Overhead Line Methodology
Overhead Line Methodology
Soukayna Jermouni
Álvaro Benito Oliva
Ignacio Álvarez Iberlucea
Meyer Montagner Murcian 1
1
Provided essential software knowledge
Abstract
Abstract
This methodology describes the design process to calculate an overhead line that connects the
so- lar plant’s station facility with the grid’s point of interconnection. The objective of this
document is to present the main steps followed to calculate the electrical and mechanical
characteristics of an overhead line.
An overhead line design goes through several stages from planning to execution. This document
will focus on explaining the stages that are in between. Following are the topics that will be
covered in this document to explain the design of the overhead line:
Note: All the calculations that are presented in this document are carried out according to the
IEC and EN standards.
Overhead line 1
Conten
Contents
Abstract 1
2 Phase conductor 12
2.1 Conductor’s type...........................................................................................................12
2.1.1 Medium voltage conductors.............................................................................12
2.1.2 High voltage conductors...................................................................................13
2.2 Selection criteria............................................................................................................13
2.2.1 Maximum admissible current...........................................................................13
2.2.2 Minimum tensile strength.................................................................................16
2.2.3 Voltage gradient................................................................................................16
2.3 Bundle calculation.........................................................................................................17
3 Earth Wire 19
3.1 Earth wire type..............................................................................................................19
3.2 Earth wire selection.......................................................................................................20
4 Tower Selection 21
4.1 Towers types..................................................................................................................21
4.1.1 Medium voltage towers....................................................................................21
4.1.2 High voltage towers..........................................................................................22
4.2 Towers selection criteria................................................................................................23
4.3 Circuit selection.............................................................................................................23
5 Insulation coordination 25
5.1 General procedure.........................................................................................................25
5.2 Determination of withstand voltage..............................................................................26
Overhead line 2
Conten
6 Insulators 27
6.1 Insulator’s types . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 27
6.1.1 Medium voltage insulator . . . . . . . . . . . . . . . . . . . . . . . . . . 27
6.1.2 High voltage insulator . . . . . . . . . . . . . . . . . . . . . . . . . . . . 28
6.2 Selection criteria . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 29
6.2.1 Electrical criterion . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 29
6.2.2 Mechanical criterion . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 30
7 Clearances 32
7.1 Electrical clearances . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 32
7.1.1 Phase to phase clearances . . . . . . . . . . . . . . . . . . . . . . . . . . 33
7.1.2 Phase to earth clearances . . . . . . . . . . . . . . . . . . . . . . . . . . 34
7.2 Mid-span clearances . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 35
7.3 Safety distances . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 39
8 Tower geometry 41
8.1 General procedure . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 41
8.2 Peak distance calculation . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 42
8.3 Standard towers top-geometry . . . . . . . . . . . . . . . . . . . . . . . . . . . . 43
9 Electrical calculation 45
9.1 Electrical models . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 45
9.1.1 Distributed Parameters Model . . . . . . . . . . . . . . . . . . . . . . . . 46
9.2 Electrical Parameters . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 47
9.2.1 Geometrical Mean Distance . . . . . . . . . . . . . . . . . . . . . . . . . 48
9.2.2 Geometrical Mean Radius . . . . . . . . . . . . . . . . . . . . . . . . . . 50
9.2.3 Resistance . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 51
9.2.4 Inductance and Reactance . . . . . . . . . . . . . . . . . . . . . . . . . . 51
9.2.5 Impedance . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 53
9.2.6 Capacitance and Susceptance . . . . . . . . . . . . . . . . . . . . . . . . 53
9.3 Voltage drop . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 54
9.4 Power factor . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 55
9.5 Losses . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 55
9.5.1 Joule effect . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 55
9.5.2 Corona losses . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 56
10 Mechanical calculation 58
10.1 Conductor Loads hypothesis . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 58
10.2 Loads calculation . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 59
10.2.1 Weight loads . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 59
10.2.2 Wind loads . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 59
10.2.3 Ice loads . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 61
10.2.4 Total loads . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 62
10.3 Catenary . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 62
10.3.1 Catenary curve calculation . . . . . . . . . . . . . . . . . . . . . . . . . 62
10.3.2 Horizontal tension . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 64
10.3.3 State change equation . . . . . . . . . . . . . . . . . . . . . . . . . . . . 65
10.4 Tower forces . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 66
10.4.1 Tower load hypothesis . . . . . . . . . . . . . . . . . . . . . . . . . . . . 67
10.4.2 Vertical forces . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 67
Overhead line 3
Conten
11 Tower spotting 70
11.1 Considerations...............................................................................................................70
11.2 Spotting process............................................................................................................70
11.2.1 Distance check..................................................................................................71
11.2.2 Ground clearance validation.............................................................................71
11.2.3 Valid towers spotting........................................................................................73
Bibliography 74
C Mechanical calculations 83
C.1 Calculation of the loads.................................................................................................83
C.2 Maximum horizontal tension.........................................................................................84
C.3 Horizontal tension calculation.......................................................................................86
C.4 Catenary calculation......................................................................................................86
C.5 Tower forces..................................................................................................................87
C.5.1 Vertical forces...................................................................................................88
C.5.2 Transversal forces.............................................................................................88
C.5.3 Longitudinal forces...........................................................................................89
Overhead line 4
List of
List of Figures
4.1 MV line towers shape: (a)Single fork tower | (b)MV Double fork tower.....................22
4.2 HV line towers shape: (a) Single S tower | (b) Single Pi tower | (c) Double T tower
| (d) HV Double fork tower............................................................................................23
11.1 The distance check: (a) User line path | (b) Path filtering | (c) Possible towers
location | (d) Suspension towers are added
71
11.2 The ground clearance validation...................................................................................72
11.3 Tower spotting sample..................................................................................................73
Overhead line 5
List of
List of Tables
6.1 Long-rod insulators according to IEC. Source IEC 60433 [14] and [15].....................28
6.2 Cap-and-pin insulators according to IEC. Source: [13] and [15]..................................29
6.3 The expected tensile strength for insulators..................................................................31
7.1 The minimum standard clearances pp and pe. Source: EN standard [17]....................33
7.2 The minimum standard clearances pp and pe [Source EN]..........................................38
10.1 Ice loads for different countries for a conductor with a 30 mm diameter. [Source:
[3] . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 61
Overhead line 6
Chapter 1. Overhead line
Chapter 1
In this chapter the overhead line’s main elements and design criteria will be described.
On the other hand, in the case of choosing a substation as the plant’s interconnection
facility, the station will have a high voltage at the receiving end which will define a
transmission line to evacuate the generated capacity.
Furthermore, the minimum medium voltage considered is 5kV and the maximum is 45kV.
Mean- while, the high voltage level starts from 46kV up to 400kV.
The overhead line is designed to connect the plant’s interconnection facility at its voltage level;
hence, the maximum high voltage accepted is 400kV as it is the highest acceptable voltage in
the plant’s substation.
Furthermore, to ensure the capability of the line, a maximum capacity that the line can evacuate
is limited by both its voltage and length. Therefore, a thermal limit as well as a voltage drop and
a power loss limit must be respected. In this regard, a voltage drop and a power loss of 5% [1] is
considered as the maximum permissible.
On the other hand, the maximum voltage gradient on the conductor surface that is considered
in selecting the conductor section is designed as 17kV/cm [1].
Overhead line 7
Chapter 1. Overhead line
Regarding the reactive power, no way of compensation is considered in this methodology. The
power factor at the receiving end is calculated accordingly and its calculation will be presented
through this methodology.
Based on several test cases that include different line lengths (short, medium, and long),
different voltage levels from 5kV to 400kV, and different capacities, the resulting line
feasibility is con- strained to comply with the voltage drop and power loss limitation. This is
also called electrical loadability of the line. In Figure 1.1 the maximum line lengths depending
on the capacity and voltage that will guarantee the performance of the line are presented,
these lengths are results of several tests as mentioned.
Overhead line 8
Chapter 1. Overhead line
1.5.2 Spans
The line’s blocks are themselves characterized by the different spans that are used further in
mechanical calculations. In this section, the types of the spans considered in the calculation are
depicted.
Length span
The length span is the distance between two adjacent towers taking into account the elevation
difference between the two towers.
Weight span
The weight span is the distance between the lowest points of the sags in two adjacent spans. The
lowest points are calculated from the catenary of the line. Moreover, the weight span represents
the vertical load applied to the tower due to the weight of the conductor.
Wind span
The wind span is defined as half of the sum of two adjacent spans in a profile view. The wind
span represents the horizontal load applied on the tower due to the wind blowing on the
conductor.
Ruling span
On the other hand, the ruling span is considered as a mean span within a block. Each block
has its ruling span that is used to approximately represent its mechanical characteristics. The
Overhead line 9
Chapter 1. Overhead line
theoretical ruling span is calculated to simplify the sagging calculation of the conductors, and it
is calculated using Equation (1.1) by making the assumption that the towers are of equal
elevations and that the horizontal tension is constant throughout the block.
√︂
𝑆𝑟 = (1.1)
Σ𝑆
Σ𝑆3
Where:
The towers that are used throughout this methodology are lattice steel towers of three types:
• Suspension tower: It carries the conductor when the line is straight, the longer the blocks
with suspension towers the better the investment of the line would be.
• Angle tower: It carries the conductor where the line deflects and changes direction.
Unlike the suspension towers, they support more tensile forces from the conductors.
• Dead-end towers: They are the towers at both ends of the line, they are usually connected
to the substation’s portals that generally leads to higher load at both ends.
Overhead line 1
Chapter 1. Overhead line
• Suspension insulator: It is the insulator connecting the conductor to the suspension tower
when the line is straight.
• Tension insulator: It is the insulator that attaches the conductors to angle or dead-end
towers, it always follows the straining of the conductor.
Overhead line 1
Chapter 2. Phase
Chapter 2
Phase conductor
The overhead line conductors correspond to up to 50% of the total investment of the line [ 3];
hence, the importance of the selection criteria of the conductor’s section and its bundles. In this
chapter, the type of the phase conductors that are considered will be described, the selection
consideration will be depicted, and the bundle calculation will be presented.
The conductors that were chosen in this methodology are of two types, conductors that are used
for medium voltage lines and made of Aluminum and conductors that are used in high voltage
lines which are made of a composition of Aluminum and steel. Both types of conductors are
designed following the IEC standard 61089 [3].
From the standardized conductors, several parameters are extracted such as the cross-section,
the number of stranding, the nominal diameter, the weight, and the rated strength of the
conductor.
Moreover, other parameters are considered based on [3] to calculate the resistance of the con-
ductor as well as its mechanical characteristics; these parameters are:
−8
The resistivity of an Aluminum conductor of type A and B being: 𝜌 = 3.27 · 10 Ω𝑚
−6◦
The coefficient of linear thermal expansion of an Aluminum alloy conductor being 𝛼 = 23 · 10 𝐶 −1
And the elasticity of the Aluminum alloy conductor being 𝐸 = 55.6 · 109𝑃𝑎
Overhead line 1
Chapter 2. Phase
This latter’s designation is defined with a number that corresponds to the cross-section of the
conductor and two codes that represent the composition materials. Using the standardized con-
ductors, some mechanical parameters are extracted such as the section, the number of stranding,
the nominal diameter, the unitary weight, and the rated strength of the conductor.
