Rejina
Rejina
Location-
Rate
Rate with Transportation Cost
SN Description Unit Local Rate without Unit Rate
VAT
VAT
Truck Manual
B Local Material
Rate
Rate with Transportation Cost
SN Description Unit Local Rate without Unit Rate
VAT
VAT
Truck Manual
Foreign Materials
0.00
3
Page 4
Rate
Rate with Transportation Cost
SN Description Unit Local Rate without Unit Rate
VAT
VAT
Truck Manual
4
Page 5
Rate
Rate with Transportation Cost
SN Description Unit Local Rate without Unit Rate
VAT
VAT
Truck Manual
5
Page 6
Rate
Rate with Transportation Cost
SN Description Unit Local Rate without Unit Rate
VAT
VAT
Truck Manual
b) 24 Gauge G.I. mosquito proof mesh wire Sqm 505.72 0.23 505.95
44 Glass 0.00
56 Plastic Emulson exterior first class(NS161) Lit Check 968.00 0.23 968.23
Plastic Emulson exterior Side medium
57 Lit check 753.00 289.04 1042.04
class(NS161)
6
Page 7
Rate
Rate with Transportation Cost
SN Description Unit Local Rate without Unit Rate
VAT
VAT
Truck Manual
57 Plastic Emulson Interior first class(NS 161) Lit check 858.00 0.23 858.23
Plastic Emulson Interior side medium class(NS
58 Lit check 683.00 289.04 972.04
161)
58 wall putine Kg 78.00 0.23 78.23
Rate
Rate with Transportation Cost
SN Description Unit Local Rate without Unit Rate
VAT
VAT
Truck Manual
91 Porsilina glazed tile for wall Sqm 688.64 688.64 0.23 688.87
92 Porsilina glazed tile for Floor sqm 742.44 742.44 0.23 742.67
94 110 mm dia PVC 2.5 k.g /cm 2 pipe Rm 257 257 0.23 257.23
3.00 40 mm dia GI heavy duty socket Pec 196.00 196.00 221.48 0.23 221.71
4.00 41 mm GI Pressure staner 1.5 mt Long pec 1090.00 1090.00 1231.70 0.23 1231.93
8
Page 9
n Materials
page No
Remarks
75
78
78
74
74
75
75
77
76
23
23
23
23 1.61
23
23
23
23
Trans
9
Page 10
page No
Remarks
Trans
Trans
23
16
16
16
16
23
23
23
23
21
5 95.75 84.73451327
5 84.070796460177
56
56
57
57
57
57
57
10
Page 11
page No
Remarks
79
2.6046 5
16
1.05 30
1.15 30
1.26 30
1.36 30
30
30
30
30
30
30
30
30
30
30
30
30
30
30
30
31
31
31
31
31
16
16
16
16
16
16
11
Page 12
page No
Remarks
17
17
17
17
17
17
17
17
17
17
17
17
17
30
30
30
30
31
31
31
31
31
31
31
31
31
31
31
31
31
12
Page 13
page No
Remarks
31
31
31
31
31
31
31
31
31 529.74 17.55562329
31
31
31 21.94452911 L
21.94452911 0.8 B
3 19.7500762 17.55562329
3 470.8842593 9300
3 529.7447917 B
4 1060.82 475.8778914
1360 610.09
30
11.21 30
402.8490028
38
38 21.94 A 1
38 17.56 B 1.22
7070 402.72
38 5530 315.00
38 11270 641.96
38
13
Page 14
page No
Remarks
38 9560 544.55
38
7180 408.99
0.60
10.69
+15%OH
+15%OH
+15%OH 45.25
+15%OH
+15%OH
+15%OH
+15%OH
+15%OH
+15%OH
+15%OH
+15%OH
+15%OH
+15%OH
14
Page 15
page No
Remarks
10
10
10
10
10
45
41
57
41
41
41
15
Page 16
1.22
sqm
16
Transportation Cost of Construction Materials-Terai
Project name:- 0
2 Sand/River Spall and gravel less than-40 mm size- For 10 Cum Quarry site:- Budhi kulo kinara
SN Description Unit Lead-Km Quantity Unit Rate Amount NRs
1 Time allowed for loading and unloading Hour 2.14 150.00 321.00
2 Labour For collection MD 10.0 530.00 5300.00
3 Earthen Road - 15 Kmph Hour 2.0 0.76 300.00 228.00
4 Gravel Road - 30 Kmph Hour 4.0 0.76 300.00 228.00
5 Bitumenious Road - 45 Kmph Hour 0.0 0.00 300.00 0.00
6 Diesel and lubricants Lit 6.0 12.16 87.89 1068.74
7 Labour for loading, unloading,stacking MD 6.0 0.72 530.00 381.60
8 Royalty Cum 10.00 211.89 2118.90
Sub-Total NRs 9646.24
Deduction of Voids 10% -964.62
Total 8681.62
Rate for I cum at Site 868.16
Transportation Cost 17
4 Bricks - Per 1000 Factory:- khairapur
SN Description Unit Lead-Km Quantity Unit Rate Amount NRs
1 Time allowed for loading and unloading Hour 2.21 150.00 331.50
Total 2890.37
Rate for I cum at site 289.04
Transportation Cost 18
8 Natural river Aggregate 5-10 mm size- For 10 Cum Quarry site:- Karnali river
SN Description Unit Lead-Km Quantity Unit Rate Amount NRs
1 Time allowed for loading and unloading Hour 2.14 150.00 321.00
2 Labour for Seiving/Collection/Stacking MD 70.00 530.00 37100.00
3 Earthen Road - 15 Kmph Hour 2.0 0.76 300.00 228.00
4 Gravel Road - 30 Kmph Hour 9.0 1.71 300.00 513.00
5 Bitumenious Road - 45 Kmph Hour 0.0 0.00 300.00 0.00
6 Diesel and lubricants Lit 11.0 21.66 87.89 1903.70
7 Labour for loading, unloading,stacking MD 11.0 1.17 530.00 620.10
8 Royalty Cum 10.00 211.89 2118.90
Sub Total NRs 42804.70
Deduction of Voids 10% -4280.47
Add Tools and Plants @3% 1155.73
Total 39679.96
Rate for I cum at site 3968.00
9 Natural river Aggregate 10-20 mm size- For 10 Cum Quarry site:- Karnali river
SN Description Unit Lead-Km Quantity Unit Rate Amount NRs
1 Time allowed for loading and unloading Hour 2.14 150.00 321.00
2 Labour for Seiving/Collection/Stacking MD 50.00 530.00 26500.00
3 Earthen Road - 15 Kmph Hour 2.0 0.76 300.00 228.00
4 Gravel Road - 30 Kmph Hour 9.0 1.71 300.00 513.00
5 Bitumenious Road - 45 Kmph Hour 0.0 0.00 300.00 0.00
6 Diesel and lubricants Lit 11.0 21.66 87.89 1903.70
7 Labour for loading, unloading,stacking MD 11.0 1.17 530.00 620.10
8 Royalty Cum 10.00 211.89 2118.90
Sub Total NRs 32204.70
Deduction of Voids 10% -3220.47
Add Tools and Plants @ 3% 869.53
Total 29853.75
Rate for I cum at site 2985.38
10 Natural river Aggregate 20-40 mm size- For 10 Cum Quarry site:- Karnali river
SN Description Unit Lead-Km Quantity Unit Rate Amount NRs
1 Time allowed for loading and unloading Hour 2.14 150.00 321.00
2 Labour for Seiving/Collection/Stacking MD 40.00 530.00 21200.00
3 Earthen Road - 15 Kmph Hour 2.0 0.76 300.00 228.00
4 Gravel Road - 30 Kmph Hour 9.0 1.71 300.00 513.00
5 Bitumenious Road - 45 Kmph Hour 0.0 0.00 300.00 0.00
6 Diesel and lubricants Lit 11.0 21.66 87.89 1903.70
7 Labour for loading, unloading,stacking MD 11.0 1.17 530.00 620.10
8 Royalty Cum 10.00 211.89 2118.90
Sub Total NRs 26904.70
Deduction of Voids 10% -2690.47
Add Tools and Plants @ 3% 726.43
Total 24940.65
Rate for I cum at site 2494.07
Transportation Cost 19
11 Crushed Aggregate 5-40 mm size- For 10 Cum Crusher:- 12 No. Noori(Sanoshri)
SN Description Unit Lead-Km Quantity Unit Rate Amount NRs
1 Time allowed for loading and unloading Hour 2.14 150.00 321.00
2 Earthen Road - 15 Kmph Hour 1.0 0.76 300.00 228.00
3 Gravel Road - 30 Kmph Hour 21.0 0.76 300.00 228.00
4 Bitumenious Road - 45 Kmph Hour 18.0 0.00 300.00 0.00
5 Diesel and lubricants Lit 40.0 76.38 87.89 6713.04
6 Labour for loading, unloading,stacking Done by Manufacturer
Sub-Total NRs 7169.04
Deduction of Voids 10% -716.90
Total 6452.14
Rate for I cum 645.21
Transportation Cost 20
21
Rate Analysis
#REF!
#REF!
