PROJECT TIME SCHEDULE
PEKERJAAN JASA REVITALISASI GUDANG CORE & CUTTING PLTP DIENG UNIT 1
PT. PRIMA JAYA SENTOSA ENERGI
ID Task Name Duration Start Finish
Oct '23 Nov '23 Dec '23 Jan '24 Feb '24 Mar '24
29 05 12 19 26 03 10 17 24 31 07 14 21 28 04 11 18 25 03 10 17 24 31
1 PEKERJAAN JASA REVITALISASI GUDANG CORE & CUTTING PLTP DIENG UNIT 1 120 days 13 November 2023 12 March 2024
2 PEKERJAAN PERSIAPAN 8 days 13 November 2023 21 November 2023
3 Kick-Off Meeting 2 days 13 November 2023 15 November 2023
4 Mobilisasi Peralatan dan Tenaga Kerja 3 days 15 November 2023 18 November 2023
5 Persiapan Listrik & Air Kerja 1 day 15 November 2023 16 November 2023
6 Direksi keet 3 days 16 November 2023 19 November 2023
7 Pekerjaan SMK3 1 day 15 November 2023 16 November 2023
8 Perizinan Awal dan Sosialisasi Pekerjaan kepada tenaga lokal 2 days 15 November 2023 17 November 2023
9 Papan Nama Proyek 1 day 19 November 2023 20 November 2023
10 Pembersihan Proyek 1 day 15 November 2023 16 November 2023
11 Pagar Pengaman Proyek 1 day 19 November 2023 20 November 2023
12 Pengukuran dan Pemasangan Bouwplank 1 day 20 November 2023 21 November 2023
13 PEKERJAAN BONGKARAN & RELOKASI 14 days 21 November 2023 05 December 2023
14 Relokasi barang-barang milik owner 7 days 21 November 2023 28 November 2023
15 Bongkaran dinding existing 7 days 21 November 2023 28 November 2023
16 Bongkaran paving block 7 days 26 November 2023 03 December 2023
17 Pekerjaan bongkaran lainnya 7 days 21 November 2023 28 November 2023
18 Buangan puing dan sampah bekas bongkaran 7 days 21 November 2023 28 November 2023
19 Pekerjaan perapihan dinding existing 7 days 28 November 2023 05 December 2023
20 PEKERJAAN STRUKTUR 58 days 05 December 2023 01 February 2024
21 Pekerjaan Beton 32 days 05 December 2023 06 January 2024
22 Pekerjaan Pondasi P-1 16 days 05 December 2023 21 December 2023
23 Galian Tanah Pondasi 3 days 05 December 2023 08 December 2023
24 Urugan Tanah Kembali 3 days 05 December 2023 08 December 2023
25 Buangan Tanah Bekas Galian 3 days 05 December 2023 08 December 2023
26 Pemadatan Tanah 3 days 08 December 2023 11 December 2023
27 Pasir Urug t=5cm 2 days 11 December 2023 13 December 2023
28 Lantai Kerja 1 day 11 December 2023 12 December 2023
29 Beton 2 days 19 December 2023 21 December 2023
30 Besi 5 days 11 December 2023 16 December 2023
31 Bekisting 3 days 16 December 2023 19 December 2023
32 Pekerjaan Pondasi P-2 14 days 05 December 2023 19 December 2023
33 Galian Tanah Pondasi 3 days 05 December 2023 08 December 2023
34 Urugan Tanah Kembali 2 days 05 December 2023 07 December 2023
35 Buangan Tanah Bekas Galian 2 days 05 December 2023 07 December 2023
36 Pemadatan Tanah 2 days 07 December 2023 09 December 2023
37 Pasir Urug t=5cm 2 days 09 December 2023 11 December 2023
38 Lantai Kerja 1 day 09 December 2023 10 December 2023
39 Beton 2 days 17 December 2023 19 December 2023
40 Besi 5 days 09 December 2023 14 December 2023
41 Bekisting 3 days 14 December 2023 17 December 2023
Issued for Tender Page 1
Rev:00
PROJECT TIME SCHEDULE
PEKERJAAN JASA REVITALISASI GUDANG CORE & CUTTING PLTP DIENG UNIT 1
