Fyp Draft
Fyp Draft
SUBMITTED BY
Abhidha Acharya (760201)
Anish Sainju (760203)
Anjan Gosai (760206)
Arjun Karki (760208)
In partial fulfillment for the award of the degree
OF
MARCH 2024
WATER SUPPLY PROJECT 2076 Batch
ABSTRACT
The final year project report intended concisely summarized the outcome of the project
and is the final document in the Sipadol drinking water supply project. The project report
is used to document success, lessons, learned, in order to improve the project, deliver for
the future. The main objective of the report is to analyze the different aspects of the
Sipadol drinking water supply project.
The project area lies in Suryabinayak Municipality, Bhaktapur Nepal. It lies in the
Southern part of Araniko Highway. The source of our project is ground water. The source
of water as per water quality test was compared to NDWQS (2079) is clear and safe for
drinking, with simple treatment for chloride. For this project, we have design population
of 1,345. For this project, we have used HDPE pipes of various diameters. We have used
overhead reservoir tank of 40m3. Water supply project is intermittent for pumping as well
as distribution. The length of transmission line is 520.330m and 90mm in diameter. It
connects the pipelines from source to our reservoir. The length of distribution line is
3559.806m and diameter varies from 20mm to 75mm.
With the help of the final year project work, we came to learn about teamwork, co-
ordination and working together to achieve a common goal.
WATER SUPPLY PROJECT 2076 Batch
ACKNOWLEDGEMENT
First of all, we must acknowledge our deep sense of gratitude to the Department of Civil
Engineering, Khwopa Engineering College for providing us the project and for the
encouragement for us to enroll the project.
We are very thankful to our supervisor Er. Razim Ganesh giving theoretical and practical
knowledge and also for guiding us during the project duration.
We would also like to express deepest gratitude to Er. Sujan Maka (Principal, Khwopa
Engineering College) and Er. Amit Shankar Ranjit (HOD, Department of Civil
Engineering) for their administrative and academic help.
