Change control procedures concerning custody transfer measurement systems.
c) Methodology and quality assurance of results obtained.
d) Uncertainty analysis including the overall uncertainty of custody transfer
measurement system(s) and the documentation of permissible errors.
e) Rules of handling measurement deviations. Maintenance intervention should be
specified.
f) Handling and communication of acknowledged measurement deviations exceeding
permissible error limits, with special attention to notification of contract parties and
the regulatory authority.
g) Methods and criteria for measurement corrections.
h) Measurement values inferred instead of directly measured, in the event of failing
input.
i) Logging of information in support of the qualitative and quantitative operation of the
measurement station including date stamped information concerning:
1) calibration results/reports of instruments and calibration equipment;
2) parameter list of flow computer;
3) maintenance activities;
4) operational activities, e.g., when meter run was changed over.
j) Detailed instructions for the operation, calibration, adjustment, maintenance and
documentation of the custody transfer measurement system(s).
k) Review of validation intervals.
l) Competence of maintenance staff.
A.1.14 In the laboratory determinations of the composition and physical properties of the (fluid), the
quality and quantity measurements specified in this Article, the appropriate tolerances of
the standard methods specified in (A.1.9) shall be applied.
If a measurement tolerance is not covered by a standard, Buyer and Sellers shall mutually
agree upon such a value, which will be specified in the Measurement Manual. Buyer and
Sellers may mutually agree values other than the tolerances specified in the standards.
A.1.15 The accuracy of metering facilities shall be validated by the Party operating the metering
facilities at the frequency specified in regulations, or as reasonably required by the
Operator whichever is more frequent. The cost of such validations shall be borne by the
Operator. Metering facilities shall be open for witnessing of calibration or inspection by the
ECCN EAR99 DEP 32.32.00.12-Gen.
February 2013
Page 47
other Party at all reasonable times. The Party performing the calibration or inspection will
provide the other Party with at least forty-eight (48) hours prior notice.
A.1.16 In case any question arises as to the accuracy of measurement, any metering facilities shall
be tested upon demand of either Party and, if found to be correct or to be in error of not
more than x percent (x.x %) with respect to equilibrium liquid measurement, or x cent
(0.x %) with respect to gas measurement (referred to as the “Relevant Percentage”), the
expense of such testing shall be borne by the Party requesting the test. If the accuracy of
measurement is found to be incorrect by more than the Relevant Percentage, the expense
of such testing shall be borne by the owner of those metering facilities.
A.1.17 If, upon any test, the metering facilities are found to be in error of not more than the
Relevant Percentage, previous readings of such metering facilities shall be considered
correct in computing the volumes being metered, but such metering facilities shall be
adjusted as soon as practicable to record accurately. If, upon any test, any metering
facilities are found to be in error by any amount exceeding the Relevant Percentage, then
any previous readings of such metering facilities shall be corrected to zero error for any
previous period which is known definitely or is agreed upon. In cases where the period is
not known definitely or not agreed upon, such correction shall be for a period covering the
last half of the time lapsed since the date of the last test.
A.1.18 In the event metering facilities are out of service or require repair, such that the volume
being measured is not correctly indicated by the reading of the metering facilities, the
volumes attributable to the period shall be estimated and agreed upon on the basis of the
best data available, using the most appropriate of the following methods:
a) by using the registration of any check metering facilities, if installed and accurately
registering; or
b) by correcting the error if the percentage of error is ascertainable by calibrations,
tests or mathematical calculations; or
c) by estimating on the basis of actual volumes measured during the preceding periods
under similar conditions when the metering facilities were registering accurately.
A.1.19 The records (electronic, written or otherwise) of the meters and the flow computer shall be
the property of the Operator and shall be retained by the Operator for a period of [x] years
from date of origination. Upon the request of the Buyer, the Seller shall submit to the Buyer
such records, together with the Seller's calculations there from, for inspection, verification
and copying, subject to return by the Buyer within thirty (30) days after receipt thereof.
A.2.5 Buyer is entitled at its sole risk and expense to connect a telemetering system to Seller’s
measurement system at the Delivery Point. Signals to be transferred shall be mutually
agreed.
A.2.6 At the request of Buyer, Sellers shall make available to Buyer at the Delivery Point the flow,
pressure and temperature signals measured at the Delivery Point and, at Buyer's request
the fluid density measurement signals for on-line transfer via Buyer's telemetering system.
The inclusion of any other quality factor(s) of the (fluid) other than those specified in the
contract is subject to mutual agreement between Sellers and Buyer. Buyer is allowed to
witness the calibration of any part of the measurement system that affects the
measurement signals that have been made available.
