BOQ Variation Order 03
BOQ Variation Order 03
Ministry of Defence
Nepal Army
Kathmandu Terai/Madesh Fast Track Express Way (KTFT)
Bhadrakali,Kathmandu, Nepal
GENERAL INFORMATIONS :
1 Project name and Contract no: KATHMANDU – TERAI/MADESH FAST TRACK (EXPRESS WAY) ROAD PROJECT
KTFT/NCB/WORKS/2074/075-21
VARIATION
The variation of some of the items in Bill of Quantities has been changed a result of final measurement of site.Due to
locking of Masonry head wall, masonry quantity is increased. Due to site condition and design change of paralink Re
wall quantity Increased. And as per site earth work quantity increased and hard rock quantity was decreased.
3 Revised Cost Estimate till VO 3 with 13% VAT & PS Nrs. 895,427,793.71
4 Increase and Decrease in estimate WRT original cost estimate Nrs. (39,680,625.88)
7 Increased Or Decreased amount with respect to original Contract amount with 13% VAT & P Nrs. (33,275,156.56)
8 Increased or decreased in percentage with respect wrt original contract amount with discou % (3.57)
9 Estimsted time Effect of the variation order wrt original contract period Months None
10 Whether the estimate for variation order involves fixing a new rates yes/no No
This is the estimate for variation Order N0.-03 to the Bill of Quantities (BoQ) of the Contract No :
KTFT/NCB/WORKS/2074/075-21.
Because of this Estimate for the variation Order 03 is NRS 33,275,156.56 with VAT respect to the original contract
amount is decreased.
The contractor Raman - Apex - Mainachuli J/V has accepted this estimate for variation Order No. 03 as conformed by
their authorized signature and official seal as indicated hereunder.
Acceptances of this estimate for variation order No.03 as confirmed by all parties are indicated by appending the
signature and the common seal as mentioined below:
………………………………………………………………………… …………………………………………………………………………………………
Binding Signature of the Contractor Binding signature of Employer
Ramesh Bahadur Adhikari
Aothorized Representative
Raman / Apex / Mainachuli J/V Project Chief
Kathmandu Terai Fast Track Express Way (KTFT) Road Project
……………………………………………………………… ………………………………………………………………………………….
Promish Banepali Indibar Gurung
Project Engineer Head of Planning and Design Division (Colonel)
Witness Witness
Government of Nepal
Ministry of Defence
Nepal Army
Kathmandu Terai/Madesh Fast Track Express Way (KTFT)
Bhadrakali,Kathmandu, Nepal
Chainage:- 42+000 to 44+450
Contract No:- KTFT/NCB/WORKS/2074/075-21
Item Justification For Variation Order No.3
Increased /
Item No. Description Unit Decreased Reason For Variation
Quanity
C2.04 Supply and Installation of polyester needle punched non woven geotextile (150 g/sm) as
per MoRTH 700 Type 3, as per Specification.
Government of Nepal
Ministry of Defence
Nepal Army
Kathmandu Terai/Madesh Fast Track Express Way (KTFT)
Bhadrakali,Kathmandu, Nepal
Chainage:- 42+000 to 44+450
Contract No:- KTFT/NCB/WORKS/2074/075-21
Item Justification For Variation Order No.3
Increased /
Item No. Description Unit Decreased Reason For Variation
Quanity
The quantity of this item increased as per
a a. At the interface of boulder filling inside TMS and structural fill behind TMS Sq.m. 1,026.80 final measurement of site.
The quantity of this item increased as per
b b. Around Perforated Pipe Sq.m. 246.08 final measurement of site.
C2.05 Providing 'U' Pins made of 8 mm dia made of Fe 500 steel of depth 400mm and width
Nos
200mm, as per Specification.
Supply of non woven coir mat blanket (BioMac CC) made with fully biodegradable coir
C2.06 fibers reinforced with fine polypropylene netting secured on both sides with 20 stitches Sq.m.
per meter of length to form a strong quilted mat, as per specification.
Supply of Drainage Composite (MacDrain) with Geotextile on both side of the core The quantity of this item increased as per
C2.08 Sq.m. 808.09 final measurement of site.
behind the structural fill, as per Specification.