These previous parameters along with others that are specific to ACSR conductors are used to
select the right conductor of the line and to calculate further mechanical characteristics. The
specific parameters are:
The elasticity of the Aluminum steel reinforced of the conductor being 𝐸 = 190 · 109𝑃𝑎
The coefficient of linear thermal expansion of an Aluminum steel reinforced conductor being
− ◦
𝛼 = 11.5 · 10 6 𝐶 −1
Therefore, two main criteria are investigated, an electrical criterion to check the thermal limit of
the conductor and a mechanical criterion that guarantee the strength withstand of this latter.
In addition, in this methodology, the conductors undergo a selection based on the voltage gra-
dient, the voltage drop and the power loss limits. The compliant conductor, therefore, must
withstand the thermal unit, comply with the voltage gradient and voltage drop maximum limits,
and must withstand the corresponding tensile strength in the line.
For given ambient conditions, the maximum admissible current is calculated based on the con-
ductor’s predetermined temperature and its DC resistance at maximum temperature [4]. To cal-
culate the DC resistance of the conductor at maximum temperature Equation (2.1) is used:
Where:
Overhead line 1
Chapter 2. Phase
• 𝑅𝑇 is the electrical resistance of the conductor per unit length at maximum temperature T
[Ω/𝑚]
◦
• 𝑅𝑇𝑓 is the DC resistance per unit length at a reference temperature being 20 𝐶 [Ω/𝑚]
−3 ◦
• 𝛼 is the variation of the resistance with temperature being 4.03 · 10 [1/ 𝐶]
◦
• 𝑇𝑚𝑎𝑥 is the maximum temperature being 80 [ 𝐶]
𝜌
𝑅𝑇𝑓 = (2.2)
𝑠
Where:
• 𝑅𝑇𝑓 is the electrical resistance of the conductor per unit length at reference temperature T
◦
being 20 𝐶 [Ω/𝑚]
• 𝜌 is the resistivity of the conductor [Ω · 𝑚]
• 𝑠 is the cross-section of the conductor [𝑚2]
To calculate the maximum admissible current a heat balance at the conductor should be reached;
this heat balance is determined based on the solar heat gained by the conductor surface, the heat
loss by convection, and the heat loss caused by radiation of the conductor.
Using the unit length DC resistance at maximum temperature of the conducto;, the heat
balanced is reflected in Equation (2.3):
√
𝐼𝑚𝑎𝑥 = ︂ 𝑁𝑅 + 𝑁𝐶 − 𝑁𝑆 (2.3)
𝑅𝑇
Where:
Given the nominal diameter of the conductor, the heat loss by radiation is given by the following
equation:
Where:
Overhead line 1
Chapter 2. Phase
Where:
Where:
−1.78
𝑅𝑒 = 1.644 · 109 · 𝑑 · 𝑣 · [𝑇𝑎𝑚 + 0.5 · (𝑇𝑚𝑎𝑥 − 𝑇𝑎𝑚)] (2.7)
Where:
The solar heat gain by the conductor’s surface is calculated by the following equation:
Overhead line 1
Chapter 2. Phase
𝑁𝑆 = 𝑌 · 𝑑 · 𝑆𝑖 (2.8)
Where:
Table 2.1: The target allowable span lengths [Source: own elaboration]
Rated voltage
Target span [m]
𝑈 [kV]
⩽24 100
⩽220
⩽132 250
200
⩽400 300
>400 400
The minimum tensile strength values depending on the target spans were obtained with an em-
pirical approach which consisted in analyzing different lines with different conductors under
several voltage levels. As the tensile strength is directly related to the catenary of the conduc-
tor, it is concluded that the weaker conductors will result in higher catenaries and to avoid not
respecting the target span lengths, a minimum tensile strength limit is defined based on the al-
lowable span length as seen in Table 2.2.
⩽100 20000
⩽200 45000
⩽250 60000
⩽300 75000
>300 90000
Overhead line 1
Chapter 2. Phase
The voltage gradient of a conductor is calculated using the following Equation (A.7)
𝐸= �
2 𝐶𝑖 [1 + 2 · (𝑟 /𝑠) (𝑛2 − 1) · 𝑠𝑖𝑛(𝜋 /𝑛2)] √ (2.9)
� 𝜋𝜖0 · 𝑛2 · 𝑟 3 · 100
Where:
In addition to the voltage gradient limit, the selected cross-section conductor must comply with
the voltage drop and losses limit which are considered as 5% based on [3].
Furthermore, in the case of not finding a compliant conductor per phase according to the voltage
gradient limit, the number of sub-conductors per bundle is increased till a convenient cross-
section is selected.
Overhead line 1
Chapter 2. Phase
Overhead line 1
Chapter 3. Earth
Chapter 3
Earth Wire
Lightning strike is one of the main reasons behind the sudden outages of an overhead line, and
the earth wire comes as a protection schema to reduce these unexpected outages.
Therefore, the earth wire’s main function is to not only to protect the phase conductors
from possible lightning but also to return the phase-to-earth short-circuit current. Consequently,
they should be designed and specified adequately to serve their function.
◦ ◦
In addition, an earth wire is installed with a shield angle that is defined between 10 and 35 ; in
◦
this methodology, the earth wires are designed with a shield angle of 30 .
The earth wires chosen in this methodology are of optical fiber wire type (OPGW) to extend
their purposes and be used to carry telecommunication signals as well. The said earth wires are
obtained from [6] and designed according to IEC 60794-4 and IEC 61395.
Overhead line 1
Chapter 3. Earth
Based on the line’s maximum voltage, the design short-circuit current is calculated according to
the IEC standard [7], [8], [9], and [10] moreover, the short-circuit time is taken as 0.3s. Hence,
the short-circuit design capacity is calculated using Equation (3.1) and compared to the earth
wire’s short-circuit capacity. The earth wire that withstands the said capacity is selected.
Where:
Overhead line 2
Chapter 4. Tower
Chapter 4
Tower Selection
The overhead line towers are another important component in granting the right-of-way as well
as in the investment of the power line, depending on their design and material, the cost of the
line can change remarkably. Therefore, the towers not only define the aesthetic of the line but
also determine its reliability by withstanding the conductor’s forces and loads.
In this chapter the overhead line’s towers will be described, their types upon voltage level and
number of circuit selection criteria will be presented.
• Single fork tower: is a tower with one circuit (Simplex) and one earth wire arrangement
and it has the shape of a fork with its three crossarms being in one side.
• MV Double fork tower: is a tower with two circuits (Duplex) and two earth wires
ar- rangement and it has the shape of two forks with one circuit crossarms being in
one side and the other circuit in the opposite side.
The two MV towers are illustrated in Figure 4.1 following the order listed above.
Overhead line 2
Chapter 4. Tower
Figure 4.1: MV line towers shape: (a)Single fork tower | (b)MV Double fork tower
• S shape tower: is a tower with one circuit (Simplex) one earth wire arrangement and
it has a shape of an S letter with 2 cross arms in one side and the third in the opposite
side.
• Single Pi tower: is a tower with one circuit (Simplex) and two earth wires
arrangement; it has the shape of the Greek letter Pi with the three phases aligned
horizontally.
• Double T tower: is a tower with two circuits (Duplex) and two earth wires
arrangement and it has the shape of the letter T with two levels, one circuit cross-arms
being in one side and the other circuit in the opposite side.
• HV Double fork tower: similar to the MV double fork tower, it is a tower with two
circuits (Duplex) and two earth wires arrangement and it has the shape of two forks
with one circuit cross-arms being in one side and the other circuit in the opposite side.
The difference with its MV similar is the middle cross-arms being longer than the others.
The HV towers shape are shown in the Figure 4.2 following the order listed above.
Overhead line 2
Chapter 4. Tower
Figure 4.2: HV line towers shape: (a) Single S tower | (b) Single Pi tower | (c) Double T tower |
(d) HV Double fork tower
To select the right tower in this methodology, a voltage and circuit arrangement criteria were
considered. For each voltage level, MV or HV, depending on the number of circuits as well as
the voltage itself, a tower type is selected. The different voltage levels considered in the towers
selection is presented in Table 4.1.
Overhead line 2
Chapter 4. Tower
Overhead line 2
Chapter 5. Insulation
Chapter 5
Insulation coordination
As mentioned in a previous chapter, the reliability of an overhead line is impacted by the elec-
trical and mechanical performance of the line. Consequently, tower electrical clearances play
an important role to reach a good mechanical performance. More particularly, the design of the
insulation coordination under, not only, temporary stresses but also different over-voltages is
crucial in defining the electrical clearances.
In this chapter, the insulation coordination design of the overhead line is described in obedi-
ence with the IEC standard [11]. The selection of the insulation levels will be explained and the
calculation of the withstand voltage to ensure the insulation of the system is stated.
The voltages are classified into two classes based on the IEC standard [11], and for each class
only some of the over-voltages are considered to calculate the withstand voltage. For class I
voltages (From 1kV to 245kV) both the temporary and the fast-front over-voltages are
considered. On the other hand, for class II voltages (Starting from 245kV) the fast-front and
slow-front over-voltages are considered in the calculation.
A detailed review of the procedure is shown in the substation methodology [12] chapter 4 where
the procedure details for class I and II are presented according to the IEC standard.
However, the insulation coordination procedure of an overhead line has few considerations that
are different from the procedure followed for the substation. To calculate the power frequency
over-voltage, the discharge factor of the earth fault for the overhead line calculation is
considered as 1.3 instead of 1.4 for the substation. Moreover, the defect factor is also considered
as 1.3 for the overhead line.
In addition to that, another difference in determining the withstand voltage for the overhead
line is the termination of the procedure followed in the substation when finding the required
withstand voltage [11].
Overhead line 2
Chapter 5. Insulation
√︁
𝑈𝑒𝑡 + 0.25
𝐸2 = · 𝑈 · 2/3 (5.1)
1.
Where:
Overhead line 2
Chapter 6.
Chapter 6
Insulators
The insulator plays important electrical and mechanical roles in the overhead line design, it
is, therefore, necessary to design it considering the insulation performance and the mechanical
withstand.
In this chapter the insulator’s types upon voltage level are described and the criteria used to
select the adequate insulator is presented.
In the following Table 6.1, the insulators used in this methodology are listed with their corre-
sponding lightning impulse, minimum failing load, diameter and maximum length.
Overhead line 2
Chapter 6.
Table 6.1: Long-rod insulators according to IEC. Source IEC 60433 [14] and [15]
lightningFailing impulse [V]load [N] MaximumMinimum length [m]creepage [m]
Designation Diameter [m]
Overhead line 2
Chapter 6.
Table 6.2: Cap-and-pin insulators according to IEC. Source: [13] and [15]
lightningFailing impulse [V]load [N] Maximum length [m] Minimum creepage [m]
Designation Diameter [m] Weight [kg]
𝑛𝑛𝑜𝑟𝑚𝑎𝑙 ⪖ 𝑈𝑠 · 𝜖0 (6.1)
𝜖
Where:
• 𝑛𝑛𝑜𝑟𝑚𝑎𝑙 is the number of elements necessary to withstand maximum voltage under normal
conditions
• 𝑈𝑠 is the maximum voltage of the system [𝑉 ]
−6
• 𝜖0 is the minimum nominal creepage for a medium level of polution being 20 · 10 accord-
ing to IEC [11] and [16] [𝑚/𝑉 ]
• 𝜖 is the insulator creepage distance [𝑚]
𝑈𝑝 𝑓
𝑛 𝑤𝑒𝑡 ⪖ (6.2)
𝑈𝑤
Overhead line 2
Chapter 6.