A.2.7 Sellers shall give at least forty-eight (48) hours' notice to Buyer of regular sampling referred
to in (A.1.7) of (fluid) at the Delivery Point for determination by laboratory analysis of the
composition and physical properties of the (fluid). Buyer and Sellers shall mutually agree
upon the frequency or change of frequency of regular sampling. Buyer may request, with
reasons given, spot samples of the (fluid) at the Delivery Point, and Sellers shall inform
Buyer of the time of sampling. The regular and spot samples will be collected by the
appropriate technique according to API 14.1 or ISO 10715. Parties may agree on other
methods if more appropriate in view of all prevailing circumstances.
The analysis shall include the composition and physical properties of the (fluid) as specified
in the contract, unless Buyer and Sellers agree otherwise. Sellers shall inform Buyer of all
results of all determinations by Sellers of the composition and physical properties of the
regular samples. Buyer shall have the right to be represented to witness the sampling and
to verify that the composition and physical properties are determined in accordance with the
standards specified in (A.1.5). Should Buyer, although notified, not be represented, the
sampling and determination by Sellers shall be considered valid until the following sampling
and determination.
c) If, in Buyer's opinion, not yet installed quality measurements at Sellers' production
location(s) are necessary for the proper operation of Buyer's facilities and for Buyer
to fulfil its obligations under the Agreement, then Buyer and Sellers shall jointly
decide on the installation of any such measuring equipment. Before implementing
such additional measurements, Parties shall agree to what extent each Party shall
bear the cost of such additional measurement(s) in view of their respective
obligations under the Agreement. Sellers shall not unreasonably withhold their
concurrence with Buyer's request unreasonably.
d) Buyer shall be allowed to witness the calibration of any part of the measurement
system at the production location that affects agreed measurement signals to Buyer.
ECCN EAR99 DEP 32.32.00.12-Gen.
February 2013
Page 50
FLOW COMPUTER
TT
FT PT 7 TE TW AT SP
DP
FC FE
1 2 3 4 5 6 8 9 10 11
Components: Notes:
1) Strainer (if required) with pressure loss monitor 1) Schematic is generic in nature and therefore all elements may not be required for a specific application.
2) Upstream straight length or flow conditioner (FC) For example, for a mass measurement application using a coriolis meter, the strainer, flow conditioner,
3) Meter (FT) pressure and temperature transmitters are not required.
4) Downstream straight lengths 2) Strainer only required for turbine meters.
5) Temperature element/transmitter (TE,TT) 3) Upstream and downstream meter straight length requirement varies with meter type and upstream piping
6) Validation thermowell (TW) disturbances.
7) Pressure transmitter (if required) (PT) 4) Flow transmitter (FT) may be close coupled to flow sensor (FE) or remote mounted.
8) Analyzer (e.g., water cut, densitometer) (AT) 5) Analyzers are typically gas chromatographs, densitometers or moisture analyzers.
9) Sample point (manual or on-line) (SP) 6) Pressure relief valves should be located to preclude unmeasured fluids via a leaky relief valve.
10) Flow control valve 7) Spacer plate installed downstream of meter downstream straight length requirement to be utilized to
11) Check valve facilitate disassembly of meter run.
Rev. 1
ECCN EAR99 DEP 32.32.00.12-Gen.
February 2013
Page 53
FT PT TT TW
FC
FE
FC
FT PT TT TW
FE
ECCN EAR99 DEP 32.32.00.12-Gen.
February 2013
Page 55
NOTES:
1) Taps for differential pressure measurement and for driving densitometer sample loop shall not be shared.
2) Sample tubing between sample point and densitometer shall be insulated.
3) Sample loop isolation valves S1 and S4 to be full port.
4) Sample loop flow meter (Fm) and needle valve (T1) to be mounted downstream of densitometer.
5) Drawing provided by manufacturer.
ECCN EAR99 DEP 32.32.00.12-Gen.
February 2013
Page 56
Removable lid
No thermal insulation, so as to
allow heat-transfer !!