C2.09 Supply of Machine Wooven, double twisted, hexagonal shaped steel wire mesh, Mesh
Sq.m.
type 10x12, Mesh wire dia 2.7/3.7mm(ID/OD ), Zn+PVC coated, as per Specification.
Supply of perforated 200mm PVC pipe at the bottom of drainage composite and across The quantity of this item decreased as per
C2.10 the reinforced soil structure for collecting and draining out the subsurface flow, as per M. (37.40) final measurement of site.
Specification.
Supply of Structural fill behind TMS/GTM, spreading at site, compaction upto 95% at The quantity of this item decreased as per
C2.11 OMC as per modified proctor density at maximum 200mm thickness all complete, as per cum - final measurement of site.
Specification.
Supply and filling of Boulders(150mm to 250mm) inside Terramesh Facia as per The quantity of this item decreased as per
C2.12 cum - joint survey data during joint varification
Specification.
The quantity of this item decreased as per
C2.13 Supply and filling of Vegetative Soil at the facia of GTM as per specification. cum - joint survey data during joint varification
Earthwork in excavation for foundation of structures including setting out, removal The quantity of this item increased as per
D1.01 of stumps and other deleterious matter dressing of sides and bottom and including all cu m 1,428.19 final measurement of site.
lifts and leads complete as per drawingss and technical specification.
Plain Cement Concrete of M15/40 grade graded course aggregate for leveling course, for The quantity of this item decreased as per
D1.02 bedding of culverts, head wall etc. and annular space filling around footing in rock, cu m (7.65) final measurement of site.
complete as per drawings and technical specification.
D1.03 Providing and laying and jointing NP4 (as per IS:458) Hume pipes for culverts, rm -
complete as per technical specification.
D1.04 Providing & laying 1st Class bedding below Hume pipes with graded sand or other cu m -
granular materialas all complete.
The quantity of this item increased as per
D1.05 Back Filling behind head walls, wing walls/retaining and return wall and earth cushion cu m 33.90 final measurement of site.
around pipes or at any other location complet.
The quantity of this item increased as per
D1.06 Structural Plain Cement Concrete M 20 for Head Walls, including formwork excluding cu m 41.16 final measurement of site.
reinforcement complete as per drawings technical specification.
D1.07 Providing and laying filter material underneath pitching in slopes complete as per cu m -
drawings and technical specification Clause 2504
D1.08 Providing and laying Pitching on slopes laid over prepared filter material completeas per cu m -
drawings and technical specification.
Government of Nepal
Ministry of Defence
Nepal Army
Kathmandu Terai/Madesh Fast Track Express Way (KTFT)
Bhadrakali,Kathmandu, Nepal
Chainage:- 42+000 to 44+450
Contract No:- KTFT/NCB/WORKS/2074/075-21
Item Justification For Variation Order No.3
Increased /
Item No. Description Unit Decreased Reason For Variation
Quanity
Earthwork in excavation for foundation of structures including setting out, removal The quantity of this item increased as per
D2.01 of stumps and other deleterious matter dressing of sides and bottom and including all cu m 1,445.27 final measurement of site.
lifts and leads complete as per drawings and technical specification.
D2.02 Boulder/ Gravel/ Sand Filling in Foundation Trenches or below raft foundation of RCC cu m -
box as per drawings & technical specification.
Plain Cement Concrete (Grade M 15) using 40 mm graded metal for leveling course, for The quantity of this item decreased as per
D2.03 bedding of culverts, head wall etc. and annular space filling around footing in rock, cu m (104.56) final measurement of site.
complete as per drawings and technical specification.
Random Rubble Stone masonary work in cement mortar 1:3 for foundation/substructure The quantity of this item increased as per
D2.04 including staging and treatment of Joints complete including other structures as per cu m 59.02 final measurement of site.
drawning and technical specification.
Back Filling behind head walls, wing walls/retaining and return wall and earth cushion The quantity of this item increased as per
D2.06 around pipes or at any other location complete as per drawings and technical cu m 119.68 final measurement of site.
specification.