A3.Site Clearance-One sqm
Labour Material and Equipment
Category MD Rate Amount Type Quantity Rate
Unskilled Labour 0.023 530.00 12.19 T&P 3%
Sub-Total 12.19
Total of Labour and Material
Contractor's Overhead @15%
Rate per Sqm
Sub-Total 0.00
Total of Labour and Material
Quality Control @2% (Norms-Page viii)
Total
Contractor's Overhead @15%
Rate per Cum
21
22
Rate Analysis
Ordinary Soil with compaction by rammer( Inported fill material )-One cum
Labour Material and Equipment
Category MD Rate Amount Type Unit Quantity Rate
Unskilled Labour 0.25 530.00 132.50 Soil Cum 1.10 289.04
Sub-Total Sqm 132.50
Total of Labour and Material Sqm
Contractor's Overhead @15% Sqm
Rate per Cum
2-42. Sand filling with water & compaction by labour -One cum
Labour Material and Equipment
Category MD Rate Amount Type Unit Quantity Rate
Unskilled Labour 0.70 530.00 371.00 Sand Cum 1.10 868.16
Sub-Total 371.00
Total of Labour and Material
Contractor's Overhead @15%
Rate per Cum
22
23
Rate Analysis
23
24
Rate Analysis
Plain Cement Concrete in foundation using natural river aggregate (By labour)
24
25
Rate Analysis
7-2-Ga . In (1:3:6) -One cum
Labour Material and Equipment
Category MD Rate Amount Type Unit Quantity Rate
Skilled labour 1.00 750.00 750.00 Cement Kg 220.00 16.03
Unskilled Labour 4.00 530.00 2120.00 sand Cum 0.47 868.16
Natural Agg.-10mm Cum 0.00 2494.07
Natural Agg.-40mm Cum 0.65 2985.38
Natural Agg.-20mm Cum 0.24 2985.38
Sub-Total 2870.00
Total of Labour and Material
Contractor's Overhead @15%
Rate per Cum
Plain Cement Concrete in Super structure using natural river aggregate (By Labour)
25
26
Rate Analysis
Labour Material and Equipment
Category MD Rate Amount Type Unit Quantity Rate
Skilled labour 1.00 750.00 750.00 Cement Kg 220.00 16.03
Unskilled Labour 4.00 530.00 2120.00 sand Cum 0.47 868.162
Crushed Agg.-40mm Cum 0.65 3399.94
Crushed Agg.-20mm Cum 0.24 3470.57
Sub-Total 2870.00
Total of Labour and Material
Contractor's Overhead @15%
Rate per Cum
26
27
Rate Analysis
D1.7-2-gha. In (1:2:4) -One cum
Labour Material and Equipment
Category MD Rate Amount Type Unit Quantity Rate
Skilled labour 1.00 750.00 750.00 Cement Kg 320.00 16.03
Unskilled Labour 4.00 530.00 2120.00 sand Cum 0.45 868.16
Crushed Agg.-40mm Cum 0.52 3399.94
Crushed Agg.-20mm Cum 0.22 3470.57
Crushed Agg.-10mm Cum 0.11 3470.57
Sub-Total 2870.00
Total of Labour and Material
Contractor's Overhead @15%
Rate per Sqm
Plain Cement Concrete in Super Structure using Crushed Aggregate (By labour)
D1.7-4-Kha. In (1:2:4) -One cum
Labour Material and Equipment
Category MD Rate Amount Type Unit Quantity Rate
Skilled labour 0.80 750.00 600.00 Cement Kg 320.00 16.03
Unskilled Labour 7.00 530.00 3710.00 sand Cum 0.45 868.16
Crushed Agg.-40mm Cum 0.52 3399.94
Crushed Agg.-20mm Cum 0.22 3470.57
Crushed Agg.-10mm Cum 0.11 3470.57
Sub-Total 4310.00
Total of Labour and Material
Contractor's Overhead @15%
Rate per Sqm
27
28
Rate Analysis
Plain Cement Concrete Foundation natural river aggregate (Using Mixer and Vibratotr)
7-4-Kha. In (1:3:6) -One cum
Labour Material and Equipment
Category MD Rate Amount Type Unit Quantity Rate
Skilled labour 0.50 750.00 375.00 Cement Kg 200.00 16.03
Unskilled Labour 3.50 530.00 1855.00 sand Cum 0.47 868.16
Natural Agg.-40mm Cum 0.65 2985.38
Natural Agg.-20mm Cum 0.24 3968.00
Disel liters 3.00 87.89
Petrol liters 0.10 0.00
Mixer hour 0.60 1000.00
Vibrator Needle hour 0.25 100.00
Sub-Total 2230.00
Total of Labour and Material
Contractor's Overhead @15%
Rate per Sqm
Plain Cement Concrete Foundation natural river aggregate (Using Mixer and Vibratotr)
7-4-Kha. In (1:2:4) -One cum
Labour Material and Equipment
Category MD Rate Amount Type Unit Quantity Rate
Skilled labour 0.50 750.00 375.00 Cement Kg 320.00 16.03
Unskilled Labour 3.50 530.00 1855.00 sand Cum 0.45 868.16
Natural Agg.-40mm Cum 0.52 2985.38
Natural Agg.-20mm Cum 0.22 3968.00
Natural Agg.-10mm cum 0.11 3968.00
Disel liters 3.00 87.89
Petrol liters 0.10 0.00
Mixer hour 0.60 1000.00
Vibrator Needle hour 0.25 100.00
Sub-Total 2230.00
Total of Labour and Material
Contractor's Overhead @15%
Rate per Sqm
Plain Cement Concrete Suprstructure natural river aggregate (Using Mixer and Vibratotr)
7-4-Kha. In (1:1.5:3) -One cum
Labour Material and Equipment
Category MD Rate Amount Type Unit Quantity Rate
Skilled labour 0.50 750.00 375.00 Cement Kg 400.00 16.03
Unskilled Labour 3.50 530.00 1855.00 sand Cum 0.43 868.16
Natural Agg.-40mm Cum 0.57 2985.38
28
29
Rate Analysis
Natural Agg.-20mm Cum 0.29 3968.00
Disel liters 3.00 87.89
Petrol liters 0.10 0.00
Mixer hour 0.60 1000.00
Vibrator Needle hour 0.25 100.00
Sub-Total 2230.00
Total of Labour and Material
Contractor's Overhead @15%
Rate per Sqm
Plain Cement Concrete Foundation crushed aggregate (Using Mixer and Vibratotr)
7-4-Kha. In (1:3:6) -One cum
Labour Material and Equipment
Category MD Rate Amount Type Unit Quantity Rate
Skilled labour 0.50 750.00 375.00 Cement Kg 220.00 16.03
Unskilled Labour 3.50 530.00 1855.00 sand Cum 0.47 868.16
CrushedAgg.-40mm Cum 0.65 3399.94
Crushed Agg.-20mm Cum 0.24 3470.57
Disel liters 3.00 87.89
Petrol liters 0.10 0.00
Mixer hour 0.60 1000.00
Vibrator Needle hour 0.25 100.00
Sub-Total 2230.00
Total of Labour and Material
Contractor's Overhead @15%
Rate per Sqm
Plain Cement Concrete Foundation crushed aggregate (Using Mixer and Vibratotr)
7-4-Kha. In (1:2:4) -One cum
Labour Material and Equipment
Category MD Rate Amount Type Unit Quantity Rate
Skilled labour 0.50 750.00 375.00 Cement Kg 320.00 16.03
Unskilled Labour 3.50 530.00 1855.00 sand Cum 0.45 868.16
crushed Agg.-40mm Cum 0.52 3399.94
crushed Agg.-20mm Cum 0.22 3470.57
Crushed Agg.-10mm cum 0.11 3470.57
Disel liters 3.00 87.89
Petrol liters 0.10 0.00
Mixer hour 0.60 1000.00
Vibrator Needle hour 0.25 100.00
Sub-Total 2230.00
Total of Labour and Material
Contractor's Overhead @15%
Rate per Sqm
Plain Cement Concrete Suprstructure crushed aggregate (Using Mixer and Vibratotr)
7-4-Kha. In (1:1.5:3) -One cum
Labour Material and Equipment
Category MD Rate Amount Type Unit Quantity Rate
Skilled labour 0.50 750.00 375.00 Cement Kg 400.00 16.03
Unskilled Labour 3.50 530.00 1855.00 sand Cum 0.43 868.16
Crushed Agg.-20mm Cum 0.57 3470.57
Crushed Agg.-10mm Cum 0.29 3470.57
Disel liters 3.00 87.89
Petrol liters 0.10 0.00
Mixer hour 0.60 1000.00
29
30
Rate Analysis
Vibrator Needle hour 0.25 100.00
Sub-Total 2230.00
Total of Labour and Material
Contractor's Overhead @15%
Rate per Sqm
14-2-kha. Rulled Pointing (1:2) cement Mortar stone masonry -One Sqm
Labour Material and Equipment
Category MD Rate Amount Type Unit Quantity Rate
Skilled labour 0.100 750.00 75.00 Cement Kg 4.08 16.03
Unskilled Labour 0.140 530.00 74.20 Sand Cum 0.0057 868.16
Sub-Total 149.20
30
31
Rate Analysis
Total of Labour and Material
Contractor's Overhead @15%
Rate per Sqm
14-1-kha. Rulled Pointing (1:2) cement Mortar Brick masonry -One Sqm
Labour Material and Equipment
Category MD Rate Amount Type Unit Quantity Rate
Skilled labour 0.105 750.00 78.75 Cement Kg 2.10 16.03
Unskilled Labour 0.120 530.00 63.60 Sand Cum 0.0029 868.16
Sub-Total 142.35
Total of Labour and Material
Contractor's Overhead @15%
Rate per Sqm
51Ka. 12mm thick Waterproof Plywood formwork for Beam up to 300mm deep-One sqm