PT. PRIMA JAYA SENTOSA ENERGI
ID Task Name Duration Start Finish
Oct '23 Nov '23 Dec '23 Jan '24 Feb '24 Mar '24
29 05 12 19 26 03 10 17 24 31 07 14 21 28 04 11 18 25 03 10 17 24 31
42 Pekerjaan Pondasi Batukali 16 days 08 December 2023 24 December 2023
43 Galian Tanah Pondasi 3 days 08 December 2023 11 December 2023
44 Urugan Tanah Kembali 5 days 11 December 2023 16 December 2023
45 Buangan Tanah Bekas Galian 4 days 11 December 2023 15 December 2023
46 Pemadatan Tanah 1 day 15 December 2023 16 December 2023
47 Pasir Urug t=10cm 1 day 16 December 2023 17 December 2023
48 Pasangan batu kosong 7 days 17 December 2023 24 December 2023
49 Pasangan batu kali 7 days 17 December 2023 24 December 2023
50 Pekerjaan Sloof 15 days 08 December 2023 23 December 2023
51 Galian Tanah Pondasi 3 days 08 December 2023 11 December 2023
52 Urugan Tanah Kembali 1 day 11 December 2023 12 December 2023
53 Buangan Tanah Bekas Galian 1 day 11 December 2023 12 December 2023
54 Pemadatan Tanah 2 days 11 December 2023 13 December 2023
55 Pasir Urug t=5cm 2 days 13 December 2023 15 December 2023
56 Lantai Kerja 1 day 15 December 2023 16 December 2023
57 Beton 2 days 21 December 2023 23 December 2023
58 Besi 5 days 13 December 2023 18 December 2023
59 Bekisting 3 days 18 December 2023 21 December 2023
60 Pekerjaan Kolom Beton Pedestal 10 days 23 December 2023 02 January 2024
61 Beton 2 days 31 December 2023 02 January 2024
62 Besi 5 days 23 December 2023 28 December 2023
63 Bekisting 3 days 28 December 2023 31 December 2023
64 Pekerjaan Plat Beton Lantai 1 14 days 23 December 2023 06 January 2024
65 Base Coarse 2 days 02 January 2024 04 January 2024
66 Lantai Kerja 1 day 04 January 2024 05 January 2024
67 Beton 2 days 01 January 2024 03 January 2024
68 Besi 5 days 23 December 2023 28 December 2023
69 Bekisting 4 days 28 December 2023 01 January 2024
70 Rabat Beton 3 days 03 January 2024 06 January 2024
71 Pekerjaan Kolom Beton Lantai 1 9 days 23 December 2023 01 January 2024
72 Beton 2 days 30 December 2023 01 January 2024
73 Besi 5 days 23 December 2023 28 December 2023
74 Bekisting 2 days 28 December 2023 30 December 2023
75 Pekerjaan Ring Balok 9 days 23 December 2023 01 January 2024
76 Beton 2 days 30 December 2023 01 January 2024
77 Besi 5 days 23 December 2023 28 December 2023
78 Bekisting 2 days 28 December 2023 30 December 2023
79 Pekerjaan Baja 31 days 01 January 2024 01 February 2024
80 Pekerjaan Kolom Atap 10 days 01 January 2024 11 January 2024
81 Kolom H 100x100x6x8mm 10 days 01 January 2024 11 January 2024
82 Plate 10-22mm (stiffener, baseplate, joint plate, etc) 5 days 01 January 2024 06 January 2024
Issued for Tender Page 2
Rev:00
PROJECT TIME SCHEDULE
PEKERJAAN JASA REVITALISASI GUDANG CORE & CUTTING PLTP DIENG UNIT 1
PT. PRIMA JAYA SENTOSA ENERGI
ID Task Name Duration Start Finish
Oct '23 Nov '23 Dec '23 Jan '24 Feb '24 Mar '24
29 05 12 19 26 03 10 17 24 31 07 14 21 28 04 11 18 25 03 10 17 24 31
83 Angkur baut M16 L 150mm include pekerjaan grouting 5 days 01 January 2024 06 January 2024
84 Chemical Angkur baut M16 L 150mm 2 days 06 January 2024 08 January 2024