Where:
• 𝑛 𝑤𝑒𝑡 is the number of elements necessary to withstand maximum voltage under wet con-
ditions
• 𝑈𝑝 𝑓 is the maximum power frequency voltage [𝑉 ]
• 𝑈𝑤 is the long term wet voltage of the insulator [𝑉 ]
𝑈𝑓 𝑓
𝑛𝑖𝑚𝑝𝑢𝑙𝑠𝑒 ⪖ (6.3)
𝑈𝑙
Where:
• 𝑛𝑖𝑚𝑝𝑢𝑙𝑠𝑒 is the number of elements necessary to withstand maximum voltage under light-
ning impulse
• 𝑈𝑓 𝑓 is the maximum lightning withstand voltage [𝑉 ]
• 𝑈𝑙 is the maximum lightning voltage of the insulator [𝑉 ]
The number of elements composing the insulator string is the biggest number of elements
among the three conditions calculated above. On the other hand, the insulator string must
comply with the minimum clearance phase to earth to guarantee the clearances respect for
all parts of the tower. To validate the insulator length a safety factor is applied to the
minimum phase-earth clearance to consider possible swing angle, then the length of the
insulator is calculated using Equation (6.4).
Where:
The insulator length calculated above, should be higher than the minimum length defined by
the phase to earth clearance such as: 𝑑𝑒𝑙 1.1 for the insulator to be electrically valid. Once the
·
electrical insulator is selected, the insulator parameters such as the length, weight or minimum
creepage are calculated upon the number of its elements.
Overhead line 3
Chapter 6.
From the possible insulator combinations, the insulator with the closest minimum failing load
to the expected tensile strength is selected, this latter is the typical tensile strength of insulators
depending on the voltage. In Table 6.3 the expected tensile strength is chosen based on several
study cases from Spain.
Ultimately, the insulators that have a minimum failing load closest one to the expected tensile
strength are the candidates that respect both the electrical and mechanical criteria. However,
there is a possibility to get two insulators with same tensile strength, and to select the appropri-
ate one, the insulator with the least length and creepage distance is prioritized by giving more
importance to minimizing the length.
Overhead line 3
Chapter 7.
Chapter 7
Clearances
There are several types of electrical clearances, some are determined to prevent disruptive dis-
charges between the conductor and the earthed tower, others to prevent disruptive discharges
between phase conductors. In addition, there are mid-span clearances that need to be respected
during wind conditions and other safety clearances to obstacles or possible objects in the path.
In this chapter the electrical clearances covered in this methodology will be described.
For each over-voltage stress, the required withstand voltage is calculated and used to determine
the required electrical clearances phase-phase and phase-earth. Following, the clearances for-
mulas are presented for each voltage stress.
After the calculation of phase to phase and phase to earth clearances for each over-voltage, the
maximum clearances among them are chosen and compared against standard clearances accord-
ing to EN 50341 [17]. Based on the voltage of the system, as listed in the Table 7.1, standard
phase to phase and phase to earth clearances are selected. The maximum between the clearances
calcu- lated and the standard values are the final minimum clearances to be respected when
designing the towers.
Overhead line 3
Chapter 7.
Table 7.1: The minimum standard clearances pp and pe. Source: EN standard [17]
Fast-front overvoltages
Where:
Slow-front overvoltages
𝐷𝑝𝑝 −𝑠 𝑓
1.4 · 𝐾𝑐𝑠 · 𝑈2%𝑠 𝑓
1080 · 𝐾𝑎 · 𝐾𝑧−𝑠 𝑓 · 𝐾𝑔−𝑠𝑓 = 2.17 · −1
(7.2)
Wher
Overhead line 3
Chapter 7.
𝑈 0.833
−
𝑒𝑥𝑝 1
𝐷𝑝𝑝−𝑝𝑓 = 1.64 · 750 · 𝐾 · �𝐾𝑧 −𝑝 𝑓 · 𝐾𝑔−𝑝 𝑓 (7.3)
Where:
• 𝐷𝑝𝑝−𝑝𝑓 is the phase to phase clearance with power frequency voltages [𝑚]
• 𝑈 is the maximum voltage of the system [𝑘𝑉 ]
• 𝐾𝑎 is the altitude factor
• 𝐾𝑧−𝑝 𝑓 is the deviation factor for power frequency voltages being 0.910 according to [3]
• 𝐾𝑔−𝑝𝑓 is the gap factor for power frequency voltages being 1.26 according to [3]
Fast-front overvoltages
𝑈 90% 𝑓 𝑓 −𝑖𝑛𝑠
𝐷𝑝𝑒 − 𝑓 𝑓 = (7.4)
530 · 𝐾𝑎 · 𝐾𝑧 − 𝑓 𝑓 · 𝐾𝑔− 𝑓 𝑓
Where:
Slow-front overvoltages
Overhead line 3
Chapter 7.
• 𝐷𝑝𝑝−𝑝𝑓 is the phase to earth clearance with power frequency voltages [𝑚]
• 𝑈 is the maximum voltage of the system [𝑘𝑉 ]
• 𝐾𝑎 is the altitude factor
• 𝐾𝑧−𝑝 𝑓 is the deviation factor for power frequency voltages being 0.910 according to [3]
• 𝐾𝑔−𝑝𝑓 is the gap factor for power frequency voltages being 1.26 according to [3]
Therefore, to calculate the mid-span clearances, the swing angle of the conductor is calculated
to determine the most unfavorable position of the phase conductors in the span.
Swing angle
The swing angle is calculated to consider possible wind actions on the conductors and
insulators; in this methodology, it is calculated considering an extreme wind speed. The swing
angle defines a swung position of the conductors that determines the mid-span clearance.
Consequently, using Equations (7.7) and (7.10) the swing angles of either a phase conductor or
an insulator with a conductor are calculated for a wind speed of 120 km/h. Figure 7.1 shows an
illustration of a swing angle of an insulator.
Overhead line 3
Chapter 7.
"
𝜙𝑐 = 𝑡𝑎𝑛𝑔 −1 (𝜌/2) · 𝐶𝑐 · 𝑉 2 · 𝐺𝐿 · 𝐷 · 𝑎𝑤
(7.7)
𝑚𝐶 · 𝑔 �· 𝑎𝑤𝑔
Where:
The air density is calculated using the following equation according to [3] :
298
𝜌 = 𝜌0 𝑇+ 𝑒𝑥𝑝 (−0.00012 · 𝐻 ) (7.8)
Where:
Overhead line 3
Chapter 7.
The span factor used to calculate the swing angle is calculated according to the IEC standard
[18] as follows:
−10 −7 −4
𝐺𝐿 = (4 · 10 · 𝑎3 ) − (5 · 10 · 𝑎2 ) − (10 · 𝑎𝑤) + 1.0403 (7.9)
𝑤 𝑤
Where:
"
(𝜌/2) · 𝐶𝑐 · 𝑉 2 · 𝐺𝐿 · 𝐷 · 𝑎𝑤 + 𝑄𝑊 𝑖𝑛𝑑 /2
𝜙𝑖𝑛𝑠 = 𝑡𝑎𝑛𝑔 −1 � (7.10)
𝑊𝐶 + 𝑊𝑖𝑛𝑠 /2
Where:
The wind load on the insulator set is calculated according to the IEC standard [18]
Where:
Overhead line 3
Chapter 7.
• 𝐴𝑖𝑛𝑠 is the area exposed by the insulator set; the area is considered as a rectangle multi-
plying the insulator diameter with its length [𝑚𝑚]
The wind pressure is calculated based on the air density according to the IEC 60826 standard
[18]:
𝑃 = 1/2 · 𝜌 · 𝑉 2 (7.12)
�
Where:
Calculating the swing angle for a conductor, allows the calculation of the mid-span clearances,
both phase-phase and phase-earth. [3]
The phase to phase mid-span clearance is the distance between two parallel phase conductors
and it is calculated as follows:
√︁
𝑐𝑚𝑖𝑛 −𝑝𝑝 = 𝐾𝑐 𝑓𝑐 + 𝑙𝑘 + 0.75 · 𝐷𝑝𝑝 (7.13)
Where:
The phase to earth mid-span clearance is the distance between the phase conductors and the
earth wire and it is calculated as follows:
Overhead line 3
Chapter 7.
√︁
𝑐𝑚𝑖𝑛 −𝑝𝑒 = 𝐾𝑐 𝑓𝑐 + 𝑙𝑘 + 0.75 · 𝐷𝑝𝑒 (7.14)
Where:
Finally, after calculating the phase to phase and phase to earth clearances at the middle of the
span, the mid-span clearance of each tower is considered as the maximum between those of its
previous and next spans.
The minimum ground clearance is the minimum distance to the ground that all the catenaries in
the line’s spans must respect. This distance is calculated considering the electrical phase to earth
clearance and it is considered from the lowest point of the conductor catenary. Accordingly, the
minimum ground clearance is calculated using Equation (7.15).
Overhead line 3
Chapter 7.
Where:
The minimum distance to object is the minimum distance that a user should consider in case of
crossing an object such as a building in the line’s path. This distance is calculated using
Equation (7.16) as follows:
Where:
Overhead line 4
Chapter 8. Tower
Chapter 8
Tower geometry
The top-geometry of the line’s towers is determined based on all the parameters explained in the
previous chapters. The clearances between the conductors, the clearances between the conductor
and the earthed parts of the tower, the mid-span clearances, and the effect of the wind action on
the conductor and the insulator are all considered when designing a tower’s top-geometry to
ensure the reliability of the line.
In this chapter the line’s towers top-geometry calculation is explained and the different param-
eters that define the tower’s parts are described.
• The tower is defined with nodes that represent the possible connections of the conductor
and insulator with the tower’s cross-arms and body, an example of these nodes is
illustrated in Figure 8.1.
• The coordinates of each node are determined based on the electrical and mid-span clear-
ances calculated previously
• Based on the tower category, either suspension or angle, some parameters such as the
swing angle is calculated to define the peak distance
• From the nodes’ coordinates, the tower’s components and distances are calculated:
Overhead line 4
Chapter 8. Tower
• If a standard tower that meets this methodology’s design criteria is found, it gets selected,
if not, the tower calculated based on the procedure above is considered instead.
Moreover, this distance is compared against the phase-earth midspan clearance calculated pre-
viously to consider the highest distance and ensure the respect of all the clearances.
Where:
Overhead line 4
Chapter 8. Tower
The dimensions of the standard towers listed in tables 8.1 to Table 8.5 are used to select the
final tower’s top-geometry for the MV and HV voltage levels.
