Earthwork
Earthwork
1.1.1 The following definitions of earthworks and materials shall apply to this and other
relevant clauses in this Specification?-
       c. 'Subgrade' means the parts of the existing ground or fill immediately below rail-
       subballast, mat slab, blinding, pile caps, ground beams, floor, raft slab in
       d. 'Top Soil shall mean the top layer of soil that contains or supports vegetation. It
       shall include all grass and turf materials that are unsuitable for incorporation in
       the works other than landscaping and turfing.
       e. 'Suitable material' for subgrade criteria shall comprise all materials that meet
       the specific requirements, physically and chemically, for incorporation in the
       works as indicated in the Contract other than the unsuitable materials           The
       selection of suitable material shall comply to design requirement as specified in
       the subgrade reference drawings and as stated in Clause 1.1.2 in this.
g. Materials that are soft or unstable merely because they are too wet or too dry for
effective compaction are not to be classified as unsuitable unless these materials are
conforming to item 1.1.2 and 1.8.1.
ii. This shall mean any hard material which can be excavated using an excavator with
    minimum weight of 44 tonnes and net horsepower rating of 321 brake horsepower
    with production rate not exceeding 50m³ / hour. The excavator unit is to be in
    good condition and operated by experienced personnel
iii. Hard material shall exclude individual masses less than 0.5m³
iv. Trial excavation shall be carried out using the above equipment
v.    to determine hard material. The trial excavation shall be carried out on a flat platform
      in order to develop the rated horsepower at maximum efficiency.
i.    Any material that 'can only be loosened or excavated by blasting, wedging or drilling
      using pneumatics tools and cannot be removed by the teeth of a mechanical
      excavator or cannot be broken with a pickaxe is defined as rock.
ii. Rock shall mean material found in ledges or masses which can be excavated using
    the following equipment with production rate not exceeding 20m³/hour:
         Equipment with minimum weight of 20 tonnes and net horsepower rating of 200
         brake horsepower or more.The tractor unit is to be in good conditions and
         operatedby experienced personnel skilled in the operation ofripping equipment.
    Ripping unit
J. Rock material normally have to be loosened either by the use of blasting or approved
pneumatic tools. Rock boulders found in general excavation shallconstitute as rock if
such boulders are of size exceeding one cubic meter.
k. Trial excavation shall be carried out using the above equipment to determine rock
L .Shale and clay boulders will not be considered as rock. The Engineer'sdecision as to
whether or not the materials of the excavation is classified asrock shall be final.
1.1.2 For the purpose of determining the compaction plant, layer thickness and
      number of passes using Table 1.5, suitable materials for subgrade as defined in
      Clause 1.1.1 (e) are grouped as follows:-
       b. The bottom-layer of subgrade bed on the first part as Sand Blanket shall consist
       of hard, clean sand conforming to the grading limits given in Table1.2. The
       material passing the 300 um as specified in JKR, sieve shall be non-plastic when
       tested in accordance with B.S. 1377as follows;
            Table 1.2-Grading Limits for Sand Blanket/Filter Material
    c. The bottom-layer of subgrade bed on the second part as bedding shall consists
    of a well graded gravel, crushed rock or medium or coarse sand,having uniformity
    coefficient of Cu 2 5, and curvature coefficient 3 > Cc≥ 1conforming to the
    grading limits given in Table 1.3. The minimum size of coarse particles shall be d
    ≥ 0.25mm. The fine particles (d < 0.075mm) in the filler shall be less than 10%,
    and the maximum particle size of filler shall not exceed 100mm.
.
1.1.3 Fill materials to be incorporated within 500 mm of concrete structures or cement
bound materials shall have a soluble sulphate content not exceeding 2.5 gm per liter when
tested in accordance with B.S.1377: Part 3: 1990 clause
5.0. Special waiver of this requirement may be given if special precautions are
being taken to protect the concrete or cement bound materials.
1.1.4 Surplus suitable material, topsoil and unsuitable materials within the railway
reserve to be removed from site shall be leveled, compacted and turfed to the satisfaction
of respective local authorities. Proper drainage shall be provided.The removed material
shall not destabilize the embankment or cut slope.
1.1.6 Turf and topsoil that is unsuitable for use during the construction of the
embankment and subgrade shall be removed and stockpiled for re-use duringlandscaping
and turfing operations.