The quantity of this item increased as per
D2.08 Structural Plain Cement Concrete M 20/20 grade for Head Walls, including formwork cu m 99.59 final measurement of site.
excluding reinforcement complete as per drawings
D2.14 Filler Joint : Providing & fixing 20 mm thick compressible fiber board in expansion rm -
joint complete as per drawings & technical specification
Part : A General
Insurance of the works, plants and materials also including other
A1.01 property, personal injury or death of contractor employee, Ls 1.00 2,500,000.00 2,500,000.00 1.00 2,500,000.00 2,500,000.00 - 5,000,000.00 5,000,000.00 5,000,000.00 - No change, as per BOQ
employer's employee and other people and third party
C1:.01 Excavation for Structures (Cross drainage, Retaining & off-road cu m 3,580.00 251.44 900,166.04 28,262.58 251.44 7,106,428.19 6.89 400.00 1,432,000.00 400.00 11,305,031.20 9,873,031.20 Quantity Increase, As per site
structures) in common material including hard rock, all complete
C1.02 Provide and place M 15/40 grade concrete including compaction, 736,678.00
cu m 75.00 12,280.23 921,017.53 118.33 12,280.23 1,453,169.18 0.58 17,000.00 1,275,000.00 17,000.00 2,011,678.00 Quantity Increase, As per site
curing, testing etc, all complete.
Supply and assembly of machine made mechanically selvedge
gabion and mattresses produced from double twisted heavy coated
C1:.03 GI wire, of hexagonal mesh size 100 mm x 120 mm, with mesh cu m 1,476.00 4,560.67 6,731,555.45 1,845.00 4,560.67 8,414,444.32 0.25 8,500.00 12,546,000.00 8,500.00 15,682,500.00 3,136,500.00 Quantity Increase, As per site
wire 3 mm, selvedge wire 3.9 mm, lacing wire 2.4 mm and stone
filling in gabion including transport and fixing of gabion in
position, all complete.
cu m 4,560.67 2,108.50 4,560.67 9,616,182.03 4,560.67 9,616,172.70 9,616,172.70
C1:.07 Providing and laying graded filter material including compaction. cu m 262.00 3,065.75 803,227.23 262.00 3,065.75 803,227.23 - 3,500.00 917,000.00 3,500.00 917,000.00 - No change, as per BOQ
C1.08 Providing and laying PVC pipe of 90 mm dia (pressure 2.5 kg / 62,896.50
Rm 391.00 324.43 126,851.48 530.77 324.43 172,196.83 0.36 450.00 175,950.00 450.00 238,846.50 No change, as per BOQ
cm2) for weep holes as instructed by the Engineer.
Total of Part C1: 19,770,402.17 44,960,475.63 29,656,550.00 62,321,539.40 32,664,989.40
a GTM-3x2x0.83 Nos 31.00 7,551.51 234,096.72 7,551.51 - (1.00) 20,000.00 620,000.00 20,000.00 - (620,000.00) Quantity Decrease, As per site
Supply of TERRAMESH® SYETEM
unit with integrated tail as reinforcement of length 2m that is made
of mechanically woven, double twisted, hexagonal shaped steel
C2.02 wire mesh, Mesh type 10x12, Mesh wire dia
2.7/3.7mm(ID/OD ), Zn+PVC coated, Mechanically
edged/selvedge, as per Specification.
a a. TMS-3x2x0.5 Nos 1,942.00 3,580.87 6,954,047.10 1,661.00 3,580.87 5,947,822.98 (0.14) 7,000.00 13,594,000.00 7,000.00 11,627,000.00 (1,967,000.00) Quantity Decrease, As per site
b b. TMS-3x2x1.0 Nos 194.00 4,674.80 906,910.29 1,187.00 4,674.80 5,548,982.03 5.12 9,000.00 1,746,000.00 9,000.00 10,683,000.00 8,937,000.00 Quantity Increase, As per site
Supply of high strength flexible Goe grids(Para link) as primary
C2.03 reinforcement for composite soil reinforcement system made of
polyester core with polyethylene coating, as per Specification.
