Job Safety Analysis
Project Name:
Address: PERSION PROTECTIVE EQUIPMENT REQUIRED
Company Name: Activity/Trade: Core Cutting
Address: EHS-
Supervisor Name: Mr.
Person
Procedure (in steps) Possible Hazards Risk Control Measures
who will
(Break the job down into steps. Each (Identify the hazards associated with each Rating (Describe what action or procedure will be taken to eliminate or
minimize the risk of injury or damage. Use the Hierarchy of ensure this
step should accomplish some major step. Examine each to find possibilities that (See
Controls below as a guide happens
task and be in logical sequence.) could lead to an accident or potential harm below)
arising.) 1. Eliminate the Hazard
2. Substitute the material or equipment
3. Isolate the hazard
4. Implement Engineering control
5. Implement Administrative control
6. PPE
1 Preparation of work environment. Tripping due to obstruction in your Inspect work / walk area for potential slip trip fall obstructions EHS &
Housekeeping path. prior to start of work and remove, if not possible mark with Civil
M visible tape / flags. Supervisor
Slips, trips & falls Keep work area organized and free of surface obstructions
during task.
Inform operator in area of ongoing works.
Close work area to prevent entrance of others.
General clean of the area prior to starting activity.
2 Collect materials from store. Material may have sharp edges and Use cut / abrasive resistant gloves, pad up the uneven
Handling of the material to be splinters. surface.
lifted. Material does not adequate side Ensure that the hand / fingers do not get jammed in between
clearance for lifting. material and vehicle sides by carrying material with hands
Material in odd shape to carry. M inside the maximum width of the item carried.
Ensure that they get additional support of personal before
Lifting beyond the capacity of the lifting. EHS &
person may lead fall on the foot and Discuss with him and then lift the material. Civil
muscle, back strain. Use the material trolley whenever possible. Supervisor
Try to take assistance if the weight of the material is beyond
Dust inhalation and entry to the eye 20kgs. Do not make single person manual lift if the weight of
the machine is beyond 20kgs.
Wear face mask and goggles whilst handling the materials.
Check the specification of the material to ascertain the
3 Establishing the exact weight of No correct information available on weight.
the material to be lifted so that it the package. Try to find out the feasibility of lifting the material without
is well within the capacity of the Lifting beyond the capacity of the M placing hand below the material
lifter/loader person may lead fall on the foot and Try to take assistance if the weight of the material is beyond EHS &
muscle, back strain. 25kgs. Civil
DOOR needs two persons or more help and single Supervisor
Do not make single person manual lift if the weight of the
material is beyond 25kgs.
Mechanical handling for possible materials.
4 Shifting the material from stored May get muscle strains while lifting Take proper and safe body position before handling material
area to working area and placing. material EHS &
M Handle the cement bag without getting damaged and follow Civil
the instruction displayed in the bag and follow the MSDS. Supervisor
Use dust mask
5 Set up chaser and vacuum . Wear hand gloves;
Use cutting / working platform to cut the material.
Cut chase along marked lines Operator of the cutting platform is to be trained its use.
Electric shock
Hammer debris from chase
Clean up Use the approved cutting machine tagged by P&E
Supervisor.
At any time the guard should be in position to avoid injury.
The cutting portion should be kept in wet condition to avoid
M duct generation.
Use correct type and size of cutting wheel before the start of EHS &
drilling. Civil
Ensure drill is not powered while mounting and dismounting Supervisor
mobile platform or ladder
Check the tools for malfunction.
Use Plug top.
Wear hand gloves & ear plug / muff.
6 Machine condition High pressure fluid Ensure all holes and fittings are in good conditions and kept
Burn of injury clean
Machine Fuelling Exposure to noise Replace immediately any damage found
Hearing lose EHS &
Shearing parts of plant M Hearing protection to be worn whenever machine is Civil
Machine start-up Death of serious injury operation hand signal to be agreed before operation Supervisor
Injury Explosion overcome by vapors machine.
Warning sign placed as necessary
Ensure hands are clear of tools when operating and work
area is clear before operation
7 Cutting Equipment malfunction or misuse Check for live service such as electrical wiring, gas,
Muscle sprain cuts and abrasions water, telephone etc near cutting area before
entrapment commencing work.
Plunge cut instead of starting at the top of the wall as
Night work M this will reduce chatter. Always operate saw at full
EHS &
throttle
Civil
Supervisor
.Don’t work alone
Light area as well as possible if lighting insufficient do
not work.
Operators of plant & equipment are to be trained
Equipment damage regarding the hazards associated with machine
operations
Minimize the potential for unauthorized person to use
council plant/equipment
8 Preparation of surface Hand injury while hacking Use gloves. Check the grip of the hamper. EHS &
Dust inhalation M Wear mask. Civil
Dust particles entering the eye Wear Goggles. Supervisor
Clear the debris regularly.
Trip and fall due to debris
9 Remove tools & equipment Slips & trips M Ensure travel path is clear EHS &
from site Back & shoulder strain Training in manual handling Civil
Hit by others plant Ensure loading area is clear Supervisor
1 Removing the Wastages Cut injury while removing the cut Use cut / Abrasive resistant gloves and use spades and EHS &
0 produced during the cutting. pieces. M brushes with pans to prevent direct contact. Civil
Supervisor
House Keeping / Clean area. Dust Inhalation and entry to eyes Use dust Mask and goggles at all times.
Tripping hazards while cleaning Keep work area clear off debris and remove tools /
work area. equipments when not in use to eliminate trip hazards.
Cleaning of all the debris after completing the task.
Any changes, additions or deletions made to this SWMS are to be covered with the above personnel and the Principal Contractors representative at a
Toolbox meeting (Record date and time of Toolbox meeting below):
Date: Time: