167
167
NEW DELHI
Coram:
Shri A.K. Singhal, Member
Shri A.S.Bakshi, Member
Dr. M.K. Iyer, Member
In the matter of
Petition under section 62 and 79 (1) (a) of the Electricity Act, 2003 read with
Chapter-V of the CERC (Conduct of Business) Regulations, 1999 for relaxation of
APC norms of Talcher Super Thermal Power Station, Stage-I (1000 MW) for the
period from 1.4.2014 to 31.3.2019
And
In the matter of
NTPC Ltd
NTPC Bhawan
Core-7, SCOPE Complex
7, Institutional area, Lodhi Road
New Delhi- 110003 …….Petitioner
Vs
Parties present:
Shri Ajay Dua, NTPC
Shri Shailendra Singh, NTPC
Shri R.K.Mehta, Advocate, GRIDCO
Ms. Himanshi, Advocate, GRIDCO
Shri S.Vallinayagam, Advocate, TANGEDCO
Shri Sanjay Sen, Senior Advocate, WBSEDCL
ORDER
This Petition has been filed by the Petitioner, NTPC that has prayed for the
following relief:
“In view of the fact and circumstances mentioned above, it is submitted that
the petition may please be admitted and NTPC TSTPS Stage-I may be allowed
relaxed operating norms for APC/ AEC from 5.75% to 7.5% for 2014-19 period
by invoking Hon‟ble Commission‟s powers under Regulation 54 „Power to
Relax‟‟.
2. In support of the above prayer, the Petitioner in this Petition has submitted as
under:
(i) The Petitioner is a Govt. company within the meaning of Companies Act,
1956 and is a „generating company‟ as defined under section 2(28) of the
Electricity Act, 2003 (the 2003 Act). Talcher Super Thermal Power Station,
Stage-I (referred to as “the generating station‟) comprises of two units of 500
MW each, is owned by the Petitioner and located in the State of Odisha. Power
from the generating station is supplied to the Respondents.
(ii) This Commission has the jurisdiction to regulate the tariff of generating
companies owned or controlled by the Central Govt. under Section 62 of the
Electricity Act, 2003. Accordingly, the Commission has notified the CERC
(Terms and Conditions of Tariff) Regulations, 2014 (hereinafter referred to as
(iii) The tariff of the generating station for the period from 1.4.2014 to
31.3.2019 was determined by the Commission by order dated 29.7.2016 in
Petition No. 281/GT/2014 in accordance with the 2014 Tariff Regulations.
(v) At the time of framing of the 2014 Tariff Regulations, the CEA in its
„Recommendations on Operational norms for Thermal Power Stations for tariff
period 2014-19‟ had recommended that the existing APC norms for coal fired
units are considered adequate and may continue. However, APC for 500 MW
and higher size units installed after 1.4.2009, may be reduced by 0.75% (three
fourth percentage points). But, the Commission under the 2014 Tariff
Regulations, reduced the APC norms by 0.75% even for units commissioned
before 1.4.2009.
(vi) Although the units of this generating station were commissioned before
1.4.2009, the APC norms were reduced to 5.75% from 6.5%. The actual APC
indicated by CEA of the generating station for the period 2008-13 is 6.7% to
7.4% (average 6.9%). Thus, this generating station has never in the past
achieved APC of 5.75% which is a norm for the period 2014-19. However, the
achieved APC of the generating station during the subsequent period is as
under:
(vii) One of the main reasons for higher APC of this generating station is that
the station is provided with Ball & Tube Mills (BBD 4772 SI) supplied by GEC
Alsthom, which are highly power intensive. The power consumption is
significantly higher than the normal BHEL bowl mills. The design details of the
Ball & Tube Mill is as under:
(ix) Thus, a total of 1.52% (approx.) is contributed from the Tube Mills
towards APC of the units as compared to 0.60 % as in case of BHEL supplied
mills. There is a percentage increase in APC of 0.92% on account of tube mills.
In addition, the power consumption of auxiliaries associated with tube mills is
higher in comparison to bowl mills. A comparison of associated auxiliaries
corresponding one tube mill and bowl mill is as under:
It can be inferred from the above table that the one Tube Mill along with
its auxiliaries has power consumption of around 4.65 times energy as compared
to bowl mill.
(xi) Thus, the contribution of ball and tube mills towards APC of the units is
comparatively much more than the bowl mills for same capacity units.