functionality in
flow computer
Mass [kg] to
supervisor
Totalizer
mass flow [kg/sec]
functionality in flow
dP tx
ISO 5167
computer
Note 1 Range selection [mbar]
functionality in flow
computer
dP tx
Volume [m3] to
functionality in
functionality in
flow computer
flow computer
Note 1
supervisor
Totalizer
Divider
Density Volumetric flow [m3/sec]
T tx [K] [kg/m3] at referenced conditions
or
Te
functionality in flow
Note 1
ISO 12213
computer
[bar]
P tx
Energy [MJ] to
functionality in
functionality in
flow computer
flow computer
supervisor
Multiplier
Totalizer
Note 1 Summation Energy flow
functionality in flow [MJ/sec]
computer at specified
[bar] conditions
barometric Mol for enthalpic
P tx weight correction
[kg/kmol]
Note 2
functionality in
at referenced
functionality in supervisor PGC
ISO 6976
Comp i [ %mol]
PGC
coditions
PGC
system
Comp n-1 [ %mol]
specific)
(stream
PAY
Note 2 Comp n [%mol]
Data validation
SYSTEM
CHECK
(stream
speific)
Calorific value [MJ/kg]
functionality in
functionality in
flow computer
Comp 1 [%mol]
at specified conditions
ISO 6976
ISO 6974
functionality in
only)
flow computer
weight
functionality in
flow computer
P tx
Mass [kg] to
supervisor
[kg/kmol]
Multiplier
Totalizer
Energy flow
Summation
functionality in flow
Note 1 [MJ/sec]
functionality in flow at specified
computer
ISO 12213
conditions
computer
for enthalpic
[bar] correction
from station barometric
pressure Tx
Note 3
Volume [m3] to
functionality in
functionality in
flow computer
flow computer
T tx
supervisor
Totalizer
Divider
or Density [kg/m3]
Volumetric flow [m3/sec]
Te (for data validation
at referenced conditions
Note 1 only)
functionality in flow
dP tx
ISO 5167
computer
computer
supervisor
Totalizer
Figure I.1 Function diagram for orifice flow meter for gas with variable
composition - diverse redundancy
NOTES:
1) Stream specific
2) Station specific, facility at common inlet header or outlet header
3) Station specific
4) If no diverse redundancy is required, both density analysers can be eliminated. Density ex ISO 12213 and
density ex ISO 6976, both in the check system, become firm in that case.
ECCN EAR99 DEP 32.32.00.12-Gen.
February 2013
Page 58
Geometric
Linearization Flow [m3/sec]
Ultrasonic correction
meter functionality in
functionality in
USM
USM
at referenced conditions
Volume [m3]
T tx
or [K]
Te
functionality in
flow computer
Totalizer
P tx [bar]
functionality in flow
ISO 12213
functionality in flow
computer
Density
Spervisory system
computer [kg/m3]
baro [bar]
Note 3
P tx
Multiplier/Divider
functionality in
flow computer
Energy flow
[kg/kmol]
weight
[MJ/sec]
Energy [MJ]
Mol
Chromatographic
Density at at specified
functionality in
functionality in
flow computer
flow computer
referenced conditions
Multiplier
Totalizer
for enthalpic
data
conditions
functionality in GC
correction
flow computer or
functionality in [kg/m3]
Component 1 [ %mol]
ISO 6976
ISO 6974
Note 3
Component i [ %mol]
GC
PGC Component n-1 [ %mol] Calorific value [MJ/kg]
at specified conditions for
Component n [ %mol] enthalpic correction
Figure I.2 Function diagram for ultrasonic flow meter for gas with variable
composition
NOTES:
1) General - GC not required in case of constant composition. Subject to updating as per (3.17), Group 1c, calorific
value and volume at base conditions to be calculated from fixed entry for gas composition and heating value in
flow computer.
2) Alternatively density and density at referenced conditions may be replaced by compressibility factor under
operating conditions and under referenced conditions respectively.
3) General - No redundancy shown.
Energy flow
[MJ/sec]
at specified
functionality in
functionality in
flow computer
Coriolis
Totalizer
Supervisory system
Pressure [bar]
P tx Calorific value
[MJ/kg]
at Base conditions
at specified
Volume [m3]
conditions for
enthalpic
functionality in GC
flow computer or
correction
functionality in
functionality in
functionality in
flow computer
flow computer
Totalizer
Divider
Figure I.3 Function diagram for Coriolis mass flow meter for gas with variable
composition
Notes:
1) General - GC not required in case of constant composition. Subject to updating as per (3.17), Group 1c, calorific
value and volume at base conditions to be calculated from fixed entry for gas composition and heating value in
flow computer.
2) Requirement for Coriolis meter sensor pressure compensation is determined assessing Coriolis meter sensor
pressure sensitivity relative to variability and magnitude of process pressure (e.g., dynamic sensor pressure
compensation is not required if station pressure is regulated.
3) Dynamic pressure compensation is to be applied in Coriolis meter electronics.
4) No redundancy shown.
ECCN EAR99 DEP 32.32.00.12-Gen.
February 2013
Page 59
RS-485 Modbus
PIT
Pressure transmitter
Moxa A Moxa B
Fiscal Measurement Network x
QT
Density transmitter
x
FC FC FC FC
Run 1A Run 1B Run 2A Run 2B
RS485/RS232
Convertor
Printer Printer
Switch Switch
FIT FIT
H1 H3
Chromatograph
Chromatograph
FIT Ticket FIT Ticket
H2 Printer H4 Printer
Gas
Gas
1
2
FIT FIT
PIT TIT PIT TIT
L1 L3
2 2 4 4
FIT PIT TIT QT FIT PIT TIT QT
L2 1 1 1 L4 3 3 2
Run 1 Run 2
Common header
Figure J.1 Dual run orifice metering station with full redundancy
ECCN EAR99 DEP 32.32.00.12-Gen.
