The document outlines the cost breakdown for construction work involving 16,000 cubic meters per month, detailing expenses such as machinery, diesel, cement, additives, and labor. The total cost per cubic meter is calculated to be Rs. 2098 without profit, incorporating various factors including management and overhead costs. The final cost reflects a comprehensive analysis of all necessary expenditures for the project.
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as DOCX, PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
16 views2 pages

Construction Cost Analysis

The document outlines the cost breakdown for construction work involving 16,000 cubic meters per month, detailing expenses such as machinery, diesel, cement, additives, and labor. The total cost per cubic meter is calculated to be Rs. 2098 without profit, incorporating various factors including management and overhead costs. The final cost reflects a comprehensive analysis of all necessary expenditures for the project.
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as DOCX, PDF, TXT or read online on Scribd
You are on page 1/ 2

Considering 16,000 Cubic Meters of work per month.

All Machinery including rent & Salaries - 50,00,000/-

OK

Diesel for all Machines - Rs.17,00,000/-

Diesel including Lubrication cost incurs = Rs 19,00,000/-

Additive - Rs.500/Cubic Meter

Ok

Cement bulk (JH) - 7.6/kg

Cement per cubic meter(Desity of the mix - 2.1) - 84 Kgs


Cement % consider only 4%, whereas need to consider 4.5% at least.

Cement per cubic meter - Rs 638.4 say Rs.638/-


Now cement cost is Rs 718.2

Machinery cost with diesel for 16,000 cubic meters - 418.75 say 420

Now the Machine cost with disel and Lubrication should be=435

Bed prepation etc - Rs.30/cubic meter

Bed preparation for cutting of trenching, scrapping of existing crust =60+150= Rs 210 Per cum

Cost of Labour , which is required during Construction of FDR works= Rs 35 Per cum

Machinery consumables - Rs.10/cubic meter

Holder and Pick cost should be Rs 30 per cum


Water cost should be added- approx. 700 lit water (Including curing) per cum is required

=700* 0.05= Rs 35 per Cum

Total of Machines, Cement, Additive, Bed preparation & Machine consumables

= Rs.1598/- Per cubic meter

Say Rs.1600/- per cubic meter

Total of Machines, Cement, Additive, Bed preparation & Machine consumables including water for
curing

= Rs.1963/- Per cubic meter

Adding Rs.100/- per cubic meter for our management team travelling and other expenses

Engineer, Supervisor, lab helper salary including his food cost needs to be added =Rs 50 Per Cum

Cost of Shifting of Equipment, Lab set up, Accommodation for Engineers and Labours, Lab
equipment, preparation of JMF, execution of Trial patch, Mob. & demob of Trail of equipment etc
need to be added= Rs 25 Per Cum
Two nos of Vehicle cost for travel of engineers & supervisor need to be added. = Rs 10 Per Cum

Adding Management team travel and other overhead= Rs 50

Grand Total for Back to back work - Rs.1700/- per cubic meter

Grand Total for Back to back work Without Profit – Rs2098/- per cubic meter