Type a b c h
N0 1 1.2 1.25 1.5
N1 1.25 1.2 1.5 1.5
N2 1.5 1.8 1.75 1.5
Type a b c h
S3 3 3.3 3.2 –
S4 4.1 4.4 4.3 –
S5 4.1 5.5 3.3 –
S3C 3 3.3 3.2 4.3
S4C 4.1 4.4 4.3 5.9
S5C 4.1 5.5 3.3 5.9
Type a b c h
D3 3 13.5 7.5 4.3
D5 3.2 15 8.6 4.3
D7 3.8 17 9.4 5.5
Overhead line 4
Chapter 8. Tower
Overhead line 4
Chapter 9. Electrical
Chapter 9
Electrical calculation
The main purpose of an overhead line is to carry the electrical energy from the generation point
to the delivery point. Therefore, calculating the electrical characteristics of the line is essential
in order to ensure a reliable transmission of the energy. A poorly designed overhead line from
an electrical perspective could cause instability and excessive losses.
The quality of the design will depend on the conductor selection and the circuit arrangement,
which will determine the electrical parameters of the line. This chapter presents the basic formu-
lae for calculating the electrical parameters of the line, as well as the voltage drop, power losses
and power factor.
• Short-Line model: The equivalent circuit shown in Figure 9.1 only takes into account the
effect of the resistance and the reactance of the conductor, disregarding the effect of the
capacitance of the line. The Short-Line model is only used for lengths up to 80 km, losing
accuracy for longer lines.
Overhead line 4
Chapter 9. Electrical
model, but the complexity of the calculation increases. The Pi model is used for lines with
a length up to 300 km.
The model is based on four electrical parameters: resistance (R), inductance (X), susceptance
(B) and conductance (G), which will be discussed in later sections of the chapter. A typical
simplifi- cation that is done is to not consider the conductance G due to its residual effect on
the result.
In order to calculate the behavior of the circuit, the differential equations of the electrical model
have to be solved, knowing the values of the voltage and current at the sending end (substation
point) Vs and Is.
Equations (9.1) and (9.2) represent the differential equations of the distributed parameters model:
𝑑𝑈 𝑑𝑥
−→ = (𝑅 + 𝑗𝑋 ) · 𝐼→
Overhead line 4
Chapter 9. Electrical
(9.1)
Overhead line 4
Chapter 9. Electrical
→
𝑑𝐼
– = (𝐺 + 𝑗𝐵) · 𝑈→ (9.2)
�
From the previous expressions, the following equations can be deduced [3] :
! !
→ − → · → → + → · →
𝑈 𝑠 𝐼 𝑠 𝑍 0 𝑈 𝑠 𝐼 𝑠 𝑍 0
𝑈→ = · exp (𝛾 · 𝑥 ) + · exp (−𝛾 · 𝑥 ) (9.3)
2 2
! !
→ → → → → →
𝐼 𝑠 − 𝑈 𝑠 /𝑍 0 𝐼 𝑠 + 𝑈 𝑠 /𝑍 0
𝐼→ = 2 · exp (𝛾 · 𝑥 ) + 2 · exp (−𝛾 · 𝑥 ) (9.4)
Where:
Equations (9.3) and (9.4) represent the distributed parameters model using exponential
equations. However, there is another way to represent the equations using hyperbolic functions,
that derives in the following expressions [3]:
It is important to note that the electrical parameters will not only depend on the conductor’s
material and composition, but also on their geometrical disposition throughout the line.
Overhead line 4
Chapter 9. Electrical
The calculation of the GMD depends on the number of circuits installed in the line. This section
only covers the calculation of the GMD of configurations with one circuit and with two circuits,
which are the most widely used configurations.
In Figure 9.5, an example configuration of a one circuit configuration is shown, with the three
phase conductors separated by distances 𝐷𝑎𝑏, 𝐷𝑎𝑐 𝑎𝑛𝑑 𝐷𝑏𝑐 .
Figure 9.4: Phases of a tower with one circuit for the GMD calculation
The GMD in this case can be calculated according to Equation (9.9) , where Dij refers to the
distance between phase i and phase j :
√︁
𝐺𝑀𝐷 = 𝐷𝑎𝑏 · 𝐷𝑎𝑐 · 𝐷𝑏𝑐
3
(9.9)
The two circuits configuration is shown in Figure 9.5, where the first circuit is formed by con-
ductors a, b and c and the second circuit is formed by conductors a’, b’ and c’.
Overhead line 4
Chapter 9. Electrical
Figure 9.5: Phases of a tower with two circuits for the GMD calculation
In this case, the GMD will be calculated according to Equations (9.10), (9.11), (9.12) and (9.13):
√︁
𝐷𝐴𝐵 = 𝐷𝑎𝑏 · 𝐷𝑎𝑏 ′ · 𝐷𝑎′𝑏 · 𝐷𝑎′𝑏 ′
4
(9.10)
√︁
4
′ ′ ′ ′𝐷 =
√︁
𝐷𝐶𝐴𝐷= 𝐷𝑐𝑎· ·𝐷𝐷𝑐𝑎′ ·· 𝐷
𝐷𝑐′𝑎 · 𝐷𝑐′𝑎′ ·𝐷
4
(9.12)
𝐺𝑀𝐷 = 𝐷𝐴𝐵 · 𝐷𝐵𝐶 · 𝐷𝐶𝐴
3
(9.13)
√︁
Another GMD that will be used in the inductance calculation is the one that establishes a rela-
tionship between the same phases of both circuits, defined by
√︁
𝐺𝑀𝐷𝑝𝑝 = 𝐷𝑎𝑎′ · 𝐷𝑏𝑏 ′ · 𝐷𝑐𝑐 ′
3
(9.14)
The previous expressions calculate the GMD of the circuits at a specific point of the overhead
line. However, the conductor’s disposition will change throughout the line, resulting in different
values for GMD for different points in the line. In order to obtain a more accurate model, an
average of the GMDs across the overhead line is calculated.
The average GMD within a span can be obtained from the GMD of its neighbor towers, accord-
ing to Equation (9.15) , with GMD1 and GMD2 being the GMD at the previous and next towers
respectively. This operation can be performed because the variation of the GMD across the span
is linear.
𝐺 𝑀 𝐷1 +
𝐺𝑀𝐷 𝑠𝑝𝑎𝑛 = (9.15)
2
𝐺 𝑀 𝐷2
Therefore, the average GMD of the entire overhead line can be calculated as a weighted average,
Overhead line 5
Chapter 9. Electrical
Overhead line 5
Chapter 9. Electrical
.𝑠𝑝𝑎𝑛𝑠
𝑖=1
𝐺𝑀𝐷 𝑜ℎ𝑙 = (9.16)
𝐿𝑜ℎ𝑙
Where: 𝐺𝑀 · 𝐿𝑖 𝑖
• 𝐺𝑀𝐷 𝑜ℎ𝑙 is the average GMD of the entire overhead line [m]
• 𝐺𝑀𝐷 𝑖 is the average GMD of span i [m]
• 𝐿𝑖 is the length of span i [m]
• 𝐿𝑜ℎ𝑙 is the sum of the length of all the spans in the overhead line [m]
Similarly, 𝐺𝑀𝐷𝑝𝑝 can also be calculated as a weighted average throughout the overhead line
with Equation (9.17) , in which 𝐺𝑀𝐷 𝑝𝑝𝑖 is the average GMDpp in a span, calculated from
Equation (9.15)
.𝑠𝑝𝑎𝑛𝑠
𝑖=1 𝑖 · 𝐿𝑖
𝐺𝑀𝐷 𝑝𝑝𝑜ℎ𝑙 = (9.17)
𝐺𝑀𝐷𝑝𝑝𝐿𝑜ℎ𝑙
Figure 9.6 shows a bundle of four conductors with a separation d between them (the separation
will be 400 mm by default for the calculation model).
Equation (9.18) shows the general expression to calculate the GMR in a symmetrical configura-
tion: 𝐺𝑀𝑅 =
𝑛
v, .
𝑑 1→𝑖 (9.18)
𝑖=2
𝑛
𝑟′·
Where:
• 𝑟 ′ is the GMR of a single conductor, defined as 𝑟 ′ = exp 0.25 𝑟 with r being the radius
of the conductor [m] (−
• 𝑛 is the number of conductors in the bundle
Overhead line 5
Chapter 9. Electrical
• 𝑑 1→𝑖 is the distance between the first conductor and conductor i [m]
For the capacitance calculation, the radius r’ will be substituted by the actual radius of the con-
ductor r, as shown in Equation (9.19)
v, 𝑛
.
𝑑 1→𝑖 (9.19)
𝐺𝑀𝑅𝐶 = 𝑛
𝑟 · 𝑖=1
The previous equation can be rewritten for different number of conductors in the bundle, where
d is the separation between conductors and r is the radius of the conductor.
9.2.3 Resistance
The resistance of the overhead line is one of the most influencing parameters due to its direct
dependency with the power losses. A high resistance value will yield high power losses,
resulting in a poor design of the line. On the other hand, low resistance conductors have larger
sections, increasing the costs and the mechanical loads.
In order to compute the resistance of the entire overhead line, the calculated AC resistance from
Equation (2.1) will be used, as it represents the AC resistance of a single conductor.
The equation that is used to calculate the resistance of the entire overhead line is the following:
𝑅𝐴𝐶
𝑅= 𝑙 (9.28)
𝑛𝑐 · 𝑛𝑠 ·
Where:
As it can be seen from Equation (9.28), the resistance of the overhead line has a linear
dependency on the number of conductors of the line.
Overhead line 5
Chapter 9. Electrical
ductance in AC systems due to the variation of the conductor’s current. When more than one
Overhead line 5
Chapter 9. Electrical
conductor coexist in an electrical configuration, the magnetic field that one conductor generates
affects the other, meaning that there will be a geometrical relationship affecting the inductance
of the overhead line.
Equations (9.29) and (9.30) refer to the calculation of the inductance for simplex and duplex
con- figurations respectively.
𝜇0
𝐿 = 2𝜋 · ln 𝐺 · 𝑙 (9.29)
𝐺𝑀𝑅 !
𝜇0
𝐿=
· ln √ 𝐺𝑀√ ·𝑙 (9.30)
𝐷 ︁
2𝜋 𝐺𝑀𝑅 𝐺𝑀𝐷𝑝𝑝
·
Where:
In order to understand Equation (9.30), it is important to take into account that each circuit’s
phase will have a counterpart in the other circuit. For the calculation model, both phases’ (a and
a’) voltage and current will be considered to have the same argument and power factor.
Knowing this, they are considered to be the same phase when calculating the GMR. If this was
the case, the GMR according to Equation (9.18) would be calculated as:
,v 𝑛 𝑛
v,
𝑛 v𝑛
. . .
𝑑 1→𝑖 ·
2𝑛
𝑑 1→𝑖 𝑑 1→𝑖 ′ (9.31)
𝐺𝑀𝑅 = 2 𝑛
′ 𝑑 ′= 2 𝑛 · ,′
2𝑐𝑖𝑟𝑐𝑢𝑖𝑡𝑠 𝑖=2 𝑖 =1 1→𝑖 𝑖=2 𝑖 =1
′
′
𝑟 · 𝑟 · .
√ √︁
𝐺𝑀𝑅2𝑐𝑖𝑟𝑐𝑢𝑖𝑡𝑠 = 𝐺𝑀𝑅 · 𝐺𝑀𝐷𝑝𝑝 (9.32)
Where 𝑑 1→𝑖 is the distance between the first conductor of the first circuit to the conductors in its
bundle and 𝑑 1 𝑖 ′ is the distance between the first conductor of the first circuit and the
→
conductors of the second circuit’s bundle.