a a. Para link - PL 200 Sq.m. 14,687.00 596.02 8,753,690.40 18,358.75 596.02 10,942,113.00 0.25 1,600.00 23,499,200.00 1,600.00 29,374,000.00 5,874,800.00 Quantity Increase, As per site
9,399.25 596.02 5,602,140.98 596.02 5,602,140.98 5,602,140.98
b b. Para link - PL 300 Sq.m. 6,864.00 766.00 5,257,824.00 11,158.00 766.00 8,547,028.00 0.63 1,800.00 12,355,200.00 1,800.00 20,084,400.00 7,729,200.00 Quantity Increase, As per site
a a. At the interface of boulder filling inside TMS and structural fill 1,494,920.00
Sq.m. 4,273.00 85.80 366,631.98 8,544.20 85.80 733,109.52 1.00 350.00 1,495,550.00 350.00 2,990,470.00 Quantity Increase, As per site
behind TMS
b b. Around Perforated Pipe Sq.m. 427.00 85.86 36,663.20 615.68 85.86 52,863.69 0.44 350.00 149,450.00 350.00 215,488.00 66,038.00 Quantity Decrease, As per site
C2.05 Providing 'U' Pins made of 8 mm dia made of Fe 500 steel of (45,000.00)
Nos 1,625.00 51.48 83,655.00 1,550.00 51.48 79,794.00 (0.05) 600.00 975,000.00 600.00 930,000.00 Quantity Increase, As per site
depth 400mm and width 200mm, as per Specification.
Supply of non woven coir mat blanket (Bio Mac CC) made with
C2.06 fully biodegradable coir fibers reinforced with fine polypropylene (67,500.00)
Sq.m. 1,625.00 292.60 475,475.00 1,550.00 292.60 453,530.00 (0.05) 900.00 1,462,500.00 900.00 1,395,000.00 Quantity Increase, As per site
netting secured on both sides with 20 stitches per meter of length
to form a strong quilted mat, as per specification.
Government of Nepal
Ministry of Defence
Nepal Army
Kathmandu Terai/Madesh Fast Track Express Way (KTFT)
Bhadrakali,Kathmandu, Nepal
Chainage:- 42+000 to 44+450
Contract No:- KTFT/NCB/WORKS/2074/075-21
Variation Order No.3
Name of the Project: Kathmandu Terai/Madesh Fast Track Express Way (KTFT) Contract Effective Date: March 11th 2018
Financed By: Nepal Government Completion Date: 18 months
Contract No:- KTFT/NCB/WORKS/2074/075-21 New Completion date up to this variation 24th Nov 2019
Name of Contractor : Raman - Apex - Mainachuli J/V [+/-] in estimate wrt original with VAT & PS cost in NRs: (39,680,625.88)
Original Cost estimate with Vat & ps Nrs: 935,108,419.59 percentage increase or decrease in estimate wrt original estimate: -4.243%
Original Contract Amount with Vat & ps Nrs: 931,965,149.60 Revised Contract amount after this variation with VAT & PS in NRs: 898,689,993.04
Revise cost estimate (till date)with VAT & PS Nrs: 895,427,793.71 [+/-] in amount after this variation wrt original contract with VAT & PS cost in NRs: (33,275,156.56)
Actual Expenditure till Date Nrs: 679,261,564.50 Percentage increase or decrease in estimate wrt original estimate: -3.57
C2.13 Supply and filling of Vegetative Soil at the facia of GTM as per (39,000.00)
cum 39.00 1,455.30 56,756.70 - 1,455.30 - (1.00) 1,000.00 39,000.00 1,000.00 - Quantity Decrease, As per site
specification.
Total of Part C2: 65,277,868.19 140,507,297.19 82,335,200.00 138,871,320.80 56,536,120.80
Total of Part C: 85,048,270.36 185,467,772.82 111,991,750.00 201,192,860.19 89,201,110.19
Part: D Cross Drainage Structure
Pipe Culvert: Single Cell of 1.2m diameter
D1
Double Cell of 1.2m Diameter
D1.03 Providing and laying and jointing NP4 (as per IS:458) Hume pipes rm 436.00 29,150.83 12,709,762.37 310.00 29,150.83 9,036,757.65 (0.29) 35,000.00 15,260,000.00 35,000.00 10,850,000.00 (4,410,000.00) Quantity Decrease, As per site
for culverts, complete as per technical specification.
D1.04 Providing & laying 1st Class bedding below Hume pipes cu m 475.00 2,883.45 1,369,636.45 - 2,883.45 - (1.00) 3,500.00 1,662,500.00 3,500.00 - (1,662,500.00) Quantity Decrease, As per site
with graded sand or other granular materials all complete.