February 2013
Page 60
APPENDIX K DATA ACQUISITION AND CONTROL ARCHITECTURE
EXTERNA
L
VENDORS
BUSINESS
INTERNET
USERS
Domain
Office
INTERNAL BUSINESS
TPA
HISTORIAN USERS &
SERVER
APPLICATIONS
L4 Office Network
TCP/IP Ethernet
Mirror image
Process Control
Access Domain
PCDP Note:
HISTORIAN PCAD
Process Control Domain
Portal
CCR
DCS
Process Control
Domain
The resolution of values presented on the visual display shall be sufficient to verify the
calculation accuracy.
It shall be possible to read the digital signal from the A/D converter as an
unscaled/uncompensated value, presented in a binary, hexadecimal or decimal form.
It shall be possible to read the pulses received from a meter directly (pulse transmission
check).
Flow computers shall accept the fault status of input devices but need not duplicate the
diagnostic functions of fit-for-purpose software associated with these devices.
Full documentation of the flow computer software shall be available providing the functional
design and the implementation of the package (e.g., for audit purposes).
The total error of the analogue to digital converter of the flow computer, including
resolution, linearity, repeatability and other random errors, shall not exceed ± 0.02 %.
Algorithm and unintentional rounding-off errors for computations of custody transfer
quantities in the flow computer shall be less than ± 0.001 %.
The flow computer shall be housed in accordance with the Manufacturer's
recommendations with respect to environmental conditions (temperature, vibration, etc.).
The flow computer firmware shall be subject to a regime of version control and be
identifiable by a unique version number.
The serial data transmission links shall be continuously monitored and an alarm generated
if faults are detected. The supervisory computer should be equipped with watchdog
ECCN EAR99 DEP 32.32.00.12-Gen.
February 2013
Page 62
functionality to monitor the performance of data transfer between flow computer and
supervisory computer.
The custody transfer computing system shall have sufficient communication capability for
recording devices and alarm printers where required by legislation.
The flow computer shall provide ample recording and logging functions through a secure
communication facility to other systems (e.g., transmission of hourly or daily reports). The
following functions shall be provided by the flow computer system (if applicable):
a) storage of accumulated custody transfer quantities for each metering run and the
total metering system and an option to print these quantities;
b) alarm reports;
c) change logs,
d) monthly storage of measured parameters and accumulated quantities for each
metering run. An option to print-out such data;
e) communication facilities via VDU, printer and terminal.
The custody transfer supervisory computer shall, for each meter run, automatically log and
store at intervals of 1 h and 24 h: cumulative applicable quantities of mass, volume and
energy, and average values of pressure, temperature and density.
The retention time for storing these data shall comply with local regulations or the contract,
whichever is the longer.
The metering system shall be powered by an uninterruptible power supply (UPS); refer to
DEP 33.65.50.31-Gen. and DEP 33.65.50.32-Gen. Failure of the normal power supply and
UPS fault status shall be monitored and alarmed by the flow computer.
Additional back-up facilities in each computer shall ensure that custody transfer data are
not lost under any circumstances.
The flow computer response to changes of the metering system's secondary input signals
shall not be greater than 1 s.
The custody transfer measurement system shall be connected to the Process Control
Network (PCN) via the supervisory computer. There shall be no other connections between
the Custody Transfer Measurement Network and the Process Control Network.
The Supervisory computer shall include the capability (e.g., an OPC (OLE for Process
Control) server) to send the data to and from the data historian. The data historian shall be
the only location where users can get access to the custody transfer data.
Internal business users and applications shall not be able to directly access the supervisory
or custody transfer flow computers.
External business users, e.g., contract partners, shall only be able to access metering data
as remote users under a Third Party Access (TPA) agreement.
Manufacturers/Suppliers shall be able to access the Custody Transfer Measurement
Network for diagnostics and repairs only via a thin client in the Process Control Domain.
No modems shall be connected to the metering hardware and instrumentation.
Control and automation (C&A) maintainers shall be allowed access to the Custody Transfer
Measurement Network and hardware. The use of laptops and portable media shall be in
strict compliance with general PCD security requirements as per DEP 32.01.20.12-Gen.
ECCN EAR99 DEP 32.32.00.12-Gen.
February 2013
Page 63
FC FC FC
FE FT FE FT FE FT
PT PT PT
TT TT TT
TW TW TW
Master
Meter
SP AT