Labour Material and Equipment
Category MD Rate Amount Type Unit Quantity Rate
Waterproof Plywood-6
Skilled labour 0.157 750.00 118.05 sqm 0.1830 990.15
uses
Unskilled Labour 0.236 530.00 125.13 Nails Cum 0.2500 110.23
Local wood - 6 uses Cum 0.0048 42380.40
31
32
Rate Analysis
Waterproof Plywood-6
Skilled labour 0.400 750.00 300.00 sqm 0.0000 0.00
uses
Unskilled Labour 0.600 530.00 318.00 Nails Cum 0.2500 110.23
Local wood - 6 uses Cum 0.0012 42380.40
Sub-Total 412.25
Total of Labour and Material
Contractor's Overhead @15%
Rate per Sqm
7-5. 8 mm diameter
Labour Material and Equipment
Category MD Rate Amount Type Unit Quantity Rate
Skilled labour 0.012 750.00 9.00 Steel Kg 1.05 82.23
Unskilled Labour 0.012 530.00 6.36 Anneled Wire Kg 0.01 112.23
Sub-Total 15.36
Total of Labour and Material
Contractor's Overhead @15%
Rate per Kg
7-5Ga. 10 mm diameter
Labour Material and Equipment
Category MD Rate Amount Type Unit Quantity Rate
Skilled labour 0.012 750.00 9.00 Steel Kg 1.05 81.23
Unskilled Labour 0.012 530.00 6.36 Anneled Wire Kg 0.01 112.23
Sub-Total 15.36
Total of Labour and Material
Contractor's Overhead @15%
32
33
Rate Analysis
Rate per Kg
7-5Gha. 12 to 25 mm diameter
Labour Material and Equipment
Category MD Rate Amount Type Unit Quantity Rate
Skilled labour 0.012 750.00 9.00 Steel Kg 1.05 81.23
Unskilled Labour 0.012 530.00 6.36 Anneled Wire Kg 0.01 112.23
Sub-Total 15.36
Total of Labour and Material
Contractor's Overhead @15%
Rate per Kg
Wood Works
10-1. Sal Wood work for chaukhat - One cum
Labour Material and Equipment
Category MD Rate Amount Type Unit Quantity Rate
Skilled labour 34.00 750.00 25500.00 Sal wood Cum 1.10 162458.20
Unskilled Labour 3.40 530.00 1802.00 Hold fast (250mm) Nos 92.00 21.67
Scew Nails Nos 184.00 1.26
Sub-Total 27302.00
Total of Labour and Material
Contractor's Overhead @15%
Rate per cum
10-2. 38x100mm sal wood pannel door shutter - One Sqm (Size - 1.07x1.982=2.114)
Labour Material and Equipment
Category MD Rate Amount Type Unit Quantity Rate
Skilled labour 10.00 750.00 7500.00 Sal wood Cum 0.084 162458.20
Unskilled Labour 1.00 530.00 530.00 100mm hinze Nos 6.000 31.08
150mm tower bolt Nos 1.000 110.00
300 mm tower bolt Nos 1.000 294.00
300mm Lucking set Set 1.000 420.00
Handel Set 2.000 320.00
Screw Nails LS 50.00
Sub-Total 8030.00
Total of Labour and Material
Contractor's Overhead @15%
Total
Rate per sqm
10-2. 38x100mm Shisam Woodpannel door shutter - One Sqm (Size - 1.07x1.982=2.114)
Labour Material and Equipment
Category MD Rate Amount Type Unit Quantity Rate
33
34
Rate Analysis
Skilled labour 10.00 750.00 7500.00 Shisam Wood Cum 0.084 151863.10
Unskilled Labour 1.00 530.00 530.00 100mm hinze Nos 6.000 31.08
150mm tower bolt Nos 1.000 110.00
300 mm tower bolt Nos 1.000 294.00
300mm Lucking set Set 1.000 420.00
Handel Set 2.000 320.00
Screw Nails LS 50.00
Sub-Total 8030.00
Total of Labour and Material
Contractor's Overhead @15%
Total
Rate per sqm
10-4 38x75mm thick sal wood shutter work with 4mm thick glass- One Sqm (Size - 1.829x1.22=2.23)
Labour Material and Equipment
Category MD Rate Amount Type Unit Quantity Rate
Skilled labour 9.00 750.00 6750.00 Sal wood Cum 0.049 162458.20
Unskilled Labour 0.90 530.00 477.00 75mm hinze Nos 8.000 18.42
3mm thick glass Sqm 1.085 850.27
100mm tower bolt Nos 4.000 53.00
Handel Set 2.000 190.00
Screw Nails LS 50.00
Sub-Total 7227.00
Total of Labour and Material
Contractor's Overhead @15%
Total
Rate per sqm
10-9. 38mm thick Sal wood framed shutter with both side 26Gauge plain sheet for - One Sqm (Size -
1.092x2.058=2.245 sqm)
Labour Material and Equipment
Category MD Rate Amount Type Unit Quantity Rate
Skilled labour 7.00 750.00 5250.00 Sal wood Cum 0.035 162458.20
Unskilled Labour 0.70 530.00 371.00 100mm hinze Nos 3.000 31.08
Plain sheet Sqm 4.650 530.14
150mm tower bolt Nos 2.000 110.00
Handel Set 1.000 190.00
Screw Nails LS 50.00
300mm Lucking set Set 1.00 420.00
Sub-Total 5621.00
Total of Labour and Material
Contractor's Overhead @15%
Total
Rate per sqm
10-9. 38mm thick sisham wood framed shutter with both side 26Gauge plain sheet for - One Sqm (Size -
1.092x2.058=2.245 sqm)
34
35
Rate Analysis
Handel Set 1.000 190.00
Screw Nails LS 50.00
300mm Lucking set Set 1.00 420.00
Sub-Total 5621.00
Total of Labour and Material
Contractor's Overhead @15%
Total
Rate per sqm
35
36
Rate Analysis
10-10. 24Gauge wiremesh with Barfi wire in sal wood shutter 38x75mm - One Sqm (Size - 1.092x2.058=2.245 sqm)
Labour Material and Equipment
Category MD Rate Amount Type Unit Quantity Rate
Skilled labour 5.00 750.00 3750.00 Sal wood Cum 0.026 162458.20
Unskilled Labour 0.50 530.00 265.00 100mm hinze Nos 3.000 31.08
24 Gauge wire mesh Sqm 2.130 452.15
150mm tower bolt Nos 2.000 110.00
Barfi zali Sqm 2.130 1183.83
Handel Set 2.000 190.00
Screw Nails LS 50.00
Door Spring Set 1.00 184.00
Sub-Total 4015.00
Total of Labour and Material
Contractor's Overhead @15%
Total
Rate per sqm
Painting Work
13-5.Two cot enamel paint over one coat of primer - One Sqm
Labour Material and Equipment
Category MD Rate Amount Type Unit Quantity Rate
Skilled labour 0.12 750.00 90.00 Primer Lit. 0.081 363.23
Unskilled Labour 0.08 530.00 42.40 Enamel Lit. 0.160 513.23
Sub-Total 132.40
Total of Labour and Material
Contractor's Overhead @15%
Rate per Sqm
36
37
Rate Analysis
13-4.KhaTwo cot watet proof cement paint on new surface -One Sqm
Labour Material and Equipment
Category MD Rate Amount Type Unit Quantity Rate
Skilled labour 0.0500 750.00 37.50 Cement paint Kg 0.485 70.23
Unskilled Labour 0.0500 530.00 26.50
Sub-Total 64.00
Total of Labour and Material
Contractor's Overhead @15%
Rate per Sqm
13-4.Ka One coat watet proof cement paint on new surface -One Sqm
Labour Material and Equipment
Category MD Rate Amount Type Unit Quantity Rate
Skilled labour 0.0170 750.00 12.75 Cement paint Kg 0.300 70.23
Unskilled Labour 0.0170 530.00 9.01
Sub-Total 21.76
Total of Labour and Material
Contractor's Overhead @15%
Rate per Sqm
13-3 GaTwo cot Distemper giving uniform colour on old surface -One Sqm
Labour Material and Equipment
Category MD Rate Amount Type Unit Quantity Rate
Skilled labour 0.0180 750.00 13.50 Primer Kg 0.000 383.00
Unskilled Labour 0.0180 530.00 9.54 Distemper Kg 0.0500 245.00
Sub-Total 23.04
Total of Labour and Material
Contractor's Overhead @15%
Rate per Sqm
J5-13-5ka,kha,ga-.Two coat of whasable distemper paint over one coat of primer - One Sqm Norms 13-5Ka
Labour Material and Equipment
Category MD Rate Amount Type Unit Quantity Rate
Skilled labour 0.120 750.00 90.00 cement Primer Lit. 0.081 383.23
Unskilled Labour 0.080 530.00 42.40 whashable distemper Lit. 0.160 248.23
Sub-Total 132.40
Total of Labour and Material
Contractor's Overhead @15%
Rate per Sqm
11-1kha . 38mm thick PCC in (1:2:4) with cement punning for flooring works - One Sqm
Labour Material and Equipment
Category MD Rate Amount Type Unit Quantity Rate
Skilled labour 0.125 750.00 93.75 Cement Kg 13.000 16.03
Unskilled Labour 0.200 530.00 106.00 Sand Cum 0.018 868.16
12mm Aggregate Cum 0.036 3470.57
Sub-Total 199.75
Total of Labour and Material
Contractor's Overhead @15%
Rate per Sqm
b) 50mm thick PCC (1:2:4) flooring work with neat cement finishing. - One sqm. G.Norms-11-1-ga