Government of Nepal
Ministry of Defence
Nepal Army
Kathmandu Terai/Madesh Fast Track Express Way (KTFT)
Bhadrakali,Kathmandu, Nepal
Chainage:- 42+000 to 44+450
Contract No:- KTFT/NCB/WORKS/2074/075-21
Variation Order No.3
Name of the Project: Kathmandu Terai/Madesh Fast Track Express Way (KTFT) Contract Effective Date: March 11th 2018
Financed By: Nepal Government Completion Date: 18 months
Contract No:- KTFT/NCB/WORKS/2074/075-21 New Completion date up to this variation 24th Nov 2019
Name of Contractor : Raman - Apex - Mainachuli J/V [+/-] in estimate wrt original with VAT & PS cost in NRs: (39,680,625.88)
Original Cost estimate with Vat & ps Nrs: 935,108,419.59 percentage increase or decrease in estimate wrt original estimate: -4.243%
Original Contract Amount with Vat & ps Nrs: 931,965,149.60 Revised Contract amount after this variation with VAT & PS in NRs: 898,689,993.04
Revise cost estimate (till date)with VAT & PS Nrs: 895,427,793.71 [+/-] in amount after this variation wrt original contract with VAT & PS cost in NRs: (33,275,156.56)
Actual Expenditure till Date Nrs: 679,261,564.50 Percentage increase or decrease in estimate wrt original estimate: -3.57
D1.07 Providing and laying filter material underneath pitching in slopes cu m 64.00 3,324.76 212,784.41 150.00 3,324.76 498,713.46 1.34 3,500.00 224,000.00 3,500.00 525,000.00 301,000.00 Quantity Increase, As per site
complete as per drawings and technical specification Clause 2504
D1.08 Providing and laying Pitching on slopes laid over prepared filter cu m 126.00 8,673.74 1,092,891.44 162.72 8,673.74 1,411,391.23 0.29 17,000.00 2,142,000.00 17,000.00 2,766,240.00 624,240.00 Quantity Increase, As per site
material completes per drawings and technical specification.
D2.05 Providing pointing with Cement Mortar(1:3), complete as per Sqm 150.00 246.35 36,951.94 100.00 246.35 24,634.63 (0.33) 400.00 60,000.00 400.00 40,000.00 (20,000.00) No change, as per BOQ
technical specification.
Back Filling behind head walls, wing walls/retaining and return
D2.06 wall and earth cushion around pipes or at any other location cu m 827.00 2,878.42 2,380,449.62 1,302.83 2,878.42 3,750,073.40 0.58 250.00 206,750.00 250.00 325,706.40 118,956.40 No change, as per BOQ
complete as per drawings and technical specification.
D2.17 Providing and laying filter material underneath pitching in slopes cu m 30.00 3,972.50 119,174.87 - 3,972.50 - (1.00) 4,000.00 120,000.00 4,000.00 - (120,000.00) No change, as per BOQ
complete as per drawings and technical specification
D2.18 Providing and laying Pitching on slopes laid over prepared filter cu m 59.00 8,811.93 519,904.07 - 8,811.93 - (1.00) 17,000.00 1,003,000.00 17,000.00 - (1,003,000.00) No change, as per BOQ
material completes per drawings and technical specification.
D2.20 Providing Floor Apron with 300mm thick plum concrete complete cu m 79.00 12,378.16 977,875.01 174.60 12,378.16 2,161,264.70 1.21 14,000.00 1,106,000.00 14,000.00 2,444,442.00 1,338,442.00 Quantity Increase, As per site
as per technical specification
Providing and Constructing RCC crash barrier M40 grade
D2.21 including centering, shuttering and reinforcement (Concrete 0.3 cu rm 29.00 14,328.57 415,528.59 - 14,328.57 - (1.00) 20,000.00 580,000.00 20,000.00 - (580,000.00) No change, as per BOQ
m/Rmt and steel 28 kg/Rmt etc all complete as per approved
drawingss and technical specification.
D2.22 Providing and fixing of drainage spouts along with drain pipes as rm 4.00 2,281.39 9,125.54 - 2,281.39 - (1.00) 5,000.00 20,000.00 5,000.00 - (20,000.00) No change, as per BOQ
complete as per drawings and technical specifications.