(xii) While framing the APC norms under Regulation 36 (E) of the 2014 Tariff
Regulations, the design aspects such as type of cooling tower, type of BFPs etc had
been considered. However, the higher APC in the “tube mills” in the units has not
been considered. Also, in the generating station some of the new schemes have
been planned and executed to meet the various statutory directives for pollution
control and safety and security of the generating station. These additional power
intensive systems are expected to be put to service during 2017-18. Accordingly,
the APC will further increase due to these additional power intensive systems
added by the Petitioner to meet statutory requirements. The details of these
additional systems are as under:
Regulation 36 (E) of the 2014 Tariff Regulations with respect to the APC norms for
the generating station from 5.75% to 7.5% in exercise of the power under
4. The matter was heard on 16.1.2018 on „admission‟. During the hearing, the
learned counsel of the Petitioner reiterated the submissions made in the Petition
and prayed that the relief sought for may be granted. The Respondent No. 8
(TANGEDCO) has filed its reply vide affidavit dated 12.1.2018. The Commission,
after hearing the parties reserved its orders on the issue of „maintainability‟.
Reply of TANGEDCO
(i) Unit I had achieved COD on 1.1.1997 and Unit II of the generating station
achieved COD on 1.7.1997 and therefore have completed the useful life of 20
years as on 31.12.2017. The CEA in its recommendations for the Operational
norms of the thermal power stations for the period 2014-19 had stated that the
Commission may review the existing APC norms based on actual performance.
Accordingly, the Commission has reviewed APC norms for existing as well as
new 500 MW units and specified Regulation 36 (E) of the 2014 Tariff
Regulations.
(ii) The 2014 Tariff Regulations notified by the Commission is guided by the
principles of CEA, National Electricity Policy and Tariff Policy and is based on
the norms and not on actuals. Moreover, the Petitioner has not raised any
issues before the Commission on the Statement of Reasons and Explanatory
Memorandum for the 2014 Tariff Regulations and has raised issue now after a
huge delay, which is not permitted in law. If the Petitioner is aggrieved by the
2014 Tariff Regulations, they should have approached the High Court
challenging the Regulations. Having failed to do so, the Petitioner is now trying
to challenge the 2014 Tariff Regulations, which is not maintainable.
(v) The terms and conditions specified under the 2014 Tariff Regulations
cannot be categorized as unreasonable to resort to the exercise of general
Power of Relaxation in the manner sought for by the Petitioner. The prayer for
relaxation is therefore beyond the Regulation 54.
(vi) The 2014 Tariff Regulations have been specified by the Commission in
exercise of its power under section 178 of the 2003 Act and thus form part of
the said Act. This has been laid down by the Hon‟ble Supreme Court in State of
UP & ors v/s Babu Ram Upadhyaya (1961) 2SCR 679. In WBSEB v/s Patel Engg
Co. Ltd (2001) 2SCC 451, the Hon‟ble Supreme Court held that where power to
relax or waive a rule or a condition exists under the rule, it has to be done
strictly in compliance with the rules.
documents on record. The Petitioner has prayed that the APC norms in respect of
the generating station may be revised from 5.75% to 7.5% for the period 2014-19 in
prayer, the Petitioner has submitted that the higher APC for this generating station
is on account of the fact that the station is provided with Ball & Tube Mills (BBD
4772 SI) supplied by GEC Alsthom which are highly power intensive and the
consumption is higher than the normal BHEL bowl mills. In addition to this, the
Petitioner has submitted that due to the addition of power intensive systems for
the generating station towards statutory compliances for pollution control and
safety & security during the year 2017-18, the APC will further increase. Thus, the
issue for consideration is whether the prayer of the Petitioner in this Petition is
maintainable.
Order in Petition No. 167/MP/2017 Page 7 of 13
Maintainability
‘’54. Power to Relax. The Commission, for reasons to be recorded in writing, may
relax any of the provisions of these regulations on its own motion or on an
application made before it by an interested person.‟‟
9. The power of relaxation under the Tariff Regulations is in general terms and
its exercise is discretionary. It is settled law that exercise of discretion must not
with justice, equity and good conscience, always in keeping with the given facts
10. The Commission vide order dated 7.6.2013 had initiated the process of
framing the terms and conditions for determination of tariff, including the norms
had directed various Central and State generating utilities to furnish the
operational and performance data for the period from 2008-09 to 2012-13. The CEA
was also requested to recommend suitable operational norms for the thermal
generating stations. Thus, the Commission, after considering the said data and
companies like the Petitioner, had notified the 2014 Tariff Regulations applicable
b. Hence, the existing AEC norms should be continued with provision of additional
AEC on account of new technologies like FGD, desalination plant, pipe conveyors,
ash disposal system, etc.