85 Pengecatan Zincromate 3 days 08 January 2024 11 January 2024
86 Pekerjaan Rangka Truss Atap Baja 21 days 11 January 2024 01 February 2024
87 Truss T 75x75x5x7 10 days 11 January 2024 21 January 2024
88 Truss Double Siku L 50x50x5 5 days 21 January 2024 26 January 2024
89 Rangka Cantilever IWF 150x75x5x7 3 days 21 January 2024 24 January 2024
90 Plate 10-22mm (stiffener, baseplate, joint plate, etc) 3 days 21 January 2024 24 January 2024
91 Mur baut ukuran sesuai gambar 2 days 21 January 2024 23 January 2024
92 Rangka Atap Gording CNP 150x50x20x2,5 3 days 23 January 2024 26 January 2024
93 Rangka Cladding Gording CNP 150x50x20x2,5 3 days 23 January 2024 26 January 2024
94 Plate dudukan gording t. 6-10mm 3 days 23 January 2024 26 January 2024
95 Mur baut dia. 10 3 days 23 January 2024 26 January 2024
96 Rangka Atap Wind Bracing dia. 13mm 5 days 26 January 2024 31 January 2024
97 Rangka Atap Trekstang dia. 12mm 3 days 26 January 2024 29 January 2024
98 Pengecatan Zincromate 3 days 29 January 2024 01 February 2024
99 PEKERJAAN ARSITEK 31 days 01 February 2024 03 March 2024
100 Pekerjaan Dinding 13 days 01 February 2024 14 February 2024
101 Dinding bata 7 days 01 February 2024 08 February 2024
102 Plester dinding 3 days 08 February 2024 11 February 2024
103 Acian dinding 3 days 08 February 2024 11 February 2024
104 Keramik dinding area KM/WC 3 days 11 February 2024 14 February 2024
105 Dinding Cladding 3 days 11 February 2024 14 February 2024
106 Rollag Bata 3 days 11 February 2024 14 February 2024
107 Pekerjaan Lantai 3 days 14 February 2024 17 February 2024
108 Area Gudang 3 days 14 February 2024 17 February 2024
109 Area Office 3 days 14 February 2024 17 February 2024
110 Area Wastafel 1 day 14 February 2024 15 February 2024
111 KM/WC 1 day 14 February 2024 15 February 2024
112 Pekerjaan Plafond 3 days 14 February 2024 17 February 2024
113 Penutup Plafond 3 days 14 February 2024 17 February 2024
114 Penutup Plafond Area Basah 3 days 14 February 2024 17 February 2024
115 Pekerjaan Finishing 15 days 17 February 2024 03 March 2024
116 Pengecatan Dinding Interior 5 days 17 February 2024 22 February 2024
117 Pengecatan Dinding Exterior 5 days 22 February 2024 27 February 2024
118 Pengecatan Plafond 5 days 27 February 2024 03 March 2024
119 Pengecatan Listplank 5 days 27 February 2024 03 March 2024
120 Pekerjaan Sanitair 1 day 17 February 2024 18 February 2024
121 Kloset duduk 1 day 17 February 2024 18 February 2024
122 Hand Spray 1 day 17 February 2024 18 February 2024
123 Floor drain 1 day 17 February 2024 18 February 2024
Issued for Tender Page 3
Rev:00
PROJECT TIME SCHEDULE
PEKERJAAN JASA REVITALISASI GUDANG CORE & CUTTING PLTP DIENG UNIT 1
PT. PRIMA JAYA SENTOSA ENERGI
ID Task Name Duration Start Finish
Oct '23 Nov '23 Dec '23 Jan '24 Feb '24 Mar '24
29 05 12 19 26 03 10 17 24 31 07 14 21 28 04 11 18 25 03 10 17 24 31
124 Kran dinding 1 day 17 February 2024 18 February 2024
125 Wastafel 1 day 17 February 2024 18 February 2024
126 Pekerjaan Pintu dan Jendela 6 days 17 February 2024 23 February 2024
127 Pintu Rolling Door 5 days 17 February 2024 22 February 2024