1.1.7 Relevant standards of testing such as BS to assess the physical and chemical
properties of the soil, sand, and rock before these materials are incorporated in the works.
All of the adopted testing procedures shall specifically assess the requirements and
properties indicated in the Drawings and Specification.
1.18 For geotextile fabrics, geotextile reinforcement, geogrids and geomats, the
relevant method of installation and product brochures as stated in Technical
Specification-Section 23 are to be submitted for approval.
1.2.1 A competent surveyor shall be engaged to perform all necessary survey work
and setting out works under this contract. All other intermediate survey works shall be
carried out by a competent surveyor. All setting out works shall be carried out after site clearing and
stripping of topsoil has been completed.
        a. After site clearing and stripping of topsoil, a survey' of the existing ground
        level shall be completed by the competent surveyor prior to of works. Chainage
        pegs shall be installed and commencement
       established at 20-meter Intervals, 2 meters outside the Limit of Earthworks.
       b. All reserves and boundary corners shall be pegged out by the competent
       surveyor. Additional reference points or benchmarks, which will not be affected
       shall installed and established a by the Construction Team to confirm existing
       ground levels within the boundaries of the Site.
1.2.3 All boundaries (where they relate to this Contract, and agree with the Survey
Department of Malaysia) shall be checked and confirmed.Permanent boundary markers
shall be formed and left at each site boundary corner.
1.2.4 On completion of the survey works, the specified and/or required copies of the as-
built drawings that show all levels, dimensions, angles, etc. of the finished platform
including slopes and embankments shall be submitted.
1.3 Excavation
1.3.1 All Excavation works shall be carried out in accordance with this Specification and
to the prescribed lines, grades and levels as shown on the Drawings. Excavation works
shall be deemed to include the following:
       d.The removal and disposal of material that is unsuitable for use in the
       proposed works.
       f .The removal of unsuitable material from below the formation level or below the
       natural ground surface in embankments as inded on theDrawings
    a)    Common excavation shall mean excavation in any materials other than rock
         materials as described in Clause 1.1.1 of this specification.
    b)    Rock excavation shall mean excavation which cannot be undertaken without the
         use of either pneumatic tools or explosives or as described in Clause 1.1.1 of this
         specification
    a.   Proper source of all fill materials together with the required quantity and quality
         of the fill materials shall be provided. The borrow pits shall bekept free from
         ponding water and the excavation shall be neat and tidy.All necessary erosion
         protection measures shall be carried out throughout and after the Contract
         period.
    b.   Prior to the use of any borrow area, representative samples shall be obtained
         from borrow pits and carry out physical and chemical tests to confirm the
         suitability of the material for incorporation in the works. Suitable materials shall
         mean those materials other than the unsuitable materials defined in section 1.1.1
         of the specification
    b.   All cut slopes shall be cleared of all loose rock fragments. Where rock and soft
         soil are present in alternate layers, the soft material shall be excavated or
         removed to an agreed depth and make up the resulting void or space with
         concrete or with masonry rip-rap.
    c.   The bottom level of the cutting shall be maintained at least 300 mm above
         formation level if there is no intention to lay the sub-ballast stone immediately.
         Any damage to the sub grade due to moving plants shall be made good by
         removing and disposing the damaged material and replacing with material
         having the same characteristics as the original material. After trimming the 300
         mm excess material above the final formation level, no movement of plant shall
         be permitted other than that allowed for the construction of the various track and
         pavement courses.
Table 1.4- Grading Limits for Granular Material Below Standing Water
    b.   In the event where soft material removal is specifically shown on the drawings
         as not required, approved rock fill material graded from 400 mm to 150 mm and
         having 150 mm size particles <10% shall be placed directly on the naturally
         occurring weak material. The rock fill material shall be deposited in accordance
         with Clause 1.5.4 and compacted to comply with Clause 1.6.5 for the
         compaction of rock, and it should be followed the in-situ test.
Table 1.5:Type Of Compaction Plants
        Unsuitable for self-propelled rollers
        D-Maximum depth of compacted layer (mm)
        N-Minimum number of passes
   a.    Excavation of foundation pits and trenches shall be completed to the line and
         levels shown in the Drawings. Excavation in rock and hard materials to achieve
         the final level shall be carried out in a cautious manner using appropriate tools
         and plant so as to avoid damage or collapse of other section of the works.