Labour Material and Equipment
Category MD Rate Amount Type Unit Quantity Rate
Skilled labour 0.125 750.00 93.75 Cement Kg 17.000 16.03
37
38
Rate Analysis
Unskilled Labour 0.250 530.00 132.50 sand Cum 0.023 868.16
Natural Agg.-20mm Cum 0.046 3399.94
Sub-Total 226.25
Total of Labour and Material
Contractor's Overhead @15%
Rate per Cum
10-11-Kha. mosquito proof wiremesh fixing with wooden listee - One Sqm
Labour Material and Equipment
Category MD Rate Amount Type Unit Quantity Rate
mosquito proof
Skilled labour 0.06 750.00 45.00 Sqm 1.000 452.15
wiremesh
Unskilled Labour 0.006 530.00 3.18 Wooden Listee meter 4.050 12.00
Nails LS 3.00
Sub-Total 48.18
Total of Labour and Material
Contractor's Overhead @15%
Rate per sqm
Dismentalling of structures
19.2 Dismentalling of cement mortared masonry and dispoal up to 10m- One Cum
Labour Material and Equipment
Category MD Rate Amount Type Unit Quantity Rate
Unskilled Labour 2.120 530.00 1123.60 Tools and Plants- 3% 0.030
Sub-Total 1123.60
Total of Labour and Material
Contractor's Overhead @15%
Rate per Cum
19.3 Dismentalling of RCC and RBC structure and dispoal up to 10m- One Cum
Labour Material and Equipment
Category MD Rate Amount Type Unit Quantity Rate
Unskilled Labour 11.000 530.00 5830.00 Tools and Plants- 3% 0.030
Sub-Total 5830.00
Total of Labour and Material
Contractor's Overhead @15%
Rate per Cum
19.4 Dismentalling of RCC and PCC structure and dispoal up to 10m - One Cum
Labour Material and Equipment
Category MD Rate Amount Type Unit Quantity Rate
Sub-Total 2120.00
Total of Labour and Material
38
39
Rate Analysis
Contractor's Overhead @15%
Rate per Cum
19.4 Dismentalling of Cement plaster structure and dispoal up to 10m - One sqm.
Labour Material and Equipment
Category MD Rate Amount Type Unit Quantity Rate
Unskilled Labour 0.108 530.00 57.24 Tools and Plants- 3% 0.030
Sub-Total 57.24
Total of Labour and Material
Contractor's Overhead @15%
Rate per Cum
Sub-Total 84.80
Total of Labour and Material
Contractor's Overhead @15%
Rate per Cum
Providing and laying Glazed Ceramic tile(Skid) on wall 1:3cemet mortar base in perfect line and level all complete . Per sqm
Material and
Labour
Equipment
Category MD Rate Amount Type Unit Quantity Rate
Skilled labour 1.3 750.00 975.00 cement Kg 13.00 16.03
Unskilled Labour 0.45 530.00 238.50 sand Cum 0.029 609.72
White Glazed tile Sqm 1.1 656.36
Sub-Total 1213.50
Total of Labour and Material
Contractor's Overhead @15%
Rate per Cum
Sub-Total 560.25
Total of Labour and Material
Contractor's Overhead @15%
39
40
Rate Analysis
Rate per Cum
37. Preparation of granular bedding for pipe with granular material-One Cum
Labour Material and Equipment
Category MD Rate Amount Type Unit Quantity Rate
Skilled labour 750.00 0.00 Granular material Cum 1.10 868.16
Unskilled Labour 1.00 530.00 530.00 Water Cum 0.10 91.67
Sub-Total 530.00
Total of Labour and Material
Contractor's Overhead @15%
Rate per Sqm
Skilled labour 0.02 750.00 15.00 NP3 pipe-300 mm dia meter 1.00 3370.25
40
41
Rate Analysis
Category MD Rate Amount Type Unit Quantity Rate
Skilled labour 1.30 750.00 975.00 Porsilina glazed tile Sqm 1.100 688.87
Unskilled Labour 0.45 530.00 238.50 Cement Kg 5.600 16.03
sand Cum 0.015 868.16
White Cement Cum 0.323 35.23
Sub-Total 1213.50
a) 26 gauge ,37mm thickMedium class CGI Sheet for roof Sada sheet - for One Sqm
G. Norms-9 -1
Sub-Total 148.75
Contractor's Overhead @15%
Rate per Sqm.
Sub-Total 148.75
Rate per Rm.
a) 26 gauge ,37mm thickMedium class CGI Sheet for roof colour sheet - for One Sqm G. Norms-9 -1
41
42
Rate Analysis
Rate per Sqm.
Sub-Total 148.75
Lowering,Jointing, Installation of casing Pipe,PVE pipe,well screen,sand trap,fitting head and packing with coarse sand around the well
Labour Material
Category Mandays Rate Amount Type Unit Quantity Rate
42
43
Rate Analysis
Skilled labour 0.50 730.00 365.00 Sand cum 0.150 382.95
Unslilled labour 510.00 0.00 Aggregate cum 0.100 2817.01
Cement Kg 25.000 9.57
Sub-Total 365.00
Total of Labour and Material Cost
Overhead cost @15%
Total NRs
Hudraulic Excavator UP
Skilled labour 0.00
to 0.63 m3 Capacity
Hour 0.0116 1800.00
Unskilled Labour 0.25 530.00 132.50 Fuel (Diesel) Lit. 0.1160 0.00
Sub-Total 132.50
Total of Labour and Material
Quality Control @2% (Norms-Page viii)
Total
Contractor's Overhead @15%
Rate per Cum
43
44
Rate Analysis
Labour Material and Equipment
Category MD Rate Amount Type Unit Quantity Rate
Unskilled Labour 0.50 530.00 265.00 T&P 3%
Sub-Total 265.00
Total of Labour and Material
Contractor's Overhead @15%
Rate per Cum
44
45
Rate Analysis
6c Roadway construction with imported fill material (natural Compaction)-One cum
Labour Material and Equipment
Category MD Rate Amount Type Unit Quantity Rate
Skilled labour 750.00 Imported fill material cum 1.10 271.74
Unskilled Labour 0.25 530.00 132.50
Sub-Total 132.50
Total of Labour and Material
Contractor's Overhead @15%
Rate per Cum
45
46
Rate Analysis
Rate per Sqm
20.Formwork for beam and slab erection and removal -One sqm
20a. Local wood
Labour Material and Equipment
Category MD Rate Amount Type Unit Quantity Rate
Skilled labour 0.125 750.00 93.75 Local wood Cum 0.0125 42384.00
Unskilled Labour 0.175 530.00 92.75 Nails kg 0.2500 124.58
Selvage Value 25%
Sub-Total 186.50
Total of Labour and Material
Contractor's Overhead @15%
Rate per Sqm
Skilled labour 0.125 750.00 93.75 water proof ply-12mm Cum 0.2000 0.00
22ba. 8 m diameter
Labour Material and Equipment
Category MD Rate Amount Type Unit Quantity Rate
Skilled labour 0.007 750.00 5.25 Steel Kg 1.05 97.46
Unskilled Labour 0.007 530.00 3.71 Anneled Wire Kg 0.01 126.84
Sub-Total 8.96
Total of Labour and Material
Contractor's Overhead @15%
Rate per Kg
22c.. 10 mm diameter
Labour Material and Equipment
Category MD Rate Amount Type Unit Quantity Rate
Skilled labour 0.007 750.00 5.25 Steel Kg 1.05 95.20
Unskilled Labour 0.007 530.00 3.71 Anneled Wire Kg 0.01 126.84
Sub-Total 8.96
Total of Labour and Material
46
47
Rate Analysis
Contractor's Overhead @15%
Rate per Kg
22c. 12 to 25 mm diameter
Labour Material and Equipment
Category MD Rate Amount Type Unit Quantity Rate
Skilled labour 0.007 750.00 5.25 Steel Kg 1.05 95.20
Unskilled Labour 0.007 530.00 3.71 Anneled Wire Kg 0.01 126.84
Sub-Total 8.96
Total of Labour and Material
Contractor's Overhead @15%
Rate per Kg
47
48
Rate Analysis
Unskilled Labour 0.040 530.00 21.20
binding clay/ laterite Cum 0.12 271.74
Water Cum 0.070 91.67
8-10 Ton Roller Hour 0.09 550.00
Diesel @7lit/Hour Liter 0.792 100.50
Sub-Total 24.95
Total of Labour and Material
Quality Control @2% (Norms-Page viii)
Total
Contractor's Overhead @15%
Rate per Cum
24c. Class III Grading [CBR=20%] - One Cum
Labour Material and Equipment
Category MD Rate Amount Type Unit Quantity Rate
Skilled labour 0.005 750.00 3.75 Gravel-(40-70mm) Cum 1.28 830.05
Unskilled Labour 0.040 530.00 21.20
binding clay/ laterite Cum 0.120 271.74
Water Cum 0.070 91.67
8-10 Ton Roller Hour 0.090 550.00
Diesel @7lit/Hour Liter 0.792 100.50
Sub-Total 24.95
Total of Labour and Material
Quality Control @2% (Norms-Page viii)
Total
Contractor's Overhead @15%
Rate per Cum
Sub-Total 560.25
Total of Labour and Material
Contractor's Overhead @15%
Rate per Cum
Sub-Total 560.25
Total of Labour and Material
Contractor's Overhead @15%
Rate per Cum
48
49
Rate Analysis
Skilled labour 0.005 750.00 3.75 Gravel-(40-70mm) Cum 1.28 830.05
Unskilled Labour 1.050 530.00 556.50
Sub-Total 560.25
Total of Labour and Material
Contractor's Overhead @15%
Rate per Cum
49
50
Rate Analysis
Unskilled Labour 0.000 530.00 0.00 Deisel (DOR) Ltrs 0.0544 0.00
Sub-Total 0.00 Motor Grader Hrs 0.0034 0.00
Total of Labour and Material
Contractor's Overhead @15%
Rate per Sqm
16. Plain Cement Concrete in Super structure using natural river aggregate
16a. In (1:2:4) -One cum
Labour Material and Equipment
Category MD Rate Amount Type Unit Quantity Rate
Skilled labour 0.66 750.00 495.00 Cement Kg 320.00 0.00
Unskilled Labour 3.31 530.00 1754.3 sand Cum 0.44 0.00
Natural Agg.-40mm Cum 0.52 0.00
Natural Agg.-20mm Cum 0.22 0.00
Natural Agg.-10mm Cum 0.11 0.00
Sub-Total 2249.30
Total of Labour and Material
Contractor's Overhead @15%
Rate per Cum
Total of Labour and Material
Contractor's Overhead @15%
Rate per Sqm
50
51
Rate Analysis
12-38mm down agg Cum 0.075 3005.31
Roller Hr 0.010 550.00
Diesel- @ 7 lit/hr Lit 14.000 100.50
Kerosin oil ls 1.200 94.00
Sub-Total 150.00
Total of Labour and Material
Contractor's Overhead @15%
Rate per Sqm
33.Supply and Laying of bitumenous binder for first layer of Otta seal- 10 Sqm
Labour Material and Equipment
Category MD Rate Amount Type Unit Quantity Rate
Skilled labour 750.00 0.00 Bitumen Kg 16.510 70.28
Unskilled Labour 0.15 530.00 79.50 Firewood kg 7.000 10.00