Once the inductance of the line has been obtained, the inductive reactance of the line can be
calculated according to Equation (9.33)
Where:
Overhead line 5
Chapter 9. Electrical
𝑋𝐿 = 2𝜋 ·𝑓 ·𝐿 (9.33)
• 𝑋𝐿 is the reactive inductance per unit length of the fully transposed overhead line [Ω]
Overhead line 5
Chapter 9. Electrical
9.2.5 Impedance
The impedance of the transmission line will be calculated using Equation (9.34)
𝑍→ = 𝑅 + 𝑗𝑋𝐿 (9.34)
Where:
2𝜋𝜖0
𝐶= · 𝑙≈ 𝜋𝜖0 · 𝑙
2𝐺𝑀𝐷 (9.35)
l 𝐺𝑀𝐷
𝐺𝑀𝑅 √ �
𝐺𝑀
1+
𝐶=
𝜋𝜖0
2𝐺𝑀𝐷 ·𝑙 (9.36)
𝑙𝑛 𝐺𝑀𝑅𝐶 ·𝐺𝑀𝐷𝑝𝑝
Where:
Equation (9.35) shows a precise and a simplified version for the calculation of the capacitance
in a simplex configuration. For conductors with considerable height above ground, both
equations will yield similar results, but for lower conductors, the differences might go up to a 5
to 10% . Therefore, the complete Equation (9.35) has been selected for simplex configurations.
Regarding duplex configuration, the simplified version in Equation (9.36) has been used due to
Overhead line 5
Chapter 9. Electrical
Overhead line 5
Chapter 9. Electrical
Once the capacitance has been calculated, the capacitive reactance and susceptance can be ob-
tained using Equations (9.37) and (9.38)
𝑋𝐶 = 1 (9.37)
2𝜋 · 𝑓 · 𝐶
𝐵 = 2𝜋 · 𝑓 · 𝐶 (9.38)
Where:
From the distributed parameters model in Subsection 9.1.1, the voltages and currents at the
send- ing and receiving end can be obtained. The power factor at the sending end will be
considered to be equal to the one established by the user in the interface. Therefore, the voltage
and current at the sending end can be determined as:
𝑈→ 𝑆
=𝑈 (9.39) 𝐼→ = (cos 𝜙 + 𝑗 sin 𝜙 ) (9.40)
𝑠 𝑠 √ 𝑠 𝑠
3𝑈
Where:
Having the electrical parameters calculated, the voltage and current at the receiving end can be
calculated using Equations (9.7) and (9.8) respectively. The voltage drop can then be obtained
using Equations (9.41) and (9.42) , where ∆V is the voltage drop, Us is the voltage at the
sending end and Ur is the voltage at the receiving end.
Overhead line 5
Chapter 9. Electrical
|𝑈𝑠 | − |𝑈𝑟 |
Δ𝑈 % = 100 (9.42)
( ) |𝑈𝑠 |
Therefore, the voltage and current at the receiving end can be calculated with the distributed
parameters model, giving out a complex value for the voltage and for the current at the
receiving end. The phase difference between these two values will determine the power factor at
the receiving end:
Where:
9.5 Losses
The purpose of an overhead line is to transmit energy from a generation point to a delivery
point. The power losses during the transmission and distribution will reduce the energy
delivered with the same proportion. This means that, if 5% of the power is lost in the overhead
line, then 5% of the energy carried will also be lost. Because of this, it is really important to
reduce the power losses as much as possible.
The electrical losses in an overhead line are generally caused by two physical phenomena: the
Joule effect, due to the conductor’s resistance and the Corona effect, caused by the ionization of
the air around the conductor. The accepted losses for an overhead line will always be lower than
5% combining the Joule effect and the corona effect.
√
𝑃𝑠 = 𝑈𝑠 · 𝐼𝑠 · 3 · cos 𝜙𝑠 (9.44)
Overhead line 6
Chapter 9. Electrical
√
𝑃𝑟 = 𝑈𝑟 · 𝐼𝑟 · 3 · cos 𝜙𝑟 (9.45)
Δ𝑃 = 𝑃𝑟 − 𝑃𝑠 (9.46)
𝑃𝑟 − 𝑃𝑠
Δ𝑃 % = 100 (9.47)
( ) 𝑃𝑠
Where:
The corona disruptive voltage is calculated according to Equation (9.48) , which is derived from
Peek’s formulae:
√ 𝐺𝑀
𝑈𝑝 = 3 · 29.8 · 𝑚 · 𝛿 · 𝑚𝑡 𝐷 (9.48)
√ �
·𝑟 ·𝑛 · l
𝑟
Where:
273 + 25
𝛿= � · exp (−0.00012 · 𝐻 ) (9.49)
Overhead line 6
Chapter 9. Electrical
If the maximum voltage of the overhead line surpasses the disruptive voltage, the Corona effect
will occur. To calculate the losses, Peek’s equation will be used:
241 √ 𝑟 −5
𝑃𝐶𝑜𝑟𝑜𝑛𝑎 = ( 𝑓 + 2 ) ︂ 𝐺𝑀 𝑈𝑚𝑎𝑥√− 𝑈𝑝 2
· 10 (9.50)
𝛿
𝐷
Where:
As a design requirement, the combination of both, Joule and Corona losses, cannot be higher
than 5% . If this percentage is surpassed, the electrical configuration must be changed. One way
to drastically reduce the effect of corona is by increasing the number of conductors per bundle,
which will increase the disruptive voltage.
Overhead line 6
Chapter 10. Mechanical
Chapter 10
Mechanical calculation
The mechanical calculation of an overhead line is an essential step in the design, ensuring that
none of the elements will fail during almost every condition. An overhead line is a set of towers,
conductors, insulators, earth wires, fittings and foundations, all of them subject to forces and
weather conditions.
In this chapter, the mechanical calculation of the towers, conductors, earth wires and insulators
will be explained, along with the design requirements for each one of them to prevent failure of
the overhead line. One extra consideration is the strength coordination of the different elements
to avoid that a failure in any component leads into a failure of the entire line.
All of the calculations that apply to conductors in this chapter will be also applicable to the earth
wires.
• Wind: When the elements of the overhead line are exposed to high wind speeds,
there will be a transversal force in the conductors, which will be transferred to the
towers and the insulators. The determination of the wind speed can usually be done from
a statistical analysis of wind speed in the area, however, a wind speed of 33.3 m/s or
120 km/h has been selected, as it is a widely used value in some countries. The
conductor’s temperature used for this hypothesis is 10ºC. This is because IEC [18]
establishes that maximum wind under average of the daily minimum temperatures
(assumed as 10ºC) condition is the most restrictive one regarding wind.
• Ice: The second hypothesis considers the ice accretion in the conductors, which leads into
a noticeable increase in their weight. The calculation of ice loads considers an ice
thickness of 30 mm and an ice density of 900 kg/m 3 , with a conductor’s temperature of -
5ºC and without wind.
• Heavy load: The third hypothesis combines the effect of wind and ice simultaneously,
yielding an increase in both vertical and transversal loads. Again, every country has a
Overhead line 6
Chapter 10. Mechanical
specific way to calculate the combined wind and ice loads, but the general consensus is
that the wind load under combined effects is a fraction of the total wind load of the first
hypothesis. Therefore the conditions for combined loads are conductors with full ice load
and 70% wind speed on them, with a conductor’s temperature of -5ºC (IEC establishes
that the least probable wind speed is between a 60% and a 85%).
• EDS: Stands for everyday stress, and refers to calm weather conditions, with a
temperature of 15ºC and no wind or ice loads. Under EDS conditions, the objective is to
study the fatigue caused by the effect of aeolian vibrations [18] [21] . Assuming that the
conductors are equipped with vibration dampers, the allowable tensile strength of the
conductors will be considered to be equal to 22% of the conductor’s tensile strength (IEC
specifies a range of values between 15% and 25% , but a 22% has been used to match the
Spanish standard).
• Maximum Temperature: Under this hypothesis, the conductors are under maximum
temperature conditions of 85ºC. Although the ambient temperature will never reach these
values, the power carried by the overhead line will increase it, reaching higher
temperature values. This hypothesis is mainly used to study the sagging of the conductor.
The equation that is used to calculate the weight loads of a conductor or earthing wire is the
following:
𝑄 𝑤𝑒𝑖𝑔ℎ𝑡 = 𝑚𝑐 · 𝑔 (10.1)
Where:
Overhead line 6
Chapter 10. Mechanical
From the wind speed, the wind pressure can be obtained from Equation (10.2) extracted from
IEC:
1
𝑞0 = · 𝜏 · 𝜇 (𝑉𝑅)2 (10.2)
2
Where:
Having the wind pressure from the previous equation, the wind load in the conductor can be
calculated as:
Where:
The final equation that is used to calculate the wind loads per unit length in conductors is the
following:
𝑄 𝑤𝑖𝑛𝑑 = 𝑞 0 · 𝑑 (10.4)
The effect of the wind also generates loads in the overhead line’s insulators, with a leaser effect
in the general design. The expression that is used to calculate the wind loads acting on insulator
strings is:
Where:
Overhead line 6
Chapter 10. Mechanical
According to IEC 60826 [18], the ice loads per unit length can be calculated as:
−
𝑄𝑖𝑐𝑒 = 9.82 · 10 3 · 𝛿 · 𝜋 · 𝑡 · (𝑑 + 𝑡 /1000) (10.6)
Where:
It is important to consider that the calculation of ice loads differs a lot depending on the
country’s standard. Because of this discrepancy, an ice thickness of 30 mm was selected, in
order to be more conservative regarding the calculation, but trying to respect most standards.
In Table 10.1 for the same 30 mm diameter conductor, the ice loads per unit length might go
from 6.5 N/m in Greece up to 79 N/m in Ireland. In order to have a conservative approach, the
conditions selected for the ice loads are an ice thickness of 30 mm and an ice density of 900
kg/m3.
Table 10.1: Ice loads for different countries for a conductor with a 30 mm diameter. [Source: [3]
CountryIce thickness [mm]Ice density [kg/m3 ]Ice load [N/m]
Belgium 20 600 19
Germany Undefined Undefined 8 - 32
Spain Undefined 750 9.9 - 29.6
]
France 20 600 19
Greece 6.35 or 12.7 900 6.5 or 15.3
Ireland 40 900 79
Italy 12 920 19
The ice loads in the insulator strings are not calculated due to the small effect that they have in
the calculation model.
Overhead line 6
Chapter 10. Mechanical
The total loads per unit length are calculated according to:
√︃
2 (10.7)
𝑄 = 𝑄 𝑤𝑒𝑖𝑔ℎ𝑡 + 𝑄𝑖𝑐𝑒 + 𝑄2 𝑤𝑖
Where:
10.3 Catenary
10.3.1 Catenary curve calculation
When a conductor is placed between two attachment points with a tensile strength, it will natu-
rally sag, following a curve called catenary, which is formed as a result of the vertical weight of
the conductor along the span.