         Pockets of soft soil or legs rock at the bottom of foundation pits and trenches
         shall be removed.
   b.    All water shall be pumped out of all foundation pits and trenches and the sides of
         the excavations shall at all times be adequately supported to prevent collapse.
   c.    No trimming of excavation side faces shall be carried out within 24 hours of the
         placement of blinding concrete
      d.    All over excavation on the sides or below the prescribed bottom of foundation or
            greater than the net volume required for the works shall be made good with
            suitable material or Grade 15 concrete.
All back fill materials stall consist of material suitable for the works and shall be
deposited and compacted using appropriate construction plant .Timber sheeting and other
excavation supports shall be removed as the filling proceeds unless otherwise approved.
The stability of the works shall be ensured after the removal of such supports
1.4.1 Suitable facilities for the storage of all explosives shall be provided and
maintained. Such storage shall be undertakes so as to fully comply with Explosive Act
1957 (Revised 1978) and the mandatory requirements of the Police .All after regulations
pertaining to the purchase, possession, safety and
storage of explosives shall be strictly complied with.
1.4.2 Access to the explosives storage area shall be strictly controlled and guarded and
only authorized personnel shall be allowed within these premises
1.4.3 Fall and proper recants shall be kept as to the purchase, use and issue of all
explosies such that the location or use of every item of explosives can be readily traced at
all times. The handing of explosives shall be entrusted to experience and authorized
personnel
1.4.5 Where permission has been granted for the use of explosives for the execution
of the work, the Contractor shall be solely responsible for obtaining the necessary
licenses for the procurement, possession, transport, storage and handling of explosives
and for ensuring the validity of such licenses at all times Before starting work, the
Contractor shall satisfy all the required permits are in order and that this category of work
is adequately covered in the policies of Insurance.
1.4.6 All drilling and blasting works shall be done in such a manner so as to bring the
excavation as close as possible to the final grade and the slope lines
     g.   Special care shall be taken or control blasting shall be introduced in wet ground
          to ensure that individual explosions are reduced to such size so as to preclude
         damage to property such as buildings, structures, etc. within the vicinity of the
         work.
1.4.8 All necessary precautions shall be ensured that the materials below and beyond
the line of excavation are not affected. If the base rock is heavily fractured due to
improper sequence or methods of blasting, guniting shall be carried out to repair the
fractured base rock.
1.4.9 In the event that blast-damaged material is present on the cut-slopes and this
material would not withstand the effect of weather after dressing, all such materials shall
be excavated and replaced to a depth and extent approved. The Contractor shall be
required to make good the designed profile with Grade 15concrete or mortared rip-rap to
ensure the long-term stability of cut slope.
   b.   Trial blast test shall be carried out for controlled perimeter blasting technique to
        test the drilling accuracy necessary to achieve the required sound uniform
        surfaces to the completed excavations and to test the efficiency of the blasting
        arrangements. Unsatisfactory trial blast results include an excessive amount of
        fragmentation beyond the indicated line sand grade, excessive fly rock, or
        violation of other requirements within the specification.
   c.   The locations for such blasting trials shall be such as to demonstrate of efficiency
        of the proposals in respect of the prevailing rock condition,topography, height
        between berms and environmental constraints.
   d.   The resultant trial faces shall be fully exposed, all loose rock scaled and the faces
        evaluated by the engineer before controlled parameter blasting of the design slope
        commences
1.4.11 The Contractor shall submit the relevant method statements for prior approval and
carry out trial blasting if the contractor intend to use a pre-split blasting technique.
1.4.12 Presplitting
b.      The Contractor shall submit a method statement for the approval, which shall
include all relevant information such as:
d.      If any part of the rock slope is damaged or the design face is disturbed, the
blasting shall be discontinued immediately and proposals for the remedial measures shall
be submitted before proceeding with further blasting works.
1.5 Embankment
To ensure that all soil treatments specified in the Drawings have been satisfactorily
carried out prior to commencing the construction an embankment over soft ground, The
soil over which the fill material is to be placed shall be given the ground improvement
treatment as specified in
drawings.
Embankments and other areas of fill shall be formed using 'suitable material"
as defined in Clause 1.1.1 of this Specification.