128 Pintu Ruang (P1) 1 day 22 February 2024 23 February 2024
129 Pintu KM/WC (P2) 1 day 22 February 2024 23 February 2024
130 Jendela (J1) 1 day 22 February 2024 23 February 2024
131 Jendela Bauven (BV) 1 day 22 February 2024 23 February 2024
132 Pekerjaan Atap 7 days 23 February 2024 01 March 2024
133 Penutup Atap 7 days 23 February 2024 01 March 2024
134 Nok Atap 2 days 23 February 2024 25 February 2024
135 Talang 2 days 23 February 2024 25 February 2024
136 Listplank 2 days 23 February 2024 25 February 2024
137 Flashing 2 days 23 February 2024 25 February 2024
138 Pekerjaan Interior 1 day 01 March 2024 02 March 2024
139 Sofa 3 seater 1 day 01 March 2024 02 March 2024
140 Sofa 1 seater 1 day 01 March 2024 02 March 2024
141 Meja Tamu 1 day 01 March 2024 02 March 2024
142 Rack Sample type 2 span 1 day 01 March 2024 02 March 2024
143 Rack Sample type 3 span 1 day 01 March 2024 02 March 2024
144 Tangga lipat tinggi 2,5m 1 day 01 March 2024 02 March 2024
145 PEKERJAAN MEKANIKAL, ELEKTRIKAL, DAN PLUMBING 8 days 01 March 2024 09 March 2024
146 Pekerjaan Mekanikal & Elektrikal 6 days 01 March 2024 07 March 2024
147 Instalasi Lampu 5 days 01 March 2024 06 March 2024
148 Pemasangan Saklar Ganda/Seri 3 days 01 March 2024 04 March 2024
149 Instalasi Stop Kontak 3 days 01 March 2024 04 March 2024
150 Instalasi dan Pasang Box Panel 3 days 01 March 2024 04 March 2024
151 Stop Kontak 3 days 01 March 2024 04 March 2024
152 Pasang Lampu Downlight 1 day 04 March 2024 05 March 2024
153 Pasang Lampu Downlight 1 day 01 March 2024 02 March 2024
154 Pasang Exhaust fan include instalasinya 3 days 04 March 2024 07 March 2024
155 Pekerjaan Plumbing 8 days 01 March 2024 09 March 2024
156 Pemasangan pipa air kotor type D dia 4" 5 days 01 March 2024 06 March 2024
157 Pemasangan pipa air bekas type WW dia 2" 5 days 01 March 2024 06 March 2024
158 Pemasangan pipa air bersih type AW dia 1" 5 days 01 March 2024 06 March 2024
159 Pemasangan pipa air bersih type AW dia 3/4" 5 days 01 March 2024 06 March 2024
160 Pemasangan pipa air bersih type AW dia 1/2" 5 days 01 March 2024 06 March 2024
161 Membuat bak kontrol uk. 30x40cm include tutup 3 days 06 March 2024 09 March 2024
162 Membuat torn air kap. 800 ltr include struktur torn 1 day 06 March 2024 07 March 2024
163 Membuat biotank uk. 1m3 include strukturnya 2 days 06 March 2024 08 March 2024
164 Membuat sumur resapan include strukturnya 3 days 06 March 2024 09 March 2024
Issued for Tender Page 4
Rev:00
PROJECT TIME SCHEDULE
PEKERJAAN JASA REVITALISASI GUDANG CORE & CUTTING PLTP DIENG UNIT 1
PT. PRIMA JAYA SENTOSA ENERGI
ID Task Name Duration Start Finish
Oct '23 Nov '23 Dec '23 Jan '24 Feb '24 Mar '24
29 05 12 19 26 03 10 17 24 31 07 14 21 28 04 11 18 25 03 10 17 24 31
165 Penyediaan APAR Kap. 4,5kg 1 day 06 March 2024 07 March 2024
166 Project Closing 5 days 07 March 2024 12 March 2024
167 Perbaikan perapihan kembali dan housekeeping 2 days 07 March 2024 09 March 2024
168 Administrasi, Dokumentasi, laporan, shop drawing, Lap. Akhir dan As Build Drawing 3 days 09 March 2024 12 March 2024
169 Demobilisasi 0 days 12 March 2024 12 March 2024 12/03
Issued for Tender Page 5
Rev:00