Bitumen distributor Hr 0.037 1300.00
kerosene oil lit 1.990 94.00
Diesel- @ 7lit/hr Lit 0.259 100.50
Sub-Total 79.50
Total of Labour and Material
Contractor's Overhead @15%
Total
Rate per Sqm
Rate per Kg
Binder for first coat Otta Seal is taken as 18 L/10 sqm inclusing westage
For MC 3000 add 9% in average kerosene on 80/100 grade bitumen +0.50 liter additional
34.Supply and Laying of bitumenous binder for seal coat for single seal Otta seal- 10 Sqm
Labour Material and Equipment
Category MD Rate Amount Type Unit Quantity Rate
Skilled labour 750.00 0.00 Bitumen Kg 7.340 70.28
Unskilled Labour 0.15 530.00 79.50 Firewood kg 3.000 10.00
Bitumen distributor Hr 0.015 1300.00
kerosene oil lit 0.910 94.00
Diesel- @ 7 lit/hr Lit 0.090 100.50
Sub-Total 79.50
Total of Labour and Material
Contractor's Overhead @15%
Total
Rate per sqm
Rate per Kg
Binder for first coat Otta Seal is taken as 8 L/10 sqm inclusing westage
For MC 3000 add 9% in average kerosene on 80/100 grade bitumen +0.25 liter additional
35.Supply, Laying and compaction of aggregate 16mm down for single seal of Otta seal-10Sqm
Labour Material and Equipment
Category MD Rate Amount Type Unit Quantity Rate
Skilled labour 750.00 0.00 16mm down aggregate Cum 0.160 2661.89
Unskilled Labour 0.25 530.00 132.50 PT Roller >12 Ton Hr 0.131 1200.00
Diesel- @ 7 lit/hr Lit 0.917 100.50
Sub-Total 132.50
Total of Labour and Material
Contractor's Overhead @15%
Total
Rate per sqm
Rate per Kg
51
52
Rate Analysis
For DBST 6 passes is required for two days=12 passes (Roller input 0.07 hour as per Norms 15(20)
For Otta Seal 15 passes is required for 3 days=45 passes
Hence Roller input for first coat of Otta Seal=0.07/12x45=.131 hour
dendity og river bed aggrigate16 mm down=2000 kg per cum
36.Supply, Laying and compaction of sand/crusher dust for seal coat of Otta seal-10Sqm
Labour Material and Equipment
Category MD Rate Amount Type Unit Quantity Rate
Skilled labour 750.00 0.00 6mm down aggregate Cum 0.120 2661.89
Unskilled Labour 0.25 530.00 132.50 PT Roller >12 Ton Hr 0.131 1200.00
Diesel- @ 7 lit/hr Lit 0.917 100.50
Sub-Total 132.50
Total of Labour and Material
Contractor's Overhead @15%
Total
Rate per sqm
Rate per Kg
For DBST 6 passes is required for two days=12 passes (Roller input 0.07 hour as per Norms 15(20)
For Otta Seal 15 passes is required for 3 days=45 passes
Hence Roller input for first coat of Otta Seal=0.07/12x45=.131 hour
dendity og river bed aggrigate16 mm down=2000 kg per cum
37. Fabrication of Gabion Boxes Medium Zinc Coater GI Wire Hexagonal Mesh 100x120 Including rolling, cutting, weaving, assembling, placing in p
stretching, packing with stone and binding all complete
37a. Box Size-2x1x1 44-1-Bii/4
Labour Material and Equipment
Category MD Rate Amount Type Unit Quantity Rate
Mesh Weaving-[44.1-B]
Mesh Weaving-[44.1-B]
52
53
Rate Analysis
Total of Labour and Material
Contractor's Overhead @15%
Rate per Box
Mesh Weaving-[44.1-B]
Mesh Weaving-[44.1-B]
Mesh Weaving-[44.1-B]
53
54
Rate Analysis
Category MD Rate Amount Type Unit Quantity Rate
Mesh Weaving-[44.1-B]
Mesh Weaving-[44.1-B]
37. Preparation of granular bedding for pipe with granular material-One Cum
Labour Material and Equipment
Category MD Rate Amount Type Unit Quantity Rate
Skilled labour 750.00 0.00 Granular material Cum 1.10 838.36
Unskilled Labour 1.00 530.00 530.00 Water Cum 0.10 91.67
Sub-Total 530.00
Total of Labour and Material
Contractor's Overhead @15%
Rate per Sqm
54
55
Rate Analysis
Sub-Total 128.00
Rate per Cum
Roofing work
a) CGI Sheet for roof - for One Sqm G. Norms-9 -1
Labour Material and Equipment
Category MD Rate Amount Type Unit Quantity Rate
Skilled labour 0.110 750.00 82.50 CGI sheet (24 - 26 guage) Sqm. 1.20 402.85
Unskilled Labour 0.125 530.00 66.25 Nutbolt 8 mm. No. 3.00 2.60
J-hook Nos. 2.50 22.21
Bituminwasher Nos. 5.50 1.01
Sub-Total 148.75
Contractor's Overhead @15%
Rate per Sqm.
Sub-Total 309.00
Rate per Rm.
a) Shisam wood work for doors and windows chaukhat - One cum.
Labour Material and Equipment
Category MD Rate Amount Type Unit Quantity Rate
Skilled labour 34.00 750.00 25500.00 Shisam wood Cum 1.100 151876.00
Unskilled Labour 3.40 530.00 1802.00 Hold fast Nos. 92.000 29.70
Screw nail Nos 184.000 1.30
Sub-Total 27302.00
Rate per Cum
b) 38mm Thick sal wood frame for panelld shutter size 1.08*1.982=2.114sqm. - One sqm.
Labour Material and Equipment
Category MD Rate Amount Type Unit Quantity Rate
Skilled labour 4.73 750.00 3547.78 Sal wood Cum 0.040 162472.00
Unskilled Labour 0.47 530.00 250.71 100mm hings Nos. 2.838 35.12
150mm t/b stl (chheskinee) Nos. 0.473 124.30
300mm t/b stl (Chhiskinee) Nos. 0.473 332.22
250mm lc.set stl Nos. 0.473 474.60
Handle 6" stl Nos. 0.946 47.46
Screw nail Nos 23.652 1.30
Sub-Total 3798.49
Rate per Sqm.
b) 38mm thick shisam wood frame for panelld shutter size 1.08*1.982=2.114sqm.-Onesqm.
Labour Material and Equipment
Category MD Rate Amount Type Unit Quantity Rate
Skilled labour 4.73 750.00 3547.78 Shisam wood Cum 0.040 151876.00
Unskilled Labour 0.47 530.00 250.71 100mm hings Nos. 2.838 35.12
55
56
Rate Analysis
150mm t/b stl (Chhiskinee) Nos. 0.473 124.30
300mm t/b stl Chhiskinee) Nos. 0.473 332.22
250mm lc.set stl Nos. 0.473 474.60
Handle 6" stl Nos. 0.946 47.46
Screw nail Nos 23.652 1.30
Sub-Total 3798.49
Rate per Sqm.
b) 50mm thick PCC (1:2:4) flooring work with neat cement finishing. - One sqm. G.Norms-11-1-ga
Labour Material and Equipment
Category MD Rate Amount Type Unit Quantity Rate
Skilled labour 0.13 750.00 93.75 Cement Kg 17.000 16.03
Unskilled Labour 0.25 530.00 132.50 sand Cum 0.023 838.36
Natural Agg.-20mm Cum 0.046 2661.89
Sub-Total 226.25
Rate per Cum
56
57
Rate Analysis
Ready made enamel paint painting work - One sqm.
a) One coat in old surface excluding primer coat. G.Norms-13-5-ka, kha & ga.
Labour Material and Equipment
Category MD Rate Amount Type Unit Quantity Rate
Skilled labour 0.05 750.00 37.50 Enamel paint Lit. 0.090 579.97
Unskilled Labour 0.02 530.00 10.60
Sub-Total 48.10
Rate per sqm.
Two Coat aluminium paint over primer coat - One sqm. G.Norms-13-6
Labour Material and Equipment
Category MD Rate Amount Type Unit Quantity Rate
Skilled labour 0.108 750.00 80.63 Metal primer Lit. 0.081 365.27
Unskilled Labour 0.108 530.00 56.98 Alumin.paint Lit. 0.108 591.27
Sand paper Nos 0.040 6.92
Sub-Total 137.60
Rate per sqm.
2-42. Sand filling with water & compaction by labour -One cum G-Norms-11
Labour Material and Equipment
Category MD Rate Amount Type Unit Quantity Rate
57
58
Rate Analysis
Unskilled Labour 0.65 530.00 344.50 Sand Cum 1.10 838.36
Sub-Total 344.50
Total of Labour and Material
Contractor's Overhead @15%
Rate per Cum
b) 38mm Thick sal wood frame for G.I. plane Sheet shutter size 1.092x2.058=2.245sqm. - Onesqm.
Labour Material and Equipment
Category MD Rate Amount Type Unit Quantity Rate
Skilled labour 3.12 750.00 2338.53 Sal wood Cum 0.015 162472.00
Unskilled Labour 0.31 530.00 165.26 100mm hings Nos. 1.336 35.12
150mm t/b stl (chheskinee) Nos. 0.891 124.30
Mortis lock Nos. 0.445 332.22
G.I. plane sheet Sqm 2.071 433.49
Handle 6" stl Nos. 0.445 47.46
Screw nail Nos 22.272 1.30
Sub-Total 2503.79
Rate per Sqm.
C) 38mm Shisam wood frame for G.I. plane Sheet shutter size 1.092x2.058=2.245sqm. - Onesqm.
Labour Material and Equipment
Category MD Rate Amount Type Unit Quantity Rate
Skilled labour 3.12 750.00 2338.53 Shisam wood Cum 0.015 0.00
Unskilled Labour 0.31 530.00 165.26 100mm hings Nos. 1.336 35.12
150mm t/b stl (chheskinee) Nos. 0.891 124.30
Mortis lock Nos. 0.445 332.22
G.I. plane sheet Sqm 2.071 433.49
Handle 6" stl Nos. 0.445 47.46
Screw nail Nos 22.272 1.30
Sub-Total 2503.79
Rate per Sqm.
58
59
Rate Analysis
b) 38mm Thick sal wood frame for 19mm thick water proof Plywood shutter size 1.092x2.058=2.245sqm. - Onesqm.
Labour Material and Equipment
Category MD Rate Amount Type Unit Quantity Rate
Skilled labour 3.12 750.00 2338.53 Sal wood Cum 0.015 162472.00
Unskilled Labour 0.31 530.00 165.26 100mm hings Nos. 1.336 35.12
150mm t/b stl (chheskinee) Nos. 0.891 124.30
Mortis lock Nos. 0.445 332.22
19mm thick Water proof
Plywood Sqm 2.071 0.00
Handle 6" stl Nos. 0.445 47.46
Screw nail Nos 22.272 1.30
Sub-Total 2503.79
Rate per Sqm.
b) 38mm sisham wood frame for 12mm thick water proof Plywood shutter 1.092x2.058=2.245sqm. - Onesqm.
Labour Material and Equipment
Category MD Rate Amount Type Unit Quantity Rate
Skilled labour 3.12 750.00 2338.53 sishim wood Cum 0.015 0.00
Unskilled Labour 0.31 530.00 165.26 100mm hings Nos. 1.336 35.12
150mm t/b stl (chheskinee) Nos. 0.891 124.30
Mortis lock Nos. 0.445 332.22
19mm thick Water proof
Plywood Sqm 2.071 0.00
Handle 6" stl Nos. 0.445 47.46
Screw nail Nos 22.272 1.30
Sub-Total 2503.79
Rate per Sqm.
