0% found this document useful (0 votes)
12 views10 pages

Variance Calculation

Variance Calculation

Uploaded by

Ppuah Paul
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
12 views10 pages

Variance Calculation

Variance Calculation

Uploaded by

Ppuah Paul
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 10

Variance Calculation

Types of Variance

The following variances can be calculated:

 Planning variances

 Production variances

 Production variance of the period

 Total variance

General
The following variance categories can be reported for the total variance:

 Input price variance

 Resource-usage variance

 Input quantity variance

 Remaining input variance

 Scrap variance

 Mixed-price variance

 Output price variance

 Lot size variance

 Remaining variance

General
Variance Categorization

Variances are classified into variance categories on the input side and variance categories on the output side.

Variances on the Input Side

Variances on the input side are variances based on goods issues, internal activity allocations, overhead allocation, and G/L
account postings. These variances are assigned to the following variance categories according to their cause:

 Input price variances

Input price variances are caused by differences between the planned and actual prices of the materials and activities.

Input price variances can only be calculated if quantities were specified. The following conditions must be met:

o Select the Material origin indicator in the costing view of the master record of all materials that have a large influence
on your costs.

Uniform units of measure must be assigned to all input materials. That is, material costs can only be totaled under a
cost element when such costs are carried under the same unit of measure.

o If you want to calculate variances by cost element/origin group, you must already have entered an origin group in the
costing view of the material master record for all material components.

If you have defined primary input price variances in Customizing, input price variance percentages will be calculated
with reference to the operation. When you start the variance calculation process at the end of the period, this data will
be canceled and the input price variances will be calculated by multiplying the difference between the planned price
and the actual price by the confirmed quantity. If the confirmed quantities are incomplete or do not exist, input price
variance percentages will be shown.

 Resource-usage variances

Resource-usage variances are caused by the use of different materials and activities than were planned.

Resource-usage variances are reported if:

o The target costs of a cost element, origin group, or origin are not zero but the actual costs of the same cost element,
origin group, or origin are zero.

o The target costs of a cost element, origin group, or origin are zero but the actual costs of the same cost element,
origin group, or origin are not zero.

General
 Input quantity variances

o Input quantity variances are caused by differences between the planned and actual consumption of materials and
activities. Select the Material origin indicator in the costing view of the master record of all materials that have a large
influence on your costs.

If you want to see input quantity variances and input price variances, make the following settings:

 Select the Material origin indicator in the costing view of the material master record.

 Select the Record quantity indicator in the cost element.

Note
Variances are calculated regardless of whether the Record quantity indicator is turned on. If quantities are not
recorded, however, it is not possible to calculate quantity variances. If the Record quantity indicator is turned on, a
warning message is issued if you do not enter a quantity in consumption postings.

If the above requirements are not met, the variances are reported as remaining input variances.

 Remaining input variances

Variances are calculated for each cost element on the input side. If a variance on the input side cannot be assigned to
any of the above categories, the variance is assigned to the remaining input variance category. This can happen when
costs are entered without a quantity, or when the overhead rates are changed.

 Scrap variances

Scrap variances are caused by differences between the operation scrap planned in the routing and the operation
scrap actually confirmed.

The difference between the planned scrap quantity and the actual scrap quantity is reported as an unplanned scrap
quantity. The unplanned scrap quantity is valued in accordance with the Valuation variant for work in process and
scrap in Customizing for Product Cost by Period or Product Cost by Order under Period-End Closing Variance
Calculation.

If you have not activated the calculation or display of scrap, scrap variances are assigned to the individual variance
categories on the input side.

For detailed information on scrap variances, see Scrap Variance.

General
Variances on the Output Side

With the following types of variances, variances will be shown on the output side:

 Total variance (SAP standard: target cost version 0)

 Production variance of period (SAP standard: target cost version 3)

 Planning variance (SAP standard: target cost version 2)

Variances on the output side are variances that result from too little or too much of the planned order quantity being delivered, or
because the delivered quantity was valued differently.

 Mixed-price variances

Mixed-price variances arise when inventories are valued using a mixed cost estimate. A mixed-price variance is
caused by a difference between the target credit (Confirmed Quantity × Standard Cost of Procurement Alternative)
determined by variance calculation, and the actual credit that was posted when the goods were received (Confirmed
Quantity × Standard Price). The standard price corresponds to the mixed price.

If you have not selected the Mixed-price variance field in the variance variant, mixed-price variances are reported as
output price variances.

 Output price variances

Output price variances are reported in the following situations:

o The standard price has changed between the time of delivery to stock and the time when the variances are calculated

o The material’s price control indicator is set to V and the material was not delivered to stock at the standard price

o The price used to value the inventory is not a mixed price

Output price variances are caused by a difference between the target credit (such as Confirmed Quantity x Standard
Price) determined by variance calculation, and the actual credit posted when the goods were received (such as
Confirmed Quantity x Moving Price).

You control which value is used for delivery to stock when the price control indicator is set to V in Customizing
for Product Cost by Period or Product Cost by Order under Define Valuation of Goods Received for Order
Delivery.

 Lot size variances

General
Lot size variances are differences between the planned costs that do not vary with the lot size and the actual costs
that do not vary with the lot size, which are passed on to inventory when you put the order quantity into inventory. A lot
size variance arises when a portion of a material’s total cost does not change when the you change the quantity of
goods manufactured.