Table of Contents
INTRODUCTION TO THE PROJECT
LIST OF ABBREVIATION
SALIENT FEATURES
1. INTRODUCTION
1.1 Background
1.2 Objective
1.3 Literature review
2. COMPONENTS OF PROJECT
2.1 Source of The Project
2.2 Technical Aspect
2.2.1 Existing Water Supply Project
2.2.2 Proposed Project
2.2.3 Coverage Population
2. METHODOLOGY
2.1 Selection of Source
2.2 Detailed Survey
2.3 Estimation of water demand
2.3.1 Domestic Demand
2.3.2 Institutional Demand
2.3.3 Public Tap
2.4 System of supply
2.4.1 Continuous Supply
2.4.2 Closed Supply
2.4.3 Gravity Supply
2.5 Reservoir Sizing
2.5.1 Storage Capacity of balancing reservoir
2.5.2 Supply
2.5.3 Demand
2.5.4 Surplus
2.5.5 Deficit
2.5.6 Volume of RVT
2.6 Hydraulic Design
WATER SUPPLY PROJECT 2076 Batch
3. TECHNICAL DEFINITION
3.1 Gravity Water Supply system
3.1.1 Open System
3.1.2 Closed System
3.1.3 Intermittent System
3.1.4 Continuous System
3.2 Intake
3.3 Overhead tank
3.4 Distribution Chamber
3.5 Collection Chamber
3.6 Storage Tank
3.7 Pipelines
3.8 Transmission main
3.9 Distribution main
3.10 Water Supply distribution system
3.11 Pipe networks
3.12 Layout of distribution work
3.12.1 Grid Iron System
3.12.2 Ring System
3.12.3 Radial System
3.12.4 Dead End System
3.13 Hydraulic Design of pipes
3.13.1 Flow Velocity
3.13.2 Static head
3.13.3 Residual head
3.13.4 HGL
3.14 Pipe losses
3.14.1 Losses in pipe
3.14.2 Friction losses in pipe
3.14.3 Calculating Head loss for a known pipe
3.14.4 Calculating flow for known head
3.14.5 Minor losses
3.15 Pipes
3.15.1 Cast Iron Pipes
3.15.2 Wrought Iron pipes
3.15.3 Steel pipes
3.15.4 Galvanized Iron Pipe
3.15.5 Concrete Pipe
3.15.6 Plastic Pipe
3.16 Valve
3.16.1 Sluice Valve
3.16.2 Reflux/Check Valve
3.16.3 Safety valves/ automatic cutoff valve
3.16.4 Air relief valve
3.16.5 Butterfly valve
3.16.6 Drained Valve
WATER SUPPLY PROJECT 2076 Batch
11. Drawings
WATER SUPPLY PROJECT 2076 Batch
SALIENT FEATURES
1. Name of Scheme: Sipadol Drinking Water Supply Project
2. Location: Sipadol
3. District: Bhaktapur
4. Municipality: Surya Binayak
5. Geographical features: Hilly Region
6. Terrain: Mild Slope
7. Climate: Moderate
8. Geology: Alluvial sandy soil
9. Type of water supply system: Gravity flow system
10. System of supply: Intermittent System
11. Type of source: Deep Boring
12. Depth of deep bore: 220m
13. Measured yield: 12 Lps
14. Pumping time: 7 hrs.
15. Distribution time: 5 hrs.
16. RVT: Overhead (1)
17. RVT size: 40 m3
18. Length of transmission line: 520.330m
19. Length of distribution line: 3559.806m
20. Tap stand: 1
21. No. of household served: 280
22. Present population: 1670
23. Design population: 1345
24. Population growth rate: 0.92% (census 2021)
25. Design period :20 yrs.
26. Total estimated cost:
27.
WATER SUPPLY PROJECT 2076 Batch
LIST OF ABBREVIATIONS
BCR : Benefit cost ratio
BPT : Break pressure tank
CC : Collection chamber
DFID : Department for international development
DC : Distribution chamber
DDC : District development committee
DWSP : Drinking water supply project
GI : Galvanized iron
HDPE : High density polyethylene pipe
HH : Household
HGL : Hydraulic grade line
IC : Interruption chamber
Lpcd : Liter per capita per day
Lpd : Liter per day
Lps : Liter per second
NGO : Non-government organization
O&M : Operation and maintenance
RCC : Reinforced concrete cement
RT : Reservoir tank
WSP : Water supply project
WATER SUPPLY PROJECT 2076 Batch
1. INTRODUCTION
1.1 Background
Water is a fundamental necessity for life, crucial for the survival and well-being of any
community. Access to clean and sufficient water is a basic human right in today's world.
It is the government's duty to ensure that all citizens have access to safe drinking water
that is easily obtainable, consistently available, and of high quality. In rural regions, water
supply systems are often managed by local communities, who actively participate in their
implementation. In contrast, urban areas rely on more advanced and carefully planned
water supply infrastructures, which are integral to maintaining a standard of living in
cities and towns.
Sipadol Planning is a low income housing planning situated at Suryabinayak
Municipality, east to Araniko Highway. Proposing planned distribution of water supply in
this region is more than a need, a corner stone for standard life of town dwellers.
1.2 Objectives
To be familiar with engineering aspects of the real project.
To get familiar with the community-based project.
To gain knowledge on the economic analysis of water supply project.
To design an urban water supply project by applying theoretical knowledge
we gain.
To get familiar with different components of urban water supply system.
To get familiar with the engineering aspects of the real project.
To gain knowledge on quantity estimation of water supply project.
To execute the acquired knowledge and skill of water system into a
practical approach.
To examine the sufficiency of water source to meet the demand and impact
of Sipadol Planning WSP due to increase demand.
For this project, we had gone through several previous reports, books, peoples and
help from our respected supervisor. Literature review was done from the starting to
the end of this project and the project would not have been completed on time without
the help of it. We visited some water supply projects that were currently running in
1
WATER SUPPLY PROJECT 2076 Batch
the nearby projected area. The project area also had a current water supply system that
was being designed due to which it was made easier for us to obtain log data about the
borehole. We carried out some reports of our seniors on the similar topic which helped
us for hydraulic design of the pipeline. We also studied guidelines for “Urban Water
Supply and Sanitation (Sector) Project” (UWSSP).