1.5.2 Forming Embankment
a.   All fill materials shall be deposited in layers of the specified thickness and
     compacted as soon as practicable after placement using construction plant as
     permitted in Table 1.5
b.   All embankments shall be built up evenly over their full width and an even surface
     shall be maintained at all times with a sufficient gradient to enable the drainage of
     surface water.
d.    Adequate temporary surface drainage shall be provided such that surfacewater flows
     toward the edge of the embankment. All completed slope faces and verges shall be
     turfed to prevent soil erosion according to EMP.
e.   The compaction of embankments and other areas of fill shall be undertaken to the
     requirements of Clause 1.6.
f.    if the material deposited as fill subsequently reaches a condition such that it cannot
     be compacted to comply with the requirements of this specification, the Contractor
     shall either:-
i.   Remove and temporarily stockpile the material elsewhere until it reaches a physical
     condition suitable for use in the proposed works, or
ii. . Make good the material by mechanical or chemical means; or
iii. Cease work on the material until its physical condition is altered such that it can be
     compacted in accordance with the requirements of this specification.
i.   For compaction of embankment slope, the Contractor may either extend each
     compacted layer beyond the design slope surface by at least 600 mm,then trim back
     to the required slope angle, or may employ a tow type roller to compact the sloping
     surface.
1.5.3 Inspection of Ground below Proposed Embankment and Other Areas of Fill
b.   b. In the assessment of the suitability of the ground, particular care and attention
     shall be given to the following areas:
         1) Soft clays, peat or swamp materials.
         ) Topsoil containing organic materials, rootlets, decomposed wood etc.
         ii) Loose sand within abandoned mining or low-lying areas.
b. b. Rock fill material shall be sound, compact, durable rock and good quality.
c.   c. Rock fill material shall be free from seams, fissures, planes of weakness,blasting
     cracks, and any other undesirable qualities.
g. Testing of rock shall apply to all selected rock materials for embankment
construction work
h.   h. Verification test such as specific gravity test and point load test shall be carried out
     at one test for every 500 cubic meter of rock
i.   Testing of the rock considered necessary during the progress of the works shall be
     made by an approved laboratory.
j.   The top surface and side slopes of embankments constructed from Rockfill shall be
     blinded with approved fine graded material to seal the surface.There shall be a
     transition layer between the rock fill and fine grained material of at least 300 mm
     compacted thickness comprising of material as defined in Table 3.4. The thickness of
     the fine graded material at the top and side slopes shall be at least 500 mm thick and,
     comprise suitable fill material as defined in Clause 1.1.1
k.   k. Isolated boulders between 0.015 m3 and 0.085 m3 in size shall not be incorporated
     in rock fill embankments unless otherwise approved and provided that the specified
     compaction requirements are met. No-isolated boulders exceeding 0.015 m3 size
     shall be placed less than 600mm below the formation level of the track, including the
     hard shoulders.
l.   I. Compaction trials for the construction of rock fill embankments shall be carried
     out as per clause 1.6.8 and a report shall be submitted for approval.
If the surface of the embankment, before trimming to the desired formation level, is to be
used by construction plants, then the embankment shall made to a level of at least 300mm
above the desired formation level. The movement and use of construction plant on
embankments shall not occur after such embankment has been trimmed to formation
level. Any damage to the subgrade shall be made good.
b.   b. In the second stage, the excess 150 mm of material above the formation level shall
     be trimmed off in a single operation and the material disposed of as appropriate.
The preparation of subgrade shall only be carried out after the completion of all specified
subsoil drainage works. It shall generally be carried out immediately before the laying of
the sub-ballast as shown in the drawings. It shall generally comprise the finishing of
formation in accordance with the
designed lines, levels and super-elevations. The subgrade shall be constructed over the
full formation width in one pass.
a.   Dry density not less than 95% of the maximum dry density of the material
     determined as per BS 1377: Part 4: 1990 clause 3.5 (4.5 kg rammer method)
b. Soaked CBR of not less than 5% determined as per BS 1377: Part 4: 1990 Clause 7
The surface of the subgrade in cuttings directly below the formation level shall be
scarified, and compacted such that the top 300mm directly below the subgrade satisfies
the compaction criteria specified in clause 1.5.10. If the CBR criterion is not satisfied, the
top 300mm of material shall be removed and replaced by an imported material to achieve
the criteria specified in clause 1.5.10.
Rock cutting shall be excavated to the subgrade level as indicated on the drawings and all
loose materials shall be removed. The subgrade shall be such so as to permit the free
drainage of all storm water and ground water in to side ditches. All depressions in the
subgrade surface shall be filled with leanconcrete or sub-ballast material to obtain the
desired cross-falls.
