Ketziora
Ketziora
1051/matecconf/202134302007
MSE 2021
1 Introduction
Following the footsteps of the largest production plants in the world, food production
companies strive for continuous development and improvement of production processes.
The complexity of production processes and the disruptions that affect them force managers
to take a fresh look at the situation. The Lean Manufacturing concept, broadly understood
as lean enterprise management, is a solution to their expectations. The main ideas of the
concept include high quality of the manufactured products, flexibility and elimination of
waste. It is difficult to make new investments today, so companies focus on the best
possible use of their resources, at the same time aiming to minimize production costs. That
is why the right approach to managing and organizing workstations and material flow
becomes so important. Even a few percent reduction in the cost of production, inventories,
or improvement of other production indicators may significantly affect the economic
situation of the company. History shows that companies that implement the Lean
Manufacturing concept find it easier to survive a crisis. This topic is particularly important
*
Corresponding author: justyna.trojanowska@put.poznan.pl
© The Authors, published by EDP Sciences. This is an open access article distributed under the terms of the Creative Commons
Attribution License 4.0 (http://creativecommons.org/licenses/by/4.0/).
MATEC Web of Conferences 343, 02007 (2021) https://doi.org/10.1051/matecconf/202134302007
MSE 2021
because lean management makes it possible to use the full potential of the company. The
aim of the paper is to demonstrate the potential benefits of implementing Lean
Manufacturing in a selected food manufacturing company. Particular attention will be paid
to the analysis of the organization of selected workstations and the reduction of changeover
time.
2
MATEC Web of Conferences 343, 02007 (2021) https://doi.org/10.1051/matecconf/202134302007
MSE 2021
The final step of SMED consists of settings times minimization. A time gain is
generated by the conversion of internal settings to external settings. If we rationalize
settings, the minimization of the production changeover time could be improved.
However, the time that is defined in the final standard must be maintained, which is
why results should be graphed. Staff should find the main cause every time a limit is
reached or exceeded, and then establish time goals.
Maintained stability of the production process is achieved with successful
implementation of SMED, which also enhances flexibility, and shortens lead time.
Using a systematic literature review, [23] showed that single-minute exchanging of die
(SMED) technique should be combined with application of other 9 lean tools such as 5S’s
(five esses), standardized work, kaizen, overall equipment efficiency, total productive
maintenance, poka-yoke, value stream mapping, A3 methodology, and visual management.
According to [24-26], SMED offers many benefits, such as: increased productivity;
eliminates stocks fail due to errors in estimating demand; increased work rates and
production capacity of machines; fewer or no errors in machines setup; improved product
quality; increased security in operations; improved setup times; reduced lot size costs.
Food and beverage industries have faced increasing regulations, which has resulted in
increased costs. These increased costs could be minimized with process improvements and
innovations. A large number of authors have stressed the lack of Lean Manufacturing tools,
and the need of Lean Manufacturing tools in these industries in order to stay competitive
[10, 27, 28, 29].
3
MATEC Web of Conferences 343, 02007 (2021) https://doi.org/10.1051/matecconf/202134302007
MSE 2021
Finished products are sent to the packing room, where they undergo checks on a metal
detector. The product is then placed in a collective packaging and is transported to a high
bay warehouse. The company has a system that monitors each manufactured product.
The production process is carried out on two lines:
• Line 1 - production of triangle sandwiches
• Line 2 - production of baguette sandwiches
The load on the production lines is uneven, as shown in the diagram (Fig. 2). About
58% of all orders are prepared on line 2. Due to the specific features of each line (mainly
due to different packaging technologies), it is not possible to transfer production from line 1
to line 2.
Line 1
Approved
Production Production Nonconforming Capacity Nonconforming
packagings
time [h] time [min] product [pcs] [pcs/min] product %
[pcs]
2333 140000 1554000 11500 11,10 0,74%
Line 2
Approved
Production Production Nonconforming Capacity Nonconforming
packagings
time [h] time [min] product [pcs] [pcs/min] product %
[pcs]
2845 170731 2100000 19000 12,30 0,90%
4
MATEC Web of Conferences 343, 02007 (2021) https://doi.org/10.1051/matecconf/202134302007
MSE 2021
5
MATEC Web of Conferences 343, 02007 (2021) https://doi.org/10.1051/matecconf/202134302007
MSE 2021
During the changeover process, the employees used only the information contained in the
recipes, i.e. concerning the components, weight and the method and sequence of layering.
Workers who performed the changeover did not use the workplace instructions. The entire
staff working on the line, i.e. 12 people, participated in the changeover process. The staff
consisted of one leader, three operators and eight production workers.
The total changeover time was 19 minutes and 34 seconds. The activities performed
during the changeover and their duration are listed in Table 4.
Table 4. Activities registered during the analysis of the changeover process.