2
WATER SUPPLY PROJECT 2076 Batch
2. COMPONENTS OF PROJECT
2.1 Source of the project
The source of project is borehole which lies at the distance of 520.330m from
the distributed area. Discharge from the borehole is 12 lps.
3.2 Topography
The purposed source for the gravity water supply project is located in hilly region.
The source is located near the jungle and the soil type of the area is sandy alluvial
soil.
3
WATER SUPPLY PROJECT 2076 Batch
3.3 Climate
The project lies in the Kathmandu valley i.e.in the hilly belt of Nepal, it has
moderate temperature. The average daily temperature of area in summer is 27°C
and that in winter is 18°C
3.4 Occupation and Socio-economic Structure
People having various occupation resides in the projected area. The major ethnic
group in the area is Brahmin, Chhetri, Newar etc. Social group collectively
participates in different social works including marriages, worships etc. which
indicates that the beneficiary communities are capable of working in group.
3.5 Projected Population and household
The present population including school student has been obtained from the
survey work by counts and sample method. The domestic water demand is 120
liters per capita per day. Population growth rate of the project is 1% and the year
2024 has been taken as survey year and 2024 has been taken as base year from
which 20-year design period and population has been forecasted in accordance
with geometrical progression method.
P = Po * (1+ r)n
4
WATER SUPPLY PROJECT 2076 Batch
4.0 METHODOLOGY
We visited the project site for both source and planning area for performing
preliminary survey where we did map study of the site via google earth. The
reconnaissance survey was carried out where the index sketch of the topography
was drawn. We also gathered some information about the previous water supply
project that existed in that area with the locals and other personals. After that the
civil engineering survey was carried out for the determination of RL for the pipe
alignment and for the proposed structure through total station. The selection of the
structures, their numbers, sizing of balancing reservoir tank etc. were done as per
the numerical assessment following the necessary guidelines of DWSS.
5
WATER SUPPLY PROJECT 2076 Batch
4.5.2 Supply
The quantity of water entering the RVT from source in a given time period is
Supply.
4.5.3 Demand
The demand for water supply refers to the total amount of water needed or
desired by individuals, businesses, and other entities within a specific area
over a given period. This demand can be influenced by various factors,
including population growth, economic activities etc.
4.5.4 Surplus
The surplus of water supply refers to the amount of excess water pumped from
the source to the reservoir tank.
4.5.5 Deficit
The deficit of water supply refers to the insufficient amount of water in the
reservoir tank to provide to the general public.
6
WATER SUPPLY PROJECT 2076 Batch
7
WATER SUPPLY PROJECT 2076 Batch
8
WATER SUPPLY PROJECT 2076 Batch
In the continuous system water is available in the distribution lines all the time. The
system is adopted when there is sufficient discharge at the source. Water in the continuous
system is available whenever the faucet is opened. Since the water is continuous
available, it is more desirable, because service is available all the time. The distribution
line is always under pressure so the possibility of contamination by negative suction in
the pipeline does not exist.
Merits of continuous flow system over storage system include:
a) Supply of water does not run out
b) No requirement to store water
Demerits of continuous flow system:
a) Waste of water by irresponsible users
b) Difficulties in operation maintenance
5.2 Intake
An intake is a structure which continuous abstract the design flow from the source. It is
the first point in a water supply system and is them funneled into the pipe line i.e.
transmission main. The fundamental purpose if the intake works is to collect water from
one or several points and focus this flow at a single point the entrance to the pipeline. The
efficiency and functioning of the water supply scheme largely relies upon the nature,
location and construction of intake, hence requires a great care. Intake are the structures
which comprises of the opening, grating or strainer through which the crude water from
source like river, canal or reservoir enters and is conveyed to transmission main. Water
from the sump well is pumped through the rising mains to the treatment plants.
The intake is sit specific in designs. Several alternate designs are possible for the intake.
Further, special care should be taken while selecting the site for intake construction. Few
measures are: -
The intake should be built on the stable soil (i.e. resistance to erosion and
landslide)
Intake should be built at such site with no possibility of contamination of the
source.