1.5.13 Trimming of Subgrade
A smooth-wheeled roller having a mass per meter width of roller greater than 4 tons shall
carry out final rolling of the subgrade for embankments and cuttings.The vertical
tolerance for the finished formation shall be in accordance with the track requirements as
stipulated in the "Track Works" Specifications.
1.6.1 All materials used in embankment and filling areas shall be compacted as soon as
practicable after deposition. All compaction shall be undertaken in accordance with the
requirements of Clause 1.6.7 The Contractor shall use those items of plant listed in Table
1.5, which are appropriate to the soil and site conditions.
1.6.2 Variations from the methods given in Table 1.5 or the use of plant not included
therein shall be permitted only if demonstration at site by trials indicate that a state of
compaction could be achieved by the alternative method which is equivalent to that
obtained using the approved methods. The procedure to be adopted for these site trials
shall be agreed and approved. Whatever method
is adopted the end result shall comply with that stated in Clause 1.6.10.
1.6.3 Comparative field density tests shall be carried out in accordance with B.S.1377:
Part 9:1990 clause 2.1 to enable to evaluate the degree of compaction achieved. If the test
results, when compared with the results of similar tests made on approved works in
similar materials show that the degree of compaction is inadequate due to failure of the
Contractor to comply with the
requirements of the specification. The Contractor shall carry out rectification works so
that such fill complies with the requirements of the Contract.
1.6.4 The types of compactor, the procedure of compaction and the thickness of the
filling shall be determined by trial carry out on the fill embankment.
Preparation of final formation shall be carried out after completion of all subgrade
drainage works, prior to laying of sub-ballast or sub-base is required. The sequence of
operations for shall be as follows:-
ii. The surface of the embankment shall be compacted to a dry density of not less than
    95% of the maximum dry density as determined in accordance with BS 1377: Part
    4:1990 clause 3.5.
iii. The formation shall then be trimmed to the specified line and levels
b) Rock fill
All rock fill formation shall be regulated and blinded in accordance with the requirements
of this specification and as shown in the Drawings
1.6.6
     a) The depth of compacted suitable fill layer is the height by which the embankment
        is raised by each successive compacted layer. Suitable fill shall be laid in layers of
        loose thickness not exceeding 400 mm and compacted with suitable compaction
        equipment. The thickness of each
        compacted layer is to be confirmed on site after conducting a simple trial
        subject to the relevant clauses of the specifications.
     b) The number of passes is the number of times that each point on the surface of the
        layer being compacted has been traversed by the item of compaction plant
c) The compactive effort of each compactor is a function of the mass of the machine
   and the compaction plant in Table 1.5 is listed in terms of their masses. The mass
   per metre width of roll is the total mass on the roll divided by the total roll width.
   Where a smooth-wheeled roller has more than one axle the machine shall be
   assessed on the basis of the axle giving the highest value of mass per metre width.
e) For pneumatic-lyre rollers, the mass per wheel is the total mass of the roller
   divided by the number of wheels.
          ii. Where the spacing exceeds 230 mm the effective width shall be the sum of
              the widths of the individual wheel tracks only.
     i.   The requirements for vibrating rollers are based on the use of the lowest gear
          on a self- propelled machine with mechanical transmission and a speed of 1.5-
          2.5 km/h for a towed machine, or a self-propelled machine with hydro static
          transmission. If higher gears or speeds are used an Increased number of passes
          shall be provided in proportion to the increase in speed of travel.
     ii. Where the mechanical vibration is applied to two rolls in tandem, the
         minimum number of passes shall be half the number given in Table 1.5 for the
         appropriate mass per metre width of one vibrating roll. If one roll differs in
         mass per metre width from the other the number of passes shall be calculated
         as for the roll with the smallest value. Alternatively the machine may be
         treated as having a single vibrating roll with a mass per metre width equal to
         that of the roll with the higher value.
     iii. Vibrating type rollers operating without vibration shall be classified as smooth
          wheeled rollers
     iv. Vibrating rollers shall be operated with their mechanism operating only at the
          frequency of vibration recommended by the manufacturers. All such rollers shall
          be equipped or provided with a device automatically indicating the frequency at
          which the mechanism is operating.
     i.   The mass per unit area of base plate of a vibrating-plate compactor is calculated
          by dividing the total mass of the machine in its working condition by its area in
          contact with compacted soil.
j)   In the case of power rammers and dropping-weight compactors one pass will be
     considered as made when the compacting shoe has made one strike on the area in
     question
k) For items marked Table 1.5 "the rollers shall be towed by track-laying tractors. Self-
   propelled rollers are unsuitable.
l) Where combinations of different types of categories of plant are used, the
   compaction requirements shall be: -
     i.   The depth of the layer shall be that for the type of plant requiring the least depth
          of layer,
    ii. The number of passes shall be that for the type of plant requiring the greatest
        number of passes.