For Road
Rate Analysis
Soft Soil Excavating and loading by Excavator -One cum
Labour Material and Equipment
Category MD Rate Amount Type Unit Quantity Rate
Hudraulic Excavator
UP to 0.63 m3
Skilled labour 750.00 Capacity Hour 0.0116 1800.00
Unskilled Labour 0.25 530.00 132.50 Fuel (Diesel) Lit. 0.1160 87.89
Sub-Total 132.50
Total of Labour and Material
Quality Control @2% (Norms-Page viii)
Total
Contractor's Overhead @15%
Rate per Cum
59
60
Rate Analysis
Quality Control @2% (Norms-Page viii)
Total
Contractor's Overhead @15%
Rate per Cum
Description of works: Providing, laying, spreading, watering, levelling and compaction of natural sand gra
Spec. cl. No: 1201 specification lead upto 10m.
Labour (A) Material (B)
Norms No.
Type Unit Qty. Rate Amount Type Unit
12.01 Skilled md 0.0050 750.00 3.75 Subbase agg. cu.m.
Unskilled md 0.0400 530.00 21.20 Diesel lit
Description of works: Providing, laying, spreading, watering, levelling and compaction of crusher run mat
(a) Machine works
Spec. cl. No: 1202
Labour (A) Material (B)
Norms No.
Type Unit Qty. Rate Amount Type Unit
12.07 Skilled md 0.0050 750.00 3.75 Base aggregate cu.m.
Unskilled md 0.0200 530.00 10.60 Diesel lit
Description of works: Providing and spraying bituminous prime coat of bitumen penetration grade 80/100
broom etc. before applying prime coat, using manual methods.
Spec. cl. No: 1301,1302
Labour (A) Material (B)
Norms No.
Type Unit Qty. Rate Amount Type Unit
Description of works: Providing and spraying bituminous tack coat of bitumen penetration grade 80/100 in
etc. before applying tack coat, using manual methods.
Spec. cl. No: 1301,1302
Labour (A) Material (B)
Norms No.
Type Unit Qty. Rate Amount Type Unit
13.02 Bitumen Penetration
Skilled md 0.0030 750.00 2.25 lit.
grade 80/100
Unskilled md 0.0460 530.00 24.38 kerosene lit
Sub total of A = 26.63 Sub tota
Sub total of A +B + C = #VALUE! Contractor's overhea
60
61
Rate Analysis
Norms No.
Type Unit Qty. Rate Amount Type Unit
13.09 Bitumen Penetration
Skilled md 0.45 750.00 337.50 lit
grade 80/100
Unskilled md 4.50 530.00 2385.00 Kerosene lit
Aggregates m3
Sub total of A = 2722.50 Sub tota
Sub total of A +B + C = #VALUE! Contractor's overhea
Description of works: Preparation of sub-grade for rehabilitation or other similar works (filling or cutting de
Spec. cl. No: 1003
Labour (A) Material (B)
Norms No.
Type Unit Qty. Rate Amount Type Unit
10.05.a Unskilled md 0.05 530.00 26.50
Sub total of A = 26.50 Sub tota
Sub total of A +B + C = 27.30 Contractor's overhea
Community rate
Description of works: Providing and mixing and laying asphalt concrete with compaction
Spec. cl. No: 1307,1308
Labour (A) Material (B)
Norms No.
Type Unit Qty. Rate Amount Type Unit
13.10 Bitumen Penetration
Skilled md 0.03 750.00 22.50 lit
grade 80/100
Unskilled md 0.13 530.00 68.90 Cement Ton
Foreman md 0.01 530.00 5.30 Diesel litre
Aggregates m3
61
62
Rate Analysis
Norms-1-2ka-A3
Material and Equipment
Amount
0.37
0.37
12.56
14.44
14.44
Norms-B1-2-1
Material and Equipment
Amount
11.13
11.13
382.13
439.45
439.45
Norms-B1-2-2
Material and Equipment
Amount
12.72
12.72
436.72
436.72
29.34
11.43
40.77
40.77
40.77
6.12
46.89
62
63
Rate Analysis
2-25-Kha
Material and Equipment
Amount
317.94
317.94
450.44
67.57
518.01
2-42- B3
Material and Equipment
Amount
954.98
954.98
1325.98
1325.98
63
64
Rate Analysis
Norms 6-5-C-10
Material and Equipment
Amount
852.34
170.47
1022.81
1817.81
2090.48
2090.48
Norms-H-15-11-15 ka
Material and Equipment
Amount
571.62
61.64
633.26
723.76
108.56
832.32
1329.64
Norms-6-ka-1-2
Material and Equipment
Amount
2548.77
390.67
937.57
3877.01
7652.01
8799.81
8799.81
34.98
9566.58
11857.58
11857.58
64
65
Rate Analysis
34.98
9493.98
11784.98
1767.75
13552.73
34.98
9039.13
11330.13
1699.52
13029.65
46.11
9513.80
12175.80
1826.37
14002.17
34.98
9039.13
11330.13
11330.13
65
66
Rate Analysis
Norms 7-2-Ga
Material and Equipment
Amount
3526.60
408.04
0.00
1940.50
716.49
6591.63
9461.63
9461.63
Norms 7-2-Gha.
Material and Equipment
Amount
5129.60
386.33
1296.92
656.78
436.48
7906.11
10776.11
12392.53
12392.53
12216.11
Norms 7-4-Kha.
Material and Equipment
Amount
6412.00
368.97
1701.67
1150.72
9633.36
13943.36
13943.36
Norms 7-2-Ga.
66
67
Rate Analysis
Material and Equipment
Amount
3526.60
408.04
2209.96
832.94
6977.54
9847.54
1477.13
11324.67
67
68
Rate Analysis
Norms D1.7-2-gha.
Material and Equipment
Amount
5129.60
386.33
1767.97
763.53
381.76
8047.43
10917.43
10917.43
Norms D1.7-4-Kha.
Material and Equipment
Amount
5129.60
386.33
1767.97
763.53
381.76
8047.43
12357.43
12357.43
68
69
Rate Analysis
Norms 7-4-Kha.
Material and Equipment
Amount
6412.00
368.97
1978.23
1006.47
9765.67
14075.67
14075.67
Norms 7-4-Kha.
Material and Equipment
Amount
3206.00
408.04
1940.50
952.32
263.67
0.00
600.00
25.00
7395.53
9625.53
1443.83
11069.36
Norms 7-4-Kha.
Material and Equipment
Amount
5129.60
386.33
1552.40
872.96
436.48
263.67
0.00
600.00
25.00
9266.44
11496.44
1724.47
13220.91
Norms 7-4-Kha.
Material and Equipment
Amount
6412.00
368.97
1701.67
69
70
Rate Analysis
1150.72
263.67
0.00
600.00
25.00
10522.03
12752.03
1912.80
14664.83
Norms 7-4-Kha.
Material and Equipment
Amount
3526.60
408.04
2209.96
832.94
263.67
0.00
600.00
25.00
7866.21
10096.21
1514.43
11610.64
Norms 7-4-Kha.
Material and Equipment
Amount
5129.60
386.33
1767.97
763.53
381.76
263.67
0.00
600.00
25.00
9317.86
11547.86
1732.18
13280.04
Norms 7-4-Kha.
Material and Equipment
Amount
6412.00
368.97
1978.23
1006.47
263.67
0.00
600.00
70
71
Rate Analysis
25.00
10654.34
12884.34
1932.65
14816.99
Norms 12 -4 -Ka.
Material and Equipment
Amount
153.89
16.93
170.82
376.52
56.48
433.00
Norms 12 -4-Kha.
Material and Equipment
Amount
129.84
19.10
148.94
354.64
354.64
Norms 12 -1-Gha.
Material and Equipment
Amount
100.19
11.11
111.30
286.10
42.92
329.02
Norms 14-2-kha
Material and Equipment
Amount
65.40
4.95
70.35
71
72
Rate Analysis
219.55
252.48
252.48
Norms 14-1-kha
Material and Equipment
Amount
33.66
2.52
36.18
178.53
178.53
Norms 14-8
Material and Equipment
Amount
83.04
83.04
211.04
31.66
242.70
Norms 8 -3-Ka.
Material and Equipment
Amount
49.44
4.59
-12.36
41.67
620.74
713.85
713.85
51-Kha
Material and Equipment
Amount
181.20
27.56
203.43
-50.86
361.33
604.51
90.68
695.19
51-Kha
Material and Equipment
Amount
72
73
Rate Analysis
0.00
27.56
49.44
-12.36
64.64
682.64
682.64
8.-4
Material and Equipment
Amount
216.64
27.56
169.52
4.67
-43.55
374.84
787.09
118.06
905.16
Norms 7-5
Material and Equipment
Amount
92.64
1.12
93.76
109.12
109.12
Norms 7-5
Material and Equipment
Amount
86.34
1.12
87.46
102.82
15.42
118.24
Norms 7-5
Material and Equipment
Amount
85.29
1.12
86.41
101.77
15.27
73
74
Rate Analysis
117.04
Norms 7-5
Material and Equipment
Amount
85.29
1.12
86.41
101.77
15.27
117.04
Norms 10-1.
Material and Equipment
Amount
178704.02
1993.33
232.26
180929.61
208231.61
31234.74
239466.35
Norms10-1.
Material and Equipment
Amount
167049.41
1993.33
232.26
169275.00
196577.00
29486.55
226063.55
Norms10-2
Material and Equipment
Amount
13646.49
186.50
110.00
294.00
420.00
640.00
50.00
15346.99
23376.99
3506.55
26883.54
12716.91
Norms10-2
Material and Equipment
Amount
74
75
Rate Analysis
12756.50
186.50
110.00
294.00
420.00
640.00
50.00
14457.00
22487.00
3373.05
25860.05
12232.76
Norms10-4
Material and Equipment
Amount
7960.45
147.33
922.54
212.00
380.00
50.00
9672.32
16899.32
16899.32
7994.00
Norms10-9
de 26Gauge plain sheet for - One Sqm (Size -
14680.47
6539.18
75
76
Rate Analysis
190.00
50.00
420.00
8692.88
14313.88
14313.88
6375.89
76
77
Rate Analysis
Norms10-10
Material and Equipment
Amount
4223.91
93.25
963.08
220.00
2521.56
380.00
50.00
184.00
8635.80
12650.80
12650.80
5635.10
Norms 10-11-Kha.