Intake should be easily accessible for regular inspection, cleaning, operation and
maintenance.
Intake should be built at the section of maximum water from the discharge.
Intake should be built site specifically.
9
WATER SUPPLY PROJECT 2076 Batch
tanks are used for domestic water storage and commercial water storage purposes. They
are generally placed over the rooftop of any house, building or apartment. These tanks
circulate the water through its distributary channels or pipes to the taps.
5.4 Distribution chambers
Distribution chamber is provided to divide the flow. From the hydraulic point of view, it
provides an environment to distribute water with reasonable accuracy. Generally, these
chambers work satisfactory up to a flow of 2 to 3 lps. By use of DC, designed separate
average flows could be supplied to multiple branches heading towards decentralized
reservoirs. For more accurate distribution of flow, mouth piece and gate valves are used at
outlet of DC. DC saves the cost of pipe between the RVT and DC.
5.5 Collection chamber
The process of collection chamber areas to collect water from more than one water
sources, settle course materials and remove floating matter like leaves as well. Also in
case, if the intake could not be constructed at the safe place, collection downward system
components. Construction of CC with provision of minimum of 5m static head can avoid
backward if multiple sources are tapped. The outlet capacity (i.e. drainage capacity) of
CC must be equal to or greater than the maximum flow capacity of the pipe line between
intake and CC to avoid overflow from it. It should have provision for inlet, outlet, over-
flow and washout mechanics.
5.6 Storage tank
Storage tank is constructed to balance the variation of water demand in a day. Reservoirs
can be created by controlling a stream that drains an existing body of water. Thay can also
be constructed in river valleys using a dam. Alternately, a reservoir can be built by
excavating flat ground or constructing retaining wall. The reservoir tank serves to store
water that is provided by source during low demand periods, for use during high demand
period. In gravity flow water supply schemes, the reservoirs are usually constructed either
of stone masonry or RCC.
Reservoirs are provided to absorb hourly fluctuation in water demand. Reservoir is
necessary in system when,
Pipeline without reservoir cannot fulfil the peak demand of the tap.
Daily water demand is greater than safe yield of source during daylight hours.
Pipeline distance from the source to community is so far that it is more
economical to use smaller pipe size and built a reservoir tank.
5.7 Pipelines
The pipelines transfers water from the source to the service area. Pipe requires high
investment outlay and hence careful consideration is necessary for its design, the
alignment selection, size and material require almost caution. Proper selection of pipe
alignment route is essential to ensure that the pipeline is laid through stable terrain to
minimize disruption later and to ease the operation and maintenance works. After the
pipeline is laid, the protection work needs to be carried out against backfill material
getting wash away.
10
WATER SUPPLY PROJECT 2076 Batch
11
WATER SUPPLY PROJECT 2076 Batch
12
WATER SUPPLY PROJECT 2076 Batch
2. In the cases of a breakdown in some section, water is available from some all
branches.
Disadvantages:
1. Extract calculation of sizes of pipes is not possible due to provision of valves on
all branches.
5.12.2 Ring system
The supply main is laid all along the peripheral roads and sub mains branches out from
the mains. Thus, this system also follows the grid iron system with the flow pattern
similar in character to that of dead-end system. So, determination of the sizes of pipes is
easy.
Advantages:
1. Water can be supplied to any point from at least two directions.
5.12.3 Radial system
The area is divided into different zones. The water is pumped into the distribution
reservoir kept in the middle of each zone and the supply pipes are laid radially ending
towards the periphery.
Advantages:
1. It gives service.
2. Calculation of pipe sizes is easy.
5.12.4 Dead end system
It is suitable for old towns and cities having no definite pattern of roads.
Advantages:
1. Relatively cheap.
2. Determination of discharges and pressure easier due to a smaller number of
valves.
Disadvantages:
1. Due to many dead ends, stagnation of water occurs in pipes.
13
WATER SUPPLY PROJECT 2076 Batch
To destroy excess head, small sizes pipes are used, which however, increases the flow
velocity. At velocities greater than 3m/s air and water tend to mix affecting the flow and
head loss. Also, at high velocities when the faucets are suddenly closed the phenomenon
of water hammer may also occur.