However, where the Contractor uses a lighter type of plant to provide some preliminary
compaction only to assist the use of heavier plant,this shall be disregarded in assessing
the above requirements.
The Contractor shall submit for the approval the proposals for the compaction of each
type of material to be used in the embankment. Such proposals shall include the types of
construction plant to be used, the number of passes compaction (Trial run of 6, 8 & 10
passes), and the maximum loose depth of each material layer. Compaction trials shall
carried to the satisfy and support trial compaction proposals. These trials shall be
supplemented by all appropriate laboratory test results as required. Approval trial
compaction proposals shall be obtained from engineer before the commencement of
embankment construction.
Compaction shall be carried out continuously from top layer of subgrade (Sub-Ballast)
throughout the embankment including its slopes, until the state of compaction complies
with the following:-
a) Top-layer of Subgrade bed shall be compacted not less than 95% of the maximum
   dry density (MDD) determined from B.S. 1377 Compaction Test (4.5Kg rammer
   method) and 4 days soaked California Bearing Ratio (CBR) ≥ 25%
b) The bottom-layer of subgrade bed on the second part as bedding shall be-compacted
   not less than 93% of the maximum dry density (MDD) determined from B.S. 1377
   Compaction Test (4.5 Kg rammer method) and 4 days soaked California Bearing
   Ratio (CBR) ≥ 10.
c) Embankment subgrade material below the subgrade bed shall be compacted to not
   less than 90% of the optimum dry density when tested in accordance with BS1377
   Part 4 (4.5 kg Rammer). Soaked CBR under 4 days soaked for the material shall not
   be less than 5% determined in accordance with BS 1377: Part4:1990 clause 7.
1.7.1 General
Construction of embankments over culvert and pipe drains shall be carried out In a
manner so that the drainage structure is not damaged. The fill on both sides of the culvert
or drain shall be raised up and compacted equally to avoid displacement of the drainage
structure. Where special methods of compaction adjacent to a structure are described in
the contract, filling may proceed over
widths less than the full width of the embankment. Rock fill adjacent to a drainage
structure shall be carefully packed so as to prevent damage to substructure.
   b) Rip-rap shall be constructed using fresh, inert and naturally occurring stone of the
      specified size. Stones of size less than 250 mm in depth shall not be used for this
      purpose. The stones shall be laid to the grade and level shown in the Drawings.
      Where necessary trenches shall be excavated at the bottom of the slope as
      protection works to such depth as is necessary to ensure a safe foundation for the
      rip-rap.
a) Prior to commencing the construction of an embankment over soft ground, the soil
   over which fill materials to be placed shall be given the ground Improvement
   treatment as specified in Drawings.
b) If founding materials are soft, loosed and unstable at certain magnitude due to
   embankment loading, excavation with full or partially removal can take place as an
   option to the ground Improvement. The maximum excavation and replacement shall
   not be more than 3.0m depth from existing ground level (EGL).
c) Layers of fill material shall be deposited over the full width of the embankment and
   counterweight berms, if required, shall be compacted as per the requirements of the
   specification.
d) (d) The deep soil foundation treatment should be adopted with DSM (deep soil
   mixing), PVD (Prefabricated Vertical Drain), RCSP (Reinforced Concrete Square
   Pile) or PHC (Pre-tensioned Spun Concrete pile) in transition section. The design
   requirements should be according to the designers.
1.9.2 The temporary watercourses, ditches, drains, pumping or other means necessary
for maintaining the earthworks free from water shall be provided.Such provision shall
include carrying out the work of forming the cuttings and embankments in such a manner
that their surfaces have at all times a sufficient minimum cross fall and, where
practicable, a sufficient longitudinal gradient to enable them to shed water and prevent
ponding.