Total of Part D2: 38,309,297.59 49,537,209.89 49,167,350.00 62,148,022.01 12,980,672.01
Total of Part D: 65,402,632.56 70,220,110.04 75,954,700.00 85,338,910.33 9,384,210.33
Part: E Schedule of Day Works
E1.01 Labour
a Skilled labour (Mason, Carpenter, mechanics etc.) per-day 100.00 720.00 72,000.00 100.00 720.00 72,000.00 - 1,000.00 100,000.00 1,000.00 100,000.00 - No change, as per BOQ
E1.02 Material
a Cement bag 500.00 760.00 380,000.00 500.00 760.00 380,000.00 - 1,100.00 550,000.00 1,100.00 550,000.00 - No change, as per BOQ
b Sand cu m 100.00 2,200.00 220,000.00 100.00 2,200.00 220,000.00 - 2,500.00 250,000.00 2,500.00 250,000.00 - No change, as per BOQ
c Stone cu m 1,200.00 1,250.00 1,500,000.00 1,200.00 1,250.00 1,500,000.00 - 2,500.00 3,000,000.00 2,500.00 3,000,000.00 - No change, as per BOQ
E1.03 Equipments
a Tippers 8 ton capacity including all complete hrs 300.00 1,990.00 597,000.00 300.00 1,990.00 597,000.00 - 2,000.00 600,000.00 2,000.00 600,000.00 - No change, as per BOQ
b Excavator 200 PC or Equivalent including all complete hrs 150.00 4,717.00 707,550.00 150.00 4,717.00 707,550.00 - 6,500.00 975,000.00 6,500.00 975,000.00 - No change, as per BOQ
c Loaders including all complete hrs 150.00 4,100.00 615,000.00 150.00 4,100.00 615,000.00 - 6,500.00 975,000.00 6,500.00 975,000.00 - No change, as per BOQ
d Rollers 8 ton vibratory all complete hrs 50.00 2,600.00 130,000.00 50.00 2,600.00 130,000.00 - 6,500.00 325,000.00 6,500.00 325,000.00 - No change, as per BOQ
e Grader all complete hrs 50.00 4,300.00 215,000.00 50.00 4,300.00 215,000.00 - 10,000.00 500,000.00 10,000.00 500,000.00 - No change, as per BOQ
Total of Part E: 4,554,550.00 4,554,550.00 7,435,000.00 7,435,000.00
Part: F Provisional Sum
F1.01 Provisional Sum ps 1.00 40,000,000.00 1.00 - 40,000,000.00 - 40,000,000.00 1.000 40,000,000.00 - No change, as per BOQ
Total of Part F: 40,000,000.00 40,000,000.00 40,000,000.00 40,000,000.00 -
Total of Part A to Part F: 827,529,574.85 792,413,976.73 824,747,920.00 795,300,878.79 (29,447,041.21) -3.57%
VAT 13% 107,578,844.73 103,013,816.98 107,217,229.60 103,389,114.24 (3,828,115.36)
Grand Total 935,108,419.59 895,427,793.71 931,965,149.60 898,689,993.04 (33,275,156.56) -3.57%
Submitted By Checked By Checked By Checked By Checked By Recommended By Recommended By Approved By Approved By
Name : Ramesh Bd. Adhikari Name : Gobardhan Banskota Name : Arbind Shrestha Name : Rupak Raj Bista Name : Name : Name : Name : Name :
Designation: Partner Incharge Designation:Sector Designation:Sector Designation:Head,Planning & Designation:Head,Implementation Designation:Head of Designation: Designation:Project
Designation:Site Incharge
Name of Firm: Raman/Apex/Mainachuli JV Individual Consultant Commander Design Division & Operation Division Procurement Division Deputy Project Chief
Chief
Part : A General
Insurance of the works, plants and materials also including other
A1.01 property, personal injury or death of contractor employee, Ls 1.00 5,000,000.00 5,000,000.00 1.00 5,000,000.00 5,000,000.00 1.00 5,000,000.00 1.00 5,000,000.00 0.00 0.00 - No Change
employer's employee and other people and third party
C1:.01 Excavation for Structures (Cross drainage, Retaining & off-road cu m 3,580.00 400.00 1,432,000.00 3,580.00 400.00 1,432,000.00 27,536.78 11,014,712.00 28,262.578 11,305,031.20 725.80 290,319.20 20.27 Qty increase as per site
structures) in common material including hard rock, all complete
C1:.07 Providing and laying graded filter material including compaction. cu m 262.00 3,500.00 917,000.00 262.00 3,500.00 917,000.00 262.00 917,000.00 262.000 917,000.00 0.00 0.00 -
a GTM-3x2x0.83 Nos 31.00 20,000.00 620,000.00 31.00 20,000.00 620,000.00 - - - 0.00 0.00 - Decrese As per Site
Supply of TERRAMESH® SYETEM - -
unit with integrated tail as reinforcement of length 2m that is made
of mechanically woven, double twisted, hexagonal shaped steel
C2.02 wire mesh, Mesh type 10x12, Mesh wire dia
2.7/3.7mm(ID/OD ), Zn+PVC coated,Mechanically
edged/selvedged, as per Specification.