Hence, the following minimum and maximum velocity limits should be adopted.
5.13.2 Static head:
It is the maximum height reached by pipe after the pump (also known as the ‘discharge
head’). Static lift is the height the water will rise before arriving at the pump (also known
as the ‘suction head’). Friction loss (or head loss).
5.13.3 Residual head
The dynamic head remaining at the end of a pipe section is referred as residual head. The
minimum residual head to be maintained is 5m. Residual head in public stand post is
desired to be 15m and the absolute maximum residual head is 56m.
5.13.4 Hydraulic grade line (HGL)
If a pipe is under pressure, the hydraulic grade line is that level water would rise to in a
small, vertical tube connected to the pipe. Hydraulic gradient is a line joining the points
of highest elevation of water in a series of vertical open pipes rising from a pipeline in
which water flows under pressure. It represents the energy line which is sum of pressure
head and datum head of water at a particular point.
5.14 Pipe losses (major/minor)
5.14.1 Losses in pipes
The basic approach to all piping system is to write the Bernoulli equation two points,
connected by a streamline, where the condition are knows. For example, the surfaces of a
reservoir and a pipe outlet.
2 2
P0 V 0 P1 V 1
H0+ + + ∆ h p =H 1+ + +∆ h m
ρg 2 g ρg 2 g
The total head at point o must match with the total head at point 1, adjusted for any
increase in head due to pump, losses due to pipe friction and so-called “minor losses” due
to entries, exits, fitting, etc. pump head developed is generally a function of the flow
through the system, however this will be dealt with in another section of the course.
5.14.2 Friction losses in pipes
Friction losses are a complex function of the system geometry, the fluid properties and the
flow rate in the system. By observation, the head loss is roughly proportional to the
square of the flow rate in most engineering flows (fully developed, turbulent pipe flow).
The observation leads to the Darcy-Weisbach Equation for head loss due to friction:
2
fL V
∆ hf =
2 gD
14
WATER SUPPLY PROJECT 2076 Batch
Which defines the friction factor, f. f is insensitive to moderate changes in the flow and is
constant for fully turbulent flow. Thus, it is often useful to estimate the relationship as the
head being directly proportion to the square of the flow rate to simplify calculation.
VD
f = f (Re, ε/d, pipe cross-section) ℜ=
γ
Reynolds number is the fundamental dimensionless group in viscous flow. Velocity
times length scale divided by kinematic viscosity.
Relative roughness relates the height of a typical roughness element to the scale of the
flow, represented by the pipe diameter, D
Pipe cross-section is important, as deviations from circular cross-section will cause
secondary flows that increase the pressure drop. Non-circular pipes and ducts are
generally treated by using the hydraulic diameter,
4 A 4∗cross−sectional area
D H= =
P wetted perimeter of pipe
In place of the diameter and treating the pipe as if it is round.
For laminar flow, the head loss is proportion to velocity rather than velocity squared, thus
the friction factor is inversely proportion to velocity.
64
Circular pipes: f = ℜ
k
Non-circular pipes: f = ℜ , 48≤ k ≤ 96
15
WATER SUPPLY PROJECT 2076 Batch
losses are any head loss present in addition to the head loss for the same length of straight
pipe.
Like pipe friction, these losses are roughly proportion to the square of the rate.
Defining k, the loss coefficient, by
2
V
∆ hm=Σ K
2g
Allows for easy integration of minor losses into Darcy-Weisbach equation. K is the sum
of all the loss coefficients in the length of pipe, each contributing to the overall head loss.
Although K appears to be a constant coefficient, it varies with different flow conditions.
Factors affecting the values of k include:
The exact geometry of the component in question
Flow Reynolds number
Proximity to other fittings, etc. (tabulated values of k are for components in
isolation with long straight runs of pipe upstream and downstream.)
Some very basic information on k values for different fitting is included with these notes
and in most introductory fluid mechanics texts.
To calculate losses in piping systems with both pipe friction and minor losses use
2
L V
∆ hf =( f +Σ K )
D 2g
In place of the Darcy-Weisbach equation. The procedures are the same except that the k
values may also change or as iteration progresses.