9 Exchange of packaging 5
6
MATEC Web of Conferences 343, 02007 (2021) https://doi.org/10.1051/matecconf/202134302007
MSE 2021
produced. The construction of the bread dosing machine makes it possible to load different
types of bread into each compartment. As a result, machine setup may take place when the
previous order is still in progress. The time-consuming activity no. 5, i.e. the exchange of
ingredients, setting the weight and the parameters of the photocells can also be performed
much earlier. It is possible thanks to the mobile design of the machine; it can be put aside
and installed on the production line at any time.
4.4 Improvements
The transformation of activities from internal to external resulted in the reduction of total
changeover time. The complexity of the process required changing many parameters on the
machine control panels during the changeover. In this phase, the parameters have been
permanently programmed. From that moment, the employee would no longer enter them
manually, but only choose the appropriate program for the required product. Fixed
parameters were programmed for labelling machines, photocells, dispensers and weight
data. Additionally, a changeover manual was implemented. It included information on the
sequence of activities performed during the changeover, the number of people required for
the changeover of the given machine, and the estimated time needed to perform the job. As
a result, the production leader responsible for the changeover was well acquainted with the
tasks.
5 Results
The introduction of the SMED method brought tangible benefits to the company. The total
changeover time was reduced by approx. 39%. The following indicators were used to verify
the effectiveness of the SMED method:
EWR - effectiveness of waste reduction
EAC - effectiveness of activity conversion
ETI - effectiveness of technical improvements
TESMED - total effectiveness of the SMED method implementation
The formulas presented in Table 5 were used to determine them.
Table 5. Indicators verifying the effectiveness of the SMED method.
(1)
(2)
(3)
7
MATEC Web of Conferences 343, 02007 (2021) https://doi.org/10.1051/matecconf/202134302007
MSE 2021
(4)
Symbols used:
– duration of internal activities
– duration of external activities
– time savings related to the implementation of improvements
– duration of redundant activities
In order to determine the effectiveness, it was necessary to examine the changeover
times after the implemented improvements. Table 6 shows the times for individual
activities before and after the implementation of the improvements. After the
implementation of SMED, the total changeover time was reduced by over 7 minutes and is
now 12 minutes.
Table 6. Analysis of the SMED method.
1 7 6 1 X
2 5 4 1 X
3 1 0,5 0,5 X
4 1 1 0 X
5 10 7 3 X
6 2 1,5 0,5 X
7 1 0,5 0,5 X
8 5 4 1 X
9 5 2 3 X
10 10 9 1 X
11 5 4 1 X
12 4 3 1 X
13 4 3 1 X
14 16 12 4 X
SUM 76 57,5 18,5
Having collected the data (Table 6), it was possible to designate EWR, EAC, ETI and
TESMED (Table 7).
Table 7. Indicator values for the analyzed production line.
EWR 1
8
MATEC Web of Conferences 343, 02007 (2021) https://doi.org/10.1051/matecconf/202134302007
MSE 2021
EAC 0.79
ETI 0.69
TESMED 0.55
All registered activities turned out to be necessary during the changeover process. Some
of the activities were simplified, thus shortening the time of their execution. The EAC
indicator shows the transformation of activities from internal to external activities. In the
analyzed case, it was successfully done for 3 activities. Other activities are performed while
the line is at standstill. The ETI indicator means that thanks to the introduced improvements
it was possible to shorten the times for many activities. Time savings were achieved for
almost every activity. The TESMED value means that the total changeover time was
significantly reduced. The complete changeover between recipe no. 1 and recipe no. 2 was
shortened by almost 8 minutes.
As a result of the implemented improvements, the changeover time between the
products was significantly reduced, making production line 1 more flexible. The time that
has so far been used to carry out activities during the changeovers can now be spent on
work related directly to production. An increase in efficiency on the tested production line
was observed, from 11.1 pcs / min to 12.3 pcs / min, which means an 11% improvement.
Apart from measurable factors, work safety has also improved.
6 Summary
The use of the SMED method on the selected production line significantly shortened the
total changeover time. A detailed analysis of the process made it possible to quite
accurately define and examine all activities performed during the changeover. The obtained
indicators confirm the effectiveness of the implemented changes. The versatility of the
method enables efficient and effective implementation of improvements. The key to
success in the case of SMED is the appropriate preparation and collection of reliable data,
which must then be subjected to detailed analysis. In line with the assumption made at the
beginning of the paper, it was possible to eliminate waste by saving time. The next step
should be to start working on maintaining the implemented changes.