It is important therefore to calculate the catenary curve in order to ensure that the
clearances and the tensile strengths are respected according to the IEC requirements. In
order to calculate the catenary, two models are typically used in projects: the hyperbolic model
and the parabolic model.
In this section, the hyperbolic model will be used, as it is more accurate than the parabolic one,
but with higher complexity. In Figure 10.1, the catenary curve is shown with some of its
characteristic points. All the equations will be referred to the coordinate system showed,
considering the origin x=0 at the lowest point of the curve.
Overhead line 6
Chapter 10. Mechanical
It is also important to note that this section will not study deeply the catenary equations. For
more detailed calculations, check Chapter 14 of [3]
The main equation that describes the catenary curve according to the hyperbolic model is the
following:
𝐻 𝑤𝑐 · 𝑥
𝑦= cosh (10.8)
𝑤𝑐 · 𝐻
Where:
The previous equation can be expressed in a more compact way with the definition of the cate-
nary constant c:
𝐻
𝑐= (10.9)
𝑤𝑐
𝑥
𝑦 = 𝑐 cosh (10.10)
· 𝑐
The length of the conductor can be calculated from Equation (10.11) , with a being the span
length in meters and h being the altitude difference between the attachment points in meters.
√︂
. .
𝑎 2
𝐿= ℎ2 + 2𝑐 · sinh 2 (10.11)
In order to calculate the distance from the lowest point of the curve x=0 (see Figure 10.1) to
both attachment points, equations (10.12) and (10.13) are used.
Overhead line 6
Chapter 10. Mechanical
𝑐
𝑥𝐴 = 𝑐 · 𝑙𝑛 · (1 − exp (−𝑎/𝑐)) (10.12)
(𝐿
𝑥𝐵 = 𝑥𝐴 + 𝑎 (10.13)
Where:
• 𝑥𝐴 is the horizontal distance from the lowest point of the catenary to the first attachment
point [m]
• 𝑐 is the catenary constant [m]
• 𝐿 is the length of the cable [m]
• ℎ is the height difference between the two attachment points [m]
• 𝑎 is the span length [m]
• 𝑥𝐵 is the horizontal distance from the lowest point of the catenary to the second
attachment point [m]
With the previous values of the catenary, the point of maximum sag can be calculated [22] using
Equation (10.14) with h being the height difference, a being the span length and xmin being the
point of lowest altitude, which is equal to 0.
𝑥𝑐 ℎ
= 𝑥𝑚𝑖 + 𝑐 · 𝑎𝑟𝑠ℎ (10.14)
The sag at any point of the catenary can be calculated using Equation :
ℎ · (𝑥 − 𝑥𝐴) 𝑥𝐴 𝑥
𝑓 = � + 𝑐 · cosh � − cosh � (10.15)
Where:
Overhead line 6
Chapter 10. Mechanical
support. However,
Overhead line 7
Chapter 10. Mechanical
the horizontal tension should be limited to ensure that the rated tensile strength (RTS) of the
conductor is not reached, which would lead into a mechanical failure.
According to table 20 of IEC 60826 [18] , the typical range of tensile strength limit is between a
70 % and an 80 % of the RTS. Values higher than that would result in potential damages in the
conductors, meaning that the target of the design will be to never surpass a 70% of the
conductor’s RTS under any meteorological condition. This requirement also affects the design
of earth wires.
When designing an overhead line for a given hypothesis, the value of the horizontal tension will
be defined by that given hypothesis. However, different conditions will result in different
values, which could potentially not fit the project’s requirements if it was only designed for the
initial hypothesis. Because of this, it is important to study the different cases and design the
project respecting all of them.
The state change equation is used to translate the horizontal tension obtained under one me-
teorological condition into a different one. This is used to check that everything is correctly
sized and that the line is designed according to the most restrictive condition, never surpassing
a certain percentage of horizontal load that could be dangerous to the elements of the line.
The state change equation begins with an initial condition with a specific load per unit length
(Q1), temperature (ϑ1) and horizontal tension (H1) which corresponds to the EDS hypothesis
mentioned in Section 10.1 .
◦
• 𝜃1 = 15 𝐶
• 𝑄 1 = 𝑄 𝑤𝑒𝑖𝑔ℎ𝑡
• 𝐻1 = 0.22 𝑅𝑇 𝑆
From these initial conditions, the horizontal tension H 2 at conditions ϑ2 and Q2 can be obtained
with the state change Equation (10.16)
Where:
Overhead line 7
Chapter 10. Mechanical
Previous equation can be rewritten in a simplified version in Equation (10.19), which can be
solved using the method proposed in [23]:
𝜖 · 𝑆 · (𝑎𝑟 · 𝑄1)2
𝑎 = −𝐻1 + + 𝜖 · 𝑆 · 𝛼 · (𝜃2 − 𝜃1) (10.17)
24 · 𝐻
2 1
𝛼 · 𝑆 · (𝑎𝑟 · 𝑄2)2
𝑏= (10.18)
2 =𝑏
𝐻 2 [𝐻2 + 𝑎] (10.19)
2
If the horizontal tension H2 gives a value higher than the required 70% RTS, the initial
conditions will be changed so that the requirements for the invalid hypothesis are within the
limits. For next hypotheses, the reference conditions used will correspond to the updated ones.
To better understand this with an example, if the ice hypothesis appears to have a horizontal
tension equal to 80%, the reference conditions would have to be changed to the following:
◦
• 𝜃1 = −5 𝐶
• 𝑄 1 = 𝑄 𝑤𝑒𝑖𝑔ℎ𝑡 + 𝑄𝑖𝑐𝑒
• 𝐻1 = 0.7𝑅𝑇 𝑆
These conditions will be used for the rest of the hypotheses until another one does not respect
the design values.
After ensuring that the horizontal tensions are correct, the different horizontal tensions under
every hypothesis will be calculated using the final state change reference conditions in order to
calculate the catenaries using Equation (10.8).
For the earth wire, the horizontal tension will be such that the sag at EDS conditions is not
higher than 90% of the sag of the conductor at the same conditions [3]. This will ensure that the
clearance between the earth wire and the conductor is respected.
Overhead line 7
Chapter 10. Mechanical
• Wind: The conditions of wind speed and temperature are equal to the ones for the
conduc- tors, with a 120 km/h wind speed and 10ºC ambient temperature. There is no
longitudinal force because the conductors’ horizontal tensions are not unbalanced for
suspension and angle towers.
• Heavy load: The conditions of ice and temperature are equal to the ones used in previous
calculations, with an ice density of 900 kg/m3 , an ice thickness of 30 mm and a
temperature of -5ºC. Additionally, a 70% of wind speed will be considered, and similar to
the previous hypothesis, no longitudinal force will be applied for suspension and angle
towers.
• Unbalance: While being under ice load, there is an unbalance in the horizontal tensions
of the conductors, resulting in a longitudinal force. A fraction of the horizontal tension
under ice conditions will be considered as the longitudinal force depending on the type of
tower: For suspension towers 0.15 multiplied by the horizontal tension; for angle towers
0.5; for dead end towers it is not considered because previous hypothesis already studied
it.
• Conductor break: If a conductor breaks, a severe longitudinal force will appear at the
tower’s attachment point. This hypothesis considers a line with ice and the following lon-
gitudinal forces as a fraction of the conductor’s horizontal tension: For suspension towers
0.5 multiplied by the horizontal tension; for angle towers 1; for dead end towers 1.
Where:
The vertical force on the entire tower can be calculated as the force of one attachment point
multiplied by the number of attachment points of the tower (3 per circuit).
Overhead line 7
Chapter 10. Mechanical
The force caused by the deflection angle will be defined as the angle resultant, and can be calcu-
lated according to Equation (10.21)
Where:
Whenever there is wind present, the force that it produces in the conductors will translate into
a transversal force in the tower, which can be calculated using Equation (10.22)
Where:
• 𝐹 𝑤𝑖𝑛𝑑 is the transversal force caused by the wind on a conductor bundle [N]
• 𝑄 𝑤𝑖𝑛𝑑 is the wind load per unit length of the conductor [N/m]
• 𝑎 𝑤𝑖𝑛𝑑 is the wind span of the tower [m]
• 𝛼 is the deflection angle [rad]
• 𝑛𝑐𝑜𝑛𝑑 is the number of conductors in the bundle
The total transversal force at the tower will therefore be calculated according to Equation (10.23):
Overhead line 7
Chapter 10. Mechanical
𝐹𝑇 = 𝐹𝛼 + 𝐹 𝑤𝑖𝑛𝑑 (10.23)
The forces calculated with Equations (10.21) and (10.22) define the transversal forces at one at-
tachment point of the tower, consequently in order to calculate the entire transversal forces of
the tower, the values must be multiplied by the number of phases of the tower.
The expression used to calculate the longitudinal forces of a conductor bundle is the following:
Where:
Similarly to the vertical and transversal calculation, the longitudinal forces refer to a single
phase. However, in this case, some of the hypotheses might not take into account the
longitudinal force of all of the conductors, therefore this force is only multiplied by the number
of phases for dead end towers.
Overhead line 7
Chapter 11. Tower
Chapter 11
Tower spotting
Another important parameter in the investment of an overhead line is the placement of the
towers within the line. Spotting the towers in a way or another impacts directly the cost of
the line. By way of explanation, tower spotting must consider the clearances, the catenary and
all the other elements that define the line.
In this chapter the tower’s spotting criteria and process will be explained.
11.1 Considerations
In this methodology, a line with the least number of angle towers is prioritized, according to [ 3]
an overhead line route which avoids angle towers is favored to be selected. Hence, the angle
towers uploaded by the users are preserved and no other angle tower is added in the spotting
process. If a user imports close angle towers that do not respect the minimum allowable span,
the towers are kept and a warning is displayed in the results.
Furthermore, a target span calculated based on the line voltage is considered to ensure a
tolerated span length, the target span is calculated as seen in Table 2.1. Moreover, the elevation
data under the entire line is considered for placing new suspension towers within the blocks; the
terrain data consideration is necessary to ensure the minimum clearance to the ground criteria.
Before jumping into the spotting process, the line imported by the users goes through a
filter based on the angle towers criteria mentioned above. The angle towers are considered
◦ ◦
when there is a deflection angle higher than 2 or less than -2 ; these towers are kept and
the rest of points/towers are removed.
Overhead line 7
Chapter 11. Tower
This process is repeated in a way that the final route respects the minimum ground clearance
and the span length while including the necessary towers only to evacuate the power.
In addition, in this step, the suspension towers are located within the blocks based on a maxi-
mum span calculated from the target span defined by the system voltage. The maximum span is
calculated as the target span multiplied by 1.15 to allow up to 15% bigger spans. For every
block imported by the user, its corresponding elevation data is calculated; hence, for every
maximum span the corresponding point is retrieved and considered as a new possible tower.
Later, the possible new towers are added to the line in a way that guarantees all the distances
between the towers respect the target spans, if not, a consideration of new possible towers is
made. Also, new elevation data is defined based on the new spans of the line.
In the Figure 11.1 an illustration of a plan view of a line imported by the user is presented; the
distance check criteria are also shown.