5.15 PIPES
1. Pipes are circular conduits in which water flows under pressure.
2. Pipes should be designed to resists the internal water pressure and external
pressure due to soil and other imposed loads.
The various types of pipes based on pipe materials are;
5.15.1 Cast iron pipe
1. Made of cast iron.
2. Easy to join, can withstand high pressure, resistant to corrosion.
3. Long life (>100years), durable, strong and moderate in cost.
4. Brittle and very heavy, expensive and difficult to transport.
5. Suitable for distribution system.
5.15.2 Wrought iron pipe
1. Made up of wrought iron
2. Light in weight, easy in transport, handling, cutting, threading, working.
3. Costly corrosive and less durable than CI pipe.
4. Suitable for inside plumbing in buildings but not used due to high cost.
16
WATER SUPPLY PROJECT 2076 Batch
17
WATER SUPPLY PROJECT 2076 Batch
5.16 Valve
The valves can be categorized into the following basic types:
5.16.1 Sluice valve
1. Commonly used valve to regulate the flow in the pipe.
2. Provided at every junction and at the interval of 3 to 5 km.
3. Cheaper and offer less head loss to flow than other valves of same purpose.
5.16.2 Reflux/Check valve
1. Maintains flow in one direction only in the pipe.
2. Normally placed after pump component.
5.16.3 Safety valve / Automatic cutoff valve
1. Use to release the unwanted pressure where the pressure where the pressure in the
pipe lines is maximum and pipes are reliable to burst.
2. Consists of a disc controlled by a spring which can be adjusted for any desired
pressure.
5.16.4 Air relief valve
1. Placed at the summit points in the pipe where air is accumulated which may block
the flow of water.
2. Releases the accumulated air.
5.16.5 Butterfly valve
1. Use for regulating the flow through pipe as in sluice valve but the head loss is
higher than in sluice valve.
2. Placed in the larger diameter because of low cost.
5.16.6 Drained valve
1. To empty or drain off the pipe for removing sand and silt deposited and for
inspection, repair etc.
2. Placed at the dead and at depression
18
WATER SUPPLY PROJECT 2076 Batch
6. DESIGN CRITERIA
6.1 Population
The total population of a community to be served by the proposed water scheme needs to
be accurately surveyed. Firstly, the present population of the community needs to be
established. Once this is done population that is likely to be reached at the end of the
design period needs to be estimated.
The benefited population is defined as follows:
Present population: Population at the time of survey
Base year population: population when construction is completed and water scheme is
commissioned.
Design population: Population at the end of design period.
The population data should be taken on household basis by actual counting. Census
records are also needed to determine the average growth rate per annum.
The main aim of population survey is to determine:
The population of residents in the residential houses/buildings.
The population of day scholars and boarders in the academic institutions.
The population of outdoor and indoor patients in hospitals and nursing homes.
The population of birds and animals in the farms/houses.
The populations of visitors (floating population) in the hotels and restaurants and
others, if any.
The population survey is the basis for determining the capacity of the pipe
network.
Knowing present population, we can forecast projected population to calculate the
projected water demand and capacity of the pipe network.
Present population
Population survey is one of the crucial activities in the design of a water scheme. The
surveyor/designer must spend sufficient time to establish the present population of the
community, in close co-operation with the members of the water users and sanitation
committee in particular and the beneficiaries in general. Population should be surveyed
according to the method explained in the procedural Guideline Vol. I.
6.2 Annual population growth rate
A water supply scheme should be designed to meet the community’s future water
requirements. The future population is estimated with the help of the past growth trend of
the particular community. Population growth rate critically affects the design because of
its impact on the projected population, and consequently on its cost.
19
WATER SUPPLY PROJECT 2076 Batch
20
WATER SUPPLY PROJECT 2076 Batch
21
WATER SUPPLY PROJECT 2076 Batch
22
WATER SUPPLY PROJECT 2076 Batch
Population
Present Population : Population at the time of survey
Base Year Population :Population when construction is completed and
Water supply scheme is
commissioned
Design Population :Population at the end of design period.
Present Population
Since the water demand calculation is based on the population size, the designer
should spent sufficient time to establish the present population of the community.