Material and Equipment
Amount
904.07
48.60
3.00
955.67
1003.85
1003.85
Norms 13-5
Material and Equipment
Amount
29.42
82.12
111.54
243.94
36.59
280.53
Norms 13-6
Material and Equipment
Amount
26.18
56.30
0.02
82.50
220.11
220.11
77
78
Rate Analysis
34.06
98.06
14.71
112.77
Norms 13-4 Ka
Material and Equipment
Amount
21.07
21.07
42.83
6.42
49.25
Norms 13-3 Ga
Material and Equipment
Amount
12.25
12.25
35.29
35.29
Norms 13-5Ka,Kha,Ga
Material and Equipment
Amount
31.04
39.72
70.76
203.16
30.47
233.63
Norms 11-1Kha
Material and Equipment
Amount
208.39
15.63
124.94
348.96
548.71
82.31
631.02
G.Norms-11-1-ga
Material and Equipment
Amount
272.51
78
79
Rate Analysis
19.97
156.4
448.88
675.13
675.13
Norms 11-20
Material and Equipment
Amount
53.86
2.00
55.86
183.86
183.86
44.13
452.15
48.60
3.00
503.75
551.93
551.93
Norms 19-2
Material and Equipment
Amount
33.71
33.71
1157.31
173.60
1330.90
Norms 19-3
Material and Equipment
Amount
174.90
174.90
6004.90
900.73
6905.63
Norms 19-4
Material and Equipment
Amount
63.60
63.60
2183.60
79
80
Rate Analysis
327.54
2511.14
Norms L5-19-4
Material and Equipment
Amount
1.72
1.72
58.96
58.96
Norms L5-19-4
Material and Equipment
Amount
2.54
2.54
87.34
87.34
49.68
cemet mortar base in perfect line and level all complete . Per sqm
Amount
208.39
17.68
722.00
948.07
2161.57
2161.57
Norms-1201
Material and Equipment
Amount
1111.25
0.00
0.00
1111.25
1671.50
80
81
Rate Analysis
1671.50
Norms-46
Material and Equipment
Amount
954.98
9.17
964.15
1494.15
1494.15
Norms-47
Material and Equipment
Amount
3370.25
12.02
90.23
3472.50
3540.50
53.11
3593.61
Norms-47
Material and Equipment
Amount
5236.85
12.02
90.23
5339.10
5407.10
811.07
6218.17
Norms-47
Material and Equipment
Amount
6896.05
32.06
180.46
7108.57
7252.07
1087.81
8339.88
Norms-47
Material and Equipment
Amount
11510.70
72.14
270.69
11853.53
12231.03
1834.65
14065.68
G.Norms-11-7
81
82
Rate Analysis
Amount
757.76
89.77
13.2
11.37
872.10
2085.60
208.56
2294.16
G.Norms-11-7
524.17
524.17
578.86
727.61
82
83
Rate Analysis
969.54
739.92
888.67
133.30
1021.97
54.63
54.63
1147.13
1147.13
458.85
Material
Amount
77.25
77.25
1622.25
1622.25
648.90
Material
Amount
99.88
99.88
2097.38
2097.38
838.95
screen,sand trap,fitting head and packing with coarse sand around the well
Material
Amount
83
84
Rate Analysis
57.4425
281.701
239.25
578.39
943.39
141.51
1084.90
Norms-05
272.95
Norms-05
382.13
545.90
20.88
0.00
20.88
153.38
0.00
153.38
153.38
DoR 2.12-(2-25Kha)
84
85
Rate Analysis
Material and Equipment
Amount
7.95
7.95
272.95
272.95
Norms-49
Material and Equipment
Amount
974.42
974.42
1504.42
1504.42
Norms-49
Material and Equipment
Amount
974.42
209.59
1184.01
1846.51
1846.51
Norms-10
Material and Equipment
Amount
11.93
9.35
12.06
7.33
33.34
430.84
8.62
439.46
430.84
Norms-10
Material and Equipment
Amount
11.93
11.93
409.43
409.43
85
86
Rate Analysis
298.92
431.42
431.42
DoR-12-4-Kha
Material and Equipment
Amount
0.00
18.44
18.44
224.14
224.14
Norms-37-B-b
Material and Equipment
Amount
0.00
11.57
11.57
192.32
192.32
Norms-37-B-c
Material and Equipment
Amount
0.00
12.24
12.24
193.74
86
87
Rate Analysis
193.74
615.00
0.00
43.60
353.20
-88.30
308.50
495.00
495.00
Norms-40
Material and Equipment
Amount
104.71
1.27
105.98
114.94
114.94
Norms-40
Material and Equipment
Amount
102.33
1.27
103.60
112.56
112.56
Norms-40
Material and Equipment
Amount
99.96
1.27
101.23
110.19
87
88
Rate Analysis
110.19
Norms-40
Material and Equipment
Amount
99.96
1.27
101.23
110.19
110.19
Norms-6a
Material and Equipment
Amount
0.79
0.79
27.30
27.30
Norms-6a
Material and Equipment
Amount
1.59
1.59
54.59
54.59
Norms-26a
Material and Equipment
Amount
0.00
0.00
0.00
32.61
0.00
0.00
79.60
112.21
137.16
137.16
137.16
Norms-26b
Material and Equipment
Amount
1062.47
88
89
Rate Analysis
0.00
32.61
6.42
49.50
79.60
1230.60
1255.55
25.11
1280.66
1280.66
Norms-26c
Material and Equipment
Amount
1062.47
0.00
32.61
6.42
49.50
79.60
1230.60
1255.55
25.11
1280.66
1280.66
Norms-26a
Material and Equipment
Amount
1062.47
0.00
0.00
1062.47
1622.72
1622.72
Norms-26b
Material and Equipment
Amount
1062.47
0.00
0.00
1062.47
1622.72
1622.72
Norms-26c
Material and Equipment
Amount
89
90
Rate Analysis
1062.47
0.00
0.00
1062.47
1622.72
1622.72
Norms-15c
Material and Equipment
Amount
3.18
3.18
109.18
109.18
Norms-27c
Material and Equipment
Amount
0.00
0.00
0.00
0.00
63.32
8.25
71.57
1398.57
1398.57
Norms-DoR12.01
Material and Equipment
Amount
0.00
0.00
0.00
0.00
0.00
0.00
0.00
0.00
24.95
0.00
24.95
24.95
Norms-DOR
Material and Equipment
Amount
90
91
Rate Analysis
0.00
0.00
0.00
0.00
Norms-38-B
5369.70
Norms-41-B
2586.70
DOR-15-24
Material and Equipment
Amount
245.98
72.00
225.40
5.50
1407.00
65.80
2021.68
2134.18
2134.18
DOR-15-24
Material and Equipment
Amount
421.68
108.00
91
92
Rate Analysis
225.40
5.50
1407.00
112.80
2280.38
2430.38
2430.38
DOR-15-20+
Material and Equipment
Amount
1160.32
70.00
48.10
187.06
26.03
1491.51
1571.01
1571.01
157.10
87.28
sing westage
e bitumen +0.50 liter additional
DOR-15-20+
Material and Equipment
Amount
515.86
30.00
19.50
85.54
9.05
659.95
739.45
739.45
73.95
59.160
using westage
ade bitumen +0.25 liter additional
DOR-15-20+
Material and Equipment
Amount
425.90
157.20
92.16
675.26
807.76
807.76
80.78
2.524
92
93
Rate Analysis
es (Roller input 0.07 hour as per Norms 15(20)
sses
45=.131 hour
per cum
DOR-15-20+
Material and Equipment
Amount
319.43
157.20
92.16
568.79
701.29
701.29
70.13
2.922
es (Roller input 0.07 hour as per Norms 15(20)
sses
45=.131 hour
per cum
GI Wire Hexagonal Mesh 100x120 Including rolling, cutting, weaving, assembling, placing in position
44-1-Bii/44-2-i/45
Material and Equipment
Amount
2548.25
261.02
102.25
1948.84
4860.36
6551.56
982.73
7534.29
44-1-Bii/44-2-i/45
Material and Equipment
Amount
3706.54
365.43
139.92
2923.26
7135.15
93
94
Rate Analysis
9647.45
9647.45
44-1-Bii/44-2-i/45
Material and Equipment
Amount
1736.90
221.87
75.34
974.42
3008.53
3939.53
3939.53
44-1-Bii/44-2-i/45
Material and Equipment
Amount
2548.25
313.23
102.25
1461.63
4425.36
5805.31
5805.31
44-1-Bii/44-2-i/45+Interpolation
Material and Equipment
Amount
2293.42
280.60
89.33
1461.63
4124.98
5494.33
824.15
6318.48
44-1-Bii/44-2-i/45
Material and Equipment
94
95
Rate Analysis
Amount
2084.93
292.56
96.87
876.98
3351.34
4284.09
4284.09
44-1-Bii/44-2-i/45
Material and Equipment
Amount
2293.42
280.60
89.33
584.65
3248.00
3876.60
3876.60
Norms-46
Material and Equipment
Amount
922.19
9.17
931.36
1461.36
1461.36
Norms-2-1-1.5-c
Material and Equipment
Amount
44.52
44.52
1528.52
1528.52
G.Norms-11-(20)
Material and Equipment
Amount
85.28
0
0
95
96
Rate Analysis
85.28
213.28
552.32
552.32
549.08
858.08
G. Norms-10-1
Material and Equipment
Amount
167063.60
2732.40
239.20
170035.20
197337.20
G. Norms-10-2
Material and Equipment
Amount
6455.84
99.68
58.80
157.15
224.50
44.90
30.75
7071.62
10870.11
G.Norms-10-2
Material and Equipment
Amount
6034.81
99.68
96
97
Rate Analysis
58.80
157.15
224.50
44.90
30.75
6650.59
10449.08
G.Norms-18-9
G.Norms-11-1-ga
Material and Equipment
Amount
272.51
19.28
122.45
414.24
640.49
G.Norms-13-4-ka&kha
Material and Equipment
Amount
23.81
0
23.81
45.57
Material and Equipment
Amount
38.50
0
38.50
102.50
148.07
97
98
Rate Analysis
G.Norms-13-6
Material and Equipment
Amount
29.59
63.62
0.28
93.49
231.09
10.73
206.73
206.73
G-Norms-12 -1 (ga)
Material and Equipment
Amount
0.00
12.24
12.24
208.24
208.24
98
99
Rate Analysis
922.1927
922.1927
1266.69
1266.69
G.Norms-11-7
G.Norms-11-7
G. Norms-10-2
Material and Equipment
Amount
2504.02
46.93
110.73
147.98
897.86
21.14
28.95
3757.61
6261.40
G. Norms-10-2
Material and Equipment
Amount
0.00
46.93
110.73
147.98
897.86
21.14
28.95
1253.59
3757.38
99
100
Rate Analysis
G. Norms-10-2
Material and Equipment
Amount
2504.02
46.93
110.73
147.98
0.00
21.14
28.95
2859.75
5363.54
G. Norms-10-2
Material and Equipment
Amount
0.00
46.93
110.73
147.98
0.00
21.14
28.95
355.73
2859.52
Rate Analysis
Material and Equipment
Amount
20.88
10.20
31.08
163.58
0.00
163.58
24.54
188.11
100
101
Rate Analysis
544.55
81.68
626.23
0
aying, spreading, watering, levelling and compaction of natural sand gravel subbase grading as per table 12.1 of standard
n lead upto 10m.