1.10.1 Soiling, Grassing and Turfing shall be carried out as soon as practicable on
slopes and other areas as shown on the Drawings.
1.10.2 Unless where specified otherwise in the Drawings the areas to be grassed shall be
soiled using topsoil not less than 50mm thick. The topsoil shall be spread evenly over the
area to be turfed and lightly compacted. The surface of the slope to be turfed shall be free
from all debris or stones of dimension greater than two-thirds the thickness of the topsoil
layer
1.10.3 Prior to seeding or turfing, approved fertilizers shall be evenly distributed on the
topsoil at a rate not less than 75 g/m2. Details of the type and composition of the
fertilizers shall depend on the type of soil.
1.10.4 Due regards shall be paid to the season and weather conditions before sowing
grass seed and all reasonable measures shall be taken to promote its growth.Immediately
prior to sowing the grass seed the topsoil shall be reduced to a fine tilts. Sowing of grass
seed shall be carried out by an even distribution,using a proper blend of seed. The rate of
application of the seed shall not be
less than 6 g per m2 for verges and central reserves and 9 g per m2 for slopes The seed
shall be covered by lightly raking into the surface of the topsoil.
1.10.5 Where hydraulic mulch seeding is specified it should be carried out in accordance
with Clause 3.10.10
3.10.6 Suitable turf available on the site before stripping shall be used wherever
possible. Turfing shall be undertaken with clean strong turfs that are well bonded and
lightly beaten and which shall be laid diagonally across side slopes.All turf shall be used
within one week of cutting. Turf not used within this period shall be removed from site.
   b)    On slopes and other locations where it is difficult to ensure that turf cells are so
        bedded they shall be secured in place by driving small wooden stakes that are 20-
        25 mm diameter and 200-250 mm long through the cells and topsoil into the
        ground material.
   c) Where turf cells fail to generate growth, they shall be removed and replaced by
      sound material to be approved.
Grid turfing if specified shall be carried out exactly as close turfing except that the
230mm x 230mm,turf cells shall be arranged in criss-crossing parallel single cell strips
intersecting each other at 60°/120°.
b)    Only skilled and experienced operators, who are approved, shall undertake seed
     casting.
1.11.1 General
        To ensure that upon completion of the earthworks the formation surface is at the
        required level and that the finished surface of the track formation is in accordance
        with the requirements of this specification.
1.11.2 Curves
1.11.3 Rolling
        Final rolling of all cut or fill surfaces after trimming to the finished formation
        level shall be completed at a low uniform speed and shall commence from the low
        side of the camber towards its top.
1.11.4 Removal of Surplus and Unsuitable Materials
        All surplus and unsuitable materials shall be removed from site and disposed of
        the site. To ensure that these materials are leveled, compacted and turfed to
        the satisfaction of the respective local authorities
1.11.5 Landslips
        All landslide, slip and slope failure debris shall be removed from the site
        including over break rock extending beyond the lines and slopes or below the
        specified levels. All work necessary to keep excavations free from water,including
        the provision of temporary watercourses and drains, shall be provided.
   a) Cuttings in rock shall be cut to the finished line and level that is shown on
      the Drawings.
   b) Surface irregularities that remain in the base of cuts after the completion of rock
        excavation shall be back-filled to the specified formation level with grout or
        material similar to that specified for the sub-ballast as shown in the drawings.
        Such material shall be laid and compacted to a sufficient depth so as to
        completely cover the rock face.
1.11.7 Protection and Maintenance of Earthworks
   a)    All necessary temporary works shall be provided to protect the completed portion
        of the works from damage due to any reason. In this connection special attention
        should be given to damage caused by flowing or stagnant water.ensure that no
        natural drainage line is intercepted by the proposed works In such a manner as to
        result in water flows being directed into the properties of adjoining landowners.
        Where this is unavoidable the Contractor shall obtain the prior written consent of
        the landowners. In any case all precautions shall be taken by the contractor to
        ensure that water discharged into adjacent/properties are free of' sand, silt and
        other objectionable sediments by the provision of proper, efficient and workable
        silt traps or other like devices.
   c) All prepared formation surfaces shall be kept well drained throughout the course
      of the work. All trenches opened up for this purpose shall at all times be properly
      maintained. Particular care shall always be exercised to
1.12 Watercourses
All works carried out to watercourses shall comply with JPS' requirements or
Specifications.