References
1. A. Galeazzo, Total Quality Management & Business Excellence, 32, 758 (2019)
2. I. Pavlenko, J. Trojanowska, O. Gusak, V. Ivanov, J. Pitel, V. Pavlenko, Periodica Polytechnica
Mechanical Engineering, 63, 52 (2019)
3. J. Bhamu, K. S. Sangwan, International Journal of Operations & Production Management, 34,
876 (2014)
4. J. K. Liker, The Toyota Way. 14 Management Principles from the World’s Greatest
Manufacturer (McGraw-Hill, New York, 2004)
5. T. Ohno, Toyota Production System: Beyond Large-Scale Production (Productivity Press,
Portland, OR, 1988)
6. T. Melton, Chemical Engineering Research and Design, 83, 662 (2005)
7. M. Szczepaniak, J. Trojanowska, Advances in Manufacturing II, Volume 2 - Production
Engineering and Management (Proceedings of Conference MANUFACTURING 2019
Poznan), Methodology of Manufacturing Process Analysis, 281 (Springer, Cham, 2019)
9
MATEC Web of Conferences 343, 02007 (2021) https://doi.org/10.1051/matecconf/202134302007
MSE 2021
8. J. P. Womack, D. T. Jones, Lean Thinking: Banish Waste and Create Wealth in Your
Corporation (Free Press, New York, 2003)
9. A. F. Araújo, M. L. R. Varela, M. S. Gomes, R. C. C. Barreto, J. Trojanowska, Advances in
Manufacturing II, Volume 1 – Solutions for Industry 4.4 (Proceedings of Conference
MANUFACTURING 2019 Poznan), Development of an intelligent and automated system for
lean industrial production adding maximum productivity and efficiency in the production
process, 131 (Springer, Cham, 2018)
10. B. Gładysz, A. Buczacki, C. Haskins, Resources, 9, 144 (2020)
11. M. Butlewski, M. Jasiulewicz-Kaczmarek, A. Misztal, M. Sławińska, Safety and Reliability -
Methodology and Applications (Proceedings of Conference ESREL 2014 Wrocław), Design
methods of reducing human error in practice, 1101 (CRC Press, London, 2015)
12. M. Jasiulewicz-Kaczmarek, A. Saniuk, Advances in Intelligent Systems and Computing 605,
Advances in Social & Occupational Ergonomics (Proceedings of AHFE 2017 Conference
Florida 2016), How to Make Maintenance Processes More Efficient Using Lean Tools, 9
(Springer, Cham, 2017)
13. S. V. Buer, J. O. Strandhagen, F. T. S. Chan, International Journal of Production Research, 56,
2924 (2018)
14. S. V. Buer, M. Semini, J. O. Strandhagen, F. Sgarbossa, International Journal of Production
Research, 59, 1976 (2020)
15. A. Azadegan, P. C. Patel , A. Zangoueinezhad, K. Linderman, Journal of Operations
Management, 31, 193 (2013)
16. D. McCarthy, N. Rich, Lean TPM: A Blueprint for Change (Butterworth, Heinemann, 2015)
17. M. Jasiulewicz-Kaczmarek, T. Bartkowiak, ModTech 2016 - IOP Conf. Series: Materials
Science and Engineering, 145, 042024, Improving the performance of a filling line based on
simulation (Iași, România, 2016)
18. O. Orynycz, K. Tucki, M. Prystasz, Energies, 13, 1184 (2020)
19. A. Shingo, A revolution in manufacturing: the SMED system (Productivity Press, Portland, 1985)
20. J. P. Womack, D. T. Jones, Lean companies. Elimination of waste - the key to success (Manager
Information Center, Warsaw, 2001)
21. J. J. Lopes, M. L. R. Varela, J. Trojanowska, J. Machado, Advances in Intelligent Systems and
Computing 721 (Proceedings of Conference ICITS 2018), Production Flow Improvement in a
Textile Industry, 224 (Springer, Cham, 2018)
22. S. A. Kumar, N. Suresh, Production and Operation Managements (New Age International, New
Delhi, 2008).
23. I. B. da Silva, M. Filho Godinho Filho, The International Journal of Advanced Manufacturing
Technology, 102, 4289 (2019).
24. J. R. Díaz-Reza, J. L. García-Alcaraz, V. Martínez-Loya, J. Blanco-Fernández, E. Jiménez-
Macías, L. Avelar-Sosa, Sustainability, 8, 1237 (2016)
25. R. Godina, C. Pimentel, F. J. G. Silva, J. C. Matias, Procedia Manufacturing, 17, 783 (2018).
26. J. Lozano, J. C. Saenz-Díez, E. Martínez, E. Jiménez E., J. Blanco, Production Planning &
Control, 30, 764 (2019)
27. I. Semenov, L. Filina-Dawidowicz, P. Trojanowski, 36 IBIMA Conference, Information
resources structuring to support decision-making process for organization of sensitive cargo
transportation in the COVID-19 Crisis (Granada, Spain, 2020)
28. N. P. Mahalik, A. N. Nambiar, Trends in Food Science & Technology, 21, 117 (2009)
29. R. B. Lopes, F. Freitas, I. Sousa, I., Journal of Technology Management & Innovation, 10, 120
(2015).
10
© 2021. This work is licensed under
https://creativecommons.org/licenses/by/4.0/ (the “License”).
Notwithstanding the ProQuest Terms and conditions, you
may use this content in accordance with the terms of the
License.