Lot size variances are calculated in the following formula:

Lot Size Variance = Lot-Size-Independent Target Costs × (1 -Control Quantity ÷ Planned Quantity)

Lot size variances are only calculated if the planned quantity is different than the confirmed quantity (the delivered
quantity).

 Remaining variances

Differences between the target costs and the allocated actual costs that cannot be assigned to any other variance
category. For example, rounding differences are reported as remaining variances.

Overhead applied to costs that do not vary with the lot size are also reported as remaining variances.

Remaining variances are reported in the following situations:

o When no target costs can be calculated, such as when no cost estimate for the material exists or because no goods
receipt for the order has taken place in the Product Cost by Period component.

o When no variance categories have been defined in the variance variant in Customizing for Cost Object Controlling.

If you do not select a variance category, the variances of that category are assigned to the remaining variances category. Scrap
variances are an exception to this. Scrap variances that are not shown as such can flow into any other variance category on the
input side.

Example

Example for Variance Categories on the Input Side

 Input price variance

Raw material 1 goes into the standard cost estimate at USD 10 (the standard price is selected according to the
valuation strategy). For the goods issue, the price control indicator specifies that the goods movement is valued with

General
the moving average price. The moving average price for raw material 1 is USD 11 at the time of withdrawal. An input
price variance of USD 1 is reported.

 Resource-usage variance

Example 1:

Raw material 1 was not available, so raw material 2 was used instead. The first raw material is assigned to cost
element 400000 and the second raw material to cost element 412000. The system reports the costs for raw material 1
and raw material 2 as resource-usage variances. Taking the order as a whole, the two amounts together result in a
resource-usage variance.

Example 2:

You are using separate valuation. The valuation type in the actuals specifies a different account than in the standard
cost estimate. Because different accounts and therefore different cost elements were used, a resource-usage
variance is reported.

 Input quantity variance

Machine time of 15 minutes was planned. 17 minutes were confirmed. The machine time costs USD 5 per minute.
This results in an input quantity variance of USD 10.

 Remaining input variance

Example:

The material overhead is higher than planned because the price for raw material 1 changed. The difference between
the planned material overhead and the actual material overhead is reported as a remaining input variance.

 Scrap variance

See also: Scrap Variances

Example for the Assignment of Costs on the Input Side

Suppose you have planned a cost of USD 10 per piece for raw material 1. The actual cost for raw material 1 is USD 11. The
planned consumption for raw material 1 was 10 pieces, but the actual consumption is 11 pieces. The planned cost is USD 100.
The actual cost is USD 121. In both cases the order quantity is 10 pieces. The difference contains both an input price variance and
an input quantity variance.

The input price variance is USD 10, the input quantity variance is USD 10, and USD 1 could be considered either an input price
variance or an input quantity variance.

General
Because the system calculates the input price variances first, it assigns the USD 1 to the input price variance category, resulting in
an input price variance of USD 11 and an input quantity variance of USD 10.

Examples for Variance Categories on the Output Side

 Mixed-price variance

Material A has multiple procurement alternatives. A mixing ratio defines the relationship between the procurement
alternatives. A mixed cost estimate is created on the basis of the mixing ratio. The mixed cost estimate calculates a
mixed price. The mixed price corresponds to the standard price of the material.

Mixed-Price Variances

The mixed price is calculated as follows:

USD 100 × 5 = USD 500

USD 110 × 3 = USD 330

USD 120 × 2 = USD 240

USD 500 + 330 + 240 = USD 1,070

USD 1,070 ÷ 10 = USD 107

General
The mixed price is USD 107.

You create a production order for the procurement alternative that is included in the mixing ratio at 30%.

Production order 4711 for material A

Planned quantity 10 units

Actual quantity 10 units

Actual cost (debit) USD 1,150

Credit from goods receipt USD 1,070

Balance USD 80

The variance calculation process goes through the following steps:

The total variance is the difference between the debit and credit. This amount is USD 80. You want to have this total
variance explained with variance calculation (target cost version 0). In variance calculation the target costs are
compared with the control costs.

Target costs = Confirmed quantity (yield) x Standard cost of procurement alternative

Result:

Target cost = 10 × USD 110 = USD 1,100

More Information

Production Process

If you compare the target costs on the order with the debited actual costs, the result is a variance of USD 50. This
difference corresponds to the variances that are not mixed-price variances.

If you compare the target costs with the allocated actual costs, the result is a variance of USD 30. This difference
between the target costs and the credit of the order is the mixed-price variance. This variance arises because the
standard cost of the procurement alternative for which an order was created is not the standard price.

General
Posted actual cost (debit) USD 1,150

Allocated actual cost (goods receipt) USD 1,070

Target cost USD 1,100

Control cost USD 1,150

Variances on the input side USD 50

Mixed-price variance USD 30

The sum of the variances on the input side and the mixed-price variance explain the balance on the order that results
from the difference between the debit and the credit.

 Output price variances

The standard cost estimate for a material calculated a standard price of USD 75. Ten units are delivered to stock for
production order 4711, and this delivery is valued at standard price. You calculate a new standard cost estimate for
the material, mark the cost estimate, and release it. The new standard price is USD 100. The target cost is calculated
as USD 1,000. The output price variance is USD 250.

 Lot size variances

The setup time and teardown time for an operation remain the same, regardless of how many times an operation is
carried out.

For example, if the order quantity is less than the costing lot size, the setup costs and the teardown costs based on
one unit of the product for the order will be higher than in the cost estimate. The system reports this difference as a lot
size variance.

General

You might also like