Annual Growth Rate
If the growth rate is below 1%, a growth rate of 1% is adopted, this will allow
some growth without substantially affecting the cost of the project. The past and
present annual population growth rate of Nepal can be seen as:
1.6922% in 2022 (Source: World Bank)
1.85% (2020 estimate) (Source: Nepal Population 2024 (Live))
1.92% (2021 estimate) (Source: Demographics of Nepal)
0.92% (2022 est.) (Source: Demographics of Nepal
Design Period
The design period of a water supply scheme generally depends on:
1. Availability of water at source
2. Budget of project
3. Population Growth Rate
4. life of pipes and construction materials
If population growth rate is greater than 2%, design period is taken 15 years.
If population growth rate is less than 2%, design period is taken 20 years.
23
WATER SUPPLY PROJECT 2076 Batch
drastically from one 22 communities to another since every consumers consumes the
water as per their conveniences depending upon his/her habits which further depends on
season to season and other factors. Hence, the study of the consumption pattern is not
practical to do on each and every new project site. Therefore, the following consumption
pattern is tacitly assumed:
Intermittent /Intermittent System (peak factor = 1.5)
Time Period 5 to 8 AM 8 to 12 AM 12 to 17 AM 17 to 19 AM 19 to 5 AM
Percent Demand 40% 0% 0% 20% 40%
Reservoir Tank (RT) Sizing Cases: In the water distribution system, normally four cases
of reservoir size determination are practiced as shown in Table
Cases Inflow to the reservoir Outflow from the
reservoir
Case I Continuous Continuous
Case II Continuous Intermittent
Case III Intermittent Continuous
Case IV Intermittent Intermittent
The most rational formula that incorporates this entire factor is the Hazen William
equation which is as follows:
24
WATER SUPPLY PROJECT 2076 Batch
HL/L = (10.659*Q1.85)/(C1.85*d4.86)
Where, HL = Head Loss, m
L = Length of Pipe, m
Q = discharge, m3/s
C = Hazen Williams coefficient
d = diameter of pipe, m
Hazen Williams Formula: Since the flow is turbulent in pipes used for water supply the
friction factors depend upon the roughness of the pipe and also upon Reynolds Number
which in turn depends in part upon the velocity in the pipe and its diameter. Hazen
Williams formula is most used in the design of water distribution network.
V= K (C) R0.63 S0.54
Where, V = Velocity in pipe, in m/s = Discharge, Q/Area
R = hydraulic radius in m = Flow Area/Wetted perimeter
S = hydraulic gradient = head loss/Length of pipe
C = a constant depending on the relative roughness of the pipe
K = a experimental coefficient, 0.849 in SI Units.
25
WATER SUPPLY PROJECT 2076 Batch
26
WATER SUPPLY PROJECT 2076 Batch
27
WATER SUPPLY PROJECT 2076 Batch
28
WATER SUPPLY PROJECT 2076 Batch
29
WATER SUPPLY PROJECT 2076 Batch
NT NHBG
0 5
1 Turbidity U V
NHBG
7 6.5 - 8.5
2 pH V
Colorles
3 Color s
Taste and NHBG
Normal Normal
4 Odor V
0