Figure 11.1: The distance check: (a) User line path | (b) Path filtering | (c) Possible towers location
| (d) Suspension towers are added
Overhead line 7
Chapter 11. Tower
The process of ground clearance validation includes the calculation of the catenaries of the line
considered from the previous step; afterwards, the maximum height of the tower’ body is calcu-
lated based on the voltage of the system as presented in Table 11.1 which was elaborated based
on market towers catalog [19]. The maximum height is used to define the lowest connection
point of the towers depending on their type to recalculate the correct catenary of the
conductors.
For every two consecutive spans, the minimum ground clearance is validated against the spans’
elevation data. For every span where the ground clearance is not respected, its corresponding
towers are defined as invalid, the ground clearance validation procedure allows keeping track of
all the spans and towers where the clearance is not respected for it to be used to find possible
valid towers in the following step.
In the Figure 11.2 below, an illustration of ground clearance validation of a line composed
of three spans is shown, the towers in red are the invalidated towers because of the invalid
first span that do not respect the ground clearance, the other spans are respecting the criteria;
hence, represented by a green color.
Overhead line 7
Chapter 11. Tower
In one hand, when the invalid span is made of two angle towers, a new tower is added at the
middle of the span to correct the ground clearance. On the other hand, if the span contains at
least one suspension tower, the adjacent spans must be evaluated. Based on the validity or
invalidity of the adjacent spans, the towers are moved forward or backward to make sure the
spans respect the minimum ground clearance criteria. The movement of the possible valid
towers considers the minimum allowable span required.
The new positions of the moved towers are selected in a way that high ground positions are
prioritized while trying to keep the towers as equally spaced as possible. Once the new towers
positions are defined, the previous step is run again to make sure the correct spans are
respecting the minimum ground clearance.
In the case of not being able to find a tower’s position that would validate a certain span, adding
an extra tower is considered. In the following Figure 11.3 an illustration of a tower path made of
three spans with the first span being invalid.
Overhead line 7
Bibliograp
Bibliography
[1] Grigsby, L.L., The Electric Power Engineering Handbook - Five Volume Set (3rd ed.) Taylor
and Francis, 2012.
[2] Félix Ignacio Pérez Cicala, Mario Bennekers Vallejo and Miguel Ángel Torrero
Rionegro, “Topography analysis methodology (2022 edition),” RatedPower, 2017.
[3] F. Kiessling, P. Nefzger, J. F. Nolasco, and U. Kaintzyk, Overhead Power Lines:
Planning Design Construction. Springer, 2003.
[4] Technical Committee 7, “Overhead electrical conductors – Calculation methods for
stranded bare conductors,” International Electrotechnical Commision, Tech. Rep. IEC
61597, 2012.
[5] Siemens AG, “Power Engineering Guide Edition 8.0,” Siemens, Tech. Rep., 2017.
[6] “Aerial optical cables along electrical power lines,” ZTT, catalog, 2007.
[7] Technical Committee 14, “Power transformers - part 5: Ability to withstand short
circuit,” International Electrotechnical Commision, Tech. Rep. IEC 60076-5:2006, 2006.
[8] Viesgo, “Norma instalaciones de enlace en alta tension: lineas de alta tension (>36 kV) y
subestaciones,” Viesgo, Technical Specification NT-IEAT.01, 2017.
[9] Viesgo, “Proyecto tpo de subestacionesc con aparamenta convencional,” Viesgo,
Technical Specification PT-SECO.01, 2017.
[10] J. P. Fernandez and E. Iraburu, “Especificaciones Particulares. Requisitos Tecnicos de Con-
struccion de Subestaciones conectadas a redes de Alta Tension de Un > 36 kV,” Union
Fenosa Distribucion, Technical Specification IT.07974.ES-DE.NOR, 2017.
[11] Technical Committee 99, “Insulation coordination. Part 2. Application guidelines,” Inter-
national Electrotechnical Commision, Tech. Rep. IEC 60071-2:2018, 2018.
[12] Ignacio Álvarez Iberlucea, Soukayna Jermouni, Miguel Ángel Torrero Rionegro, Félix
Ig- nacio Pérez Cicala and Juan Romero González, “Substation methodology (2020
edition),” RatedPower, 2020.
[13] Technical Committee 36, “Insulators for overhead lines with a nominal voltage above
1000 V - Ceramic or glass insulator units for AC systems - Characteristics of insulator
units of the cap and pin type,” International Electromechanical Commision, Tech. Rep.
IEC 60305:2021, 2021.
[14] Technical Committee 36, “Insulators for overhead lines with a nominal voltage above
1000 V - Ceramic insulators for AC systems - Characteristics of insulator units of the
long rod type,” International Electromechanical Commision, Tech. Rep. IEC 60433:2021,
2021.
Overhead line 8
Bibliograp
Overhead line 8
Appendix A. Selecting a phase conductor and an
Appendix A
In this appendix, the process and calculation of the phase conductor cross-section as well as the
selection of the line insulator will be presented.
The overhead line to be designed is a transmission line evacuating a capacity of 100MW for a
high voltage level of 132kV and frequency of 50Hz. The system is simplex with one circuit and
one conductor per phase.
The line is of a transmission nature; hence, the conductors to select from are of type ACSR. In
this example, the conductor used for the selection is the "160-A1/S2A" with a total diameter of
0.0177 m and a unitary mass of 0.64459 kg/m.
The thermal limit withstand is checked by calculating the conductor maximum admissible cur-
rent using Equation (2.3) and comparing it with the total current of the line calculated as:
𝑆 6
𝐼𝑡𝑜𝑡 = 100 ·
𝑈𝑚𝑎𝑥 √
= √ ≈ 437𝐴 (A.1)
·𝑛 · 3 132000 · 1 · 3
To calculate the maximum admissible current, first, the DC resistance at maximum temperature
must be calculated:
−8
𝜌 3.35 · 10 −4
𝑅𝑇 = [1 + 𝛼 (𝑇𝑚𝑎𝑥 − 20)] = [1 + (0.00403(80 − 20))] ≈ 2.234 · 10 𝑊 /𝑚 (A.2)
𝑠 1.8622 · 10−4
Next, the heat loss by radiation, the convection loss and the solar heat gain must be calculated
respectively:
Overhead line 8
Appendix A. Selecting a phase conductor and an
−8
𝑁𝑅 = 𝑘 · 𝜋 · 𝑑 · 𝐾𝑒 (𝑇𝑚𝑎𝑥 4 − 𝑇𝑎𝑚4) = 5.67 · 10 · 𝜋 · 0.0177 · 0.45(3534 − 3184) ≈ 7.52𝑊 /𝑚 (A.3)
Since the conductor admissible current is higher than the total current of the line, the conductor
"160-A1/S2A" is electrically eligible.
Next, the mechanical withstand is checked for the conductor using the empirical approach ex-
plained in section 2.2.2. For the high voltage of 132kV, the maximum target span is 200 m (
Table 2.1). Hence, from Table 2.2 it is deducted that the minimum tensile strength is 45000 N .
On the other hand, the electrical eligible conductor has a maximum load of 61340 N. Conse-
quently, the conductor withstands mechanically.
The final step in the conductor selection is checking the voltage gradient criterion, as mentioned
in the Chapter 2 using Equation (A.7) and ensuring that the line’s voltage drop and power losses
are not exceeding 5%. In Appendix B, both, the voltage drop and total losses are calculated for
this line’s design and both do not exceed the 5% criterion. The voltage gradient is calculated as
follows:
𝐸 = 𝐶𝑖 [1 + 2 · (𝑟 /𝑠) (𝑛2 − 1) · 𝑠𝑖𝑛(𝜋 /𝑛2)] √� =
2
� 𝜋𝜖0 · 𝑛2 · 𝑟 3 · 100
−
8.23 · 10 12 (A.7)
2 · 𝜋 · 8.854 · 10−12 · 1 · 0.00885 132000
For the same transmission line with the conductor "160-A1/S2A" having a maximum load of 61340
N, the insulator selection will depend, first, on the electrical withstand of the cap and pin insula-
tor. The insulator "U160BS" is chosen as an example of insulator selection. To assess the electrical
withstand, the length of the insulator is calculated under different conditions to ensure it
respects the electrical clearances and to guarantee the insulator withstands the maximum
Overhead line 8
Appendix A. Selecting a phase conductor and an
voltage.
Overhead line 8
Appendix A. Selecting a phase conductor and an
- Normal conditions:
−6
𝑛𝑛𝑜𝑟𝑚𝑎𝑙 ≥ 𝑈𝑠 · 𝜖0 = 145000 · 20 · 10 = 9 21 (A.8)
𝜖 0.
For both conditions, the number of disks that withstand the maximum wet voltage and the light-
ning impulse voltage is seven.
Hence, for the three conditions the longest insulator is composed of 10 pins, which is the integer
immediately superior to 9.21; and for a phase to earth clearance of 1.2m, the insulator minimum
length is calculated as:
Since the insulator total length 10 0.146 = 1.46 is higher than the minimum length, then the
( ·
insulator is electrically compliant.
Next, the minimum failing load of the insulator must be checked against the conductor
maximum load at worst conditions. The different combinations of insulators sets are also
assessed. As the minimum failing load is 160000 N and higher than the conductor maximum
load, the insulator "U160BS" withstands mechanically.
Finally, as explained in the chapter, the typical tensile strength for insulators under the voltage
of 132kV is 160000 N Table 6.3 which is equal to the insulator "U160BS" minimum failing
load. Hence, the said insulator is selected.
Overhead line 8
Appendix B. Electrical parameters
Appendix B
In this appendix, the process and calculation of the electrical calculations of an overhead line are
presented.
The overhead line in question has the same characteristics mentioned in Appendix A. The line
operating under a voltage of 132kV has a length of 8955m and a power factor at the sending end
of 0.95. As explained in Chapter 9, the distributed parameters model will be considered for the
electrical calculation.
B.1 Resistance
The resistance of the line per unit length is calculated using Equation (9.28) as follows:
𝑅𝐴𝐶 −4
2.24 · 10
𝑅= ·𝐿 = · 8955 ≈ 2Ω/𝑚 (B.1)
𝑛𝑐 · 1·1
𝑛𝑠
.𝑠𝑝𝑎𝑛𝑠
𝑖=1
𝐺𝑀𝐷 𝑜ℎ𝑙 ≈ 7.9𝑚 (B.2)
= 𝐿𝑜ℎ𝑙
𝐺𝑀
As for GMR, it is calculated using Equation · 𝐿𝑖
(9.18): 𝑖
v,
𝑛
.