Material (B)
Qty.
1.2800
0.7900
Sub total of B =
Contractor's overhead expenses 15% =
aying, spreading, watering, levelling and compaction of crusher run materials for base course lead upto 10m.
e works
Material (B)
Qty.
1.200
0.990
Sub total of B =
Contractor's overhead expenses 15% =
nd spraying bituminous prime coat of bitumen penetration grade 80/100 including cleaning the road surface using wire, brushes,
before applying prime coat, using manual methods.
Material (B)
Qty.
1.0500
0.1000
Sub total of B =
Contractor's overhead expenses 15% =
nd spraying bituminous tack coat of bitumen penetration grade 80/100 including cleaning the road surface using wire, brushes, broo
applying tack coat, using manual methods.
Material (B)
Qty.
1.0500
0.1000
Sub total of B =
Contractor's overhead expenses 15% =
Material (B)
101
102
Rate Analysis
Qty.
77.00
7.70
1.20
Sub total of B =
Contractor's overhead expenses 15% =
Material (B)
Qty.
6.6000
0.1000
0.8100
0.1200
Sub total of B =
Contractor's overhead expenses 15% =
of sub-grade for rehabilitation or other similar works (filling or cutting depth of 10 to 20 cm) in common soil.
Material (B)
Qty.
Sub total of B =
Contractor's overhead expenses 15% =
Community rate
Material (B)
Qty.
117.00
0.022
10.45
1.20
Sub total of B =
Contractor's overhead expenses 15% =
102
103
103
104
1.6
104
105
105
106
106
107
107
108
108
109
20.88
10.19524
109
110
#VALUE!
#VALUE!
#VALUE!
compaction of natural sand gravel subbase grading as per table 12.1 of standard Unit : 1
m3
Material (B) Equipment (C)
Amount Type Unit Qty. Rate Amount
#VALUE! Grader hr 0.022 1600.00 35.20
#VALUE! Vibrator Rolller hr 0.022 475.00 10.45
Water bowser hr 0.038 550.00 20.90
Loader hr 0.011 1000.00 11.00
#VALUE! Sub total of C = 77.55
Contractor's overhead expenses 15% = #VALUE! Unit Rate = #VALUE!
compaction of crusher run materials for base course lead upto 10m. Unit : 1
m3
Material (B) Equipment (C)
Amount Type Unit Qty. Rate Amount
#VALUE! Grader hr 0.033 1600.00 52.80
#VALUE! Vibrator Rolller hr 0.033 475.00 15.68
Water Bowser hr 0.033 550.00 18.15
Loader hr 0.011 1000.00 11.00
#VALUE! Sub total of C = 97.63
Contractor's overhead expenses 15% = #VALUE! Unit Rate = #VALUE!
men penetration grade 80/100 including cleaning the road surface using wire, brushes, Unit : 1
methods. lit.
Material (B) Equipment (C)
Amount Type Unit Qty. Rate Amount
en penetration grade 80/100 including cleaning the road surface using wire, brushes, broom Unit : 1
s. lit.
Material (B) Equipment (C)
Amount Type Unit Qty. Rate Amount
#VALUE! Boiler hr 0.0140 180.00 2.52
#VALUE! Hand Sprayer hr 0.0140 160.00 2.24
#VALUE! Sub total of C = 4.76
Contractor's overhead expenses 15% = #VALUE! Unit Rate = #VALUE!
arpet. Unit : 1
m3
Material (B) Equipment (C)
110
111
Unit : 10
m2.
Material (B) Equipment (C)
Amount Type Unit Qty. Rate Amount
#VALUE! Boiler hr 0.040 180.00 7.20
#VALUE! Roller hr 0.040 500.00 20.00
#VALUE! Sprayer hr 0.010 160.00 1.60
#VALUE!
#VALUE! Sub total of C = 28.80
Contractor's overhead expenses 15% = #VALUE! Rate (10m2) = #VALUE!
Unit Rate(1 m2) = #VALUE!
h compaction Unit : 1
m3
Material (B) Equipment (C)
Amount Type Unit Qty. Rate Amount
Asphalt mixing
#VALUE! hr 0.044 1000.00 44.00
plant
#VALUE! Wheel loader hr 0.66 1000.00 660.00
#VALUE! Asphalt Paver hr 0.22 1400.00 308.00
#VALUE! Steel Tyre roller hr 0.55 500 275.00
Pneumatic Roller hr 0.55 1000.00 550.00
Tipper Truck hr 0.32 450.00 144.00
#VALUE! Sub total of C = 1981.00
Contractor's overhead expenses 15% = #VALUE! Unit Rate = #VALUE!
111
Summary of Unit Rates
112
154.81
265.55
331.09
113
SHREE KARNALI SECONDARY SCHOOL
TIKAPUR MUNICIPALITY
SUDURPASHCHIM PROVINCE
Detail Estimate
Plinth Beam
Grid A-A,B-B 3 11.30 0.35 0.15 1.78
Grid 1-1,2-2,3-3,4-4 6 4.15 0.35 0.15 1.31
Sill Band
Grid A-A,B-B 2 11.30 0.23 0.10 0.52
Grid 1-1,3-3,4-4 3 4.15 0.23 0.10 0.29
Lintle Band
Grid A-A,B-B 2 11.30 0.23 0.10 0.52
Grid 1-1,3-3,4-4 3 4.15 0.23 0.10 0.29
top of wall
Grid A-A,B-B 2 11.30 0.23 0.08 0.42
Grid 1-1,3-3,4-4 3 4.15 0.23 0.08 0.23
Deduction
Door -1 1.07 0.23 0.10 -0.02
Door -1 0.90 0.23 0.10 -0.02
Sub Total 5.30 cum
Used mild steel bar supply including material and labour
7 required for cutting plasing binding all complite work.
For Column
12mm dia vertical bar for column 8 5.05 0.89 35.91
For Beam
12mm dia Throuh out for Grid Grid A-A,B-B 8.0 11.90 0.89 84.62
12mm dia bar Through for Grid Grid 1-1,2-2,3-3,4-4 16 5.45 0.89 77.51
8mm dia strioups 150mm c/c 280 0.90 0.39 98.28
Sill Band
Grid A-A,B-B 4.0 11.30 0.89 40.23
Grid 1-1,3-3,4-4 4.0 4.85 0.89 17.27
Lintle Band
Grid A-A,B-B 4.0 11.30 0.89 40.23
Grid 1-1,3-3,4-4 4.0 4.85 0.89 17.27
Deduction
Door 2 1.07 0.89 1.90
Door 2 0.90 0.89 1.60
Sub Total 414.82 k.g
local wood formwork including materials, labour and
8 other incidentals required for construction, erection in `
level and position and removal form its position.
Tie Beam
Grid A-A,B-B 4 11.30 0.15 6.78
Grid 1-1,2-2,3-3,4-4 8 4.15 0.15 4.98
Sill Band
Grid A-A,B-B 6 11.30 0.10 6.78
Grid 1-1,3-3,4-4 6 4.15 0.10 2.49
Lintle Band
Grid A-A,B-B 4 11.30 0.10 4.52
Grid 1-1,3-3,4-4 6 4.15 0.10 2.49
top of wall
Grid A-A,B-B 4 11.30 0.08 3.62
Grid 1-1,3-3,4-4 6 4.15 0.08 1.99
Deduction
Door 2 1.07 0.10 0.21
Door 2 0.90 0.10 0.18
Sub Total 34.04 sqm
Supplying Placing Curing 1st class Cimni Brick
9 Masonary work 1:4 cement ratio
Below Plinth Level
1st Footing Grid A-A,B-B 2 11.55 0.45 0.45 4.68
1st Footing Grid 1-1,2-2,3-3,4-4 4 4.40 0.45 0.45 3.56
2nd Footing Grid A-A,B-B 2 11.30 0.35 0.60 4.75
2nd Footing Grid 1-1,2-2,3-3,4-4 4 4.15 0.35 0.60 3.49
Above Plinth Level
Grid B-B,C-C 2 9.90 0.23 2.75 12.52
Grid 1-1,3-3,4-4 3 4.15 0.23 2.75 7.87
Column 8 0.35 0.35 2.75 2.69
Chuli Wall
Column 3 0.35 0.35 0.75 0.28
Grid 1-1,4-4 2 4.85 0.23 0.38 0.84
Step 1 1 3.68 0.90 0.15 0.50
Step 2 1 3.68 0.60 0.15 0.33
Step 3 1 3.68 0.30 0.15 0.17
Deduction
Door(D1) -1 1.07 0.23 2.00 -0.49
Door(D2) -1 0.90 0.23 2.00 -0.41
Windows -6 1.50 0.23 1.20 -2.48
Sub Total 38.28 cum
12.5 mm thick Cement Plaster work in 1:4 Cement Ratio
10
Plain cement concrete for RCC work of grade M20 (1:1.5:3) used
Natural Aggregate including material and labour required for
6 mixing, placing in position, compacting, finishing, curing and all cum 5.299 14676.55 77769.72
other incidentals required to produce concrete of specified
strength.
Plain cement concrete for RCC work of grade M15 used Natural
Aggregate including material and labour required for mixing,
6 placing in position, compacting, finishing, curing and all other cum 5.30
incidentals required to produce concrete of specified strength.
F.Y
2080/081
#REF!
#REF!
#REF!
#REF!
Final Valuation Quantity & Cost
Running Bill
#REF!
#REF!
F.Y
2076/077