a a. TMS-3x2x0.5 Nos 1,942.00 7,000.00 13,594,000.00 1,942.00 7,000.00 13,594,000.00 1,773.00 12,411,000.00 1,661.000 11,627,000.00 -112.00 -784,000.00 (5.77) Decrese As per Site
b b. TMS-3x2x1.0 Nos 194.00 9,000.00 1,746,000.00 194.00 9,000.00 1,746,000.00 1,286.00 11,574,000.00 1,187.000 10,683,000.00 -99.00 -891,000.00 (51.03) Qty increase as per site
Supply of high strength flexible Goegrids(Paralink) as primary
C2.03 reinforcement for composite soil reinforcement system made of - -
polyster core with polyethylene coating, as per Specification.
Sq.m. 14,687.00 1,600.00 23,499,200.00 14,687.00 1,600.00 23,499,200.00 18,358.75 29,374,000.00 18,358.750 29,374,000.00 0.00 0.00 - Qty increase as per site
a a. Paralink - PL 200
596.02 7,528.25 4,486,987.56 9,399.250 5,602,140.98 1,871.00 1,115,153.42 New Rate
b b. Paralink - PL 300 Sq.m. 6,864.00 1,800.00 12,355,200.00 6,864.00 1,800.00 12,355,200.00 12,031.00 21,655,800.00 11,158.000 20,084,400.00 -873.00 -1,571,400.00 (12.72) Qty increase as per site
GOVERNMENT OF NEPAL
MINISTRY OF DEFENCE
NEPALI ARMY
KATHMANDU – TERAI/MADESH FAST TRACK (EXPRESS WAY) ROAD PROJECT (Chainage: km 42+000 to km 44+450)
CONTRACT NO.: KTFT/NCB/WORKS/2074/075-21
Supply and filling of Boulders(150mm to 250mm) inside 1,942.00 3,500.00 6,797,000.00 1,942.00 3,500.00 6,797,000.00 1,942.00 6,797,000.00 1,942.000 6,797,000.00 0.00 0.00 - Qty increase as per site
C2.12 cum
Terramesh Facia as per Specification. 1,643.17 4,681.00 7,691,678.77 4,693.000 7,711,396.81 12.00 19,718.04 New Rate
C2.13 Supply and filling of Vegetative Soil at the facia of GTM as per
cum 39.00 1,000.00 39,000.00 39.00 1,000.00 39,000.00 - - - 0.00 0.00 -
specification.
Total of Part C2: 82,335,200.00 82,335,200.00 137,880,616.34 138,871,320.80 990,704.46
Total of Part C: 111,991,750.00 111,991,750.00 196,580,749.30 201,192,860.19 4,612,110.89
Part: D Cross Drainage Structure
Pipe Culvert: Single Cell of 1.2m diameter
D1
Double Cell of 1.2m Diameter
Earthwork in excavation for foundation of structures including
D1.01 setting out, removal of stumps and other deleterious matter dressing
cu m 803.00 400.00 321,200.00 803.00 400.00 321,200.00 5,961.83 2,384,730.00 7,390.014 2,956,005.52 1,428.19 571,275.52 177.86
of sides and bottom and including all lifts and leads complete as per
drawingss and technical specification.