𝑑 1→𝑖 ≈ 0.0069𝑚 (B.3)
𝐺𝑀𝑅 = 𝑛
𝑟′· 𝑖=2
Next, as the transmission line is Simplex with one circuit, the inductance of the line is calculated
using the following formula:
Overhead line 8
Appendix B. Electrical parameters
−6
𝜇0 𝐺𝑀𝐷 1.256 · 10 7.9
𝐿= · ln ·𝑙 = · ln · 8955 ≈ 0.0126𝐻 /𝑚 (B.4)
2𝜋 𝐺𝑀𝑅 2𝜋 0.0069
Finally, the inductive reactance can be deduced from Equation (9.33) as follows:
B.3 Impedance
Having the resistance and the inductive reactance of the line calculated in the previous sections,
the impedance of the entire line can be calculated using Equation (9.34):
−12
𝐶=
2𝜋𝜖0
·𝑙 = 2𝜋 · 8.854 · 10 · 8955 ≈ 7.37 · 10− 𝐹 / (B.7)
ln √ 𝐺𝑀𝐷
2
ln 8 𝑚
√ 7.9
2
𝐺𝑀𝑅𝐶 · 1+ 0.00885· 1+(7.9/2·14.7)
(𝐺𝑀𝐷/2ℎ𝑀 )
Once the capacitance is calculated, the capacitive reactance and the susceptance are calculated
as follows:
1 1
𝑋𝐶 = = ≈ 43203.7Ω/𝑚 (B.8)
2𝜋 · 𝑓 · 𝐶 2𝜋 · 50 · 7.37 · 10−8
−8 −
𝐵 = 2𝜋 · 𝑓 · 𝐶 = 2𝜋 · 50 · 7.37 · 10 ≈ 2.32 · 10 5 Ω−1𝑚−1 (B.9)
Consequently, the voltage drop and its percent are calculated as follows:
Overhead line 8
Appendix B. Electrical parameters
Overhead line 8
Appendix B. Electrical parameters
Next, with the receiving end power factor being 0.9544, both the power losses at sending and
receiving ends are calculated as follows:
√ √
𝑃𝑠 = 𝑉𝑠 · 𝐼𝑠 · 3 · cos 𝜙𝑠 = 132000 · 437.38 · 3 · 0.95 ≈ 9.5 · 107𝑊 (B.14)
√ √
𝑃𝑟 = 𝑉𝑟 · 𝐼𝑟 · 3 · cos 𝜙𝑟 = 74845.06 · 437.92 · 3 · 0.9544 ≈ 9.4 · 107𝑊 (B.15)
Finally, the joule effect and its percent are calculated using Equation (9.46) and Equation (9.47):
Δ𝑃 = 𝑃𝑟 − 𝑃𝑠 ≈ 1151654𝑊 (B.16)
𝑃𝑟 − 𝑃𝑠
Δ𝑃 % = 100 1.2% (B.17)
( ) 𝑃𝑠 · ≈
29.8 𝐺𝑀𝐷
𝑉𝑝 = √ ·0.85·0.96553·0.8·0.885·1·ln ≈ 144139.4𝑉 (B.18)
√ ·𝑚𝑐 ·𝛿 ·𝑚𝑡 ·𝑟 l = 22 0.885
0.008
·𝑛·2 𝑟
As the maximum voltage of the line 145kV is higher than the disruptive voltage, the corona
effect will occur and its loss is calculated as follows:
241 𝑟 −5
𝑃𝐶𝑜𝑟𝑜𝑛𝑎 = · ( 𝑓 + 2) 𝐺𝑀 2 · 10
·𝛿 𝐷 𝑉𝑚𝑎𝑥 − 𝑉𝐶𝑚𝑎𝑥
Overhead line 8
√︂ Appendix B. Electrical parameters
√
= · (50 + 25) · (B.19)
0.96553 √︂ 0.885 145000 − 144139.4
2 −
792.03 2 √ · 10 5 ≈
0.0016𝑊
Overhead line 9
Appendix B. Electrical parameters
The corona loss is then multiplied by the total number of phases, the number of sub-conductors
and the length of the line to get the corona loss of the line resulting in this case a loss of 41.5W.
Overhead line 9
Appendix C. Mechanical
Appendix C
Mechanical calculations
This appendix presents the different mechanical calculations performed for the design of an
over- head line. The appendix will cover the conductor’s loads and the catenary of a span under
dif- ferent hypotheses as well as the tower forces of a suspension and a tension tower.
The weight load per unit length can be calculated from (10.1):
1 1
𝑞75% = 𝜏 𝜇 (𝑉75%)2 = · 1 · 1.225 ∗ (0.75 ∗ 33.33)2 = 382.74 𝑁 /𝑚2 (C.3)
2 2
The wind load per unit length is therefore calculated using (10.3):
Overhead line 9
Appendix C. Mechanical
For this, the state change equation must be used in order to compare the tensions of the different
hypotheses. None of the conditions should reach a horizontal tension higher than 70% of the
conductor’s RTS:
𝐻𝑚𝑎𝑥 < 0.7 · 61340 = 42938 𝑁 (C.7)
The initial conditions for this calculation will be EDS conditions with a horizontal tension equal
to 22% of the conductor’s tensile strength:
◦
• 𝜃1 = 15 𝐶
• 𝑄 1 = 𝑄 𝑤𝑒𝑖𝑔ℎ𝑡 = 6.326 𝑁 /𝑚
• 𝐻1 = 0.22 · 61340 = 13494.8 𝑁
The first hypothesis to study will be the max wind one, with the following final conditions:
◦
• 𝜃2 = 10 𝐶
√
• 𝑄2 = 6.3262 + 12.042 = 13.6 𝑁 /𝑚
From equations (10.17), (10.18) and (10.19)
−4
7.454 · 1010 · 1.862 · 10 · (211.85 · 6.326)2
𝑎 = − 13494.8 24 · 13494.82 (C.8)
+
−5 −4
+ 7.454 · 1010 · 1.887 · 10 · 1.862 · 10 · (10 − 15) = −9100.8 𝑁
−4
𝑏 = 7.454 · 10 · 1.862 · 10 · (211.85 · 13.6)
10
= 4 8 1012 𝑁 (C.9)
3
. ·
24
Solving previous equation, the value of H2 obtained is 𝐻2 = 20510.7 𝑁 , which is lower than the
maximum allowed of 42938 N, meaning that the wind conditions are correct.
The second hypothesis will be the ice conditions hypothesis, with the final conditions:
◦
• 𝜃2 = −5 𝐶
Overhead line 9
Appendix C. Mechanical
Overhead line 9
Appendix C. Mechanical
−4
7.454 ·21010 · 1.862 · 10 · (211.85 ·
46.056) 13 3
𝑏= = 5.5 · 10 (C.12)
𝑁
24
𝐻2 = 42905.86 𝑁 (C.13)
Since the value of 𝐻2 is lower than the 42938 N limit, the ice hypothesis is correct.
The third hypothesis to study is the combined loads one, with the following final conditions:
◦
• 𝜃2 = − 5 𝐶
√︁
• 𝑄2 (6.326 + 39.73)2 + 6.772 = 46.551 𝑁
−
𝑏 = 7.454 · 10 · 1.862 · 10 · (211.85 ·
10 4
13
𝑁3 (C.15)
46.551)2
= 5.62 · 10
24
𝐻2 = 43176.37 𝑁 (C.16)
In this case, the horizontal tension for the heavy load hypothesis is higher than the maximum
horizontal tension allowed. This means that the horizontal tension should be lowered so that,
under heavy load conditions, the horizontal tension is within the safety limits of the conductor.
Therefore, the initial conditions are changed to the following:
◦
• 𝜃1 = −5 𝐶
• 𝑄1 = 46.551 𝑁 /𝑚
• 𝐻1 = 42938 𝑁
These conditions will make sure that the heavy load hypothesis is respected while ensuring that
the previously studied hypotheses are also respected since the horizontal tension will be lower
with the new conditions (lowering the tension under one hypothesis will lower it for the rest of
them).
The maximum temperature hypothesis is not taken into account when trying to study if the
horizontal tension is respected, since this hypothesis will yield really low values of 𝐻2.
Overhead line 9
Appendix C. Mechanical
Because the initial conditions were changed, the values for the horizontal tensions calculated
previous to the heavy loads hypothesis will have changed, meaning that they have to be recal-
culated with the new initial conditions.
In order not to repeat all the calculations, the final horizontal tensions with the new conditions
are obtained following the previous procedure with the heavy load’s conditions as the initial
conditions. The results are shown in Table C.2.
• 𝐻 = 42938𝑁
• 𝐴 = {0, 0, 0} , coordinates in meters
• 𝐵 = {245.4, 2.3, −4.4} , coordinates in meters
• 𝑚𝑐 = 46.056 𝑁 /𝑚 , considering the weight of the conductor and the ice
√︃
The difference in altitudes is calculated from:
ℎ = 𝐵.𝑧 − 𝐴.𝑧 = −4.4 − 0 = −4.4 𝑚 (C.18)
√︂ √︄
. . 245.41 2
𝐿= 𝑎 2
= (−4.4)2 2 · 932.3 · sinh = 246.16 𝑚 (C.20)
ℎ2 + 2𝑐 · sinh 2·
+
2
𝐻
𝑥𝐴 =𝑐 · 𝑙𝑛 · (1 − exp (−𝑎/𝑐)) =
𝑤𝑐 · (𝐿 − (C.21)
ℎ)
−
932.3 · 𝑙𝑛
Overhead line 9
Appendix C. Mechanical
· 1−
exp = −139.38 𝑚
42938 (−4.4)) 245.41
46.056 · (246.16 − 932.3
Overhead line 9
Appendix C. Mechanical
The point where the maximum sag appears is calculated from Equation (10.14)
ℎ −4 . 4
𝑥 =𝑥 + 𝑐 · 𝑎𝑟𝑠ℎ = 0 + 932.3 · 𝑎𝑟𝑠ℎ = −16.61 𝑚 (C.23)
� �
� 245.
All of the catenaries for the different hypotheses will be calculated for every span. By doing
this, the worst case scenarios for both, horizontal tension and clearances will be studied,
providing a good quality design.
The result for the different hypotheses are shown in Table C.2:
Overhead line 9
Appendix C. Mechanical
Where 𝑚𝑐 · 𝑔 is equal to the conductor weight, which considers ice if there is.
For the other conditions, the calculation will be the same, changing the values for the weight
span and the conductor loads.
For the suspension tower, the angle resultant will be disregarded, as no deflection angle can
exist for the designs provided by the software for this kind of towers. Therefore, only the wind
effect will be calculated using Equation (10.22):
𝐹 𝑤𝑖𝑛𝑑 = 𝑄 𝑤𝑖𝑛𝑑 · 𝑎 𝑤𝑖𝑛𝑑 · cos 𝛼 · 𝑛𝑐𝑜𝑛𝑑 = 12.043 · 216.0 · cos 0 · 1 = 2601.3 𝑁 (C.27)
The total transversal load on the suspension tower is calculated with Equation (10.23):
For the angle tower, the angle resultant will have a value, calculated according to Equation (10.21):
Overhead line 9
Appendix C. Mechanical
Since the angle tower has two neighbor spans that correspond to different blocks, the first span
and the second span will have different horizontal tensions. The first span has the same horizon-
tal tension as the suspension tower of study, whereas the second one has the value specified at
Table C.3.
𝐹 𝑤𝑖𝑛𝑑 = 𝑄 𝑤𝑖𝑛𝑑 · 𝑎 𝑤𝑖𝑛𝑑 · cos 𝛼 · 𝑛𝑐𝑜𝑛𝑑 = 12.043 · 216.8 · cos 3. · 1 = 2609.86 𝑁 (C.30)
2
For the unbalanced condition with suspension towers, the corresponding percentage of horizon-
tal load that will appear due to the unbalance is equal to a 15%. Therefore, according to
Equation (10.24), the longitudinal force is calculated as:
For the angle tower, the conductor break hypothesis yields a horizontal force factor of 100%.
The longitudinal force is calculated as:
Overhead line 1