5 Temperature C 24.4
mg/ NHBG
0 0.3
6 Iron l V
mg/ NHBG
1.5 1.5
7 Ammonia l V
mg/ NHBG
500 250
8 Chloride l V
30
WATER SUPPLY PROJECT 2076 Batch
9. Reservoir Sizing
Reservoir Tank Sizing
31
WATER SUPPLY PROJECT 2076 Batch
32
WATER SUPPLY PROJECT 2076 Batch
Ite L or
No B A H Qty. Uni Remar
m Description D
. t k
no. m m m2 m
Upto Plinth
Beam
Earthwork
1 Excavation
Footing 1 4 12.56 1 12.560 m3
Brick Soiling in
2 Footing
Footing 1 4 12.56 12.560 m2
PCC Work in
3 Footing
Footing 1 4 12.56 0.1 1.256 m3
4 RCC Work
0.1
Footing 1 4 12.56 5 1.884 m3
Column 8 0.4 0.126 0.7 0.703 m3
0.65
Plinth Beam 8 8 0.3 0.3 0.474 m3
Total 3.061 m3
Brick Work in
5 Footing
0.65
Below GL 8 8 0.3 0.7 1.105 m3
6 Back Filling
Below GL
Total excavation 12.560 m3
Deduction
Volume of Brick 0.0
soiling 5 0.628 m3
Volume of PCC
work 1.256 m3
Volume of RCC
work 3.061 m3
Volume of Brick
work 1.105 m3
Total 6.509 m3
7 Formwork
33
WATER SUPPLY PROJECT 2076 Batch
34
WATER SUPPLY PROJECT 2076 Batch
Ite L or
B A H Qty
m Description No. D Unit Remark
no. m m m2 m
Above Plinth
Level
1 RCC work
0.12
Column 32 0.4 6 3 12.058 m3
0.65
Braces 24 8 0.3 0.3 1.421 m3
Circular Ring 0.65
Beam 8 8 0.3 0.3 0.474 m3
Bottom Dome 1 0.959 m3
Conical Dome 1 0.2 2.227 m3
1.53
Bottom Ring Beam 8 8 0.23 0.23 0.651 m3
12.5
Circular Side Wall 1 6 0.15 3.5 6.594 m3
1.53
Top Ring Beam 8 8 0.23 0.23 0.651 m3
Top Dome 1 4 1.321 m3
Total 26.355 m3
2 Formwork
1.25
Column 32 0.4 6 3 120.576 m2
Except Column
0.65
Braces 24 8 0.3 0.3 14.213 m2
Circular Ring 0.65
Beam 8 8 0.3 0.3 4.738 m2
Bottom Dome 1 6.531 m2
Conical Dome 1 11.134 m2
1.53
Bottom Ring Beam 8 8 0.23 0.23 8.490 m2
Circular Side Wall 1 4 0.15 3.5 84.623 m2
1.53
Top Ring Beam 8 8 0.23 0.23 8.490 m2
Top Dome 1 4 14.570 m2
Total 152.787 m2
3 Plastering
Ceiling
0.65
Braces 24 8 0.3 4.738 m2
Circular Ring 0.65
Beam 8 8 0.3 1.579 m2
35
WATER SUPPLY PROJECT 2076 Batch
Except Ceiling
1.25
Column 32 0.4 6 3 120.576 m2
0.65
Braces 24 8 0.3 9.475 m2
Circular Ring 0.65
Beam 8 8 0.3 3.158 m2
Bottom Dome 1 7.662 m2
Ite L or
No B A H Quantit Remark
m Description D Unit
. y s
no. m m m2 m
4 Coloring
Column 32 0.4 1.256 3 120.576 m2
0.65
Braces 24 8 0.3 0.3 18.950 m2
0.65
Circular Ring Beam 8 8 0.3 0.3 4.738 m2
Bottom Dome 1 6.531 m2
Conical Dome 1 11.134 m2
1.53 0.2
Bottom Ring Beam 8 8 3 0.23 11.320 m2
12.5
Circular Side Wall 1 6 3.5 43.960 m2
1.53 0.2
Top Ring Beam 8 8 3 0.23 11.320 m2
Top Dome 1 4 15.103 m2
Total 243.632 m2
36
WATER SUPPLY PROJECT 2076 Batch
Drawings
37
WATER SUPPLY PROJECT 2076 Batch
38
WATER SUPPLY PROJECT 2076 Batch
39
WATER SUPPLY PROJECT 2076 Batch
40
WATER SUPPLY PROJECT 2076 Batch
41
WATER SUPPLY PROJECT 2076 Batch
42
WATER SUPPLY PROJECT 2076 Batch
43
WATER SUPPLY PROJECT 2076 Batch
44
WATER SUPPLY PROJECT 2076 Batch
45
WATER SUPPLY PROJECT 2076 Batch
46
WATER SUPPLY PROJECT 2076 Batch
47
WATER SUPPLY PROJECT 2076 Batch
48
WATER SUPPLY PROJECT 2076 Batch
49
WATER SUPPLY PROJECT 2076 Batch
50