Plain Cement Concrete of M15/40 grade graded course aggregate
D1.02 for leveling course, for bedding of culverts, head wall etc. and
cu m 36.00 17,000.00 612,000.00 36.00 17,000.00 612,000.00 212.52 3,612,755.00 204.860 3,482,620.00 -7.65 -130,135.00 (21.26)
annular space filling around footing in rock, complete as per
drawings and technical specification.
D1.03 Providing and laying and jointing NP4 (as per IS:458) Hume pipes Qty decrese as per site
rm 436.00 35,000.00 15,260,000.00 436.00 35,000.00 15,260,000.00 310.00 10,850,000.00 310.000 10,850,000.00 0.00 0.00 -
for culverts, complete as per technical specification.
D1.04 Providing & laying 1st Class bedding below Hume pipes with Qty decrese as per site
cu m 475.00 3,500.00 1,662,500.00 475.00 3,500.00 1,662,500.00 - - - 0.00 0.00 -
graded sand or other granular materialas all complete.
GOVERNMENT OF NEPAL
MINISTRY OF DEFENCE
NEPALI ARMY
KATHMANDU – TERAI/MADESH FAST TRACK (EXPRESS WAY) ROAD PROJECT (Chainage: km 42+000 to km 44+450)
CONTRACT NO.: KTFT/NCB/WORKS/2074/075-21
D1.07 Providing and laying filter material underneath pitching in slopes Qty increase as per site
cu m 64.00 3,500.00 224,000.00 64.00 3,500.00 224,000.00 150.00 525,000.00 150.000 525,000.00 0.00 0.00 -
complete as per drawings and technical specification Clause 2504
D1.08 Providing and laying Pitching on slopes laid over prepared filter Qty increase as per site
cu m 126.00 17,000.00 2,142,000.00 126.00 17,000.00 2,142,000.00 162.72 2,766,240.00 162.720 2,766,240.00 0.00 0.00 -
material completeas per drawings and technical specification.
Total of Part D1: 26,787,350.00 26,787,350.00 21,708,859.55 23,190,888.32 1,482,028.77
D2 RCC Box Culvert of size 1m x 6m x 5m
Earthwork in excavation for foundation of structures including
D2.01 setting out, removal of stumps and other deleterious matter dressing Qty increase as per site
cu m 1,007.00 400.00 402,800.00 1,007.00 400.00 402,800.00 1,913.75 765,500.00 3,359.023 1,343,609.20 1,445.27 578,109.20 143.52
of sides and bottom and including all lifts and leads complete as per
drawings and technical specification.
D2.18 Providing and laying Pitching on slopes laid over prepared filter
cu m 59.00 17,000.00 1,003,000.00 59.00 17,000.00 1,003,000.00 59.00 1,003,000.00 - - -59.00 -1,003,000.00 (100.00)
material completeas per drawings and technical specification.
D2.20 Providing Floor Apron with 300mm thick plum concrete cmplete
cu m 79.00 14,000.00 1,106,000.00 79.00 14,000.00 1,106,000.00 175.74 2,460,360.00 174.603 2,444,442.00 -1.14 -15,918.00 (1.44)
as per technical specification
Providing and Constructing RCC crash barrier M40 grade
D2.21 including centering, shuttering and reinforcement (Concrete 0.3 cu
rm 29.00 20,000.00 580,000.00 29.00 20,000.00 580,000.00 29.00 580,000.00 - - -29.00 -580,000.00 (100.00)
m/Rmt and steel 28 kg/Rmt etc all complete as per approved
drawingss and technical specification.
D2.22 Providing and fixing of drainage spouts along with drain pipes as
rm 4.00 5,000.00 20,000.00 4.00 5,000.00 20,000.00 4.00 20,000.00 - - -4.00 -20,000.00 (100.00)
complete as per drawings and technical specifications.
Total of Part D2: 49,167,350.00 49,167,350.00 62,877,247.00 62,148,022.01 (729,224.99)
Total of Part D: 75,954,700.00 75,954,700.00 84,586,106.55 85,338,910.33 752,803.78
GOVERNMENT OF NEPAL
MINISTRY OF DEFENCE
NEPALI ARMY
KATHMANDU – TERAI/MADESH FAST TRACK (EXPRESS WAY) ROAD PROJECT (Chainage: km 42+000 to km 44+450)
CONTRACT NO.: KTFT/NCB/WORKS/2074/075-21