c. As gas stations are facing heavy partial loading due to low schedule, the existing
AEC norms of gas stations need to be revisited with additional consideration for
partial loading below 80% for all gas stations.
d. Beneficiaries should share the energy bill paid by NTPC stations for drawing
energy from grid during plant shutdown due to lower schedule in the proportion of
their allocation.”
including the above submissions of the Petitioner had concluded (vide Para 37.83 &
“37.82 Most of the generating stations have suggested allowing the current norms as
per tariff Regulation 2009 along with additional margin for various equipment‟s to
be installed. The Commission while specifying the auxiliary energy consumption
norms for 200/210/250 MW and 500 MW stations had retained the current norms.
However, CEA in its report has recommended to reduce the auxiliary energy
consumption for new 500 MW Units by 0.75% stating that though there is a scope of
reducing the norm by 1%, however, with a view to allow some operational flexibility
to the stations, 0.75% has been recommended by CEA. In view of the same, the
Commission has reviewed the auxiliary energy consumption norm for existing as
well as new 500 MW Units and has reduced the current norm by 0.75%. As regards
the norms for 200/210/250 MW Units, the Commission has retained the norms
proposed in the draft Regulations.
12. It is therefore evident that the Commission after considering the comments /
suggestions of the stakeholders, including the Petitioner, had specified the Terms
applicable for the period from 1.4.2014. In our considered view, the operational
norms (Regulation 36(E) specified by the Commission under the 2014 Tariff
the prayer of the Petitioner for relaxation of the APC norms and the same is
beyond the scope of Regulation 54 of the 2014 Tariff Regulations. The Petition is
13. The Petitioner has prayed for relaxation of the APC norms under Regulation
36 (E) of the 2014 Tariff Regulations on account of usage of Ball & Tube Mills (BBD
4772 SI) in the generating station. This submission of the Petitioner is not
for determination of the tariff of the generating station for the period 2014-19,
the Petitioner had sought for relaxation of APC norms from 5.75% to 7.25%, under
Regulation 54 of the 2014 Tarff Regulations, based on the actual operating data.
The relevant portion of the submissions of the Petitioner in the said Petition is
extracted as under:
Petitioner, by order dated 29.7.2016 had rejected the prayer of the Petitioner for
relaxation of APC norms and held that the APC of 5.75% in terms of the 2014 Tariff
Regulations shall be made applicable for the generating station. The relevant
74. Regulation 36(E)(a) of 2014 Tariff Regulations, provides for the Auxiliary Energy
Consumption of 5.25% for coal based generating stations of 500 MW sets with Natural
Draft cooling tower or without cooling tower with steam driven BFP. It further
provides that for thermal generating stations with induced draft cooling towers, the
norms shall be further increased by 0.5%. Accordingly, the Auxiliary Energy
Consumption to be considered is 5.75% as per the norms and the same is allowed for
the purpose of tariff computations.”
norms from 5.75% to 7.25% on the ground of usage of Tube Mills etc., had been
rejected the prayer of the Petitioner for relaxation of APC norms in order dated
29.7.2016, there is no justification for the Petitioner to seek the relaxation of the
APC norms now from 5.75% to 7.5% in this Petition, on the same grounds. The
Petitioner cannot be permitted to unsettle the settled issue. In our view, the
review of order dated 29.7.2016 in disguise. In this background, the relief sought
maintainable.
16. The Petitioner has further submitted that due to addition of some power
intensive systems like Retrofitting of ESP (ESP R & M), 4th Ash Slurry Series, Dry Ash
Handling System and Fire Fighting system to meet various statutory directives for
pollution control and safety & security during 2017-18, there is increase in APC of
the generating station. This submission of the Petitioner is also not acceptable. In
our view, the planning and addition of power intensive schemes for the station
during the period 2017-18 cannot be a ground for relaxation of the APC norms
under the 2014 Tariff Regulations had taken into consideration the operational and
performance data furnished by the generating utilities for the period from 2008-09
to 2012-13, i.e prior to the period 2014-19. Hence, the addition of power intensive
systems during the year 2017-18 cannot be a factor for relaxation of the APC norms
Petitioner for relaxation of the APC norm specified under Regulation 36(E) is not